Ramming
Date Days Daily plan Cum. Plan %
Machine
Ramming
# of
Date Days Daily plan Cum. Plan % Ramming
Machine
22-Aug-20 Saturday 115 115 0.98% 2
23-Aug-20 Sunday 115 230 1.96% 2
24-Aug-20 Monday 115 346 2.94% 2
25-Aug-20 Tuesday 115 461 3.92% 2
26-Aug-20 Wednesday 115 576 4.90% 2
27-Aug-20 Thursday 115 691 5.88% 2
28-Aug-20 Friday 0 691 5.88% 2
29-Aug-20 Saturday 115 806 6.86% 2
30-Aug-20 Sunday 115 922 7.84% 2
31-Aug-20 Monday 115 1037 8.82% 2
1-Sep-20 Tuesday 230 1267 10.78% 4
2-Sep-20 Wednesday 230 1498 12.73% 4
3-Sep-20 Thursday 230 1728 14.69% 4
4-Sep-20 Friday 0 1728 14.69% 4
5-Sep-20 Saturday 230 1958 16.65% 4
6-Sep-20 Sunday 230 2189 18.61% 4
7-Sep-20 Monday 230 2419 20.57% 4
8-Sep-20 Tuesday 384 2803 23.84% 4
9-Sep-20 Wednesday 384 3187 27.10% 4
10-Sep-20 Thursday 384 3571 30.37% 4
11-Sep-20 Friday 0 3571 30.37% 4
12-Sep-20 Saturday 384 3955 33.63% 4
13-Sep-20 Sunday 384 4339 36.90% 4
14-Sep-20 Monday 384 4723 40.16% 4
15-Sep-20 Tuesday 384 5107 43.43% 4
16-Sep-20 Wednesday 384 5491 46.69% 4
17-Sep-20 Thursday 384 5875 49.96% 4
18-Sep-20 Friday 0 5875 49.96% 4
19-Sep-20 Saturday 384 6259 53.22% 4
20-Sep-20 Sunday 384 6643 56.49% 4
21-Sep-20 Monday 384 7027 59.76% 4
22-Sep-20 Tuesday 384 7411 63.02% 4
23-Sep-20 Wednesday 384 7795 66.29% 4
24-Sep-20 Thursday 384 8179 69.55% 4
25-Sep-20 Friday 0 8179 69.55% 4
26-Sep-20 Saturday 384 8563 72.82% 4
27-Sep-20 Sunday 384 8947 76.08% 4
28-Sep-20 Monday 384 9331 79.35% 4
29-Sep-20 Tuesday 384 9715 82.61% 4
30-Sep-20 Wednesday 384 10099 85.88% 4
1-Oct-20 Thursday 384 10483 89.14% 4
2-Oct-20 Friday 0 10483 89.14% 4
3-Oct-20 Saturday 384 10867 92.41% 4
4-Oct-20 Sunday 384 11251 95.67% 4
5-Oct-20 Monday 384 11635 98.94% 4
6-Oct-20 Tuesday 259 11760 100.00% 4
Activity Name Start Finish Total QTY
Piling and concreting (B09) 19-Aug-20 26-Aug-20 736
Piling and concreting (B12) 27-Aug-20 2-Sep-20 472
Piling and concreting (B15) 3-Sep-20 8-Sep-20 0
Piling and concreting (B16) 9-Sep-20 13-Sep-20 160
Piling and concreting (B17) 14-Sep-20 17-Sep-20 132
Piling and concreting (B13) 19-Sep-20 22-Sep-20 153
Piling and concreting (B14) 23-Sep-20 27-Sep-20 182
Piling and concreting (B10) 28-Sep-20 1-Oct-20 686
Piling and concreting (B11) 3-Oct-20 6-Oct-20 544
Total 19-Aug-20 6-Oct-20 3065
Drilling
Date Days Daily Plan Cum. Plan %
Machine