Stone Delivery Status Summary

Total Quantity Required Delivered Cumulative


Original Design Revised Design as of 25/Dec/2017 As of 04/Jan/2018
Description Target Size Unit Unit
Progress Balance
Q'ty (m3) Weight Q'ty (ton) Q'ty (m3) Weight Q'ty (ton) Q'ty (ton)
(%) (ton)
(t/m3) (t/m3)
Primary Run 2,300 2.20 5,060 2,300 2.20 5,060 1,676 33% 3,384
Crusher Run 0-30mm 0-3cm 2,550 2.20 5,610 2,550 2.20 5,610 0 0% 5,610
Pea Gravel 40mm~ 4-6cm 2,000 1.80 3,600 2,000 1.80 3,600 0 0% 3,600
Gravel 0-200mm 0-20cm 1,315 2.28 3,000 4,262 2.28 9,724 5,386 55% 4,338
Stone 10-30kg 15-23cm 1,436 1.80 2,586 1,506 58% 1,079
Stone 30-100kg 23-34cm 2,102 1.80 3,784 1,386 37% 2,398
Stone 30-200 kg 23-43cm 23,400 1.80 42,120 31,046 1.80 55,884 29,104 52% 26,780
Stone 300-500 kg 49-58cm 11,600 1.70 19,720 27,926 1.70 47,474 21,510 45% 25,964
Stone 1 ton 75cm 2,700 1.60 4,320 2,700 1.60 4,320 0 0% 4,320
Stone 3 ton 105cm 6,700 1.60 10,720 6,700 1.60 10,720 2,903 27% 7,817
TOTAL 52,565 1.79 94,150 83,023 1.79 148,761 63,471 43% 85,290

Revision Record
(21/Dec/2017) - 10-30kg (1,197m3 net x 1.2), 30-100kg (1,752m3 net x 1.2) were added for Gabion / Filter Unit and the same quantities were deducted from 30-200kg
(21/Dec/2017) - 30-200kg for Main Breakwater (8,244m net x 1.2) was replaced with 300-500kg
(25/Dec/2017) - 0-200mm for stone access along Seawall and sand access along Idling Quay (total 1,560m3 net x 1.2) were added
(25/Dec/2017) - 0-200mm for SWCA / MBWOTD / GPEGTD (896m3 net x 1.2) were added
(25/Dec/2017) - 300-500kg for excess quantity MBW Outside Tmp Dyke vs permanent MBW (5,361m3 net x 1.2) were added
(25/Dec/2017) - 30-200kg for Groin(N) Temp Dyke (3,011m3 net x 1.2) was added
(25/Dec/2017) - 30-200kg for Groin(S)/PEG Temp Dyke (14,554m3 net x 1.2) was added