Establish Agile Work Environment

#1 Narrative Charter

a. Project purpose or justification


The project changes the work environment of the whole company. Traditional forms of
working are being challenged by new agile forms. Due to the change of requirements form
our customers, users and employees and the current situation with Covid-19 it is necessary
to provide a form of working which enables the company to further grow and be successful.
The current setup is not working anymore.

b. Measurable project objectives and related


success criteria

Objective Success Criteria

We will change 80% of the meeting rooms 80% of all current meeting rooms are
to agile workshop rooms. equipped with whiteboards, post-its, small
tables, no more big tables and chair,
templates to work with

We will establish team-areas where team Each team has a team-are that is equipped
members can share working tables and with the necessary amount of tables (70%
also have a common workshop room. of team members) and a workshop room.

We will establish a basic training for all The trainings are live for booking by the
employees on how to hold effective employees. After 6 months of running the
meetings. training, at least 20% of all employees
should have taken part in the training

c. High-level requirements
Enable employees with the knowledge to hold effective meetings.
Enable employees to hold effective meetings and workshops.
Give employees flexibility where and how to work.

d. Assumptions and constraints


Some rooms must contain comfortable seeting for official bigger meetings.
The assumption is, that the workforce remains stable.
We are restricted to the current rooms that we have.
e. High-level risks
The management cuts the resources due to a second wave of Covid-19.
The employees don’t use the provided rooms.
Employees do not want to give up their current seats.

f. Summary milestone schedule


1. GO of the management
2. Finalization of concept and information of all stakeholders
3. Go-Live of new workshop room concept
4. Go-Live of team areas and individual workshop rooms
5. GO-Live of trainings

g. Summary budget
Expected budget: 124k EUR:
● Labor: 62k EUR
● Material: 32k EUR
● Moving firm: 40k EUR