REVISION NO : 00

REVISION DATE : Sept. 27, 2018

INTEGRATIVE COURSE PROGRESS REPORT

COURSE: CHE CAPSTONE PROJECT 1 COURSE CODE: CHE200D-1 SECTION: A03 SY/TERM: 2019 -2020 /2ND TERM

TITLE OF RESEARCH PROJECT: FEASIBILITY STUDY OF PRODUCTION OF R-134A BY VAPOUR PHASE GROUP CODE:
FLUORINATION 2019CHE020

INTEGRATIVE COURSES THESIS PHASE

THESIS
PLANT DESIGN PROPOSAL DEFENSE FINAL DEFENSE
CAPSTONE PROJECT `
BUSINESS PLAN DATA GATHERING
FEASIBILITY STUDY

Name of Students
Student No. Program of Study Signature
(SURNAME, GIVEN NAME MI.)

HEROMIANO, KATE DREW G. 2014101913 CHEMICAL ENGINEERING

PABALAN, FRANCIS AERON R. 2012102620 CHEMICAL ENGINEERING

SALAMAT, AVA JOBELLE A. 2015105620 CHEMICAL ENGINEERING

DESCRIPTION OF WORK DONE FOR THE TIME PERIOD


(Use back page or additional sheets if necessary)

WEEK #: 10 COVERED DATE: FEB 3-9, 2020

In the tenth week of the project, the group finalized all the missing parts of the four chapters of the plant

design project. For the chapter 1, addition of some related literatures and data sheets were made. For the second

chapter, the group finalized the criteria for plant location selection and other minor parts of the chapter. The third

chapter tables and equations at the fourth chapter were finalized in preparation for the proposal defense on the

following weeks.

To be filled up by adviser.
Endorsed by: Preferred Schedule:
Ready for Oral Defense

ATTESTED BY NOTED BY

ADVISER COURSE COORDINATOR


Signature over printed name / Date Signature over printed name / Date

Copies : (1) Student (2) Adviser (3) Course Coordinator OVPAA-039-09


This form is available at the Office of Vice President for Academic Affairs