Activity Name Start Finish Total QTY

Pile marking (B09) 15-Aug-20 18-Aug-20 1820


Pile marking (B12) 19-Aug-20 24-Aug-20 1820
Pile marking (B15) 25-Aug-20 29-Aug-20 888
Pile marking (B16) 30-Aug-20 2-Sep-20 1625
Pile marking (B17) 3-Sep-20 7-Sep-20 1750
Pile marking (B13) 8-Sep-20 12-Sep-20 1745
Pile marking (B14) 13-Sep-20 16-Sep-20 1575
Pile marking (B10) 17-Sep-20 21-Sep-20 1820
Pile marking (B11) 22-Sep-20 26-Sep-20 1782
Total 15-Aug-20 26-Sep-20 14825

Date Days Daily plan Cum. Plan %


18-Aug-20 Wednesday 353 353 2.38%
19-Aug-20 Thursday 353 706 4.76%
21-Aug-20 Friday 0 706 4.76%
22-Aug-20 Saturday 353 1059 7.14%
23-Aug-20 Sunday 353 1412 9.52%
24-Aug-20 Monday 353 1765 11.91%
25-Aug-20 Tuesday 353 2118 14.29%
26-Aug-20 Wednesday 353 2471 16.67%
27-Aug-20 Thursday 353 2824 19.05%
28-Aug-20 Friday 0 2824 19.05%
29-Aug-20 Saturday 353 3177 21.43%
30-Aug-20 Sunday 353 3530 23.81%
31-Aug-20 Monday 353 3883 26.19%
1-Sep-20 Tuesday 353 4236 28.57%
2-Sep-20 Wednesday 353 4589 30.95%
3-Sep-20 Thursday 353 4942 33.34%
4-Sep-20 Friday 0 4942 33.34%
5-Sep-20 Saturday 353 5295 35.72%
6-Sep-20 Sunday 353 5648 38.10%
7-Sep-20 Monday 353 6001 40.48%
8-Sep-20 Tuesday 353 6354 42.86%
9-Sep-20 Wednesday 353 6707 45.24%
10-Sep-20 Thursday 353 7060 47.62%
11-Sep-20 Friday 0 7060 47.62%
12-Sep-20 Saturday 353 7413 50.00%
13-Sep-20 Sunday 353 7766 52.38%
14-Sep-20 Monday 353 8119 54.77%
15-Sep-20 Tuesday 353 8472 57.15%
16-Sep-20 Wednesday 353 8825 59.53%
17-Sep-20 Thursday 353 9178 61.91%
18-Sep-20 Friday 0 9178 61.91%
19-Sep-20 Saturday 353 9531 64.29%
20-Sep-20 Sunday 353 9884 66.67%
21-Sep-20 Monday 353 10237 69.05%
22-Sep-20 Tuesday 353 10590 71.43%
23-Sep-20 Wednesday 353 10943 73.81%
24-Sep-20 Thursday 353 11296 76.20%
25-Sep-20 Friday 0 11296 76.20%
26-Sep-20 Saturday 353 11649 78.58%
27-Sep-20 Sunday 353 12002 80.96%
28-Sep-20 Monday 353 12355 83.34%
29-Sep-20 Tuesday 353 12708 85.72%
30-Sep-20 Wednesday 353 13061 88.10%
1-Oct-20 Thursday 353 13414 90.48%
2-Oct-20 Friday 0 13414 90.48%
3-Oct-20 Saturday 353 13767 92.86%
4-Oct-20 Sunday 353 14120 95.24%
5-Oct-20 Monday 353 14473 97.63%
6-Oct-20 Tuesday 352 14825 100.00%
7-Oct-20 Wednesday 0 14825 100.00%
8-Oct-20 Thursday 0 14825 100.00%
9-Oct-20 Friday 0 14825 100.00%
Activity Name Start Finish Total QTY
Rammig (B09) 19-Aug-20 26-Aug-20 1084
Rammig (B12) 27-Aug-20 2-Sep-20 1348
Rammig (B15) 3-Sep-20 8-Sep-20 888
Rammig (B16) 9-Sep-20 13-Sep-20 1465
Rammig (B17) 14-Sep-20 17-Sep-20 1618
Rammig (B13) 19-Sep-20 22-Sep-20 1592
Rammig (B14) 23-Sep-20 27-Sep-20 1393
Rammig (B10) 28-Sep-20 1-Oct-20 1134
Rammig (B11) 3-Oct-20 6-Oct-20 1238
Total 19-Aug-20 6-Oct-20 11760

Ramming
Date Days Daily plan Cum. Plan %
Machine

22-Aug-20 Saturday 115 115 0.98% 2


23-Aug-20 Sunday 115 230 1.96% 2
24-Aug-20 Monday 115 346 2.94% 2
25-Aug-20 Tuesday 115 461 3.92% 2
26-Aug-20 Wednesday 115 576 4.90% 2
27-Aug-20 Thursday 115 691 5.88% 2
28-Aug-20 Friday 0 691 5.88% 2
29-Aug-20 Saturday 115 806 6.86% 2
30-Aug-20 Sunday 115 922 7.84% 2
31-Aug-20 Monday 115 1037 8.82% 2
1-Sep-20 Tuesday 230 1267 10.78% 4
2-Sep-20 Wednesday 230 1498 12.73% 4
3-Sep-20 Thursday 230 1728 14.69% 4
4-Sep-20 Friday 0 1728 14.69% 4
5-Sep-20 Saturday 230 1958 16.65% 4
6-Sep-20 Sunday 230 2189 18.61% 4
7-Sep-20 Monday 230 2419 20.57% 4
8-Sep-20 Tuesday 384 2803 23.84% 4
9-Sep-20 Wednesday 384 3187 27.10% 4
10-Sep-20 Thursday 384 3571 30.37% 4
11-Sep-20 Friday 0 3571 30.37% 4
12-Sep-20 Saturday 384 3955 33.63% 4
13-Sep-20 Sunday 384 4339 36.90% 4
14-Sep-20 Monday 384 4723 40.16% 4
15-Sep-20 Tuesday 384 5107 43.43% 4
16-Sep-20 Wednesday 384 5491 46.69% 4
17-Sep-20 Thursday 384 5875 49.96% 4
18-Sep-20 Friday 0 5875 49.96% 4
19-Sep-20 Saturday 384 6259 53.22% 4
20-Sep-20 Sunday 384 6643 56.49% 4
21-Sep-20 Monday 384 7027 59.76% 4
22-Sep-20 Tuesday 384 7411 63.02% 4
23-Sep-20 Wednesday 384 7795 66.29% 4
24-Sep-20 Thursday 384 8179 69.55% 4
25-Sep-20 Friday 0 8179 69.55% 4
26-Sep-20 Saturday 384 8563 72.82% 4
27-Sep-20 Sunday 384 8947 76.08% 4
28-Sep-20 Monday 384 9331 79.35% 4
29-Sep-20 Tuesday 384 9715 82.61% 4
30-Sep-20 Wednesday 384 10099 85.88% 4
1-Oct-20 Thursday 384 10483 89.14% 4
2-Oct-20 Friday 0 10483 89.14% 4
3-Oct-20 Saturday 384 10867 92.41% 4
4-Oct-20 Sunday 384 11251 95.67% 4
5-Oct-20 Monday 384 11635 98.94% 4
6-Oct-20 Tuesday 125 11760 100.00% 4
Activity Name Start Finish Total QTY
Ramming (B09) 19-Aug-20 26-Aug-20 1084
Ramming (B12) 27-Aug-20 2-Sep-20 1348
Ramming (B15) 3-Sep-20 8-Sep-20 888
Ramming (B16) 9-Sep-20 13-Sep-20 1465
Ramming (B17) 14-Sep-20 17-Sep-20 1618
Ramming (B13) 19-Sep-20 22-Sep-20 1592
Ramming (B14) 23-Sep-20 27-Sep-20 1393
Ramming (B10) 28-Sep-20 1-Oct-20 1134
Ramming (B11) 3-Oct-20 6-Oct-20 1238
Total 19-Aug-20 6-Oct-20 11760

Ramming
# of
Date Days Daily plan Cum. Plan % Ramming
Machine
22-Aug-20 Saturday 115 115 0.98% 2
23-Aug-20 Sunday 115 230 1.96% 2
24-Aug-20 Monday 115 346 2.94% 2
25-Aug-20 Tuesday 115 461 3.92% 2
26-Aug-20 Wednesday 115 576 4.90% 2
27-Aug-20 Thursday 115 691 5.88% 2
28-Aug-20 Friday 0 691 5.88% 2
29-Aug-20 Saturday 115 806 6.86% 2
30-Aug-20 Sunday 115 922 7.84% 2
31-Aug-20 Monday 115 1037 8.82% 2
1-Sep-20 Tuesday 230 1267 10.78% 4
2-Sep-20 Wednesday 230 1498 12.73% 4
3-Sep-20 Thursday 230 1728 14.69% 4
4-Sep-20 Friday 0 1728 14.69% 4
5-Sep-20 Saturday 230 1958 16.65% 4
6-Sep-20 Sunday 230 2189 18.61% 4
7-Sep-20 Monday 230 2419 20.57% 4
8-Sep-20 Tuesday 384 2803 23.84% 4
9-Sep-20 Wednesday 384 3187 27.10% 4
10-Sep-20 Thursday 384 3571 30.37% 4
11-Sep-20 Friday 0 3571 30.37% 4
12-Sep-20 Saturday 384 3955 33.63% 4
13-Sep-20 Sunday 384 4339 36.90% 4
14-Sep-20 Monday 384 4723 40.16% 4
15-Sep-20 Tuesday 384 5107 43.43% 4
16-Sep-20 Wednesday 384 5491 46.69% 4
17-Sep-20 Thursday 384 5875 49.96% 4
18-Sep-20 Friday 0 5875 49.96% 4
19-Sep-20 Saturday 384 6259 53.22% 4
20-Sep-20 Sunday 384 6643 56.49% 4
21-Sep-20 Monday 384 7027 59.76% 4
22-Sep-20 Tuesday 384 7411 63.02% 4
23-Sep-20 Wednesday 384 7795 66.29% 4
24-Sep-20 Thursday 384 8179 69.55% 4
25-Sep-20 Friday 0 8179 69.55% 4
26-Sep-20 Saturday 384 8563 72.82% 4
27-Sep-20 Sunday 384 8947 76.08% 4
28-Sep-20 Monday 384 9331 79.35% 4
29-Sep-20 Tuesday 384 9715 82.61% 4
30-Sep-20 Wednesday 384 10099 85.88% 4
1-Oct-20 Thursday 384 10483 89.14% 4
2-Oct-20 Friday 0 10483 89.14% 4
3-Oct-20 Saturday 384 10867 92.41% 4
4-Oct-20 Sunday 384 11251 95.67% 4
5-Oct-20 Monday 384 11635 98.94% 4
6-Oct-20 Tuesday 259 11760 100.00% 4
Activity Name Start Finish Total QTY
Piling and concreting (B09) 19-Aug-20 26-Aug-20 736
Piling and concreting (B12) 27-Aug-20 2-Sep-20 472
Piling and concreting (B15) 3-Sep-20 8-Sep-20 0
Piling and concreting (B16) 9-Sep-20 13-Sep-20 160
Piling and concreting (B17) 14-Sep-20 17-Sep-20 132
Piling and concreting (B13) 19-Sep-20 22-Sep-20 153
Piling and concreting (B14) 23-Sep-20 27-Sep-20 182
Piling and concreting (B10) 28-Sep-20 1-Oct-20 686
Piling and concreting (B11) 3-Oct-20 6-Oct-20 544
Total 19-Aug-20 6-Oct-20 3065

Drilling for piles

Drilling
Date Days Daily Plan Cum. Plan %
Machine

22-Aug-20 Saturday 56 56 1.83% 2


23-Aug-20 Sunday 56 112 3.65% 2
24-Aug-20 Monday 56 168 5.48% 2
25-Aug-20 Tuesday 56 224 7.31% 2
26-Aug-20 Wednesday 56 280 9.14% 2
27-Aug-20 Thursday 56 336 10.96% 2
28-Aug-20 Friday 0 336 10.96% 2
29-Aug-20 Saturday 56 392 12.79% 2
30-Aug-20 Sunday 56 448 14.62% 2
31-Aug-20 Monday 56 504 16.44% 2
1-Sep-20 Tuesday 56 560 18.27% 2
2-Sep-20 Wednesday 56 616 20.10% 2
3-Sep-20 Thursday 56 672 21.92% 2
4-Sep-20 Friday 0 672 21.92% 2
5-Sep-20 Saturday 56 728 23.75% 2
6-Sep-20 Sunday 56 784 25.58% 2
7-Sep-20 Monday 56 840 27.41% 2
8-Sep-20 Tuesday 112 952 31.06% 2
9-Sep-20 Wednesday 112 1064 34.71% 2
10-Sep-20 Thursday 112 1176 38.37% 2
11-Sep-20 Friday 0 1176 38.37% 2
12-Sep-20 Saturday 112 1288 42.02% 2
13-Sep-20 Sunday 112 1400 45.68% 2
14-Sep-20 Monday 112 1512 49.33% 2
15-Sep-20 Tuesday 112 1624 52.99% 2
16-Sep-20 Wednesday 112 1736 56.64% 2
17-Sep-20 Thursday 112 1848 60.29% 2
18-Sep-20 Friday 0 1848 60.29% 2
19-Sep-20 Saturday 112 1960 63.95% 2
20-Sep-20 Sunday 112 2072 67.60% 2
21-Sep-20 Monday 112 2184 71.26% 2
22-Sep-20 Tuesday 112 2296 74.91% 2
23-Sep-20 Wednesday 112 2408 78.56% 2
24-Sep-20 Thursday 112 2520 82.22% 2
25-Sep-20 Friday 0 2520 82.22% 2
26-Sep-20 Saturday 112 2632 85.87% 2
27-Sep-20 Sunday 112 2744 89.53% 2
28-Sep-20 Monday 112 2856 93.18% 2
29-Sep-20 Tuesday 112 2968 96.84% 2
30-Sep-20 Wednesday 97 3065 100.00% 2
1-Oct-20 Thursday 0 0 100.00% 0
2-Oct-20 Friday 0 0 0.00% 0
Concreting for piles

Date Days Daily plan Cum. Plan % Skilled

22-Aug-20 Saturday 0 0 0.00% 0


23-Aug-20 Sunday 0 0 0.00% 0
24-Aug-20 Monday 32 32 1.04% 10
25-Aug-20 Tuesday 32 64 2.09% 10
26-Aug-20 Wednesday 32 96 3.13% 10
27-Aug-20 Thursday 32 128 4.18% 10
28-Aug-20 Friday 0 128 4.18% 10
29-Aug-20 Saturday 32 160 5.22% 10
30-Aug-20 Sunday 32 192 6.26% 10
31-Aug-20 Monday 32 224 7.31% 10
1-Sep-20 Tuesday 48 272 8.87% 15
2-Sep-20 Wednesday 48 320 10.44% 15
3-Sep-20 Thursday 48 368 12.01% 15
4-Sep-20 Friday 0 368 12.01% 15
5-Sep-20 Saturday 48 416 13.57% 15
6-Sep-20 Sunday 48 464 15.14% 15
7-Sep-20 Monday 48 512 16.70% 15
8-Sep-20 Tuesday 48 560 18.27% 15
9-Sep-20 Wednesday 48 608 19.84% 15
10-Sep-20 Thursday 120 728 23.75% 15
11-Sep-20 Friday 0 728 23.75% 15
12-Sep-20 Saturday 120 848 27.67% 15
13-Sep-20 Sunday 120 968 31.58% 15
14-Sep-20 Monday 120 1088 35.50% 15
15-Sep-20 Tuesday 120 1208 39.41% 15
16-Sep-20 Wednesday 120 1328 43.33% 15
17-Sep-20 Thursday 120 1448 47.24% 15
18-Sep-20 Friday 0 1448 47.24% 15
19-Sep-20 Saturday 120 1568 51.16% 15
20-Sep-20 Sunday 120 1688 55.07% 15
21-Sep-20 Monday 120 1808 58.99% 15
22-Sep-20 Tuesday 120 1928 62.90% 15
23-Sep-20 Wednesday 120 2048 66.82% 15
24-Sep-20 Thursday 120 2168 70.73% 15
25-Sep-20 Friday 0 2168 70.73% 15
26-Sep-20 Saturday 120 2288 74.65% 15
27-Sep-20 Sunday 120 2408 78.56% 15
28-Sep-20 Monday 120 2528 82.48% 15
29-Sep-20 Tuesday 120 2648 86.39% 15
30-Sep-20 Wednesday 120 2768 90.31% 15
1-Oct-20 Thursday 80 2848 92.92% 10
2-Oct-20 Friday 0 2848 92.92% 10
3-Oct-20 Saturday 80 2928 95.53% 10
4-Oct-20 Sunday 80 3008 98.14% 10
5-Oct-20 Monday 57 3065 100.00% 10
6-Oct-20 Tuesday 0 3065 100.00% 10