3
CURRENT SOLAR FARMS IN OPERATION
4
PROJECT HIGHLIGHTS
Details 2012 2017
Solar System Capacity 8 MW 37.5 MW
Solar Modules Used 29,092 Pcs 110,500 Pcs (Made in
Malaysia)
Solar Inverters Used 390 Nos 14 Nos
Cables DC 6mm: DC 6mm:
24 km 400 km
- MPHTJ - PEKA
- PTHM - PHCDC
7 Collaboration with - NCIA - HRD
- MIDA - NCIA
- HRD - MIDA
Government Revenue
- RM10 Mill - RM27 Million
8 GST
- RM 4 Mill - RM12 Million
Corporate taxation
EMPLOYMENT OPPORTUNITIES
DESIGNATION NO
PLANT MANAGER 1
ENGINEER 40
INSTALLERS 180
TECHNICIAN 60
GENERAL WORKER 20
ADMINISTRATION & EVENT 3
TOTAL 304
SPIN-OFF BUSINESS OPPORTUNITY
O&M
Contract
EPC
F&B
Contractor
EVENT
MANAGEMENT
CONTRACT
R&D Landscape
Partnership & Nursery
Industrial
Training &
CHALLENGES FACED IN THE PROJECT
• FINANCIAL
Local financial institutions have limited capital
and low experience in lending to RE projects.
• RISK PERCEPTION
Risk perceptions related to new technologies
–reluctance to finance RE projects.
• TIME IS OF ESSENCE
Timely approvals from various authorities
and critical to meet timeline of
Power Purchase Agreement (PPA).
LSS Bidor, 30 MWac Solar PV Power Plant
10
Project Timeline
2 3 9 10 11 12 2 3 4 5 6 7 8 9 10 11 12
4 5 6 7 8
1 1
1
X X X X X X X X X X
AC AC AC AC AC
DC DC DC DC DC
Solar PV Panel
DC Combiner Box
HV Transformer
33/132kV
1000 VDC
33 kVAC
360 VAC 33 kVAC 33 kVAC
14
THANK YOU