Mapping DS
Mapping DS
Periode
No Sisi Lokasi DS-5 Pemasangan STA Awal
Progress
DS-5
JUMLAH TOTAL
END OF FILTER
Volume
Panjang Volume Durasi
Panjang Komulatip
Komulatip Pengecoran Pemasangan
STA Akhir DS-5 Pengecoran
DS-5 Beton Kelas C DS-5
(m) Beton Kelas C
(m) (m³) (hari)
(m³)
6,240.00 2,321.280
26-Sep-18 25-Oct-18 30
26-Oct-18 25-Nov-18 31
26-Nov-18 25-Dec-18 30
VOLUME BETON/M 0.372 M3
26-Dec-18 25-Jan-19 31
26-Jan-19 25-Feb-19 31
26-Feb-19 25-Mar-19 28
VOLUME BETON/M 0.372 M3
26-Mar-19 25-Apr-19 31
26-Apr-19 25-May-19 30
26-May-19 25-Jun-19 20
VOLUME BETON/M 0.372 M3
PELAKSANAAN PEMBANGUNAN
PT. HUTAMA KARYA (Persero) JALAN TOL TRANS SUMATERA
DIVISI JALAN TOL
RUAS PEMATANG PANGGANG - KAYU AGUNG
PT. WASKITA KARYA
Sta. 135+600 - Sta. 157+600 (Persero), Tbk
KONTRAKTOR : PT. WASKITA KARYA (Persero), Tbk KONSULTAN MK : KSO. PT. CCM - PT. Indec Internusa - PT. CCME
KONSULTAN : PT. JAYA CM PEMILIK PROYEK : PT. HUTAMA KARYA (Persero)
DIVISI : 6 Nomor MC :
SUB DIVISI : DRAINASE Periode :
N0. ITEM :
ITEM : Saluran Samping DS-5 ( Saluran Beton )
SALURAN DS-5 SISI KIRI (L) SALURAN DS-5 SISI KANAN (R)
STATION STATION
NO NO
JARAK (M') VOLUME (M') KETERANGAN JARAK (M') VOLUME (M') KETERANGAN
AWAL AKHIR AWAL AKHIR
JUMLAH TOTAL
END OF FILTER
Volume
Panjang Volume Durasi
Panjang Komulatip
Komulatip Pengecoran Pemasangan
STA Akhir DS-5B Pengecoran
DS-5B Beton Kelas C DS-5B
(m) Beton Kelas C
(m) (m³) (hari)
(m³)
3,079.24 1,145.477
26-Jan-19 25-Feb-19 31
26-Feb-19 25-Mar-19 28
26-Mar-19 25-Apr-19 31
VOLUME BETON/M 0.372 M3
26-Apr-19 25-May-19 30
26-May-19 25-Jun-19 31
Sta. 135+600 -
SUMMARY PERHIT
596.85 611.87
439.87
MEI 2019 JUNI 2019
AKHIR ( R ) PANJANG AWAL ( L ) AKHIR ( L ) PANJANG AWAL ( R ) AKHIR ( R ) PANJANG
136+541 511.79 136+023 136+540 516.91 135+600 136+024 423.88
-
511.79 516.91 423.88
JULI 2019
AWAL ( L ) AKHIR ( L ) PANJANG
135+600 136+018 417.79
417.79 3,079.09
Tanggal Mulai
Periode
No Sisi Lokasi DS-13 Pemasangan STA Awal
Progress
DS-13
TOTAL
END OF FILTER
Volume
Panjang Volume Durasi
Panjang DS- Komulatip
Komulatip Pengecoran Pemasangan
STA Akhir 13 Pengecoran
DS-13 Beton Kelas C DS-13
(m) Beton Kelas C
(m) (m³) (hari)
(m³)
2,827.00 126.65
3,067.00 137.40
2,982.00 133.59
3,246.00 145.42
2,750.00 123.20
3,001.00 134.44
20,830.00 933.18
2827 26-Dec-18 25-Jan-19 31
145.42
VOLUME BETON/M 0.0448 M3/M'