Factory Acceptance Test Protocol

(FAT)

Project Name
Project Workorder
Customer
Customers Address
Quotation No
Customer PO No
Date of Order
Machine type
Machine Code
Quotation No
Layout
Schematics
Pneumatic Diagram
Specification Sheet
Electrical Diagram
Factory Acceptance Test Protocol (FAT)

Contents
1. Inspection Equipment used..........................................................................................2

2. Completion of scope of delivery...................................................................................3

3. General Checkpoints....................................................................................................3

4. General functional test.................................................................................................5

5. General process test..................................................................................................10

6. Safety devices............................................................................................................13

7. Machine asethetics and egronomics.........................................................................15

8. Machine Labeling.......................................................................................................16

9. Software and Control.................................................................................................17

10. Accessories / Baskets................................................................................................19

11. Documentation...........................................................................................................19

12. Delivery / Commissioning / Consumables.................................................................21

13. Trainings / Instructions...............................................................................................22

14. Work still to be accomplished / Open Points List (OPL)............................................23

15. Scheduling / Next steps.............................................................................................25

16. Remarks.....................................................................................................................26

Page 2 of 29
Factory Acceptance Test Protocol (FAT)

Y = Passed / N = Not passed / NA = Not applicable

1. Inspection Equipment used


During the FAT-acceptance test, the following inspection equipments have been used:

Type of the inspection


equipment Type / Supplier Comment
( inspection equipment)

Decibel meter PROSKIT

Multimeter
HANNA
Thermometer
INSTRUMENT
Stop watch N/A

Pressure measuring device JKS

Vacuum measuring unit N/A


Conductivity/Resistivity/pH
MYRON L
measuring unit
Tape measure Stanley
Ultrasonic Meter
Ultrasonic Meter
Online
Electrostatic Meter Field SIMCVO
PROVA
Air Flow Meter
INSTURMENT
Endoscope ADRONIC

Page 3 of 29
Factory Acceptance Test Protocol (FAT)

2. Completion of scope of delivery


Checkpoint Y N

Does the machine scope as per describe in quotation?


2.1
Remarks:
Is all accessories for the project present and completed as per
quotation (Example, basket or other supporting equipment,
2.2 such as DI systems, Chillers)

Remarks:

3. General Checkpoints
Checkpoint Y N NA

Do the machine dimensions and / or the installation


dimensions correspond to the signed layout?
3.1
Remarks:
Are the exhaust outlet location executed as per layout?
3.2
Remarks:
Are the piping inlet/outlet location and port sizes executed as
per layout?
3.3

Remarks:
Are piping executed as per schematics? Size of pipeline etc.
etc.
3.4
Remarks
Are all instrumentations and equipment present as per
schematics?
3.5

Remarks

Page 4 of 29
Factory Acceptance Test Protocol (FAT)

Visual check for potential leaks (any leaks in the tubings,


pipings or tank)?
3.6

Remarks:
Are pneumatic systems executed as per pneumatic diagram?
3.7
Remarks:
Does the specification of instrumentation and equipment as
per specification sheet?
3.8
Remarks:
Does the accessibility for maintenance is by acceptable
standard?
3.9

Remarks:

Page 5 of 29
Factory Acceptance Test Protocol (FAT)

4. General functional test


Functional test for robotic arm
Checkpoint Y N NA

Is robotic arm vertical and horizontal movements smooth


without unusual noises and vibration?
4.1
Remarks:
Robotic arm vertical and horizontal movements max speed?
Horizontal :
4.2 Vertical :

Remarks:
Robotic arm vertical and horizontal sensors in correct position
and quantity?
4.3

Remarks:
Robotic arm vertical and horizontal safety sensors functioning
and tested?
Top Overtravel :
Btm Overtravel :
Left Overtravel :
4.4
Right Overtravel :
Mishook :
Crash :

Remarks:
Robotic arm tested with rated basket load?
Please simulate robotic arm movement with rated load
4.5

Remarks:
Robotic arm movement speed profiles tested and checked?
4.6
Remarks:

Page 6 of 29
Factory Acceptance Test Protocol (FAT)

Robotic arm pick up and put down for each STN tested and
with safety tolerance?

Loading :
STN 1 :
STN 2 :
STN 3 :
4.7 STN 4 :
STN 5 :
STN 6 :
STN 7 :
STN 8 :
Unloading :

Remarks:

Functional test for agitation mechanism


Checkpoint Y N NA

Is the agitation movements smooth without unusual noises


and vibration?
4.8

Remarks:
Agitation movements speed?
Times/min :
4.9

Remarks:
Agitation height?
Height:
4.10

Remarks:

Page 7 of 29
Factory Acceptance Test Protocol (FAT)

Functional test for liftout mechanism


Checkpoint Y N NA

Is the liftout movements smooth without unusual noises and


vibration?
4.11

Remarks:
Liftout min and maxspeed?
Min :
4.12 Max :

Remarks:
Liftout mechanism safety sensors functioning and tested?
Top Overtravel :
4.13 Btm Overtravel :

Remarks:

Functional test for loading/unloading conveyor


Checkpoint Y N NA

Is the loading/unloading conveyor movements smooth without


unsual noises and vibration?
4.14

Remarks:
Loading / unloading movement speed?
Speed :
4.15

Remarks:
Loading/Unloading conveyor tested with full load?
4.16
Remarks:

Page 8 of 29
Factory Acceptance Test Protocol (FAT)

Loading/Unloading conveyor interface with Robotic arm


tested?
Loading/Robotic arm interface :
4.17
Robotic arm/Unloading interface :

Remarks:
Loading/Unloading conveyor basket pitching adjustment
done?
4.18

Remarks:

Functional test for basket IN/OUT mechanism


Checkpoint Y N NA

Is the basket IN/OUT mechanism movements smooth without


unusual noises and vibration?
4.19
Remarks:
Basket IN/OUT movement speed?
Speed :
4.20

Remarks:
Basket IN/OUT tested with full load?
4.21
Remarks:

Page 9 of 29
Factory Acceptance Test Protocol (FAT)

Functional test for shutter door mechanism


Checkpoint Y N NA

Is the shutter door mechanism movements smooth without


unusual noises and vibration?
STN 1 :
STN 2 :
STN 3 :
4.23
STN 7 :
STN 8 :

Remarks:
Shutter door movement speed?
STN 1 Speed :
4.24

Remarks:
Can the shutter door close the tank fully?
STN 1 :
STN 2 :
STN 3 :
4.25
STN 7 :
STN 8 :

Remarks:

Functional test for conveyor system


Checkpoint Y N NA

Does the conveyor mesh size and type as per quotation?


4.26
Remarks:
Does the part fit into the conveyor mesh?
4.27
Remarks:

Page 10 of 29
Factory Acceptance Test Protocol (FAT)

Does the conveyor speed range as per quotation?


Please record down Min and Max speed.
Please check actual with measuring tape

4.28
Max speed: /
Min Speed: /

Remarks:
Does all parts go through all conveyor station without any
collision?
4.29

Remarks:
Does the anti-jam sensor work?
4.30
Remarks:
Does the Torque limiter properly adjusted?
Please test by using stopping the conveyvor mesh by hand to
4.31 check if the torque limiter disengaged properlu.

Remarks:

5. General process test


Checkpoint Y N NA

Page 11 of 29
Factory Acceptance Test Protocol (FAT)

Is the Heat up time and max achievable temperature for each


station (incl. air blow and dryer STN) according to
specification?
STN 1 : / /
STN 2 : / /
STN 3 : / /
5.1 STN 4 : / /
STN 5 : / /
STN 6 : / /
STN 7 : / /
STN 8 : / /

Please fill up initial temp(°C) / max temp(°C / time(s)


Is the Recirculation / Spray pressure for each station
according to specification? If applicable
STN 1 :
STN 2 :
STN 3 :
5.2
STN 4 :
STN 5 :
STN 6 :

Please fill up operating pressure(bar)


Is the Max vacuum level for each station according to
specification? If applicable
5.3

Please fill up operating vacuum level(kPA)

Page 12 of 29
Factory Acceptance Test Protocol (FAT)

Is the Conductivity/Resistivity/pH sensor each station


calibrated according to specification? If applicable
STN 1 :
STN 2 :
5.4
STN 6 :
STN 6 :

Please compare handheld value with machine value.


Is the Ultrasonic for each station functioning and according to
specification? If applicable
STN 1 :
5.5 STN 2 :
STN 4 :

Please fill up measured kHZ and mV


Is the Bubbling feature for each station functioning and
according to specification? If applicable

STN 4 :
5.6
STN 5 :
STN 6 :

Please fill up operating pressure(bar)


Is the Chilling feature for each station functioning and
according to specification? If applicable
5.7

Please fill up operating temp(°C)


Is the Air blow/dryer function for each station functioning and
according to specification? If applicable
STN 7 :
5.8
STN 8 :

Please fill up air flow reading(m3/min)

Page 13 of 29
Factory Acceptance Test Protocol (FAT)

Is the Dosing function for each station functioning and


according to specification? If applicable

STN 1 :
5.9 STN 2 :
STN 3 :

Please manually trigger machine to dose 100ml and measure


actual value.
Is the exhaust function for each station functioning and
according to specification? If applicable
5.10

Please fill up air flow reading(m3/min)


Is all parts dry after drying process? If applicable.
5.11
Remarks

Page 14 of 29
Factory Acceptance Test Protocol (FAT)

6. Safety devices
Safety devices personal security

Checkpoint Y N NA

Are all required emergency buttons/pull string available?


Have they been tested and located at a suitable position.
Is the location suitable to minimised accidental triggering?

6.1
Emergency button:
Pull string:

Remarks:
Are all light curtain safety sensor functioning and tested?
6.2
Remarks
Are the necessary safety-switches, door-switches or optical
barriers of the installation (personal security) available? Have
6.3 they been tested?

Remarks:
Are all necessary machine doors and covers available? Are
the locks and key functioning as per intended?
6.4

Remarks
Is the tower light functioning and positioned in a visible
location? Is the colour of the tower light as per standard?
Please specify and test if special request.
Red - Alarm(all alarm)
6.5
Yellow -Manual Mode
Green - Automode

Remarks

Page 15 of 29
Factory Acceptance Test Protocol (FAT)

Safety elements aqueous machines


Checkpoint Y N NA

Are the required safety interlock sensor present and


functioning? (Pump/Ultrasonic dry run protection/Heater)

STN 1 :
STN 2 :
6.6 STN 3 :
STN 4 :
STN 5 :
STN 6 :

Remarks:
Are the required thermostats for heaters present and
functioning?( All wet and dryer tanks)

STN 1 :
STN 2 :
STN 3 :
6.7
STN 4 :
STN 5 :
STN 6 :
…..

Remarks:

Safety elements JKS solvent machines


Checkpoint Y N NA

Has the vacuum safety-pressure switch been installed


according to the JKS specification? if applicable
6.8

Remarks:

Page 16 of 29
Factory Acceptance Test Protocol (FAT)

Has the hot-water safety-pressure thermostat been installed


according to the JKS specification? if applicable
6.9

Remarks:
Has the chamber temperature thermostat been installed
according to the JKS specification? if applicable
6.10
Remarks:
Has the gas detector been installed according to the JKS
specification? if applicable
6.11

Remarks:
Has the hot water temperature thermostat been installed
according to the JKS specification? if applicable
6.12
Remarks:
Has the exhaust-air-flow-meter been installed according to
the JKS specification? If applicable
6.13

Remarks:

7. Machine aesthetics and ergonomics


Has all welding marks in the tanks and machine structure
cleaned?
7.1
Please indicate welding mark locations
Are there any scratches or damaged marks on the machine?
Please check all external and visible surface.
7.2

Please indicate problematic location


Are there any scratches or cracks on the sliding door glass/
polycarbonate cover / vacuum shutter door glass?
7.3

Please indicate problematic location

Page 17 of 29
Factory Acceptance Test Protocol (FAT)

Are all drippan / bottom on machine cleaned of all rubbish and


dirt?
7.4

Remarks
Is the touchscreen height and location suitable for ergonomic
handling?
7.5

Remarks
Is all electrical button and switches height and location
suitable for ergonomic handling?
7.6

Remarks
Is the loading/unloading position suitable for ergonomic
handling of baskets?
Please ensure that there are no obstructions to baskets
7.7 during loading/unloading operation

Remarks
Are all machine covers / sliding door handles at the location
suitable for ergonomic handling?
7.8

Remarks

8. Machine Labelling
Are all pneumatic valve properly labelled and corresponds
with schematic?
8.1
Qty of checked and correct valve
Qty of Valves on machine :
Are all instruments properly label and corresponds with
schematic?
8.2
Qty of checked and correct instruments
Qty of instruments on machine :

Page 18 of 29
Factory Acceptance Test Protocol (FAT)

Are all electrical components properly label and corresponds


with electrical diagram?
8.4

Remarks
Are all wiring components properly label and corresponds with
electrical diagram?
8.5

Remarks
Are all piping direction arrows properly labelled and
corresponds with the schematic?
8.6

Remarks
Is the machine name plate properly installed with correct
information?
8.7

Remarks
Is all warning labels properly labelled at all danger zones?

High Voltage Warning


Chemical Warning
8.8
Hot Warning
Finger Pinching Warning.

Remarks

Page 19 of 29
Factory Acceptance Test Protocol (FAT)

9. Software and Control


Checkpoint Y N NA

Does the HMI process value corresponds with the actual


measured value?

9.1 Temperature :
Conductivity/Resistivity/pH :
Flowrate :

Remarks:
Does all the buttons in manual page function as per intended?
9.2
Remarks:
Is all the buttons labels in the manual page corresponds with
actual instrument controlled and schematic?
9.3 (Ex. Valve number )

Remarks:
Is all the light indicators functions as per intended?
(Ex. Valve ON/OFF indication)
9.3

Remarks:
Is the login feature functioning as per intended?
(Ex. Operator , Engineer , Admin restriction)
9.4

Remarks:
Is the all the process setting limits set properly as per
intended
(Ex. Process temperature max allowable temperature setting.
9.5
Slow pull speed limits)

Remarks

Page 20 of 29
Factory Acceptance Test Protocol (FAT)

Does all the manual buttons on the machine function as per


intended? (Ex. Buzzer Reset button / Alarm Reset / Fast load/
9.6 Fast unload etc...)

Remarks:
Does all water level sensor trigger and functions as per
intended?

STN1 /Max level


STN1SBT1 / Min level
9.7
STN = STATION
SBT = SUB TANK
BFT = BUFFER TANK

Remarks:
Can the machine auto-mode function without alarm for 10
baskets consecutively?

9.6
Time:

Please record time to complete all 10 basket

10. Accessories / Baskets


Checkpoint Y N NA

Does all basket fit into the machine and are according
10.1 requirements/dimensions?

Remarks:
Do the parts fit into the basket and ergonomic to load/unload?
10.2
Remarks:
Is the basket treatment done properly? Is all the welding
marks cleaned?
10.3
Remarks:

Page 21 of 29
Factory Acceptance Test Protocol (FAT)

11. Documentation
Checkpoint Y N NA

Is the complete technical documentation available?


… Number of copies on paper
11.1

Remarks:
Is the part Operations manual written in the language of the
country of destination?
11.2
Remarks:
Standard: English
Is the schematic available?
11.3
Remarks:
Is the pneumatic diagram available?
11.4
Remarks:
Is the electrical diagram available?
11.5
Remarks:
Is the BOM list available?
11.6
Remarks:
Is the Machine certification available?
11.7
Remarks:
Is the list of recommended spare parts available and has it
been discussed?

11.8
Have these spare-parts been ordered by the customer?

Remarks:

Page 22 of 29
Factory Acceptance Test Protocol (FAT)

Supplier document of components


-..
-
-
11.9 -

Available?

Certificates of the components

-..
-
-
11.9
-
-

Available?

12. Delivery / Commissioning / Consumables


Checkpoint Y N NA

Can the machine be brought into the building (dimensions and


weight) and has the customer prepared the necessary
12.1 equipment?

Remarks: None
Are the necessary consumables for start up available; who will
organize them?

12.2 Solvent
Azotes
Detergents

Page 23 of 29
Factory Acceptance Test Protocol (FAT)

13. Trainings / Instructions

The following trainings and instructions have been accomplished before


or during the FAT:
Date Participant Training level / topic Duration Instructor

According the contract / order confirmation, the following trainings / instructions at or


after the start-up at the customer side are planned / have been sold:
Date Participant Training level / topic Duration Planned?

Page 24 of 29
Factory Acceptance Test Protocol (FAT)

14. Work still to be accomplished / Open Points List (OPL)


Work to be done by / Remarks

10

Page 25 of 29
Factory Acceptance Test Protocol (FAT)

Work to be done by the customer / Remarks

10

Page 26 of 29
Factory Acceptance Test Protocol (FAT)

15. Scheduling / Next steps


Works / Activities Date Responsible

Handling of the open


issues concerning the
machine until:

Handling of open points at


Customer
the customer side
Disassembly of the
machine at the factory ;

Ready for dispatch at


Delivery of the machine
(acc. to the order
confirmation)
Positioning of the machine
(ramp to location of Customer
machine)
Preparation of infrastructure
Customer
till

Start date for the assembly


of the machine:
Connection of the machine
to the infrastructure Customer
customer side
Start date for the initial
start-up
Additional training of the
with customer
personal, technicians and
operators
SAT / Final acceptance /
with customer
hand over of the machine

Page 27 of 29
Factory Acceptance Test Protocol (FAT)

16. Remarks

Page 28 of 29
Factory Acceptance Test Protocol (FAT)

FAT / Machine Commissioning Acceptance Signature list

The machine complies in all points to the order to, as to the order confirmation dated
on ………………….and any possible supplementary agreements.

The machine has been checked thoroughly concerning functionality and completion.
No deficiencies (except the ones mentioned in the protocol) were found in
connection with the applied materials and the workmanship.

The machine is considered as accepted at the factory/customer site and is released


for delivery/to customer.

Approved/Accepted by:

JKS <Customer >

(Project Engineer) (Customer Project PIC #1)


Name: Name:
Position

(Project Electrical Engineer) (Customer Project PIC #2)


Name: Name:
Position

(Project Manager) (Customer Project PIC #2)


Name:
Name:
Position

Page 29 of 29