The document provides instructions for grouting and leveling a baseplate after installation. Any wedges used to level the baseplate should be removed and their voids filled with putty. The baseplate should be checked for voids, which should then be drilled and filled with grease to prevent lifting. Finally, all edges of the epoxy grout should be smoothed with sanding.
The document provides instructions for grouting and leveling a baseplate after installation. Any wedges used to level the baseplate should be removed and their voids filled with putty. The baseplate should be checked for voids, which should then be drilled and filled with grease to prevent lifting. Finally, all edges of the epoxy grout should be smoothed with sanding.
The document provides instructions for grouting and leveling a baseplate after installation. Any wedges used to level the baseplate should be removed and their voids filled with putty. The baseplate should be checked for voids, which should then be drilled and filled with grease to prevent lifting. Finally, all edges of the epoxy grout should be smoothed with sanding.
4. I F WEDGES WERE USED TO L E V E L THE BASEPLATE, THEY
SHALL BE REMOVED AT T H I S T I M E AND T H E I R VOIDS I N THE GROUT F I L L E D WITH ESCOWELD7501 PUTTY. SHIMS SHALL BE L E F T I N PLACE.
5. THE TOP OF THE B A S E P L A T E SHALL B E SOUNDED FOR VOIDS.
AFTER ALL THE V O I D S HAVE BEEN D E F I N E D THE BASEPLATE SHALL HAVE TWO HOLES D R I L L E D THROUGH TO EACH V O I D I N OPPOSITE CORNERS OF THE VOIDS. ONE OF THE P A I R OF HOLES SHALL BE TAPPED AND F I T T E D W I T H A PRESSURE GREASE FITTING. THE OTHER HOLD SHALL BE USED A S A VENT HOLE FOR I T S V O I D . THE V O I D SHALL BE F I L L E D WITH U N F I L L E D ESCOWELD7505 WITH A HAND GREASE GUN. CARE MUST B E TAKEN TO PREVENT L I F T I N G THE BASEPLATE SHOULD A BLOCK- AGE OCCUR BETWEEN THE GREASE F I T T I N G AND THE VENT. WHEN THE V O I D HAS BEEN F I L L E D THE GREASE F I T T I N G SHALL B E REMOVED AND BOTH HOLES DRESSED SMOOTH.
6. ALL EDGES OF THE EPOXY GROUT SHALL BE DRESSED SMOOTH
BY G R I N D I N G TO A 114 I N C H CHAMFER,
IX. CLEAN-UP
1, IMMEDIATELY AFTER GROUTING I S COMPLETED ALL TOOLS AND
M I X I N G EQUIPMENT SHALL BE CLEANED U S I N G EITHER WATER OR ESCOWELD9615 CLEAN-UP SOLVENT.
2. ALL UNUSED M I X E D EPOXY MATERIALS SHALL BE DISPOSED
OF I N ACCORDANCE WITH INSTRUCTIONS ON THE EPOXY CONTAINERS.