Professional Documents
Culture Documents
2024
S. N. Contractor/DTM Man Power Description of Work Block Section Location/KM Remarks
Switch rail loading work at AAL Yard AAL Yard Line No. 03 881/22-26 Loading = 05 Nos. (BT 13:05 - 13:35)
1 UTV M/C-035 8
Switch rail unloading work APR Yard APR Yard Line No. 07 Unloading work = 05 Nos. (BT 14:30- 15:00)
4 With UTV M/C for unloading of switch rail APR Yard Line No. 07 With UTV M/C for unloading of switch rail
2 DTM 01AK (i) Rail Renewal = 12.20 mtr.
1+7 Weld fracture rail renewal and welding work APR
APR-MZH, UP Line 868/15-17 (ii) Cutting = 03 Nos. (OC = 1, OT = 2)
Yard
3 MPG 4 (iii) Welding OT = 01 Nos.) (BT 10:55 - 12:20)
SEJ packing and with UTV M/C for switch loading & SEJ packing and with UTV M/C for switch loading &
4 DTM 02AK 6 AAL Yard Line No. 03 881/22-26
unloading work AAL & APR Ayrd unloading work AAL & APR Yard