You are on page 1of 34

CHALLENGES OF DEVELOPING

MICROGRIDS IN THE PHILIPPINES


Meralco’s experience on Cagbalete Island and Isla Verde

RAMON L. ASAÑA Jr.


Head, Network Technology Strategy and Architecture
Manila Electric Company (MERALCO)
Outline
▪ MERALCO Company Profile

▪ Overview on Rural Electrification in the Philippines

▪ Overview on Microgrids

▪ MERALCO Microgrid Implementations

▪ Key Challenges of Developing Microgrids in the


Philippines based on Meralco’s Experience on
Cagbalete Island and Isla Verde

2
We are the largest power distribution company in
the Philippines, serving close to 27 million Filipinos in 111 cities
and municipalities, and in a franchise area of over 9,685 km2.

We serve the country’s social, political, and economic centers


where 50% of our GDP is produced.

We are US$7.4 billion* company, serving our customers for the


past 115 years, with the commitment to be
the total energy solutions provider of choice in the Philippines.
_________________
7,399 MW peak demand (2018 YTD)
41,389 GWh energy (output) sales
120 substations / 17,795 MVA substation capacity

*Market capitalization as of end 2017


Overview on Rural Electrification in the Philippines
As of 2017, only 90.65% of the households in the Philippines and
97.73% in Meralco’s Franchise Area have access to electricity

Distribution of Unserved
HH Population Household Households
Distribution Unserved
Projected Served HH Electrification
Utilities (2015)
HH
Level (%) Meralco
6%
Other DUs
9%
Electric
13.34 11.72 1.62 87.92
Cooperatives

MERALCO 7.00 6.84 0.16 97.73%


Electric
Cooperatives
Other 85%
Distribution 2.29 1.95 0.34 85.05
Utilities

Grand Total 22.63 20.51 2.12 90.65%

Notes:
• The Household Population number was projected and provided by NSO based from the 2010 Census
• Served Household figure was sourced from the consolidated Distribution Development Plan (DDP)
2015-2024 of all the Distribution Utilities (DU) and National Electrification Administration’s (NEA) Status
of Energization Reports

Source: NEA Updates on Rural Electrification Program; 2016 Year-end

Page 4
Overview on Rural Electrification in the Philippines

Rural Areas Electricity Service Hours

• The Philippines is an archipelago of 7,641 islands

• About 2,000 islands are inhabited; hundreds of


small islands have limited or no access to
electricity

• These islands are usually powered with diesel


generator sets only

o Only 18 out of 287 areas (or 6.2%) have 24/7


electricity; Source: MEDP – DOE 2016-2020

o 84 out of 287 (or 29.3%) have 10-22 hours;

o while the rest (64.2%) have less than 10 hours


of electric service

Page 5
Overview on Rural Electrification in the Philippines

Philippine Rural Electrification Target

The 100 percent electrification of targeted and


identified households accessible to the grid is
target to be attained by 2022,
while the 100 percent electrification of household
in off-grid areas are expected in the long term
period (2023-2040).

Page 6
Overview on Microgrids

Key Components of a Microgrid

A microgrid is a localized energy grid aimed to achieve


specific grid objectives, with the capability to Key Components:
Non-exhaustive
disconnect from the traditional grid and operate
autonomously 1
Distributed Generation
Fossil Fuel, Renewable Energy

2
3 Controls
EMS, DR, Dynamic Pricing

3
Energy Storage
Utility Batteries, Electric Vehicles
4
4
1 2 Electric Load
Single, Multiple, Distributed
*Microgrid designs vary based on the scope of work and the complexity of the objective

Source: HOMER Energy Page 7


Overview on Microgrids

Distributed Energy Resources Types:

Small Wind
Solar PV
Turbine

Combine Heat Micro Hydro


and Power

www.energids.be
www.homepower.com

http://www.seao2.com
www.eneria.fr

Biogas Generator Tidal Energy Generator Diesel Generator


Page 8
Page 9
Page 10
Overview on Microgrids

Integrating Intermittent Energy Sources in Microgrid

Intermittent + Energy Storage = Stable Power

Intermittent + Dependable Supply = Stable Power

Intermittent + Energy Storage + Dependable Supply = Most Ideal


Page 11
Overview on Microgrids

Energy Storage Technology in Microgrid

Lead Acid Battery

Vanadium Redox Flow Battery

Lithium Ion Battery

Page 12
Overview on Microgrids

Microgrid Modes of Operations

Parallel/Grid-tied
▪ Operating connected and synchronized
to the main grid
▪ Power may flow in and out of the
microgrid
University of California San Diego Microgrid (USA)

Island/Isolated
▪ Operating independently
from the main grid

Miyako Island Microgrid (Japan) Camiguin Island

Page 13
Overview on Microgrids
What are the Use Cases of Microgrids?

Economics Achieve incremental income / cost


• Self-Consumption
• Diesel Optimization savings for the end-user by creating
1 • Battery Arbitrage an optimal energy mix in both
• Peak Reduction
• Net Metering supply and demand side
• Facilities Upgrade Deferral

Ensure business continuity to end-


Power Quality and
2 users by increasing quality of
Reliability electric service

Market Participation Participate in the Electricity Energy,


3 • Energy Reserve and Ancillary Services
• Reserve
• Ancillary Services market

Provide electricity to off-grid


4 Electrification communities

Page 14
MERALCO Microgrid Implementations

Meralco’s Microgrid Implementations


APPLICATION
✓ Microgrids for the electrification of households
located in remote islands and far-flung areas

✓ Hybrid energy system composed of solar PV,


battery storage, and diesel gen-set to replace
full diesel gen-set scheme as power source

CAGBALETE ISLAND ISLA VERDE


LOCATION LOCATION
Cagbalete Island is situated Isla Verde is situated along the
in Mauban, Quezon and can bodies of Verde Island Passage
be accessed via 1-hour boat between the Luzon main island
ride from Mauban Port. It is and Mindoro. It lies south of
a booming tourist attraction Batangas City and is composed
because of its beautiful of 6 barangays.
white sand beach.
CUSTOMERS
CUSTOMERS There are about 1,990
There are about 887 households in the island that
households in the island that currently have no access to
currently have no access to electricity.
electricity. Page 15
MERALCO Microgrid Implementations

Current Power Supply Situation

EXISITING POWER SOURCE AVAILABILITY

DIESEL 6pm – 10pm


GENERATORS
Sizes range from 5 – 30 KVA daily operation

Few residents with their own diesel generators Note that not all households have access to
are also selling electricity to neighbors electricity

DISTRIBUTION SYSTEM POWER QUALITY

Low quality of power due to:


230V • high voltage drops
• overloaded generators
single-phase system
(evident on the flickering of the lights)

Page 16
MERALCO Microgrid Implementations

Objectives of the Pilot Projects

❑ Evaluate the feasibility and sustainability of using Microgrids for


island electrification in providing reliable, affordable, sustainable, and
clean 24/7 electric service
• Demonstrate stable system operation with high RE penetration
• Prove financial viability (least cost option)
• Develop a sustainable O&M scheme
• Develop a communications plan for the residents to boost awareness

❑ Gain actual learning experience from planning to operations and


maintenance of Microgrids

❑ Prepare Meralco for future Microgrid installations


• Replicate to other areas for electrification

Page 17
MERALCO Microgrid Implementations

Resource Assessment Cagbalete Island

Page 18
MERALCO Microgrid Implementations

Load Curve Estimation of Cagbalete Island

Page 19
MERALCO Microgrid Implementations

Proposed Microgrid Scheme for Cagbalete Island

Monocrystalline
Prime Polycrystalline Consumption
Flow
Back-up Thin Film Curve
Lithium Based

Load

CAPEX/OPEX

• Hybrid Optimization Modeling Software used for designing and analyzing hybrid
power systems

• It allows the user to input hourly power consumption profile and match renewable
energy generation to the required load allowing a user to analyze microgrid
potential, peak renewables penetration, ratio of renewable sources to total energy,
and grid stability

• Additionally, It contains a powerful optimizing function that is useful in determining


the cost of various energy project scenarios. This functionality allows for
minimization of cost and optimization of scenarios based on various factors.

Page 20
MERALCO Microgrid Implementations

Proposed Microgrid Scheme for Cagbalete Island

60 kWp 150 kWh 2 x 30 kW


Solar PV Battery Storage Diesel Generator
S Y S T E M I N T E G R AT I O N

AC
DC DC

PV Inverter Battery PCS Generator Controller

AC AC AC

communication communication communication

Micro-Grid
Loads
Controller

30 kW
(200 HH)
Page 21
MERALCO Microgrid Implementations
APPLICATION: ISLAND ELECTRIFICATION CAGBALETE ISLAND
MICRO-GRID SLD

230 V Line to Ground 3PH 4W


Load

Gen-Sets
Master Controller Micro Grid
Controller

Isolating
Controller Controller
Transformer

AC AC
Inverter PCS
DC DC

DC Line
AC Line
Communication Line
Page 22
Key Challenges of Developing Microgrids in the Philippines

Daily Generation Profile (Illustrative)

Page 23
Key Challenges of Developing Microgrids in the Philippines

Key challenges in developing Microgrids in the Philippines

Affordability Regulatory Policies Logistics

Choice of Technology & Scalability Sustainability


System Optimization
Page 24
Key Challenges of Developing Microgrids in the Philippines
Key Challenge: AFFORDABILITY OF ELECTRICITY

Rates imposed in Cagbalete Island


FLAT RATE PER
METERED RATE • Very high electricity price is
APPLIANCE
(Peso/kWh) currently imposed in the island,
(Peso/day)
about 7 times more than in the
• 1 light bulb – P 10.0
mainland
• 1 Radio – P 10.0 P 31.00 – 36.00
• 1 TV – P 15.0 per kWh • If rates are subsidized, effectively
• 1 Ref – P 20.0 bringing down electricity price
close to mainland rates, customers
COMPARIS ON OF in the mainland will be burdened
ELECTRICIT Y PRICES PER
KWHR • Microgrid developers for rural
Island Mainland* electrification must be prudent
36
and exert considerable effort in
minimizing the amount of
subsidies yet providing the same
10.50
quality of service to island
customers

*latest 3-month average of a residential customer consuming 0 - 50


kWh; includes cross-subsidies Page 25
Key Challenges of Developing Microgrids in the Philippines

Key Challenge: REGULATORY POLICIES

• DUs, who have the resources and the to


serve the islands, have no access to
missionary electrification fund to cover
the difference between the Full Cost
Recovery Rate (FCRR) and Subsidized
Approved Retail Rate (SARR).

• The process of waiving of franchise


rights, QTP accreditation, approval of
subsidized rates, and all other
permitting and processing until the
Microgrid is in operation entails
significant effort and resources (may
even take a few years)

Page 26
Key Challenges of Developing Microgrids in the Philippines

Key Challenge: LOGISTICS

• Cagbalete Island and Isla Verde Docking of boat going to Verde Island (no port)
have no ports which makes
transport of equipment (e.g.,
poles, transformers, generators,
fuel) difficult

• Large boats are not regularly


plying to/from the island to
transport heavy equipment

• MERALCO estimates a 7 - 9
multiplying factor on manual Mini Port (made of wood) in Cagbalete Island
hauling and installation costs
incurred during construction of
island microgrids*

• Hauling costs add not only on


construction cost but also on
O&M costs
*based on a time-and-motion study conducted on similar installations Page 27
Key Challenges of Developing Microgrids in the Philippines

Key Challenge: LOGISTICS

Narrow and steep road network Heavy vegetation


Page 28
Key Challenges of Developing Microgrids in the Philippines
Key Challenge: CHOICE OF TECHNOLOGY AND SYSTEM DESIGN
OPTIMIZATION

• Slowly gaining expertise in running initial


simulations to determine optimal system
Optimization
size and architecture (lowest LCOE & NPV) Software
• Lack of tools and knowledge in conducting
detailed engineering to ensure stable
Microgrid operation with high RE
penetration
• Frequency control
• Right sizing of BESS energy capacity and
power rating (power to energy ratio) and
appropriate technology (li-ion vs. redox
flow vs. lead-acid)
• Optimal diesel operation considering
efficiency, reliability, and asset life

• Identification of appropriate technical


specifications considering the prevailing
environmental conditions such as high
ambient temperature, humidity etc.
Page 29
Key Challenges of Developing Microgrids in the Philippines

Key Challenge: SCALABILITY

• Initial electrification initiatives usually do not


achieve 100% electricity access
• However, most of the systems are not scalable and
normally implemented through various
independent grids
• Initial system voltage is 230V single-phase
• Only tree branches or bamboo stems are used for holding
the lines No provision for MV
• If poles are installed, they are usually not sized to support distribution system
primary line devices such as distribution transformers,
insulators, and alley arms.

• Forecasting methods specifically for island


microgrids must be established. Demand increases
significantly shortly after system commissioning.
• Interoperability of systems (protocols, BMS)
• Proper master planning (ultimate scheme) must be
established Need to replace with poles
that can carry primary lines
Page 30
Key Challenges of Developing Microgrids in the Philippines

Key Challenge: SUSTAINABILITY

• In the Philippines, most of the


existing off grid electrification
which are not under SPUG and
QTP schemes, are not
sustainable.

• Generation systems, such as Defective diesel generator in Cagbalete Island


diesel generators or small solar after only 4 years (~5,000 hrs) of operation
home systems, usually fail after a
few years of operation due to
poor product quality or lack of
maintenance.

• Hence, after an area has been


electrified, the same effort is
needed to re-electrify them again
due to rapid deterioration of
facilities. Solar panels installed in a house in Isla Verde now
mounted on the roof using ropes only
Page 31
Key Challenges of Developing Microgrids in the Philippines
Cagbalete Microgrid Project - Progress

SUSTAINABILITY?
• Service Commitment
• Good Maintenance Plan
• Competent Service Provider
• Remote Monitoring and Supervision
• Quality Products
• Community Partnership-Load
Management

Page 32
Key Challenges of Developing Microgrids in the Philippines

Summary

• Microgrids are relatively new to the Philippines. Gaining of technical


expertise and experience has just started. Economies of scale,
particularly for battery storage, must be achieved in order to bring
down the overall cost.

• Benchmarking with other Microgrid developers from other countries


will help increase know-how. Engaging with technology partners are
likewise important and beneficial.

• A lot of learning based on actual experiences will happen in the next


few years as Microgrid deployment advances.

• The Government is a critical role player in expanding Microgrid


implementations specifically in setting appropriate regulatory policies
and building the necessary infrastructures.

Page 33
STRICTLY CONFIDENTIAL: FOR INTERNAL USE ONLY

End of Presentation
16 November 2018

You might also like