Professional Documents
Culture Documents
Erection Work
WP 6 Material Warehouse
2022.12.28
MS-IKM-CONS-WP6-001
1 KINE PROJECT JO
Material Warehouse Model And Weight Steel Structure
2 KINE PROJECT JO
Man Power And Equipment Plan
4 KINE PROJECT JO
Temporary Access
100cm
Access For
Worker
Access
For Crane
Access Access
For For
Crane Worker
5 KINE PROJECT JO
Protection Floor
12M
6M
6 KINE PROJECT JO
Stock Yard and temporary Plan Layout
To
04/ ilet
4m
01
She /2023
24m
Clear
04/ l
01/ ter
w 2
023 BEA ST
M, OCKY
6m RA AR
09/ FTER D:
Area
0 1/ , PU
202 RLI
3 N
6m
05/01/2023
m
R YA
12
N
CK
COL D:
UM
STO
09/ E-2
202 /
01
ZON
A
CKY
N
MATERIAL COL D:
UM
STO
R YA
09/ E-4
R
20 2 /
N
CK
01
ZON
3
COL D:
UM
Clear
STO
WAREHOUSE
09/ E-1
2 02 1 /
ZON
0
3
R YA
Area
N
CK
COL D:
UM
STO
09/ E-3
202 1/
ZON
3
0
05/01/2023
7 KINE PROJECT JO
Stock Yard and temporary Plan Layout
8 KINE PROJECT JO
Clear, Soil Compaction, and Back Filling Area
9 KINE PROJECT JO
Machine Equipment
Equipment
Aerial Work ( Bolting, Welding, Fin- For Material Unloading and Small
Part Unloading and Installation Work
ishing ) Transportation
10 KINE PROJECT JO
Specification Crane 60T
11 KINE PROJECT JO
Specification Crane 25T
12 KINE PROJECT JO
Specification Man Lift 227kg
13 KINE PROJECT JO
Lifting angle And Factor
X X X X X
Angle
Angle Weight T Changed Weight P Changed Angle Weight T Changed Weight P Changed
14 KINE PROJECT JO
Delivery Plant
1. Material Warehouse
10-01-2023
15 KINE PROJECT JO
Delivery Handling
Prohibition of carrying
commuting time Roadside
parking around the site, no
stopping Double-check sleeper
support and fastening before
departure Be careful not to
exceed the weight when loading
BH is stacked in 1 stage, other
parts are stacked in 2~3 stages
16 KINE PROJECT JO
Unloading Handling
17 KINE PROJECT JO
Stock Yard Handling
18 KINE PROJECT JO
Material Warehouse Squence
Start On Section A - B - C
Sum
Sec Desc Vol Start Finish
Vol
MATERIAL WAREHOUSE
40% Col- 11/01/2023 21/01/2023
umn
A 110T 110T 0 110T
40% Beam
Installation
40% Rafter 0% 48% A
Anchor Bolt B
Sum
Sec Desc Vol Start Finish
Vol C
22/01/2023 09/02/2023
Installation 80% Col-
umn
Column B
80% Beam
80T 190T 110T 190T
80% Rafter 48% 83%
Installation Sum
Sec Desc Vol Start Finish
Beam/Grid Vol
100% Col- 10/02/2023 18/02/2023
umn
C 38,7T 228,7T 190T 228,7T
Installation 100% Beam
100% Rafter
Rafter 83% 100%
Finish
19 KINE PROJECT JO
C2 B1 A2
C B A
C1 B2 A1
20 KINE PROJECT JO
Lifting Plan Material Warehouse
Range CRANE
25T 28M/0,95T
21 KINE PROJECT JO
Lifting Plan Material Warehouse
Toi
4m
let
S he
lte 24m
r
BE
6m AM STOC
, R KY
AF AR
TE D:
R,
PU
R LIN
5m
m
A CKY
CO RD:
M
12
STO
LU
N
N E-2
ZO
A KY
A KY
C
MATERIAL
CO RD:
M
STO
C
CO RD:
M
LU
STO
LU
E-4
N
E-1
WAREHOUSE
Re
N
ZO
N
ZO
m
A KY
ove
C
CO RD:
M
STO
LU
M
N
E-3
Wa
28
N
ZO
ll
22 KINE PROJECT JO
Padding grouting Design
23 KINE PROJECT JO
Padding grouting Design
24 KINE PROJECT JO
Padding grouting Erection
25 KINE PROJECT JO
Padding grouting Erection
Grouting Only
Baji Plate
26 KINE PROJECT JO
Padding grouting Erection
27 KINE PROJECT JO
Padding grouting Erection
28 KINE PROJECT JO
Padding grouting Erection
4 Non-shrink
Grouting
ERECTION LEVELLING
29 KINE PROJECT JO
Erection Squence Model
1 2
3 4
For Column Installation Picture Number 1 Need Sling 8mm 2 pcs/side tightened To side Pedestal Use
Wood Plank for Cover pedestal damaged by sling.
30 KINE PROJECT JO
Erection Squence Model
5 6 7
8 9 10
31 KINE PROJECT JO
Column Erection and Verticality
32 KINE PROJECT JO
Beam Erection and Horizontality
33 KINE PROJECT JO
Rafter, Purlin, and bracing Erection
34 KINE PROJECT JO
Tightening Bolt Method
Torque Wrench
1
12
7 6
3 9
10 8 4
5
11
2
Squence Torque
35 KINE PROJECT JO
Roof and Wall Installation
36 KINE PROJECT JO
Sandwich Panel Handling
37 KINE PROJECT JO
Erection Sandwich Panel Step Gutter Installation
38 KINE PROJECT JO
Step Flashing Installment and Mobilization Sandwich panel
39 KINE PROJECT JO
Step Installment and Screwd Sandwich Panel
40 KINE PROJECT JO
Step Joint Installment, Sealed, and Screwd Sandwich Panel
41 KINE PROJECT JO
Step Cleaning Sandwich Panel
42 KINE PROJECT JO
Step Installation Wall Sandwich Panel
43 KINE PROJECT JO
Installation Wall Panel
44 KINE PROJECT JO
Installation Wall Panel Cover, Sealed and Fixing Panel
45 KINE PROJECT JO
Joint Detail
46 KINE PROJECT JO
47 KINE PROJECT JO
48 KINE PROJECT JO
49 KINE PROJECT JO
Safety Management
FALL PROTEC-
TION
Life Line For
Conncecting FBH
50 KINE PROJECT JO
Thank You
51 KINE PROJECT JO