Column - Concrete (2nd to Foundation)

qty h A B Volume Excavation Total


C1 8 5.1 0.2 0.5 4.08 Concrete Total
C2 6 5.1 0.2 0.5 3.06 Rebar Total
C3 6 5.1 0.2 0.5 3.06 Form Total
C4 16 5.1 0.45 0.2 7.34
C5 4 5.1 0.45 0.2 1.84
C6 6 5.1 0.45 0.2 2.75
22.13
Column - Rebar (2nd to Foundation)
qty no. set dia. Cut Length Wt. @6m length
C1 8 8 1 20 6.000 947.00 64
C2 6 8 1 20 6.000 710.25 48
C3 6 8 1 20 6.000 710.25 48
C4 16 8 1 16 6.000 1212.16 128
C5 4 8 1 16 6.000 303.04 32
C6 6 8 1 16 6.000 454.56 48
Tie 1 20 22 2 10 1.440 781.28 220
Tie 2 20 22 2 10 0.840 455.74 126
Tie 3 26 22 2 10 1.340 945.13 286
Tie 4 26 22 2 10 0.775 546.62 164
7066.04
Column - Concrete Forming (2nd to Foundation)
qty h A B SA
C1 8 5.1 0.2 0.5 57.12
C2 6 5.1 0.2 0.5 42.84
C3 6 5.1 0.2 0.5 42.84
C4 16 5.1 0.45 0.2 106.08
C5 4 5.1 0.45 0.2 26.52
C6 6 5.1 0.45 0.2 39.78
315.18
Column - Concrete (3rd to 2nd)
qty h A B Volume
C1 8 3.05 0.2 0.4 1.95
C2 6 3.05 0.2 0.4 1.46
C3 6 3.05 0.2 0.4 1.46
C4 16 3.05 0.45 0.2 4.39
C5 4 3.05 0.45 0.2 1.10
C6 6 3.05 0.45 0.2 1.65
12.02
Column - Rebar (3rd to 2nd)
qty no. set dia. Cut Length Wt. @6m length
C1 8 8 1 20 3.730 588.72 64 2.270 145.28
C2 6 8 1 20 3.730 441.54 48 2.270 108.96
C3 6 8 1 16 3.590 271.98 48 2.410 115.68
C4 16 8 1 16 3.590 725.28 128 2.410 308.48
C5 4 8 1 16 3.590 181.32 32 2.410 77.12
C6 6 8 1 16 3.590 271.98 48 2.410 115.68
Tie 1 20 22 2 10 1.240 672.77 220
Tie 2 20 22 2 10 0.760 412.34 126
Tie 3 26 22 2 10 1.340 945.13 286
Tie 4 26 22 2 10 0.775 546.62 164
5057.67
Column - Concrete Forming (2nd to Foundation)
qty h A B SA
C1 8 3.05 0.2 0.5 34.16
C2 6 3.05 0.2 0.5 25.62
C3 6 3.05 0.2 0.5 25.62
C4 16 3.05 0.45 0.2 63.44
C5 4 3.05 0.45 0.2 15.86
C6 6 3.05 0.45 0.2 23.79
188.49
Column - Concrete (Roof to 3rd)
qty h A B Volume
C1 8 3.05 0.2 0.4 1.95
C2 6 3.05 0.2 0.4 1.46
C3 6 3.05 0.2 0.4 1.46
C4 16 3.05 0.4 0.2 3.90
C5 4 3.05 0.4 0.2 0.98
C6 6 3.05 0.4 0.2 1.46
11.22
Column - Rebar (Roof to 3rd)
qty no. set dia. Cut Length Wt. @6m length
C1 8 8 1 16 3.450 348.50 64
C2 6 8 1 16 3.450 261.37 48
C3 6 8 1 16 3.450 261.37 48
C4 16 8 1 16 3.450 696.99 128
C5 4 8 1 16 3.450 174.25 32
C6 6 8 1 16 3.450 261.37 48
Tie 1 14 22 2 10 1.240 470.94 77
Tie 2 14 22 2 10 0.760 288.64 44
Tie 3 32 22 2 10 1.240 1076.43 176
Tie 4 32 22 2 10 0.390 338.55 47
4178.41
Column - Concrete Forming (2nd to Foundation)
qty h A B SA
C1 8 3.05 0.2 0.5 34.16
C2 6 3.05 0.2 0.5 25.62
C3 6 3.05 0.2 0.5 25.62
C4 16 3.05 0.45 0.2 63.44
C5 4 3.05 0.45 0.2 15.86
C6 6 3.05 0.45 0.2 23.79
188.49
0.00 m3
45.38 m3 0.1
16302.12 kg 0.1
692.16 m2 0.1
0.09
0.09
0.09

1.24 0.133333
0.76