ID Task Name January 2021 February 2021 March 2021 April 2021 May 2021

21 26 31 5 10 15 20 25 30 4 9 14 19 24 1 6 11 16 21 26 31 5 10 15 20 25 30
1 Construction of
Electrical Sub
Station
2 Temporary Works
3 Retaining system Retaining System[1]

4 Soil Improvement Soil Improvement[1]

5 Excavation Excavation[1]

6 Permanent Works
7 Piling Piling[1]

8 Sub Structure &


Super Structure
Works Pile Cap & Stump[1]
9 Pile Cap & Stump
10 Ground Beam & Slab Ground Beam & Slab[1]

11 Column Column[1]

12 Roof Beam & Flat Roof Roof Beam & Flat Roof[1]

13 Architectural Works
14 Brick Laying Brick Laying[1]

15 Plastering Plastering[1]

16 Tiling Tiling[1]

17 Painting Painting[1]

18 M&E Works
19 Plumbing Plumbing[1]

20 Lighting Lighting[1]

21 Ventilation Ventilation[1]

22 Fire Protection Fire Protection[1]

23 External Works
24 Drains Drains[1]

25 Access Road Access Road[1]

26 Testing & Commissioning


27 RI Inspection RI Inspection[1]
28 Certificate of 21/4
Statutory
Completion
Task Inactive Task Manual Summary Rollup External Milestone

Split Inactive Milestone Manual Summary Deadline


Project: Construction of TNB su
Milestone Inactive Summary Start-only Progress
Date: Sat 12/12/20
Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks