3.1 3.1.28 Work is submitted on a shutdown work request form (see Shutdown Work Request
Checklist) and reviewed by the turnaround team (Turnaround Team Work Request
Review Checklist), and if accepted prior to the work list cut-off date, is sent to the
planner for work package preparation
3.1 3.1.32 Are there master turnaround support plan files archived from previous plant facility
turnarounds
Estimated Actual
Task Required Person Completion Completion
Yes/No Responsible Date Date
Additional Comments
3.2 3.2.18 Is there a maximum received/completion lag time for the planner to complete the plant
asset shutdown initial work package development for quantity and/or time before other
resources may need to be added
3.2 3.2.19 Is this maximum received/completion lag time review on the master milestone schedule
for the plant asset initial work package development
3.2 3.2.20 Is this maximum received/completion lag time acceptable to the planner and the
turnaround team for the plant asset initial work package development
3.2 3.2.21 Is there a plant asset master technical file associated with this accepted shutdown work
request
3.2 3.2.22 Is the plant asset master technical file up to date with the last shutdown information
3.2 3.2.23 Did the master technical file reduce the plant asset work package development time
3.2 3.2.24 Is the plant asset shutdown master initial work package completed and ready for a
turnaround team review
3.2 3.2.25 Has the turnaround team received the plant asset shutdown initial master work package
3.2 3.2.26 Has each turnaround team member reviewed and commented on the plant asset
shutdown master initial work package
3.2 3.2.27 Has each turnaround team member signed off on the plant asset shutdown master initial
work package review
3.2 3.2.28 Was the plant asset shutdown master initial work package review returned to the planner
for the plant asset shutdown master final work package development
3.2 3.2.29 Has the planner received the turnaround team review and comments regarding the plant
asset shutdown master initial work package
3.2 3.2.30 Has the planner completed the plant asset shutdown final master work package
3.2 3.2.31 Has the plant asset final master work package been received by the turnaround team
3.2 3.2.32 Has the turnaround team reviewed the plant asset final master work package
3.2 3.2.33 Has the turnaround team accepted the plant asset final master work package
3.2 3.2.34 Is there a maximum received/completion lag time for the planner to complete the plant
asset shutdown final master work package for quantity and/or time before other
resources may need to be added
3.2 3.2.35 Is this maximum planner received/completion lag time review on the turnaround master
milestone schedule for the plant asset final work package development
3.2 3.2.42 Has the turnaround team accepted the shutdown support plan work requests
3.2 3.2.43 Has the turnaround team forwarded the shutdown support plans to the planner for
shutdown support plan initial master work package development
3.2 3.2.44 Has the planner received the turnaround team shutdown support plans from the
turnaround team
3.2 3.2.45 Is there a maximum received/completion lag time for the planner to complete the
shutdown support plan initial master work packages
3.2 3.2.46 Is this maximum planner received/completion lag time review on the turnaround master
milestone schedule for the shutdown support plan initial master work package
development
3.2 3.2.47 Is this maximum planner received/completion lag time acceptable by the planner and
turnaround team for the shutdown support plan initial master work package
development
3.2 3.2.48 Are there previous shutdown support plan work package files that the planner can access
3.2 3.2.49 Is the completion of shutdown support plan initial master work packages included on the
turnaround master milestone schedule
3.2 3.2.50 Has the planner sent the shutdown support plan initial master work packages to the
turnaround team for review
3.2 3.2.51 Is the turnaround team shutdown support plan initial master work package review on the
turnaround master milestone schedule
3.2 3.2.52 Has the turnaround team reviewed, commented and accepted the shutdown support
plan initial master work packages
3.2 3.2.53 Has the turnaround team forwarded the support plans to the planner for support plan
final master work package development
3.2 3.2.54 Has the planner received the turnaround team accepted initial shutdown support plans
from the turnaround team
3.2 3.2.58 Are there archived shutdown support plan final master work package files that the
planner can access
3.2 3.2.59 Is the completion of shutdown support plan final master work packages included on the
turnaround master milestone schedule
3.2 3.2.60 Has the planner sent the shutdown support plan final master work packages to the
turnaround team for review
3.2 3.2.61 Has the turnaround team reviewed, commented and accepted the shutdown support
plan final master work packages
3.2 3.2.62 Is the turnaround team shutdown support plan final master work packages review on the
turnaround master milestone schedule
3.2 3.2.63 The turnaround team sends the accepted shutdown support plan final master work
packages to the planner for development of sub work packages
3.2 3.2.64 The turnaround team sends the accepted shutdown support plan final master work
packages to the scheduler to start loading time commitments and resource needs
3.2 3.2.65 Has the plant asset/support plan work list cut-off date been added to the turnaround
master milestone schedule
3.2 3.2.66 Is the turnaround team final work package approval date later than the work list cut-off
date to allow for work package development time
3.2 3.2.67 Is the turnaround team final work package approval included in the turnaround master
milestone schedule
3.2 3.2.68 Has the control budget final development been added to the turnaround master
milestone schedule
3.2 3.2.69 Has the control budget been developed
3.2 3.2.70 Has the control budget been presented by the Turnaround Manager to senior
management
3.2 3.2.71 Has senior management approved the control budget
3.2 3.2.72 Are the plant asset shutdown work packages ready for contractor bid package
development
3.2 3.2.73 Are the shutdown support plan work packages ready for contractor bid package
development
3.2 3.2.78 Does the original decision making process updated by the turnaround team to determine
if the work request can be deleted or modified also include an Engineering risk based
assessment
3.2 3.2.79 Has the Turnaround Manager requested senior management involvement to review
required shutdown work after the work list cut-off date
3.2 3.2.80 Has senior management accepted this involvement
3.2 3.2.81 Has senior management delegated this responsibility
3.2 3.2.82 Have new work, cancellations or work package modifications been approved by senior
management
3.2 3.2.83 Have new work, cancellations or work package modifications to either the plant assets or
support plans caused changes to the shutdown master execution schedule
3.2 3.2.84 Have new work, cancellations or work package modifications to either the plant assets or
support plans caused changes to the control budget
3.2 3.2.85 Have new work, cancellations or work package modifications been forwarded to the
planner to change the plant asset shutdown master work package and the associated sub
packages
3.2 3.2.86 Have new work, cancellations or work package modifications been forwarded to the
planner to change the support plan shutdown master work package and associated sub
packages
3.2 3.2.87 Has the scheduler made changes to the shutdown master execution schedule regarding
new work, cancellations or modifications of the plant asset or support plan work
packages
3.2 3.2.88 Has the control budget been updated regarding the new work, cancellations and
modifications
3.2 3.2.89 Has senior management approved the shutdown master execution schedule changes
3.2 3.2.90 Has senior management approved the changes to the control budget
3.2 3.2.91 Has the shutdown master work list been updated
Shutdown Work
Request
Submission
Checklist
Is the name of the person submitting the request on the shutdown work request
3.3 3.3.1 submission form
3.3 3.3.2 Is the requestor’s contact information provided: phone, fax, e-mail, cell
3.3 3.3.3 The person submitting the request: operating unit/trade, submission location
3.3 3.3.4 The date of the request
3.3 3.3.5 Who was the original request being sent to
3.3 3.3.6 How was the request originally sent: written, digital, fax, scan/e-mail
3.3 3.3.7 What plant asset or tag number is the shutdown work request for
3.3 3.3.8 Was a drawing, P&ID or sketch attached by the requester
For piping, was an isometric drawing, sketch or other location detail attached to the
3.3 3.3.9 request
3.3 3.3.10 Did the shutdown work request provide a detailed description
3.3 3.3.11 What is the priority of the shutdown work request
3.3 3.3.12 What is the history of the shutdown work request: did it break, wear out, mystery
3.3 3.3.13 Has this shutdown work request been sent before and when
Has the turnaround team recognized this as a duplicate request from two separate
3.3 3.3.14 operating teams
3.3 3.3.15 Could the requester suggest a repair procedure for this shutdown work request
Is there any way this shutdown work request can be completed without shutting the plant
3.3 3.3.16 down; if not, provide explanation why not
3.3 3.3.17 Can this shutdown work request be completed with only a partial plant outage
3.3 3.3.18 Can the shutdown work request be completed during an outage of opportunity
If a shutdown work request submission form was generated, was the work list cut‑off date
3.3 3.3.19 on it
If a shutdown work request submission form was generated, does it include the contact
information of the turnaround team member delegated the responsibility of receiving
3.3 3.3.20 shutdown work requests