ACI CEPHALOSPORIN PROJECT

Technical Discussion

Not
Sl. No Description Work Details Include
Include
Earth work in excavation in foundation trenches or drains including
dressing of sides and ramming of bottom including getting out the
excavated earth & refilling the earth supplied in foundation plinth and
under floor in layers not exceeding 60cm in thickness before 1. Earth cutting and filling to located site.
compaction and 40 cm after compaction consolidating each deposited
layer by ramming and watering .This is based on assumption that full
01
plinth area will be excavated for 2.0m since this is loose soil.

Backfilling of approved earth obtained as per site conditions or as


directed by site in charge for all depth and height (payment shall be
02 1. Back Filling to located site.
made for solid measurement of filling) - Workmanship only

1. We fill the rubbish to movement the 50 ton crane its


need to cut for to do macadam.
2. After cutting rubbish it need to stack nearby place for
Providing & laying 200mm thick (compacted) hard core stone soling as future macadam work.
per locally available stone size, including watering, ramming, rolling in 3. Earth cutting if required.
layers, binding with cement mortar 1:6 / locally available soil with 4. Back filling if required.
03
binding properties, including cost of all labour, material complete as
per specification and as directed by Consultant. - Workmanship only 5. Bed compaction by 10 tons soil compactor.
6. Water bound macadam required compaction by 10
tons roller.

7. Necessary pipe line need to complete before macadam.

1. Leveling and dressing if required.


Providing and laying plain cement concrete 1:4:8( 1 cement ,4 coarse
sand, 8 graded stone aggregate 40mm nominal size) under Pile caps, 2. Laying Polythine sheet.
under plinth beam, under cable / pipe trench and equipment 3. Maintain the required mixing ratio.
04
foundations including necessary formwork as per dwg and as 4. Curing as required.
directed by Consultant
5. All Materials caring for materials yard.
ACI CEPHALOSPORIN PROJECT
Technical Discussion
1. Chipping and clean the RCC Surface.
2. Maintain ratio, level (By Level Machine), Finishing
strictly.
3. On top of patent stone finishing will be as like plaster
Up to 50mm thick patent stone flooring including Plaster finishing,
finishing.
05 curing etc. All complete as per direction of the Engineer-in-charge.
4. Curing as required.
5. Must clean the casting spot of all steel member.
6. All construction materials shall be properly washed &
need to sieving if necessary.
7. All Materials caring for materials yard.
1. All types of leakage need to sill.
2. All types of casting equipment (Concrete vibrator,
Double hopper Mixer Machine, Pump for water etc.
Need to check previous day of casting.
3. Clean and wash the surface of decking sheet.
4. All construction materials shall be properly washed &
Providing & laying reinforced cement concrete work in col pedestal, need to sieving if necessary.
plinth beam, pile cap, RCC wall, Ramp and mass concrete excluding 5. Proper ratio maintain strictly and two supervisor
06 the cost of centering, shuttering & reinforcement, as per drawing and attend with the mixer machine to maintain the ratio.
directed by Consultant. 6. 4 sets of concrete cylinder must be made by the
contractor for each day of casting. (10 sets of concert
cylinder must test from BUET by own cost of vendor)
7. Slump test also arrange by the contractor.
8. Curing as required.
9. Must clean the casting spot of all Steel members.

10. All materials caring for materials yard.


1. All wooden shutter must be new.
Centering and shuttering including strutting, propping etc. and
removal of form for col pedestal, plinth beam, Slab, RCC wall, Road 2. For second time use wooden shutter clean properly.
07
etc. and mass concrete.
3. In between gap of shutter Rubban Sheet use every
time.
ACI CEPHALOSPORIN PROJECT
Technical Discussion

4. Proper support need to ensure before casting.

Reinforcement for RCC work including supplying bending, binding & 1. Old rod need to clean by steel brush.
placing position complete by using annealed binding wire f 18 gauge 2. As per drawing proper spacing maintain by vendor.
08
etc. and as directed by Consultant.
3. Good quality GI wire use for rod binding.
Brick work with bricks class designation 65 in foundation and plinth in 1. Proper curing & clean the Brick.
09 cement mortar(1:4) below grade slab 2. And necessary precaution should take for start the
Brick work.
Minimum 12mm thick cement plaster (1:5) to wall both inner and 1. Proper curing & clean the surface area.
outer surface, finishing the corner and edges including of sand
10 2. And necessary precaution should take for start the
cleaning the surface, curing etc. all complete as per direction of the
plaster work.
Engineer-in-charge.
1. AS Per previous work in our site.
Unipaver Block fitting work all complete as per direction of the 2. Insure the proper compaction of soil.
11
Engineer-in-charge.
3. Insure any type of leakage not found in drain pit.
RCC Braking work all complete as per direction of the 1. After braking the RCC all debris shifting to as per our
12
Engineer-in-charge. selected area.

Terms and Conditions for work. (As per BOQ)


1. Contactor shall complete the work as per agreed Time line in provide gantt chart. (Gantt chart must provide with this document)
2. Contactor will arrange labor shed and site office at a fixed space shown by AHL.
3. Contactor will arrange own power source throughout the work period.
4. Contactor shall ensure quality of work by stringent monitoring and using necessary equipment.
5. All construction materials shall be properly washed/ sorted prior to manual mixing.
6. Contractor shall arrange 4 set of concrete cylinder at site for testing of compressive strength of concrete.
7. Contractor shall use standard measuring container (Fera) and double hopper machine for mixing the concrete.
8. Proper curing must be ensure by the contactor as per instruction of engineer in charge.
9. All vertical shutter shall be keep for at last 72 hours.
10. All side shutter shall be keep for at last 48 hours.
11. Timber shutter with polythene, GP sheet and associated materials. (All new)
ACI CEPHALOSPORIN PROJECT
Technical Discussion
12. Equipment such as mixer machine, vibrator machine, high speed cutter machine, welding machine, curing accessories of necessary quantity shall be deployed by
contractor. (Own Equipment list must provide to AHL)
13. Contractor will appoint qualified and experienced engineers (At last 10 years) along with a site in charge during the job. The site in charge shall take care of all safety
issues.
14. Contactor shall ensure that all of its personal ware Clean uniform (With ID card) throughout the work period. (Copy of National ID card should provide for permanent
staff)
15. All the accidents and incidents related to the aforesaid work is under contractor responsibility.
16. All works to be completed as per drawing and direction from engineering department.
17. Contractor will clean all debris, rubbish and sludge from the site after the finishing work.
18. Contractor will clean all concrete spot from Steel member after finishing the casting.
19. Day wise progress report must submit after finishing the work.

# Years of experience.
# Number of Project Completed. (Provide copy of work order)
# Financial condition. (Contractor can submit 2 running bill and a final bill)

Note: Drawing and decision may change on basis of project demand.