APPROVAL OF REVISED DETAILED ARCHITECTURAL AND ENGINEERING DESIGN

(RDAED) PLANS (PARTIAL REVISION OF DAED)

HCC DPWH SCT


START
thru SCT
DPWH-UPMO
HCC/Aidea/AECOM BSPMC-NSBP
Architectural Section

Design Coordination Meetings (DCM)


Phase 1: Upon receipt of initial instruction to revise approved DAED, HCC will prepare sketches, submit, the parties will coordinate & DPWH will issue
clarification on the desired changes by Senate thru SCT
(60 calendar days)

Prepare and print RDAED


Issue instruction to print Instruct to
1. Architectural and interior RDAED for approval print RDAED Yes OK?
Design to coordinate with HCC for Approval
consultants on possible
impact/implication of RPAED
base plans
No
2. Workshop
3. Consultants to provide RDAED
(60 calendar days)

Submit RDAED DPWH-BSPMC


Review and Endorse Phase 2: HCC will prepare
revised sketches, resubmit,
the parties will coordinate
Bureau of Design
& DPWH will issue
Recommend Approval
clarification changes by
SCT.

No OK?
Appropriate Action

Yes

USEC for Technical Services


Approve

END DPWH-BSPMC-UPMO
Forward RDAED for Concurrence For Signature
by Senate

1.Furnish copies of
approved RDAED to Issue approved RDAED with
DPWH and Senate Forward RDAED with
concurrence by Senate and for
thru SCT concurrence by Senate
implementation; submission and
2.Implement
approval of cost prior to
approved RDAED
implementation