You are on page 1of 2

ETIHAD TOWERS – Khalideyah Site Development

INSPECTION & TEST PLAN - REINFORCED CONCRETE WORKS (GENERIC)

CLIENT - SSPD PROJECT MANAGER : HILL INTERNATIONAL ITP REFERENCE NO.


Specification 3 Digit
DESIGN CONSUTANT -DBI SUPERVISION : CANSULT MAUNSELL AECOM Originator Code
No.
Discipline
Serial No.
Rev.

MAIN CONTRACTOR ARABIAN CONSTRUCTION COMPANY. 04 03300 S 001/ 0 0

INSPECTION AND
ITP RESPONSIBLE REFERENCE TYPE OF ACCEPTANCE VERIFYING TEST CODE
Clause DESCRIPTION OF ACTIVITY
No. PERSON DOCUMENT INSPECTION CRITERIA RECORDS SUBCO CANS
ACC
N. ULT

Approvals Required Prior to Concrete Works.

1 Drawings & Quality Documentation

Construction
Preparation of relevant drawings and Manager, Approved for construction All documents approved or
Method Statement,
method statement, Inspection and Engineering drawings/ Review of documents approved as noted.
1.1 drawings, HSE plan DS DS
Test Plan, HSE procedure. manager, QA/QC Project Specifications Comments – Incorporate
& ITP approval
Eng. Section 01001/26.5 (3) and Proceed with works
HSE officer

Approval for :
Project Manager,
1. Concrete supplier. All documents to be
QA/QC
2. Cut and bend reinforcement Project Specifications approved as noted. Prequalification
1.2 Engineer Review of documents DS DS
supplier. Comments – Incorporate documents.
(with supplier/
3. Third party materials testing and Proceed with works
subcontractor)
laboratory.
4. Subcontractor prequalification

LEGEND FOR INSPECTION AND TEST CODE


S = SURVEILLANCE H = HOLD POINT W = WITNESS POINT R = REVIEW DS = DOCUMENT SUBMITTAL

ET / ITP / 001 / 0 / REV 0 (CONCRETE – GENERIC) Page 1 of 2 FM E01 Rev. 0


INSPECTION AND
ITP RESPONSIBLE REFERENCE TYPE OF ACCEPTANCE VERIFYING TEST CODE
Clause DESCRIPTION OF ACTIVITY
No. PERSON DOCUMENT INSPECTION CRITERIA RECORDS SUBC CANS
ACC
ON. ULT.

Materials & Concrete mix


design to conform to
specifications and approved
by Engineer (Cement to BS-
Project Manager, 12, ASTM-150; Aggregates
Concrete mix design & material Project Specifications Material submittal.
1.3 QA/QC Engineer Review of documents. to BS 812,882 & table: 1,2 ; DS R
testing prior to production Section03300/ 3.2(3) (MIX DESIGN)
Concrete supplier. Water to BS 3148)
Conformity certificates for
admixtures and other
constituents shall be
submitted.
2 Materials and Testing

All Submittals to be
Project Specifications Review of documents & approved as noted. Product data through
2.1 Materials submittal and approval. Material Engineer DS DS
03300 Samples Comments – Incorporate submittal review
and Proceed with works

Trial mix is carried out &


hardened concrete tested as
Witness the trial & Approved material
Concrete trial mix and all concrete Supplier/ QA/QC Project Specifications per BS-1881for strength
Tests. submittal / tests
2.2 constituents, admixtures, curing Eng. / Material Section 03300/ 3.2(2,3,4,5 requirements result DS DS
Review of documents & reports of
materials, and repair materials. Engineer & 6) conforming to BS 5328
Samples. conformity.
part 4, and sulphate &
chloride contents.

Compliance with the


requirements of type II - BS
4449 for physical, chemical
Submission of steel reinforcement and Approved material
Project Specifications and mechanical properties.
accessories. (Spacers, Binding wire submittal
2.3 PM, Material Eng. Section 03200 Review of documents Tie wire shall be annealed DS DS
etc.) (sample mill
Section03300/3.1(4.2) steel wire 16 gauge
Stressing anchors certificates)
complying with BS-4449
Anchors as per approved
(ZETAS) design.
Attachments: i) Drg. Numbering System ii) Document Coding System iii) Sample of Submittal Form iv) Concrete Pour Card vi) WIR/Engineers Clearance Form vi) Cube Result Formats

Prepared by : ACC QA/QC ENGINEER Approved by : ACC CONSTRUCTION MANAGER Reviewed by : CANSULT LIMITED

LEGEND FOR INSPECTION AND TEST CODE


S = SURVEILLANCE H = HOLD POINT W = WITNESS POINT R = REVIEW DS = DOCUMENT SUBMITTAL

ET / ITP/ 001/ 0 / REV 0 (CONCRETE - GENERIC) Page 2 of 2 FM E01 Rev. 0