PROJECT DAILY MONITORING SHEET

Contractor: MECHATRENDS CONTRACTORS CORPORATION Date: 1 October ’21 # of Days:


Project : 2018 TK P1 RECONSTRUCTION Location: PSCPC TAGBILARAN BOHOL

Personnel Qty Equipment Qty Weather Chart


1 Chain block 2
Project In-charge Yellow – Sunny Red - Heavy Rain
2 Level block 2
Project Supervisor Orange - Light Rain Blue - Lightning storm
1 Sling 4
Safety Officer
QA/QC 1 Vertical clamps 2
Office Staff Shackles 4
Welder 3 Tape line 1
Electrician 1 Line yarn/guy line 2
Fitter/Fabricator 3 Welding machine 3
Carpenter / Mason Grinder 3
Scaffolder 2 Ball hammer 2
Equipment Tender 1 Erection jigs
Helper 1 Pulley 3
TOTAL 16 Nylon Rope

Activities
1.) Continuous Fabrication of Roof Frames (center ring hole drilling)
2.) Preparation for Pre-assemble of Roof Structures
3.) Continuous Fabrication of Cargo & Service Line
4.) Rail Post Cutting (14/14 )
5.)

Accomplishment
1.) Continuous Fabrication of Roof Frames (center ring hole drilling)
2.) Preparation for Pre-assemble of Roof Structures
3.) Continuous Fabrication of Cargo & Service Line
4.) Rail Post Cutting (14/14)
5.)

Remarks
1.) Continuous Fabrication of Roof Structures, and Other Tank Appurtenances- activity for tomorrow
2.) Continuous Fabrication of Cargo & Service Line- activity for tomorrow
3.)
Manpower List
Sn Name Designation Sn Name Designation
01 F. DOROMAL FOREMAN 10 A.ENRIQUEZ TENDER/RIGGER

02 M. DUMAHOD JR. FOREMAN 11 E. ORAPA HELPER

03 B. VILLAVER FITTER/FABRICATOR 12 S. ESPERAS SCAFFOLDER

04 M. MAGSAYO FITTER/SCAFFOLDER 13 J. GUINTO QA/QC

05 E. GELLADO FITTER/FABRICATOR 14 S. MAURICIO CEP

06 J.MABOLOC FITTER 15 C. BAGON SO3

07 J. PONTE WELDER 16

08 R. SALARDA WELDER 17

09 J. SALIBAY WELDER 18

Signatories Name Signature Date


Rhannie M. Garcia
Project Supervisor
Safety Officer
Chito Bagon (SO3) . 1 October 2021
1 October 2021
Ace Montehermoso
TPE