JINDAL STEEL & POWER LIMITED (ANGUL)

SCOPE OF WORK FOR ENGINEERING CONSULTANT (EC) FOR DR-2

Table of Contents

1. INTRODUCTION...................................................................................................................... 2

2. BATTERY LIMITS.................................................................................................................... 3

3. ENGINEERING SCOPE OF WORK.........................................................................................4

4. OBLIGATIONS OF EC......................................................................................................... 10

5. OBLIGATIONS OF JSPL ......................................................................................................11

6. EXCLUSION........................................................................................................................... 12

ANNEXURE-1 Page 1 of 30
ENGINEERING CONSULTANT SCOPE

1. INTRODUCTION:

JSPL proposes to install second DRI plant (DR 2) adjacent to the upcoming first DRI plant
(DR 1) in the upcoming Steel Complex at Angul.

This scope has been proposed by JSPL for the engineering consultant (EC) to submit their
techno commercial offer for DR 2 proposed to be of 2.5 MTPA capacity, to produce Hot DRI
& Cold DRI simultaneously; with ENERGYIRON technology, using synthesis gas (to be
produced from upcoming LURGI design Coal Gasification plant) and COG (Coke-oven gas a
byproduct from Coke Oven Batteries in the proposed Steel Complex) for Jindal Steel &
Power Ltd (JSPL) at our Angul location.

The DR 2 will also include COG gas cleaning system and pressure boosting, CO2 removal
system, Process gas Heater, DR Furnace, process gas, cooling gas and HYTEMP transport
compressors, material handling system, utilities, Fire protection system and turbo expander
system. Syn Gas from Coal Gasification plant shall be made available at Battery Limit (BL)
of DR Plant., whereas BL for COG is proposed to be at source of COG to include scope of
cleaning and pressure boosting & transportation to DR 2.

The scope of work which includes following major heads and a detailed scope spilt are
provided in “Engineering Scope of Work” part,
Process License : by JSPL
Statutory Licenses :    by JSPL
Basic Information and Basic Engineering :          by JSPL from Licenser and to be
issued to EC as per scope matrix
Detail engineering incl. procurement support by EC as per scope matrix
Erection support : Support as per man day basis
Commissioning support : Support as per man day basis

Annexure-1 ENGINEERING CONTRACT Page 2 of 30


ENGINEERING CONSULTANT SCOPE
2. BATTERY LIMITS

Raw Material & Product:

a. Battery limits for the Project will start from ore receipt at the junction house DRJ 4 from
yard conveyor, and will end at belt discharge of product conveyor feeding to SMP
feeding conveyor or belt discharge of Export conveyor – at DRJ 4 junction house.

b. Review of RMHS from Oxide Day bin to Common conveyor related to DR2 plant and
Review of Common product conveyor related to DR2 plant. Product storage design is
excluded from Present scope.

Redcution Gas:

c. Syn Gas: Battery limits for the Syn gas will start from tap-off point from DR-1 syn gas
line.

d. Coke Oven Gas: Battery limits for the Coke oven gas will start from tap-off point from
COG network within 2km from DR 2 Plant boundary.

Utility Service Requirement:

e. Make-up water, process water, Fire water, drinking water, steam, Oxygen, Nitrogen
shall be provided at DR plant battery limit by JSPL at required temperature, pressure
and flow.

f. BOF Gas: gas line for BOF gas from tap off point within 2km from DR plant boundary
to be used as fuel.

Power:

g. Battery for electric power will be at the control room building at 33KV level.

Slurry:

h. Slurry discharge in sludge pond within DR 2 plant boundary and return water back to
clarifier by EC.

Annexure-1 ENGINEERING CONTRACT Page 3 of 30


ENGINEERING CONSULTANT SCOPE
Hy- Temp System:

From the furnace discharge up to the discharge point of surge bins at Melt Shop Area. This
excludes the support and civil engineering and structural support of bins within the Melt
Shop area.

3. ENGINEERING SCOPE OF WORK

3.1 Basic Information (BI):

The scope covers review & suggestions for possible improvements of Basic
information documents received from Licenser within Battery Limit (BL) of DR plant in
terms of completeness to carryout basic engineering and complete basic information
will be provided by EC for its scope of activities as specified in scope matrix. In general
the basic information documents shall include: the sketches and design basis
necessary for the development of basic engineering, which are:
 Main Process data
 Description of the main features of the machine, main technical data and list of
the main components.
 Feed materials and Finished Products main data.
 Main Process Parameters and Conceptual process scheme.
 Preliminary overall material balance.
 Power calculation of the Production Line. Indications related to the basic
operating conditions
 utility consumption figures and fluid characteristics
 Specification, main description and general data.

3.2 Basic Design( BD):

The scope covers review of Basic Engineering documents and suggests possible
improvements if any, received from Licenser for BL of DR plant in terms of
completeness to carryout detail engineering and complete basic engineering will be
provided by EC for its scope of activities as specified in scope matrix. In general the
basic engineering documents shall include:
 Mass and energy balance
 Process flow diagrams

Annexure-1 ENGINEERING CONTRACT Page 4 of 30


ENGINEERING CONSULTANT SCOPE
 process and instrument diagrams (P&ID’s)
 Equipment list, motor list, line list, valve list
 Equipment duty specifications or data sheets
 Layout with Core plant and auxiliary units
 Piping specifications and pipe classification sheets
 Control System Specification
 Hazardous area classification drawings
 Foundation outlines/loading diagrams, structural design concepts, and building
requirements.

3.3 Detailed Design (DD):

The detail engineering scope covers EC scope of work materials and shall not
include the Licenser supplied equipments within BL of DR plant as specified in
scope matrix. The detail engineering documents shall include following including
Technical specifications of respective areas as applicable:

Process Engineering
 Utility balance
 P&ID’s including vendor information
 Logic diagram including vendor information
 Preparing technical bid/tender document
 Technical evaluation of Vendor offers up to five(5) vendors
 Vendor drawing/document approvals
 Interface engineering with vendor information within BL.
 Hazop study for non - core area as applicable; and participate for integration
with the core area Hazop and preparation of combined report thereof, within BL
of DR 2 plant.
General Layout Engineering: (BL of DR Plant)
 Layout with DR plant & auxiliary units- and also with roads and drains within the
BL of Layout.
 Integration up to HDRI bins at SMS feeding tower, however Integration with
Steel Melting Shop (SMS) is not in scope.
 Interface engineering with vendor information within BL.

Annexure-1 ENGINEERING CONTRACT Page 5 of 30


ENGINEERING CONSULTANT SCOPE
Mechanical/Equipment Engineering
 CO2 removal system technical specification
 Process gas heater technical specification
 Syn gas turbo expander technical specification
 COG and BOF compressors technical specifications
 Process gas compressors and cooling gas package technical specification
 Technical Specification for other auxiliary system equipments including DM
water plant.
 Technical specification for all bought out equipments/materials including lifting
devices for plant buildings within BL.
 DM plant – Technical specification for package supply
 Boiler -- Technical specification for package supply
 Fire water booster pumps
 Instrument air buffer tanks
 Equipment Engineering: Basic General Arrangement (GA) drawings will be
prepared with necessary details for fabricators to prepare detail fabrication
drawings.  Fabrication drawings will be developed by vendors / manufacturers
and will be approved.
 Preparing technical bid/tender document.
 Technical evaluation of Vendor offers up to five(5) vendors.
 Vendor drawing/document approvals.
 Vendor Quality control plan approvals.
 Interface engineering with vendor information within BL.
 Incorporation of vendor details in detail engineering.

Material Handling
Raw Material Handling System (RMHS):
 Review of RMHS from Oxide day bin to common conveyors related to DR2
plant.
 Detail engineering of RMHS from material receipt from DRJ 4 JH conveyor to
DR2 furnace feeding

Annexure-1 ENGINEERING CONTRACT Page 6 of 30


ENGINEERING CONSULTANT SCOPE
Product Material Handling System (PMHS):
 Detail engineering of RMHS from furnace discharge to DRJ 4 conveyor feeding
SMP or storage.
 Review of common conveyor system for related to DR2 plant
 Storage design for product is excluded from the present scope
 Review of Remet handling system.

Dedusting System:
 Dedusting of RMHS within BL.
 Dedusting of DRI within BL.
 Material handling bins, chutes and conveyor arrangement drawings with in BL
 Tender documents for material handling equipments like belt, conveyor belt,
pulleys, idlers, screw take-up, drive assembles, screens, feeder, etc
 Preparing technical bid/tender document
 Technical evaluation of Vendor offers up to five(5) vendors
 Vendor drawing/document approvals
 Vendor Quality control plan approvals
 Interface engineering with vendor information within BL.
 Incorporation of vendor details in detail engineering
 EOT or similar hoists needed at different locations.

Piping & Ducting


 Piping: complete detail Piping engineering and issue of GA, ducting drawings,
isometric and Material Take-Off (MTO).
 Preparing technical bid/tender document
 Technical evaluation of Vendor offers up to five(5) vendors
 Vendor drawing/document approvals
 Vendor Quality control plan approvals
 Interface engineering with vendor information within BL.
Refractory & Insulation
 Refractory & insulation engineering drawings for Noncore plant
 Refractory & insulation material specification for Noncore plant
 Refractory & insulation tender documents for Core plant and noncore plant area
 Preparing technical bid/tender document

Annexure-1 ENGINEERING CONTRACT Page 7 of 30


ENGINEERING CONSULTANT SCOPE
 Technical evaluation of Vendor offers up to five(5) vendors
 Vendor drawing/document approvals
 Vendor Quality control plan approvals
 Interface engineering with vendor information within BL.

Structural Engineering
 Fabrication drawing preparation for reactor tower and technological structure
using detail engineering drawings provided by Danieli/HYL
 Detailed engineering for following buildings/facilities and Racks
a. Material handling- Junction house and conveyor galleries
b. Non technological pipe racks between auxiliary facilities and to core
plant battery limit
c. CO2 Removal system ( on package basis)
d. Heater (on package basis)
e. Syn gas Turbo expander building
f. Syn gas station for receiving & metering
g. Compressed air plant building
h. MCC & Control room building for DR plant
i. Cable Racks
j. Oxide and product handling Junction Houses & Conveyor Galleries
 Preparing technical bid/tender document
 Technical evaluation of Vendor offers up to five(5) vendors
 Vendor drawing/document approvals
 Vendor Quality control plan approvals
 Interface engineering with vendor information within BL.

Civil Engineering
 Pile design and piling layout, if required
 Detail engineering for civil foundation for all equipments and structures of BL
which includes the following Buildings :
a. Civil work for areas specified in above structural detail engineering part
b. Sludge Pond
c. Water sumps
d. Clarifier

Annexure-1 ENGINEERING CONTRACT Page 8 of 30


ENGINEERING CONSULTANT SCOPE
e. Cooling towers ( by Vendor)
f. Road in-side plant battery limit
g. Storm water drain in-side plant battery limit
 Preparing technical bid/tender document
 Technical evaluation of Vendor offers up to five(5) vendors
 Vendor drawing/document approvals
 Vendor Quality control plan approvals
 Interface engineering with vendor information within BL.

Instrumentation Engineering
 Technical specifications and typical hook ups for field instruments, analyzers,
and DCS
 Final Control system Logic Diagrams for non core area & integration with core
area
 Final Control system for packages -Process Gas Heater, CO2 Removal system,
Turbo Expander, PG&CG compressors will be supplied by Package Vendor
 DCS Screen Layouts support with Supplier/Vendor
 Process Automation Design support with Supplier/Vendor
 Cable scheduling and routing
 Preparing technical bid/tender document
 Technical evaluation of Vendor offers up to five(5) vendors
 Vendor drawing/document approvals
 Vendor Quality control plan approvals
 Interface engineering with vendor information within BL.
 CO and Explosive monitoring system
Electrical Engineering
 Single Line Diagrams (SLD)
 Cable scheduling and routing
 Substation layout at control room building
 MCC room layout
 Transformers
 Lighting
 Earthing
 Preparing technical bid/tender document

Annexure-1 ENGINEERING CONTRACT Page 9 of 30


ENGINEERING CONSULTANT SCOPE
 Technical evaluation of Vendor offers up to five(5) vendors
 Vendor drawing/document approvals
 Vendor Quality control plan approvals
 Interface engineering with vendor information within BL.
 FDA system, Intercom and Clock system, CCTV and Telecom and paging
system.

3.3 Review (RE):

Review of all Basic Information, Basic Design, Detail Design documents submitted by
Licenser, Vendor for completeness to carryout procurement and/or construction.

3.4 Inspection Services (IS):

Inspection at vendor facility is not considered in EC scope however it will provide


necessary document issuable to Third Party Inspection Agency appointed by JSPL.

3.5 Erection Support:

Erection support services shall be taken by way of deputation of EC experts to JSPL


engineering office/project site at agreed man-month basis.
3.6 Commissioning Support:

 EC shall provide necessary technical assistance service during commissioning


support to JSPL to during commissioning and start-up stage of the project by
way of deputation of their experts to JSPL engineering office/project site at
agreed man-month basis.
 For all bought out equipments, EC will provide necessary support along with
equipment supplier.

4. OBLIGATIONS OF EC

a. Planning and scheduling of engineering activities.

b. Planning and scheduling work as per the overall project schedule.

c. Submission of Co-ordination Procedure and document submission procedure for


review or approval.

Annexure-1 ENGINEERING CONTRACT Page 10 of 30


ENGINEERING CONSULTANT SCOPE
d. Cooperation with all Parties involved as to be mutually defined, including provision of
information to Owner of any interface matter arising there from.

e. Provide all its engineering data/documents/ drawings in AUTO CAD format in English
language through “fnps portal” method or it’s “edocs” a document sharing portal.

f. Provide the project sequence for execution of DR-2 plant activities within the battery
limit and review the execution schedule for integration with other units.

g. Provide general layout and integrated packages of DR-2 Plant in 3D modeling.

5. OBLIGATIONS OF JSPL

a. Furnish to EC, all the information regarding equipment procured from LICENSER /
other party.

b. Furnish complete technical data / details of equipment including drawings, BOQ,


weights of equipment and any other relevant data /information received regarding
LICENSER supplied items. JSPL shall also furnish various reports prepared by other
agencies/ JSPL on the proposed plant.

c. Provide all basic engineering data/documents/ drawings including mass, material &
utility balance sheets, PFDs, P&IDs, Logic Diagrams, Data sheets for equipments,
instruments, & Piping, electrical load data, equipment list to EC.

d. Furnish plant location details, climatic conditions, Site survey maps and soil
investigation study.

e. Arrange drawings/data as per EC requirement for engineering in consultation with


original equipment manufacturers or ‘Technological & Process Consultant” for
supplementing the missing data/ drawings for LICENSER equipment where complete
details are not available. JSPL will also arrange / assist to provide all individual
schedules for preparation and updating of overall schedule by EC.

f. Organize all the discussions / meetings with technological / process consultant/ local
authorities as and when required in connection with engineering of the plant.

g. Provide all basic design data/documents/ drawings in soft copy in CD in English


language from licenser, as required by EC for detail engineering.

Annexure-1 ENGINEERING CONTRACT Page 11 of 30


ENGINEERING CONSULTANT SCOPE
h. Commissioning of all items shall be done by JSPL. EC to assist in the same along with
equipment supplier on man-month basis.

6. EXCLUSIONS:

The following items of work are excluded from EC Scope of Services:-


a. Infrastructure facilities, such as, external power, external water including intake-
water & transportation of water, external roads/transport, mines, township, etc.
b. Testing and Linkage of raw materials.
c. Supply and Construction
d. Site Survey and Soil Investigation Study, etc.
e. Environmental Impact Assessment (EIA) Monitoring and Preparation of EIA /
EMP Reports including generation of base line data.
f. Detailed design of all bought out items.
g. Integration with SMS(Steel Melt Shop)
h. Waste & sewage Drainage and handling outside BL ( this will be connected to
common plant facility of such services)
i. Waste & sewage treatment design
j. Quantity survey and Certification of Contractors bills.
k. Liaison and obtaining clearance from Govt. and statutory bodies. However,
technical assistance will be provided for the same.
l. Stamping of drawings and Professional Engineer’s Certification by local
consultant / authorities.
m. Performance Guarantee for the bought out and licensers equipments.
n. Health Study of old plant and equipments for usability, refurbishment
requirement, list of missing items, etc.
o. Modification on the Equipments procured from other company.

Annexure-1 ENGINEERING CONTRACT Page 12 of 30


ENGINEERING CONSULTANT SCOPE

SCOPE MATRIX WITH LIST OF ITEMS


The splitting up of scope of services among EC, JSPL and technology licenser to JSPL
(Danieli & HYL) are indicated in detail hereafter.

RESPONSIBILITY LEGEND FOR DETAIL ENGINEERING


EC-ENGINEERING CONSULTANT, J-JSPL, D-Daniali, H-HYL, V-Vendor for Package items

BI-BASIC INFORMATION, BD- BASIC DESIGN, DD- DETAIL DESIGN, RE- REVIEW
ES- ERECTION SUPPORT, CS- COMMISIONING SUPPORT.
CORE PLANT AREA
QT BI BD DD RE ES CS
Y
1. REACTOR CHARGING            

1.1 Iron Ore Charging To Reactor            


1.1.1 Flexowell conveyor RH126-V 1 D D EC EC EC EC
1.1.2 Recovery devices RH140-V and RH127- 2 D D EC EC EC EC
V
1.2 Reactor Charging System
1.2.1 Rotary charger RE 250-F 1 H H - EC EC EC
1.2.2 Iron ore loading bin RE 251-F 1 D D D EC EC EC
1.2.3 Solid Cut-Off Valve RE 206-L11h-L14 4 H H - EC
1.2.4 Conical Adapter RE 202-L11h-L14 4 H H - EC
1.2.5 Solids Cut-Off & Gas Seal Valve VS2 4 H H - EC
RE 201-L11h-L14
1.2.6 Pressurization valve RE 214-L1 1h-L14 4 H H - EC
1.2.7 Venting valve RE 204-L11h-L14 4 H H - EC
1.2.8 Iron Ore Pressurized Bin RE 253-F11h- 1 D D D EC EC EC
F14
1.2.9 Solids cut-off & gas seal valve VS2 RE 4 H H - EC
205-L11h-L14
1.2.10 Expansion Joint Pressurized RE 203- 4 H H - EC
L11h-L14
1.2.11 Plug Valve RE 208-L11h-L14 4 H H - EC
1.2.12 Fittings and spool pieces (for solids 1 H H - EC
only) set

Annexure-1 ENGINEERING CONTRACT Page 13 of 30


ENGINEERING CONSULTANT SCOPE
2. REACTOR            
2.1 Reactor Complete including feeding 1 D D D EC EC EC
legs, cooling jackets and Refractory
Supports RE 221-D1
2.2 Reactor Refractory 1 D D D EC
2.3 Cluster breakers RE209-L11/L12 2 H H - EC
2.4 Flow Feeders RE 212-L1/L2/L3 3 D D - EC
2.5 Flow Feeders Cooling System including 1 D D D EC EC EC
tank WS 366-F, Flow Feeders Pumps set
(WS 365-J1/J2) and associated Piping
3. REACTOR DISCHARGING            
3.1 Reactor Discharging System            
3.1.1 Manual Blocking Valve RE 210-L 1 H H - EC
3.1.2 Expansion Joint RE 211-L 1 H H - EC
3.1.3 Rotary Valve RE 276-L 1 H H - EC
3.1.4 Diverter Valve RE 278-L 1 H H - EC
3.1.5 Diverter Valve RE 279-L 1 H H - EC
3.1.6 Solids Cut off and Gas Seal Valve VS2 2 H H - EC
PH 130-L1/L2
3.1.7 Expansion Joint PH 132-L 1 H H - EC
3.1.8 Fittings and spool pieces (for solids 1 H H - EC
only) set
3.2 Sampling Bin System            
3.2.1 Solids Cut off and Gas Seal Valve VS2 1 H H - EC
RE 223-L1/L2
3.2.2 Expansion Joint RE 215-L 1 H H - EC
3.2.3 Solids Cut-off & Gas Seal Valve VS2 RE 1 H H - EC
236-L
3.2.4 Pressurization Valve RE 227-L 1 H H - EC
3.2.5 Gas Seal Valve RE 222-L 1 H H - EC
3.2.6 Sampling Bin RE 255-F 1 D D D EC EC EC

3.2.7 Solids Cut-off Valve VS2 RE 240-L 1 H H - EC


3.2.8 Solids Cut-off & Gas Seal Valve VS2 RE 1 H H - EC
226-L
3.2.9 Sampler RE 260-L 1 H H - EC

Annexure-1 ENGINEERING CONTRACT Page 14 of 30


ENGINEERING CONSULTANT SCOPE
3.2.10 Cooing Device 1 H H - EC
3.2.11 Solids Cut-off & Gas Seal Valve VS2 RE 1 H H - EC
232-L
3.2.12 Flow Restrictor PH 103-L 1 H H - EC
3.2.13 Fittings and spool pieces (for solids 1 H H - EC
only) set
3.3 Cold DRI Discharging System            

3.3.1 DRI Cooler Surge Bin PH 131-F 1 D D D EC EC EC


3.3.2 DRI Cooler CG 121-D 1 D D D EC EC EC
3.3.3 Manual Blocking Gate PH 133-L 1 H H - EC
3.3.4 Expansion Joint PH 134-L 1 H H - EC
3.3.5 Rotary Valve PH 136-L 1 H H - EC
3.3.6 Diverter Valve PH 138-L 1 H H - EC
3.3.7 Solids cutt of and Gas Seal Valve VS2 4 H H - EC
PH 140-L11/L14
3.3.8 Expansion Joints PH 142-L11/L12 2 H H - EC
3.3.9 Solids Cut-off & Gas Seal Valves PH 2 H H - EC
143-L11/L12
3.3.10 Cold DRI Pressurized Discharge Bins 2 D D D EC EC EC
CG 155-F1/F2
3.3.11 Solids Cut-off & Gas Seal Valves PH 2 H H - EC
146-L11/L12
3.3.12 Pressurization Valves PH 382-L11/L12 2 H H - EC
3.3.13 Depressurization Valves PH 383- 2 H H - EC
L11/L12
3.3.14 Depressurizing Gas Venturi UT 710-G 1 D D D EC EC EC
3.3.15 Depressurizing Gas Separator UT 700-F 1 D D D EC EC EC
3.3.16 Depressurizing Scrubber Pumps UT 700 1 D D EC EC EC EC
J1/J2
3.3.17 Flow Restrictor PH 104-L1/L2 2 H H - EC
3.3.18 Fittings and connecting pieces (for 1 H H - EC
solids only) set
4. GAS SYSTEM            
4.1 Reduction Gas Circuit            
4.1.1 Top Gas Heat Recuperators PG 221- 2 H H - EC
C1/C2 (including one (1) steam drum

Annexure-1 ENGINEERING CONTRACT Page 15 of 30


ENGINEERING CONSULTANT SCOPE
PG 221-F with raisers and down
comers)
4.1.2 Process Gas Quench Orifice PG 211- 2 D D D EC EC EC
C1/C2
4.1.3 Process Gas Venturi PG 312-G1/G2 2 D D D EC EC EC
4.1.4 Process Gas Separator PG 313-F 1 D D D EC EC EC
4.1.5 Process Gas Quench Tower PG 231-E 1 D D D EC EC EC
4.1.6 Humidifier Water Pumps PG 631-J1/J4 4 D D EC EC EC EC
4.1.7 Process Gas K.O. Drum PG 416-F 1 D D D EC EC EC
4.1.8 Process Gas Compressor Filter PG 436- 3 D D EC EC EC EC
G1/G2/G3
4.1.9 Process Gas Compressors PG 436- 2 D D EC EC EC EC
J1/J2
Note: This will be handled as a package
system. Detail engineering for this will
be done by the Vendor except civil
which will be done by EC. Integration of
this with main plant will be done by EC.
Automation logic diagram including
surge control will be in the scope of
package vendor and integration with
main plant will be done by EC
4.1.10 Process Gas Compressor After cooler 1 D D D EC EC EC
PG 671-E
4.1.11 Process Gas Humidifier PG 622-E 1 D D D EC EC EC
4.1.12 Syn gas K.O. Drum RG 611-F 1 D D D EC EC EC
4.1.13 Sampling Bin Quench Orifice PG 256-C 1 D D D EC EC EC
4.1.14 Sampling Bin Venturi PG 257-G 1 D D D EC EC EC
4.1.15 Sampling Bin Separator PG 258-F 1 D D D EC EC EC
4.1.16 Dispersant Addition Unit PG 212-U 1 D D EC EC EC EC
4.1.17 Start-up Quench orifice PG 650-G 1 D D D EC EC EC
4.1.18 Start-up KO Drum PG 651-F 1 D D D EC EC EC
4.2 Process Gas Heater            
4.2.1 Process Gas Heater including Sulfur 1 D D EC/ EC EC EC
Addition System; V
Note: This will be handled as a package
system. Detail engineering for this will
be done by the Vendor except civil
which will be done by EC. Integration of

Annexure-1 ENGINEERING CONTRACT Page 16 of 30


ENGINEERING CONSULTANT SCOPE
this with main plant will be done by EC.
4.2.2 Structure, Piping & Ducting, E&I, 1 V V V EC V V
Refractory, within the package by
Vendor.
4.2.3 Automation logic diagram will be in the 1 V V V EC V/EC V/EC
scope of package vendor and
integration with main plant will be done
by EC
4.3 Partial Combustion System         EC    
4.3.1 Oxygen Injection System including 1 H H - EC EC EC
Lances (2) and valve stands. set
4.4 CO2 Removal System3            
4.4.1 CO2 Removal system; 1 D D EC/ EC EC EC
Note: This will be handled as a package V
system. Detail engineering for this will
be done by the Vendor except civil
which will be done by EC. Integration of
this with main plant will be done by EC.
4.4.2 Structure, Piping & Ducting, E&I, 1 V V V EC V V
insulation, within the package by
Vendor.
4.4.3 Automation logic diagram will be in the 1 V V V EC V/EC V/EC
scope of package vendor and
integration with main plant will be done
by EC
4.4.4 CO2 Absorber Column CO 323-E 1 D D V EC V/EC V/EC

4.4.5 Decarbonated Gas Washer CO 333-E 1 D D V EC V/EC V/EC


4.4.6 Gas Washing Water Pumps CO 331- 2 D D V EC V/EC V/EC
J1/J2
4.4.7 Stripper Column CO 324-E 1 D D V EC V/EC V/EC
4.4.8 Stripper Overhead Condenser CO 315- 1 D D V EC V/EC V/EC
C
4.4.9 Reflux K.O. Drum CO 313-F 1 D D V EC V/EC V/EC
4.4.10 Reflux Pumps CO 325-J1/J2 2 D D V EC V/EC V/EC
4.4.11 Incinerator CO 347-B 1 D D V EC V/EC V/EC
4.4.12 Re-boiler CO 316-C1/C2 2 D D V EC V/EC V/EC
4.4.13 Re-boiler Condensate Drum CO 335-F 1 D D V EC V/EC V/EC
4.4.14 Re-boiler Condensate Pumps CO 336- 2 D D V EC V/EC V/EC
J1/J2

Annexure-1 ENGINEERING CONTRACT Page 17 of 30


ENGINEERING CONSULTANT SCOPE
4.4.15 Rich/Lean Solution Heat Exchanger CO 2 D D V EC V/EC V/EC
314-C1/C2
4.4.16 Lean Solution Circulating Pumps CO 2 D D V EC V/EC V/EC
322-J1/J2
4.4.17 Lean Solution Heat Exchanger CO 320- 2 D D V EC V/EC V/EC
C1/C2
4.4.18 Centrifuge Filters CO 330-G1/G2 2 D D V EC V/EC V/EC
4.4.19 Mechanical Filter CO 327-G1/G2 2 D D V EC V/EC V/EC
4.4.20 Activated Carbon Filter CO 337-G 1 D D V EC V/EC V/EC
4.4.21 Carbon Traps CO 338-G 1 D D V EC V/EC V/EC
4.4.22 Solution Storage Tank CO 317-F 1 D D V EC V/EC V/EC
4.4.23 Storage Tank Pump CO 328-J 1 D D V EC V/EC V/EC
4.4.24 Solution Filter CO 340-G 1 D D V EC V/EC V/EC
4.4.25 Solution Preparation Tank CO 341-F 1 D D V EC V/EC V/EC
4.4.26 Solution Sump Pump CO 329-J 1 D D V EC V/EC V/EC
4.4.27 Make up Solution Filter CO 339-G 1 D D V EC V/EC V/EC
4.4.28 Antifoam metering system CO 346-L 1 D D V EC V/EC V/EC
4.4.29 Condensate Buffer Tank CO 336-F 1 D D V EC V/EC V/EC
4.4.30 De-super-heater CO 302-L 1 D D V EC V/EC V/EC
4.4.31 Hydro cyclone CO 321-G1/G2 2 D D V EC V/EC V/EC
4.4.32 Rich Solution Strainers CO 317-G1/G2 2 D D V EC V/EC V/EC
4.4.33 Lean Solution Strainers CO 318-G1/G2 2 D D V EC V/EC V/EC
4.4.34 Sewage Pump CO 342-J 1 D D V EC V/EC V/EC
4.4.35 Solution Charging Pump CO 343-J 1 D D V EC V/EC V/EC
4.5 Steam System      
4.5.1 Make up Condensate Cooler CO 336-C 1 D D EC EC EC EC
4.5.2 Make up Condensate Tank CO 349-F 1 D D EC EC EC EC
4.5.3 Make up Condensate Pumps CO 350- 2 D D EC EC EC EC
J1/J2
4.6 Cooling Gas Circuit            
4.6.1 Cooling Gas Quench Orifice CG 439-C 1 D D D EC EC EC
4.6.2 Cooling Gas Venturi CG 440-G 1 D D D EC EC EC
4.6.3 Cooling Gas Separator CG 442-F 1 D D D EC EC EC

Annexure-1 ENGINEERING CONTRACT Page 18 of 30


ENGINEERING CONSULTANT SCOPE
4.6.4 Cooling Gas Quench Tower CG 443-E 1 D D D EC EC EC
4.6.5 Cooling Gas Compressor K.O. Drum 1 D D D EC EC EC
CG 444-F
4.6.6 Filter CG 445-G1, G2 1 D D D EC EC EC
4.6.7 Cooling Gas Compressor CG 438-J 1 D D EC EC EC EC
Note: This will be handled as a package
system. Detail engineering for this will
be done by the Vendor except civil
which will be done by EC. Integration of
this with main plant will be done by EC.
Automation logic diagram including
surge control will be in the scope of
package vendor and integration with
main plant will be done by EC
4.6.8 Cooling Gas Compressor After cooler 1 D D D EC EC EC
CG 446-E
4.6.9 Dispersant Addition Unit CG 441-U 1 D D D EC EC EC
4.7 Flare System            
4.7.1 Flare PG 639-F 1 D D EC EC EC EC
4.7.2 Flare Seal Drum PG 640-F 1 D D EC EC EC EC
4.8 Nitrogen and Compressed Air            
System
4.8.1 Nitrogen Storage Tank UT 429-F 1 D D D EC EC EC
4.8.2 Seal Gas Storage Tanks UT 430- 3 D D D EC EC EC
F5/F6/F7
4.8.3 Instrument Air Storage Tank UT 454-F 1 D D D EC EC EC
4.9 COKE-OVEN GAS SYSTEM
4.9.1 Cleaning of COG ,pressure boosting & 1 H H H EC EC EC
Transport to DR-2 plant set

4.10 BOF GAS SYSTEM


4.10.1 Pressure boosting & Transport of BOF 1 H EC EC EC EC EC
to DR-2 plant. set

5. MECHANICAL EQUIPMENT –            
HYTEMP
5.1 Pneumatic Transport to Meltshop            
5.1.1 Manual Plug Valve RE 218-L 1 H H -- EC

Annexure-1 ENGINEERING CONTRACT Page 19 of 30


ENGINEERING CONSULTANT SCOPE
5.1.2 Expansion Joint RE 234-L 1 H H -- EC
5.1.3 Solids Cut-Off & Gas Seal Valve VS2 1 H H -- EC
PH 213-L11
5.1.4 Pneumatic Transport Tee PH 185-L11 1 H H -- EC
5.1.5 Pneumatic Transport Cross PH 183-L 1 H H -- EC
5.1.6 Expansion Joint PH 120-L11/L12 2 H H -- EC
5.1.7 Pneumatic Transport Cross PH 178- 2 H H -- EC
L11/L12
5.1.8 Manual Plug Valve PH 150-L1/L2 2 H H -- EC
5.1.9 Expansion Joint PH 122-L11/L16 6 H H -- EC
5.1.10 Expansion Joint PH 124-L11/L12/ 4 H H -- EC
L21/L22
5.1.11 Pneumatic Transport Cross PH 187- 2 H H -- EC
L1/L2
5.1.12 Expansion Joint PH 340-L11/L12 2 H H -- EC
5.1.13 Solids Cut-Off & Gas Seal Valve VS2 2 H H -- EC
PH 180-L1/L2
5.1.14 Pneumatic Transport Pipes 23 H H -- EC
0M
5.1.15 Fittings and Connecting Pieces 1 H H -- EC
Se
t
5.2 EAF #1 Charging System            
5.2.1 Pneumatic Transport Surge Bin PH 110- 1 D D D EC EC EC
F1
5.2.2 Solids Cut-Off and Gas Seal Valves 1 H H -- EC
VS2 PH 101-L1
5.2.3 Expansion Joint Pressurized PH 111-L1 1 H H -- EC
5.2.4 Pressurized Interface Bin PH 111-F1 1 D D D EC EC EC
5.2.5 Interface Bin PH 111-F1 1 H H -- EC
Pressurization/Depressurization valves SE
T
5.2.6 Solids Cut-Off and Gas Seal Valves 1 H H -- EC
VS2 PH 102-L1
5.2.7 Diverter Valve PH 104-L1 1 H H -- EC
5.2.8 Solids Cut-Off and Gas Seal Valves 2 H H -- EC
VS2 PH 106-L11/12
5.2.9 Expansion Joint Non Pressurized PH 2 H H -- EC

Annexure-1 ENGINEERING CONTRACT Page 20 of 30


ENGINEERING CONSULTANT SCOPE
105-L11/12
5.2.10 EAF Surge Bins PH 112-F11/F12 2 D D D EC EC EC
5.2.11 Manual Blocking Valves PH 110- 2 H H -- EC
L11/L12
5.2.12 Expansion Joint Non Pressurized PH 2 H H -- EC
107-L11/L12
5.2.13 Rotary Valve PH 176-L11/L12 2 H H -- EC
5.2.14 Solids Cut-Off and Gas Seal VS2 PH 2 H H -- EC
108-L11/L12
5.2.15 Expansion Joint Non Pressurized PH 2 H H -- EC
109-L11/L12
5.2.16 Receiving Hopper PH 114-F1 1 H H -- EC
5.2.17 Rotary Joint PH 126-L1 1 H H -- EC
5.2.18 Expansion Joint PH 131-L1 1 H H -- EC
5.2.19 Rotary Loading Chute PH 149-L1 1 H H -- EC
5.2.20 Fittings and Connecting Pieces 1 H H -- EC
Se
t
5.3 EAF #2 Charging System            
5.3.1 Pneumatic Transport Surge Bin PH 110- 1 D D D EC EC EC
F2
5.3.2 Solids Cut-Off and Gas Seal Valves 1 H H -- EC
VS2 PH 101-L2
5.3.3 Expansion Joint Pressurized PH 111-L2 1 H H -- EC
5.3.4 Pressurized Interface Bin PH 111-F2 1 D D D EC
5.3.5 Interface Bin PH 111-F2 1 H H -- EC
Pressurization/Depressurization valves set
5.3.6 Solids Cut-Off and Gas Seal Valves 1 H H -- EC
VS2 PH 102-L2
5.3.7 Diverter Valve PH 104-L2 1 H H -- EC
5.3.8 Solids Cut-Off and Gas Seal Valves 2 H H -- EC
VS2 PH 106-L21/L22
5.3.9 Expansion Joint Non Pressurized PH 2 H H -- EC
105-L21/L22
5.3.10 EAF Surge Bins PH 112-F21/F22 1 D D D EC EC EC
5.3.11 Manual Blocking Valves PH 110- 2 H H -- EC
L21/L22

Annexure-1 ENGINEERING CONTRACT Page 21 of 30


ENGINEERING CONSULTANT SCOPE
5.3.12 Expansion Joint Non Pressurized PH 2 H H -- EC
107-L21/L22
5.3.13 Rotary Valve PH 176-L21/L22 2 H H -- EC
5.3.14 Solids Cut-Off and Gas Seal VS2 PH 2 H H -- EC
108-L21/L22
5.3.15 Expansion Joint Non Pressurized PH 2 H H -- EC
109-L21/L22
5.3.16 Receiving Hopper PH 114-F2 1 H H -- EC
5.3.17 Rotary Joint PH 126-L2 1 H H -- EC
5.3.18 Expansion Joint PH 131-L2 1 H H -- EC
5.3.19 Rotary Loading Chute PH 149-L2 1 H H -- EC
5.3.20 Fittings and Connecting Pieces 1 H H -- EC
set
5.4 Pneumatic Transport Gas System            

5.4.1 PTS Quench Orifice PH 640-C1 1 D D D EC EC EC


5.4.2 PTS Venturi PH 642-G1 1 D D D EC EC EC
5.4.3 PTS Separator PH 641-F1 1 D D D EC EC EC
5.4.4 PTS Quench Orifice PH 640-C2 1 D D D EC EC EC
5.4.5 PTS Venturi PH 642-G2 1 D D D EC EC EC
5.4.6 PTS Separator PH 641-F2 1 D D D EC EC EC
5.4.7 PTS Quench Tower PH 643-E 1 D D D EC EC EC
5.4.8 PTS Water Cooler Pumps PH 643 J1/J2 2 D D EC EC EC EC
5.4.9 PTS K.O. Drum PH 646-F 1 D D D EC EC EC
5.4.10 PTS Gas Filter PH 645-G1/G2 2 D D EC EC EC EC
5.4.11 PTS Compressor PH 645-J 1 D D D EC EC EC
5.4.12 PTS Gas Heater PH 303-B 1 D D D EC EC EC
5.4.13 PTS Depressurizing Gas Quench Orifice 1 D D D EC EC EC
PH 648-C1
5.4.14 PTS Depressurizing Gas Venturi PH 1 D D D EC EC EC
649-G1
5.4.15 PTS Depressurizing Gas Stack PH 647- 1 D D D EC EC EC
F1
5.4.16 PTS Depressurizing Gas Quench Orifice 1 D D D EC EC EC
PH 648-C2
5.4.17 PTS Depressurizing Gas Venturi PH 1 D D D EC EC EC

Annexure-1 ENGINEERING CONTRACT Page 22 of 30


ENGINEERING CONSULTANT SCOPE
649-G2
5.4.18 PTS Depressurizing Gas Stack PH 647- 1 D D D EC EC EC
F2
5.4.19 Dispersant Addition System PH 651-U1 1 D D D EC EC EC
5.4.20 1.4.20 Dispersant Addition System PH 1 D D D EC EC EC
651-U2

NON-CORE PLANT AREA

6. NON-CORE PLANT AREA QTY BI BD DD RE ES CS

6.1 Water Treatment Plant (WTP) which 1 Set   D EC  E C EC EC E C
includes Clarifier, Cooling Towers,
and Pumping facilities.
6.1.1 DM Plant & Boiler 1 set   D E C EC  EC EC  EC 
6.2 Compressed Air Plant         EC    
6.2.1 Compressed Air Plant for Instrument 1 Set D D EC EC EC EC
and Service Air
6.3 Seal Gas System         EC    
6.3.1 Seal Gas Storage Tanks UT 431-F1h- 4 D D D EC EC EC
F4
6.4 Material Handling            
6.4.1 Iron Oxide Handling 1 Set D D EC EC EC EC
6.4.2 Coating Station Complete (excluding 1 H H -- EC EC EC
1.3 )
6.4.3 Bin, Piping & Structures for 1 H H H EC EC EC
Coating Station
6.4.4 Cold DRI Handling 1 Set D D EC EC EC EC
6.4.5 Bins with in Battery Limit 1 Set D EC EC EC EC EC
6.4.6 Dedusting within BL 1 Set D D EC EC EC EC
6.5 Syn Gas Turbo Expander
6.5.1 Syn Gas Turbo Expander; 1 D D EC/ EC EC EC
Note: This will be handled as a V
package system. Detail engineering
for this will be done by the Vendor
except civil which will be done by EC.
Integration of this with main plant will
be done by EC
6.5.2 Structure, Piping & Ducting, E&I, 1 V V V EC V V
insulation, within the package by
Vendor.
6.5.3 Automation logic diagram will be in the 1 V V V EC V/EC V/EC

Annexure-1 ENGINEERING CONTRACT Page 23 of 30


ENGINEERING CONSULTANT SCOPE
scope of package vendor and
integration with main plant will be done
by EC
6.6 Syn Gas Station            
6.6.1 Syn Gas Receiving Station 1 Set D D EC EC EC EC
6.6.2 Syn Gas Metering Station 1 Set D D EC EC EC EC
6.7 Heating, Ventilation and Air            
Conditioning (HVAC)
6.7.1 HVAC for DR Plant 1 Set D D EC EC EC EC
6.8 Fire Fighting System            
6.8.1 Firefighting System 1 Set D D EC EC EC EC

GENERAL FOR CORE & NON CORE AREA


  QTY BI BD DD RE ES CS

7. DRP – GENERAL            
7.1 Steel Structures            
7.1.1 Reactor Technological Tower Steel 1 D D D EC EC EC
Structure Set
7.1.2 Main Technological Pipe Rack inside 1 D D D EC EC EC
Technological Area Set
7.1.3 Heater Supporting Steel structures 1 D D EC EC EC EC
Set
7.2 Piping & Ducting            
7.2.1 Yard Piping (Type 1 Piping) 1 Set D D EC EC EC EC
7.2.2 Technological Rack Piping (Type 2 1 Set D D D EC EC EC
Piping)
7.2.3 On Field Piping Type 3 Piping 1 Set D D D EC EC EC
7.2.4 Packages Piping Type 4 Piping 1 Set D D EC EC EC EC
7.2.5 Technological Tower Piping Type 5 1 Set D D D EC EC EC
Piping
7.2.6 Process Ducts 1 Set D D D EC EC EC
7.3 Instrumentation            
7.3.1 Measuring Instrumentation for Core & 1 Set D D D EC EC EC
Non core area
7.3.2 Mass spectrometer 1 Set D D EC EC EC EC
7.4 Refractory & Insulation            

Annexure-1 ENGINEERING CONTRACT Page 24 of 30


ENGINEERING CONSULTANT SCOPE
7.4.1 Refractory for Reactor Vessel 1 Set D D D EC EC EC
7.4.2 Refractory for Bins and Cooler 1 Set D D D EC EC EC
7.4.3 Refractory for Ducts (including 1 Set D D D EC EC EC
Transfer Line from Heater)
7.4.4 Insulating Material 1 Set D D D EC EC EC
7.5 Lifting Devices            
7.5.1 Reducing Tower Elevator 1 Set D D EC EC EC EC

7.5.2 Maintenance Hoists 1 Set D D EC EC EC EC


7.6 Hydraulic System incl. Piping 1 Set D D - EC EC EC
7.7 Lubrication System incl. Piping 1 Set H H - EC EC EC
             
8. DRP – GENERAL HYTEMP SYSTEM            
8.1 Steel Structures            
8.1.1 HyTemp® Tower Steel Structure 2 Set D D D EC EC EC
8.1.2 Pneumatic Transport Bridge Steel 1 Set D D D EC EC EC
Structure
8.2 Piping, Ducts & Instrumentation            
8.2.1 Yard Piping (Type 1 Piping) 1 Set D D EC EC EC EC
8.2.2 Technological Rack Piping (Type 2 1 Set D D D EC EC EC
Piping)
8.2.3 On Field Piping Type 3 Piping 1 Set D D D EC EC EC
8.2.4 Packages Piping Type 4 Piping 1 Set D D EC EC EC EC
8.2.5 Technological Tower Piping Type 5 1 Set D D D EC EC EC
Piping
8.2.6 Process Ducts 1 Set D D D EC EC EC
8.3 Instrumentation relevant to            
HYTEMP
8.3.1 Measuring Instrumentation relevant to 1 Set D D D EC EC EC
HyTemp System
8.4 Refractory            
8.4.1 Refractory for Bins relevant to 1 Set D D D EC EC EC
HyTemp® System
8.4.2 Refractory for Ducts relevant to 1 Set D D D EC EC EC
HyTemp® System

Annexure-1 ENGINEERING CONTRACT Page 25 of 30


ENGINEERING CONSULTANT SCOPE
8.4.3 Insulating Material 1 Set D D D EC EC EC
8.5 Lifting Devices            
8.5.1 Maintenance Hoists relevant to 1 Set D D EC EC EC EC
HyTemp® System
8.5.2 HyTemp Tower Elevators 2 Set D D EC EC EC EC
8.6 Lubrication System relevant to 1 Set H H - EC EC EC
HyTemp® System
8.7 Hydraulic System relevant to 1 Set D D EC EC EC EC
HyTemp® System
9. CIVIL WORK            
9.1 Probing on Site            
9.1.1 Topographic Survey J J J J J J

9.1.2 Geotechnical Survey J J J J J J

9.2 Site Preparation            

9.2.1 Site Clearance & Leveling   J J J J J J 

9.2.2 Piling, if required   EC EC EC EC EC  EC

9.3 Civil Construction Works            

9.3.1 Foundations for structures and   D D EC EC EC  EC


equipments for Core specified in EC
Scope of Work
9.3.2 Foundations for structures and EC EC EC EC EC  EC
equipments for Non Core area
specified in EC Scope of Work
9.4 Civil Infrastructures inside BL            

9.4.1 Roads and Paved Areas   EC EC EC EC EC  EC

9.4.2 Storm water Drainage   EC EC EC EC EC  EC

9.4.3 Civil Works for Yard Lighting   EC EC EC EC EC  EC

9.5 Ancillary Buildings            

9.5.1 MCC & Control Room Building for DR   EC EC EC EC EC E C


Plant

GENERAL FOR CORE & NON CORE AREA


ELECTRICAL & AUTOMATION

10. AUTOMATION            

  QTY BI BD DD RE ES CS

Annexure-1 ENGINEERING CONTRACT Page 26 of 30


ENGINEERING CONSULTANT SCOPE
10.1 Software
10.1.1 Application Software for PLC for 1set D D D EC D/E D/EC
reduction tower C

10.1.2 Application Software for PLC for 1set D D D EC D/E D/EC


process gas treatment C

10.1.3 Application Software for PLC for 1set D D D EC D/E D/EC


safety interlocking (excluding C
packages)
10.1.4 Application Software for PLC for CO2 1set V V V EC V/E V/EC
system (Package) C

10.1.5 Application Software for PLC for fired 1set V V V EC V/E V/EC
Heater (Package) C

10.1.6 Application Software for PLC for 1set V V V EC V/E V/EC


compressor (Package) C

10.1.7 Application Software for PLC for WTP 1set EC EC EC EC EC EC

10.1.8 Application Software for Material 1set EC EC EC EC EC EC


handling
10.1.9 Application Software integration of 1set D/E D/E D/E EC EC EC
interface signals to/from PLCs of sub- C C C
suppliers packages, Material
Handling and WTP
10.2 Automation system            

10.2.1 Process Control System for Non-core - EC EC EC EC EC EC


Area
10.3 Operator Interface (HMI)            

10.3.1 Application Software for Scada 1SE D D D EC EC EC


server for OWS Operator Workstation T

10.3.2 Application Software for Operator 1 D D D EC EC EC


Interface (HMI) (Common for Danieli SET
and Packages Suppliers)
10.4 Equipment Control System            

10.4.1 PLC for reduction tower 1 D D EC EC EC EC

10.4.2 PLC for process gas treatment 1 D D EC EC EC EC

10.4.3 PLC for safety interlocking 1 D D EC EC EC EC

10.4.4 PLC for CO2 adsorber system 1 V V V EC EC/ EC/V


(Package) V

10.4.5 PLC for fired Heater (Package) 1 V V V EC EC/ EC/V


V
10.4.6 PLC for CO2 compressor (Package) 1 V V V EC EC/ EC/V
V

Annexure-1 ENGINEERING CONTRACT Page 27 of 30


ENGINEERING CONSULTANT SCOPE
10.4.7 PLC for WTP 1 EC EC EC EC EC EC

10.4.8 PLC for material handling 1 EC EC EC EC EC ECC

10.4.9 Equipment Control System 1set D D D EC D/E D/EC


provision of interface to Level 2 C

10.4.10 Main Control Desk 1 D D EC EC EC EC

10.4.11 Local Control Boxes (excluding 1set D D EC EC EC EC


packages)
10.4.12 Local Control Boxes (packages) 1set V V V EC EC/ EC/V
V
10.4.13 Local Area Network Components 1set D D J J J J

10.4.14 UPS unit 1 D D EC EC EC EC

10.5 Maintenance Equipment            

10.5.1 PLC programming unit 1 D D EC EC EC EC

10.5.2 Engineering workstation 1 D D EC EC EC EC

10.5.3 Historical Data Station 1 D D EC EC EC EC


           

11. ELECTRICAL EQUIPMENT            

11.1 MV switchboard with main motor 1set D D EC EC EC EC


starters
11.2 MV Starting Reactors 1set D D EC EC EC EC

11.3 PFC system 1set D D EC EC EC EC

11.4 Battery charger with batteries 110 V 1set D D EC EC EC EC

11.5 LV MCC for CORE Area 1set D D EC EC EC EC

11.6 LV MCC for Material Storage Area 1set D EC EC EC EC EC

11.7 LV MCC for WTP Area 1set D D EC EC EC EC

11.8 MV Motors 1set D D EC EC EC EC

11.9 MV Motors (supplied with 1set D D EC EC EC EC


mechanical package)
11.10 LV Motors 1set D D EC EC EC EC

11.10.1 Cables and installation material 1set D D EC EC EC EC


for the technological equipment
wiring for Core Area
11.10.2 Cables and installation material 1set D EC EC EC EC EC
for the technological equipment
wiring for WTP Area
11.10.3 Cables and installation material for 1set D EC EC EC EC EC

Annexure-1 ENGINEERING CONTRACT Page 28 of 30


ENGINEERING CONSULTANT SCOPE
the technological equipment wiring
for Material Handling Area
12. POWER DISTRIBUTION FOR DR            
PLANT
12.1 MV Power Distribution            

12.1.1 Safety disconnect switches with 1set D D EC EC EC EC


ground switch and manual operating
device
12.1.2 Transformers for the technological 1set D D EC EC EC EC
and auxiliary services LV power
supply
12.2 LV Power Distribution            

12.2.1 LV switch-gear 415 V for CORE area 1set D D EC EC EC EC


including:
•   Incoming line switches
•   Set of Outgoing switches (as
necessary)
•   LV Power Factor Compensation
(as necessary)
12.2.2 LV switch-gear 415 V for Diesel 1set D D EC EC EC EC
generator area including: Incoming
line switches Set of Outgoing
switches (as necessary)
12.2.3 Sub-distribution boards as necessary 1set D D EC EC EC EC

12.2.4 Cables and installation material for 1 D D EC EC EC EC


the power distribution equipment LOT
wiring for Core Area
12.2.5 Cables and installation material for 1 D EC EC EC EC EC
the power distribution equipment LOT
wiring for WTP Area
12.2.6 Cables and installation material for 1 D EC EC EC EC EC
the power distribution equipment LOT
wiring for Material Handling Area
13. AUXILIARY ELECTRICAL            
INSTALLATIONS EQUIPMENT AND
ENGINEERING
13.1.1 Emergency Diesel generator set 1 D D EC EC EC EC

13.1.2 Grounding network and lightning 1set D D EC EC EC EC


system
13.1.3 Intercom system 1 D D EC EC EC EC

13.1.4 Socket outlet system 1 D D EC EC EC EC

13.1.5 EOT cranes power supply feeding 1set D EC EC EC EC EC

Annexure-1 ENGINEERING CONTRACT Page 29 of 30


ENGINEERING CONSULTANT SCOPE
systems
13.1.6 Clock system 1 D D EC EC EC EC

13.1.7 CCTV system 1 D D EC EC EC EC

13.1.8 Telephone system 1 D D EC EC EC EC

13.1.9 Paging system 1 D D EC EC EC EC

13.1.10 Lighting system (technological 1set D D EC EC EC EC


areas, electrical cabins, workshop)
13.1.11 HVAC System 1set D D EC EC EC EC

13.1.12 Fire Detection and Alarm System 1set D D EC EC EC EC

14. AUXILIARY ELECTRICAL            


INSTALLATIONS EQUIPMENT AND
ENGINEERING, WTP AND
MATERIAL HANDLING
14.1.1 Fire Detection and Alarm System 1set D D EC EC EC EC

14.1.2 Grounding network and lightning 1set D EC EC EC EC EC


system
14.1.3 Intercom system 1 D EC EC EC EC EC

14.1.4 Socket outlet system 1 D EC EC EC EC EC

14.1.5 Clock system 1 D EC EC EC EC EC

14.1.6 Telephone system 1 D EC EC EC EC EC

14.1.7 Paging system 1 D EC EC EC EC EC

14.1.8 Lighting system Indoor, outdoor 1set D EC EC EC EC EC