SCOPE MATRIX FOR PILING WORKS

A Working piles Pile Vendor L&T Remarks


1 Marking of Pile point locations √
2 Mobilisation of pile equipments (Hydralic rig, Crane, Pump, Compressor,etc..) √
3 Supply and installation of Guide casing √
4 Supply of water and storage facilities √
5 Supply of bentonite slurry (DMC) √
6 Supply of reinforcement steel √
7 P&M for cutting and bending of reinforcemnt √
8 Cut, bend and installation of reinforcement steel (incl supply of binding wire and cover block) √
9 Supply & Installation of Tremie pipes √
10 Flushing of pile bore √
11 Supply of M30 Grade concrete (Including all wastages) with required sampling/tests √
12 Pouring of M30 Grade concrete with Tremmie pipes/Hopper √
13 Disposal of pile muck from foundation area √
14 Excavation upto founding/PCC level √
15 Supply and laying of PCC for Pile cap √
16 Pile chipping up to cut off level and dressing the top surface neatly √
17 Conducting integrity test on all piles √

B Preliminary Test Pile (Compression, Tension, Lateral) / Working Test Pile


*NOTE- 1.5 % of total pile is required to be tested in Working piles as per (IS 2911-Part IV )
1 Marking of Pile point locations √
2 Mobilisation of pile equipments (Hydralic rig, Crane, Pump, Compressor,etc..) √
3 Supply and installation of Guide casing √
4 Supply of water and storage facilities √
5 Supply of bentonite slurry (DMC) √
6 Supply of reinforcement steel √
7 P&M for cutting and bending of reinforcemnt √
8 Cut, bend and installation of reinforcement steel (incl supply of binding wire and cover block) √
9 Supply & Installation of Tremie pipes √
10 Flushing of pile bore √
11 Supply of M30 Grade concrete (Including all wastages) with required sampling/tests √
12 Pouring of M30 Grade concrete with Tremmie pipes/Hopper √
13 Disposal of pile muck from foundation area √

C Kentledge method of loading for Compression Load test


1 Plant and machineries to handle loads (Crane, Trailor etc) √
2 Supply and placing of Dead loads for Testing √
3 Supply and placing of Steel beams, hydraulic jack, dial gauges, etc all accessories for testing √
4 Conducting of load tests (Compression, Tension, Lateral) √
5 Submission of test results and obtaining approval from Client/Consultant √

D Concrete Design Mix Proportions/Materials Testing


1 Proposal of Concrete Design Mix with Trial mix/Cube results and obtaining approval from Client/Consultant √
2 Testing of Cement, Sand , Aggregate & Construction water and submission of satisfactory results √
3 Testing of Reinforcemnt Steel and test results √

E Calibration Certificates
1 Hydraulic Rotary Rig √
2 Hydraulic Jack, Pressure gauge & Dial gauges √
3 Crane / Hydra √
4 Survey Instruments √

F General
1 Providing of levelled ground and clear access for piling equipments √
2 Submission of FQAP and Check list for Piling works for approval and Implementation √
3 Required PPE's during Piling works √
4 All Consumables required in Piling work √