Professional Documents
Culture Documents
RE
monthly
Update
November 2020
Lead Sponsors
www.renesola.com
Features:
w Globally reputed & recognised International brand
w Well equipped Sales & Technical support staff in India
w TIER-1 Solar PV Module manufacturer Contact us:
w High conversion efficiencies modules Office: 1604, Regus, 16th Floor, Tower B,
w Easy installation & handling World Trade Tower, Sector -16,
Noida - 201301, UP (INDIA)
w Cost competitive
Tel.: +91- 120- 6829475
w Certified by TUV, UL, BIS and other International labs Email: manoj.tanwar@renesola.com
w ISO9001, OHSAS18001, ISO 14001 Certified
HIGH PERFORMANCE
RANGE
Upto
Life cycle
EXCLUSIVE
FEATURES
OUR LITHIUM ION BATTERIES ARE MANUFACTURED WITH UTMOST CARE & PASSES THROUGH
30+ QUALITY TESTS BEFORE REACHING YOU
Combustion test Acupuncture test Thermal shock test Drop test Temperature cycling test
Contents
1. Tenders | 5
New RFS Issued | 5 Re-
Tendered | 6
Date extension | 7
Auctions Completed | 7
2. Installed Capacity | 8
3. Investments/ Deals | 9
4
1.Tenders
New • About 191 MW of renewable tenders were issued in November 2020.
Tenders Meghalaya alone issued 80 MW of solar tenders this month.
New RFS
Issued
Other Bid
Tender Capacity
Tender Name Technology Details Submission
Scope (MW)
(EMD) date
5
Other Bid
Tender Capacity
Tender Name Technology Details Submission
Scope (MW)
(EMD) date
Re-Tendered
Bid
Tender Name Technology Other Details
Submission date
"Amount of Bid security:
• INR 20 Mn – 50 MW
NTPC, Gujarat, 500 MW, Solar EPC
• INR 50 Mn – 60 – 110 MW 24-Nov-20
Solar EPC package with land, May 2020 with land
• INR 100 Mn – 120 – 220 MW
• INR 200 Mn – 230-300 MW"
6
Date Extension
Bid
Tender Name Technology Other Details
Submission date
SECI, Pan India, 5,000 MW, Thermal + RE, EMD - INR 0.5 million/MW/Project
Thermal + RE 2-Dec-20
Mar 2020 PBG - INR 1.0 million/MW/Project
SECI, 2500 MW, ISTS, Solar UMREPP, EMD - INR 0.4 million /MW
Solar 28-Dec-20
Karnataka (ISTS X), April 2020 PBG - INR 0.8 million /MW
Auctions Completed
Capacity Capacity
Tender name Status tendered allotted Bidder details
(MW) (MW)
• Aljomalh Energy and Water Co.- 200
SECI, 1070 MW, Solar PV Results MW (INR 2.00/kWh)
1070 1070
Tranche III, Rajasthan, July announced • Sembcorp – 400 MW (INR 2.00/kWh)
2020 • NTPC Ltd. – 470 MW (INR 2.01/kWh)
KSEB, 200 MW, Solar, Results • Tata Power – 110 MW (INR 2.97/kWh)
200 200
Kerala, Sep 2020 announced • NTPC – 90 MW (INR 2.97/kWh)
7
2. Installed Capacity
In October 2020, a total of 406.22 MW of renewable energy capacity was
added, taking the cumulative RE capacity to 89.63 GW as on October
31, 2020. According to MNRE, projects of 49.59 GW are at various stages
of implementation while another 27.41 GW of projects are under various
stages of bidding.
Fig 2.1: State-wise installations in Solar and Wind during October 2020 – 406.22 MW
ll Hydro
Sma 300
r 14%
we
Po
% 250
11
o
Bi
200
Capacity (MW)
Win
43%
d
150
100%= 89.6 GW
100
50
1%
ar
4
0
ol
S Solar Wind
8
3. Investments/ Deals
Table 3.1: Investment and deals in November, 2020
Deal
Company Name Deal Type Sector Asset Investor
Value
Vibrant Energy Holdings Acquisition Solar Blueleaf Energy Value not disclosed
9
Exports Imports
Jun-19
Jul-19
Aug-19
Sep-19
Oct-19
Nov-19
Dec-19
Jan-20
Feb-20
Mar-20
Apr-20
May-20
Jun-20
Jul-20
Aug-20
Sep-20
Oct-20
10
0.25
0.23
0.21
Mono PERC modules
0.19
Prices (USD/wp)
0.17
Multi crystalline module
0.15
0.13
0.11
0.09
Cell
0.07
0.05
Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20
11
Central MNRE releases Concept Note for Development of Wind and Wind-
Solar Hybrid Parks
• The state government will play its role in selecting park for develop-ers
and helping them to acquire the identified sites. In case the power
generated from the park is exported to other states, the state govern-
ment will be entitled to a facilitation charge of Rs.0.05 /kWh of elec-
tricity exported to other states by the project developer.
Ministry of New and Renewable Energy (MNRE) with its notification dated
13 November 2020 has increased the aggregate target to 30.8 GW from
25.7 GW by FY2023.
12
• MNRE noted that the quantity equivalent to 10% of the total under the
particular category would be allocated to the L1 bidder. Further, the
option to match the lowest (L1) bidder will be provided to all bidders
falling under L1+15%. In case the number of bidders is less than five, the
same will be further extended to all bidders in ascending order of the
price quoted by them until all bidders agree on the L1 price.
13
• There will be a separate bid price for the solar water pumping system
with a universal solar pump controller (USPC). The subsidy will be
granted for these pumps according to the benchmark price for solar
pumps without USPC.
• The peak hours will be declared by the regional load despatch center
14
• Earlier, bidders were allowed to quote a single composite tariff for RTC
renewable energy bundled with thermal energy. As per the revised
guidelines, the quoted tariff must now comprise four components – a
fixed component for the renewable power and non-renewable power,
and a variable component for the non-renewable component (scalable
for fuel) and non-renewable power (scalable for transportation).
• Fixed components must be quoted every year for the tenure of the
PPA. The variable components must be quoted on the scheduled date
of commissioning. Following this, the levelized tariff will be computed
as per CERC escalation indices depending on the type of fuel being
used and the discount factor, which will be specified in the bidding
document.
• MoP also revised the timeline for attaining financial closure of RTC pro-
jects by generators. Projects that are 1 GW and below must be closed
within 18 months from the date of execution of the PPA. For projects
larger than 1 GW, this limit was set at 24 months. Previously, projects
that are 500 MW and below were to be closed within one year, pro-
jects between 500 MW and 1 GW were to be closed in 18 months,
while projects over 1 GW were given two years to achieve financial
closure.
15
• The Central Electricity Authority (CEA), in its annual report for 2019-20,
issued updates on the Green Energy Corridor program for the trans-
mission and integration of renewable energy.
16
ment for financial assistance of €500 million from KfW, Germany has
been signed by PGCIL.
• In 2015, MoP assigned works for the transmission programs for so-
lar parks in Kunta (1500 MW), Pavagada (2000 MW), Rewa (750 MW),
Bhadla-III (500 MW), Bhadla-IV (250 MW), Essel (750 MW), and Ba-
naskantha (700MW). The transmission works for these solar parks have
been completed, according to the latest report.
• The annual report further noted that the country’s total energy require-
ment during the year 2019-20 was 1,291,010 MUs against 1,274,595 MUs
during the previous year 2018-19, an increase of 1.3%. The total energy
supplied in the country during the year 2019-20 was 1,284,444 MUs as
against 1,267,526 MUs during the previous year 2018-19.
• This benefit would not apply to contracts under dispute whose pro-
ceedings are already underway in court. All tenders and contracts that
17
• UPERC with its order dated 11 November, 2020 has issued Tariff order
for state owned distribution companies Dakshinanchal Vidyut Vitran
Nigam Ltd., Agra (DVVNL), Madhyanchal Vidyut Vitran Nigam Ltd.,
Lucknow (MVVNL), Pashchimanchal Vidyut Vitran Nigam Ltd., Meerut
(PVVNL), Purvanchal Vidyut Vitran Nigam Ltd., Varanasi (PuVVNL),
Kanpur Electricity Supply Company Ltd., Kanpur (KESCO) and for Noida
Power Company Ltd. (NPCL).
• UPERC in its Tariff Order stated that there would be no hike in power
tariffs and rejected the proposal of power distribution companies for a
marginal hike in tariffs.
• UPERC decided not to change the slab category and fixed charge,
which was kept at Rs. 110/kW/month.
• For urban domestic consumers the charges are at the rate of Rs. 5.50
per unit for first 150 units, followed by Rs. 6 per unit on consumption of
150-300 units.
• The wind power generator had offered to reduce the interest rate to
6% per year if TANGEDCO paid the due amount within 60 days. Since
TANGEDCO failed to clear the dues, the Commission has now asked
TANGEDCO to pay interest at 12% per year for dues beyond 30 days of
receipt of the bill.
Tamil Nadu Sets Benchmark Tariff of Rs. 2.28/kWh for 20,000 Solar
Pumps
• TNERC also set a Rs. 1 /kWh incentive for farmers for exporting sur-
plus energy back into the grid.
19
Assumptions Value
Interest on Loan 9%
Karnataka KERC issued Tariff Order for Power Distribution Companies for FY
2020-21
20
• KERC has continued with the tariff schedule for concessional power
supply to the electric vehicle charging stations by including the EV
battery swapping stations, without increasing the energy charges of
Rs.5 /kWh. It has been maintained in the orders for all the DISCOMs in
the state.
• The green tariff of an additional Rs. 0.50 /kWh over the standard
tariff, which was introduced a few years ago for HT industries and HT
commercial consumers, to promote the purchase of renewable ener-
gy from ESCOMs has been maintained. It will be the same for all the
DISCOMs.
• KERC determined a wheeling charge of Rs. 0.23 /kWh for the HT net-
work and Rs. 0.54 /kWh for the low tension (LT) network.
• KERC also noted that the wheeling charges would apply to all open
access consumers using the BESCOM network only, except for ener-
gy transmitted from renewable sources. For wheeling of energy from
renewable energy sources, separate orders issued by the Commission
from time to time will be applicable.
• KERC has extended the validity of the existing tariff structure deter-
mined by the Commission in August 2019. The earlier regulation had
expired in April 2020. The extension has been provided for one year
from 1 April, 2020, to 31 March, 2021. The extension will facilitate the
seamless development of solar projects, including rooftop solar instal-
lations in the state.
21
• Existing wind projects that have been in operation for at least ten years
would be considered for repowering. Wind, solar, small hydro, so-
lar-wind hybrid, and MSW projects will be treated as “must-run” pro-
jects.
• Surcharges for bill payments delayed over 45 days from the date of in-
voice will be charged at a rate equivalent to the base rate on April 1 of
the corresponding year along with a 400 basis-point-per year for each
day the payment is delayed.
22
• Banking charges of 10% of the banked energy must be paid and ad-
justed against the energy banked before it was drawn.
• The regulations stated that renewable energy projects must pay grid
connectivity charges of Rs. 250,000 /MW to transmission or distribu-
tion licensees. They also said that energy would be accounted for by
metering when power is sold to distribution licensees.
• The regulation will be in effect from 1 April, 2020. The control peri-
od for these regulations will be four years starting 1 April, 2020, to 31
March, 2024. The regulations will apply to new and existing renewable
energy-based sources of power in Rajasthan that generate and sell
electricity to distribution licensees in the state.
23