MAN- OCTOBER 2020 NOVEMBER 2020


WORK / ACTIVITIES RESPONSIBLE PERSON M T W T F S S M T W T F S S M T W T F S S M T W T F S M T W T F
DAYS
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12
A. APARTMENT BUILDING - OFFICER / ENLISTED
Architectural R. Colot / J. Duma 10
Structural To be Determined 10
Electrical G. Cuevas 10
Mechanical / Fire Protection R. Alo 9
Plumbing J. Carba 9
Cost Estimate F. Nulud 7

S. Zamora - Structural 7
L. Ramos - Electrical / Sanitary 8
CAD Works and Cost (As required
M. Mallare - Mechanical 5
by Engineers )
V. Lingat - Quantity ( if needed
by F. Nulud) 5

B. CLUB HOUSE
Architectural R. Colot / J. Duma 5
Structural To be Determined 7
Electrical G. Cuevas 5
Mechanical / Fire Protection R. Alo 4
Plumbing J. Carba 4
Cost Estimate F. Nulud 5

S. Zamora - Structural 5
L. Ramos - Electrical / Sanitary 4
CAD Works and Cost (As required
M. Mallare - Mechanical 3
by Engineers )
V. Lingat - Quantity ( if needed
by F. Nulud) 3