Progress of Contractor/DTM work in the section of SSE/P.Way/APR - Date: 09.02.

2024
S. N. Contractor/DTM Man Power Description of Work Block Section Location/KM Remarks
Switch rail loading work at AAL Yard AAL Yard Line No. 03 881/22-26 Loading = 05 Nos. (BT 13:05 - 13:35)
1 UTV M/C-035 8
Switch rail unloading work APR Yard APR Yard Line No. 07 Unloading work = 05 Nos. (BT 14:30- 15:00)
4 With UTV M/C for unloading of switch rail APR Yard Line No. 07 With UTV M/C for unloading of switch rail
2 DTM 01AK (i) Rail Renewal = 12.20 mtr.
1+7 Weld fracture rail renewal and welding work APR
APR-MZH, UP Line 868/15-17 (ii) Cutting = 03 Nos. (OC = 1, OT = 2)
Yard
3 MPG 4 (iii) Welding OT = 01 Nos.) (BT 10:55 - 12:20)
SEJ packing and with UTV M/C for switch loading & SEJ packing and with UTV M/C for switch loading &
4 DTM 02AK 6 AAL Yard Line No. 03 881/22-26
unloading work AAL & APR Ayrd unloading work AAL & APR Yard

BUH Yard, UP, DN & (i) SEJ carry = 04 Nos.


5 DTM - 03AK 1+8 SEJ sleeper carry and X-ing carry work 891/17A-3A & 890/15-891/16
3rd Line (ii) CMS X-ing carry = 01 Nos.
(i) Rail renewal = 9.80 Mtr.
6 DTM -04AK 1+6 IMR rail renewal and welding work BUH,SNGP, DN Line 894/16-14 (ii) Cutting = 03 Nos. (OC = 01, OT = 02)
(iii) Welding OT = 02 Nos. (BT 12:55-14:25)
7 DTM - 05 AK 5 Sleeper carry and renewal work SNGP-SDL, UP Line 904/41-905/01 Sleeper carry & renewal = 03 Nos.
8 Cont. B.N. Mishra 3+38 Post tamping and dressing boxing work APR yard, Line No.01, 02 & 03 870/02-869/25 Progress slp = 1141 Nos.
Sri Kedar Nath Sahu JE/P.Way/APR Leave
Sri Lalan Kumar Sinha SSE/P.Way/Sect./AAL Attend toWeld fracture rail renewal and welding work APR Yard
Sri Vinay Kumar Sharma JE/P.Way/BUH Attend to UTV M/C - 035 for switch rail loading & unloading work at AAL & APR Yard
Sri Surendra Ram SSE/P.Way/Sect./SNGP Attend to IMR rail renewal and welding work at km 894/16-14 DN Line
Caution Order
Rail Temperature 08/28 (05:00 AM-13:00 PM) Rain Fall = 0 mm , Commulative = 700 mm
Items Scope Progress Cummulative Balance
OMS Peak Location
UP = 16, DN = 0, Total = 16 UP = 0, DN = 0 UP = 0, DN =0 UP = 16, DN = 0
Date:- 09.02.2024 UP Line