LINE PROJECT

Erection Work
WP 6 Material Warehouse
2022.12.28
MS-IKM-CONS-WP6-001

1 KINE PROJECT JO
Material Warehouse Model And Weight Steel Structure

2 KINE PROJECT JO
Man Power And Equipment Plan

Erection Work 1 Unit Crane


Operator =1
1 Team Person
1 Unit Crane 25 Rigger =2
1 Unit Telehandler or Forklift Person
1 Unit Telehandler / Forklift
Operator =1
2 Unit Man Lift Person
Rigger =1
Total 1 Team Person
1 Unit Man Lift
Operator = 4 Person Operator =1
Rigger = 3 Person Person
Erection Worker = 7 Person
Material Control = 2 Person
Welder = 1 Person
( Stand By )
Team 2 For Erection if needed at end of
January
Erection Worker = 7 Person
Welder = 1 Person
3 KINE PROJECT JO
Size Crane 25 T

4 KINE PROJECT JO
Temporary Access

Slope 17 Crane 30cm


Access

100cm

Access For
Worker

Access
For Crane

Access Access
For For
Crane Worker

Access Crane Use Sand compaction


Access Worker Use Scaffolding

5 KINE PROJECT JO
Protection Floor

Double Protection Carpet 0,8mm 12x6M


1. Not direct damaged the floor
2. Easy Disassemble protection Carpet
3. Can Following floor Texture

12M
6M

6 KINE PROJECT JO
Stock Yard and temporary Plan Layout

To
04/ ilet

4m
01
She /2023
24m
Clear
04/ l
01/ ter
w 2
023 BEA ST
M, OCKY
6m RA AR
09/ FTER D:

Area
0 1/ , PU
202 RLI
3 N

6m
05/01/2023

m
R YA

12
N
CK
COL D:
UM
STO

09/ E-2
202 /
01
ZON

A
CKY

N
MATERIAL COL D:
UM
STO
R YA

09/ E-4
R

20 2 /
N
CK

01
ZON

3
COL D:
UM

Clear
STO

WAREHOUSE
09/ E-1
2 02 1 /
ZON
0
3

R YA

Area
N
CK
COL D:
UM
STO

09/ E-3
202 1/
ZON

3
0

05/01/2023

7 KINE PROJECT JO
Stock Yard and temporary Plan Layout

8 KINE PROJECT JO
Clear, Soil Compaction, and Back Filling Area

9 KINE PROJECT JO
Machine Equipment

Equipment

Name RTC/Crane Boom Lift Telehandler


( Specification ) (60ton/25 Ton) (227kg/14,32M) (7ton/3ton)

Aerial Work ( Bolting, Welding, Fin- For Material Unloading and Small
Part Unloading and Installation Work
ishing ) Transportation

10 KINE PROJECT JO
Specification Crane 60T

11 KINE PROJECT JO
Specification Crane 25T

12 KINE PROJECT JO
Specification Man Lift 227kg

13 KINE PROJECT JO
Lifting angle And Factor

Lifting Lug And Wire

X X X X X

Angle
Angle Weight T Changed Weight P Changed Angle Weight T Changed Weight P Changed

14 KINE PROJECT JO
Delivery Plant
1. Material Warehouse
10-01-2023

1. Delivery Plant In Night 159 Km


2. Start From 7.00 PM
3. Time travel 12 Hours 35 min±
4. Arrived At Site 07.00 AM
5. Unloading Building Material Warehouse
6. Unloadng time Estimation 1 Day

15 KINE PROJECT JO
Delivery Handling

Prohibition of carrying
commuting time Roadside
parking around the site, no
stopping Double-check sleeper
support and fastening before
departure Be careful not to
exceed the weight when loading
BH is stacked in 1 stage, other
parts are stacked in 2~3 stages

16 KINE PROJECT JO
Unloading Handling

17 KINE PROJECT JO
Stock Yard Handling

18 KINE PROJECT JO
Material Warehouse Squence
Start On Section A - B - C
Sum
Sec Desc Vol Start Finish
Vol
MATERIAL WAREHOUSE
40% Col- 11/01/2023 21/01/2023
umn
A 110T 110T 0 110T
40% Beam

Installation
40% Rafter 0% 48% A
Anchor Bolt B
Sum
Sec Desc Vol Start Finish
Vol C
22/01/2023 09/02/2023
Installation 80% Col-
umn
Column B
80% Beam
80T 190T 110T 190T
80% Rafter 48% 83%

Installation Sum
Sec Desc Vol Start Finish
Beam/Grid Vol
100% Col- 10/02/2023 18/02/2023
umn
C 38,7T 228,7T 190T 228,7T
Installation 100% Beam
100% Rafter
Rafter 83% 100%

Finish

19 KINE PROJECT JO
C2 B1 A2
C B A
C1 B2 A1

20 KINE PROJECT JO
Lifting Plan Material Warehouse

Range CRANE
25T 28M/0,95T

21 KINE PROJECT JO
Lifting Plan Material Warehouse

Toi

4m
let
S he
lte 24m
r
BE
6m AM STOC
, R KY
AF AR
TE D:
R,
PU
R LIN

5m

m
A CKY
CO RD:
M

12
STO

LU
N

N E-2
ZO

A KY
A KY

C
MATERIAL
CO RD:
M
STO
C
CO RD:
M

LU
STO

LU

E-4
N

E-1

WAREHOUSE
Re
N
ZO
N
ZO

m
A KY

ove
C
CO RD:
M
STO

LU

M
N

E-3

Wa
28
N
ZO

ll

22 KINE PROJECT JO
Padding grouting Design

23 KINE PROJECT JO
Padding grouting Design

24 KINE PROJECT JO
Padding grouting Erection

25 KINE PROJECT JO
Padding grouting Erection

Grouting Only

Baji Plate

26 KINE PROJECT JO
Padding grouting Erection

27 KINE PROJECT JO
Padding grouting Erection

28 KINE PROJECT JO
Padding grouting Erection

4 Non-shrink
Grouting

ERECTION LEVELLING

29 KINE PROJECT JO
Erection Squence Model

1 2

3 4

For Column Installation Picture Number 1 Need Sling 8mm 2 pcs/side tightened To side Pedestal Use
Wood Plank for Cover pedestal damaged by sling.
30 KINE PROJECT JO
Erection Squence Model

5 6 7

8 9 10

31 KINE PROJECT JO
Column Erection and Verticality

For Installation Column Need To Check Verticality


before continue Installation Beam

32 KINE PROJECT JO
Beam Erection and Horizontality

For Installation Beam


Need To Check
Horizontality before
continue Installation
Rafter

Note : This Report also can use for Horizontality

33 KINE PROJECT JO
Rafter, Purlin, and bracing Erection

34 KINE PROJECT JO
Tightening Bolt Method

Torque Wrench

1
12
7 6
3 9
10 8 4
5
11
2

Squence Torque

Tabel Torque grade 10.9

35 KINE PROJECT JO
Roof and Wall Installation

Roof and Wall


Specification Volume (M2) Ratio Man Power
Composition
Inner layer ADH 7500

Glasswool Density 48kg/m3 1 Group


±1000 2 Day
( 10 Person )
Outer Layer ADH

36 KINE PROJECT JO
Sandwich Panel Handling

37 KINE PROJECT JO
Erection Sandwich Panel Step Gutter Installation

38 KINE PROJECT JO
Step Flashing Installment and Mobilization Sandwich panel

39 KINE PROJECT JO
Step Installment and Screwd Sandwich Panel

40 KINE PROJECT JO
Step Joint Installment, Sealed, and Screwd Sandwich Panel

41 KINE PROJECT JO
Step Cleaning Sandwich Panel

42 KINE PROJECT JO
Step Installation Wall Sandwich Panel

43 KINE PROJECT JO
Installation Wall Panel

44 KINE PROJECT JO
Installation Wall Panel Cover, Sealed and Fixing Panel

45 KINE PROJECT JO
Joint Detail

46 KINE PROJECT JO
47 KINE PROJECT JO
48 KINE PROJECT JO
49 KINE PROJECT JO
Safety Management

FALL PROTEC-
TION
Life Line For
Conncecting FBH

Safety Net ( Fall


Protection )

50 KINE PROJECT JO
Thank You