Professional Documents
Culture Documents
Note:
*Rental rates are used to calculate the cost of ERCC dump trucks
*Contract rates are used to calculate the cost of ERCC machineries other than dump trucks
13/2/2014
Cost Revenue Net amount Net %
Material Production 345,149.85 260,933.00 -84,216.85 -32.28%
Borrow/sub base production 245,480.62 188,055.00 -57,425.62 -30.54%
Quary rock production & haulling 39,662.28 6,854.12 -32,808.16 -478.66%
Base Course Crushing 24,446.79 21,594.00 -2,852.79 -13.21%
Concrete Agg. Crushing 35,560.16 44,429.88 8,869.72 19.96%
Earthwork 522,556.57 452,395.72 -70,160.85 -15.51%
Section 1 (0+000-21+900) 352,656.35 302,777.86 -49,878.48 -16.47%
Mulugeta Site 86,651.07 69,371.35 -17,279.73 -24.91%
Samuel site 67,964.19 41,192.51 -26,771.68 -64.99%
Kidus Site 198,041.09 192,214.01 -5,827.08 -3.03%
Section 2 (18+700-29+500) 169,900.23 149,617.86 -20,282.37 -13.56%
Henok Site / Feleke site 169,900.23 149,617.86 -20,282.37 -13.56%
Total 0 625.92
1 Dozer(59282) 1 8.5 2272 19312 Laborer 1 1.00 11.5 12 8.27 99.24
Borrow operator 1 1.00 11.5 12 43.89 526.68
Production
(0+800) 19937.92 4984.48 24,922.40 27.00 680.00 18,360.00 -6,562.40
Concrete Aggregate 1 Crusher(39502) 1 6.17 3600 22212 foreman 1 0.25 12 3 45.83 137.49
crushing (5+000) 25291.41 6322.8525 31,614.26 336.59 98.00 32,985.82 1371.56
2 Loader(58545) 0.5 8 579 2316 operator 1 1.00 12 12 43.89 526.68
Total 24528 763.41
Total Sum 164,852.97 95,442.04 -69,410.93
Date: 10/04/2014 Activity: Earthwork work
Actual cost Revenue
Equipment Man Power Material
Activity Total Direct 25% Unit Rate Excuted Amount Net Amount
Equipment Working Hourly Rate Amount No of Workin Man Hour Hourly Amount Material Cost Over Head Total Cost
Description Description hy Hour (A) (B) C=(A*B) Trade Worker U.F g Hour F=(D*G) Indexed H=(F*G) Description Unit Quantity (I) Unit(J)Cost Amount
K=(I*J) L=(C+H+K) Cost
(m) Quantity (n) o=(m*n)
(With Plate No) s (D) (E) Rate(G)
No
1 Grader(60200) 1 9.5 1115.00 10592.5 foreman 1 0.60 12 7.2 45.83 329.976
2 Grader(0538) 1 2.08 1140.90 2373.072 Laborer 12 1.00 12 144 8.27 1190.88
Grader(0166) 1 5.33 1115.00 5942.95
Borrow
Placing(8+660- 3 Grader(55656) 1 3 1140.90 3422.7 operator 3 1.00 12 36 43.89 1580.04
8+760-3+600- 4 Roller(0552) 1 2.17 697 1512.49 27,994.61 6,998.65 34,993.26 32.72 1,380.00 45,153.60 10,160.34
4+100)
5 Roller(0283) 1 0 812.00 0
6 W/truck(60122) 1 0 300.00 0
7 W/Truck(59807) 1 3.5 300 1050
Total 24,893.71 3,100.90 -
1 Grader(0538) 1 7.17 1115.00 7994.55 foreman 1 0.50 12 6 45.83 274.98
2 Grader(0166) 1 0 1115.00 0 Laborer 10 1.00 12 120 8.27 992.4
3 Grader(60200) 1 0 1115.00 0 operator 3 1.00 12 36 43.89 1580.04
Sub base Placing
(5+820-6+180) 4 Roller(0283) 1 2.67 812.00 2168.04 17,867.31 4,466.83 22,334.14 32.72 1,740.00 56,932.80 34,598.66
5 Roller(0483) 1 4.33 810.00 3507.3
6 W/truck(60122) 1 4.5 300.00 1350
7 W/truck(59813) 1 0 300.00 0
Total 15,019.89 2,847.42 -
1 Dozer(0676) 1 7.17 1900 13623 foreman 1 0.20 12 2.4 45.83 109.992
Rock excavation
(4+700-7+800) 2 Laborer 1 1.00 12 12 8.27 99.24
13832.232 3458.058 17,290.29 155.16 136.23 21,137.45 3,847.16
3
Total 13623 209.232
1 Loader(0396) 1 0 649 0 foreman 1 0.60 12 7.2 45.83 329.976
Loader(0905) 1 0 649 0 Laborer 1 1.00 12 12 8.27 99.24
No. D/Truck Km No.Trip Capacity operator 3 1.00 12 36 43.89 1580.04
1 D/Truck(28854) 5 0 14.2 0
Borrow Haulling 2 D/Truck(27593) 5 0 14 0
(10+200) 3 D/Truck(58805) 5 0 16 0 2009.256 502.314 2,511.57 33.33 - - -2,511.57
4 D/Truck(58806) 5 0 16 0
5 D/Truck(47608) 5 0 17.9 0
6 D/Truck(50143) 5 0 14 0
7 D/Truck(59765) 5 0 16 0
Total 0 2009.256
1 Loader(0905) 1 0 649 0 foreman 1 0.33 12 3.96 45.83 181.4868
No. D/Truck Km No.Trip Capacity Laborer 12 1.00 12 144 8.27 1190.88
1 D/Truck(53834) 5 0 16.7 0 operator 2 1.00 12 24 43.89 1053.36
2 D/Truck(32939) 5 0 14 0
3 D/Truck(62147) 5 0 14 0
Lime Material
Haulling(24+400) 4 D/Truck(47608) 5 0 17.9 0
2425.7268 606.4317 3,032.16 33.33 - - -3,032.16
5 D/Truck(27593) 5 0 14 0
6 D/Truck(54263) 5 0 18 0
7 D/Truck(58805) 5 0 16 0
8 D/Truck(58982) 5 0 14 0
9 D/Truck(50143) 5 0 13.8 0
Total 0 2425.7268
1 Loader(0266) 1 0 649 0 foreman 1 0.60 12 7.2 45.83 329.976
No. D/Truck Km No.Trip Capacity Laborer 1 1.00 12 12 8.27 99.24
1 D/Truck(59752) 5 0 14 0 operator 3 1.00 12 36 43.89 1580.04
2 D/Truck(58979) 5 0 16 0
Waste haulling
(7+600) 3 D/Truck(59912) 5 0 16 0
2009.256 502.314 2,511.57 83.34 - - -2,511.57
4 D/Truck(59933) 5 0 14 0
5 D/Truck(58980) 5 0 16 0
6 D/Truck(60117) 5 0 16 0
7 D/Truck(58979) 5 0 16 0
Total 0 2009.256
1 Excavator(0789) 1 8.42 1474 12411.08 foreman 1 0.60 12 7.2 45.83 329.976
2 Excavator(1149) 1 0 1474 0 Laborer 14 1.00 12 168 8.27 1389.36
3 Dozer(58829) 1 8.83 2500.9 22082.947 operator 3 1.00 12 36 43.89 1580.04
Cut to waste 4 Loader(0544) 1 4.42 649 2868.58
(9+480-9+540- No. D/Truck Km No.Trip Capacity 0
9+540-9+580) 47228.983 11807.24575 59,036.23 45.09 #REF! #REF! #REF!
2 D/Truck(54263) 5 4 14 1114.4
3 D/Truck(59777) 5 8 14 2228.8
4 D/Truck(58980) 5 5 14 1393
5 D/Truck(58978) 5 2 14 557.2
Total 43929.607 3299.376
1 Loader(0396) 1 0 649 0 foreman 1 0.60 12 7.2 45.83 329.976
No. D/Truck Km No.Trip Capacity Laborer 14 1.00 12 168 8.27 1389.36
1 D/Truck(32939) 5 0 14 0 operator 3 1.00 12 36 43.89 1580.04
2 D/Truck(58806) 5 0 16 0
Borrow Material
Haulling(10+200) 3 D/Truck(27593) 5 0 14 0
3299.376 824.844 4,124.22 33.33 - - -4,124.22
4 D/Truck(47608) 5 0 17.9 0
5 D/Truck(27958) 5 0 14 0
6 D/Truck(58805) 5 0 16 0
7 D/Truck(59924) 5 0 14 0
Total 0 3299.376
1 Loader(0396) 1 9.33 649 6055.17 foreman 1 0.33 12 3.96 45.83 181.4868
No. D/Truck Km No.Trip Capacity Laborer 12 1.00 12 144 8.27 1190.88
1 D/Truck(62147) 5 4 14 1114.4 operator 2 1.00 12 24 43.89 1053.36
2 D/Truck(53834) 5 3 16.7 996.99
3 D/Truck(32939) 5 3 14 835.8
4 D/Truck(28263) 5 3 14 835.8
5 D/Truck(57995) 5 3 13.8 823.86
Lime Material 6 D/Truck(27593) 5 3 14 835.8
Haulling(24+400) 19770.1668 4942.5417 24,712.71 33.33 567.30 18,908.11 -5,804.60
7 D/Truck(27958) 5 2 14 557.2
8 D/Truck(58806) 5 3 16 955.2
9 D/Truck(28854) 5 3 14.2 847.74
10 D/Truck(50143) 5 3 13.8 823.86
11 D/Truck(47608) 5 2 17.9 712.42
12 D/Truck(58805) 5 3 16 955.2
13 D/Truck(54263) 5 2 18 716.4
14 D/Truck(59924) 5 1 14 278.6
Total 17344.44 2425.7268
1 Loader(0544) 1 3.25 649 2109.25 foreman 1 0.25 12 3 45.83 137.49
No. D/Truck Km No.Trip Capacity Laborer 10 1.00 12 120 8.27 992.4
1 D/Truck(62147) 5 1 14 278.6 operator 3 1.00 12 36 43.89 1580.04
Sub base haulling 2 D/Truck(27958) 5 4 14 1114.4
(10+200) 3 D/Truck(27593) 5 4 14 1114.4 10478.74 2619.685 13,098.43 83.34 284.40 23,701.90 10,603.47
4 D/Truck(50143) 5 4 13.8 1098.48
5 D/Truck(57995) 5 4 13.8 1098.48
6 D/Truck(58806) 5 3 16 955.2
Total 7768.81 2709.93
1 Grader(55656) 1 7 1140.90 7986.3 foreman 1 0.25 12 3 45.83 137.49
Borrow 2 Grader(0166) 1 5.33 1115.00 5942.95 Laborer 10 1.00 12 120 8.27 992.4
Placing(12+900- 3 Grader(59990) 1 2 1115.00 2230 operator 3 1.00 12 36 43.89 1580.04
13+100-9+600-
10+360-10+280- 4 Roller(0552) 1 2.17 810 1757.7
21,676.88 5,419.22 27,096.10 32.72 1,740.00 56,932.80 29,836.70
10+400-11+440- 5 Roller(0148) 1 0 697 0
11+900)
6 W/Truck(59807) 1 3.5 300 1050
7 W/Truck(60122) 1 0 300 0
Total 18,966.95 2,709.93 -
1 Loader(1376) 1 0 649 0 foreman 1 0.25 12 3 45.83 137.49
2 Loader(0266) 1 0 649 0 Laborer 10 1.00 12 120 8.27 992.4
No. D/Truck Km No.Trip Capacity operator 3 1.00 12 36 43.89 1580.04
1 D/Truck(28793) 5 1 13.9 276.61
2 D/Truck(34083) 5 1 13.6 270.64
3 D/Truck(34761) 5 1 13.8 274.62
4 D/Truck(44662) 5 1 16.5 328.35
Borrow Haulling
(15+720-16+020) 5 D/Truck(53411) 5 1 17.6 350.24
6739.68 1684.92 8,424.60 83.34 202.50 16,876.35 8,451.75
6 D/Truck(57038) 5 1 16.7 332.33
7 D/Truck(32940) 5 1 14 278.6
8 D/Truck(27783) 5 1 14 278.6
9 D/Truck(29177) 5 1 14 278.6
10 D/Truck(16834) 5 1 12.4 246.76
11 D/Truck(62148) 5 1 14 278.6
12 D/Truck(59754) 5 3 14 835.8
Total 4029.75 2709.93
1 Loader(0968) 1 8.92 649 5789.08 foreman 1 0.60 12 7.2 45.83 329.976
2 Loader(1376) 1 5 649 3245 Laborer 14 1.00 12 168 8.27 1389.36
3 Loader(0266) 1 6.58 649 4270.42 operator 3 1.00 12 36 43.89 1580.04
No. D/Truck Km No.Trip Capacity
1 D/Truck(44662) 5 1 16.5 328.35
2 D/Truck(53411) 5 5 17.6 1751.2
3 D/Truck(29177) 5 6 14 1671.6
4 D/Truck(59755) 5 1 14 278.6
Sub base haulling 5 D/Truck(59754) 5 4 14 1114.4
(14+040- 6 D/Truck(27783) 5 5 14 1393
14+400) 34939.736 8734.934 43,674.67 83.34 921.40 76,789.48 33,114.81
7 D/Truck(32940) 5 4 14 1114.4
8 D/Truck(28793) 5 5 13.9 1383.05
9 D/Truck(34761) 5 5 13.8 1373.1
10 D/Truck(16834) 5 4 12.4 987.04
11 D/Truck(34083) 5 5 13.6 1353.2
12 D/Truck(62148) 5 5 14 1393
13 D/Truck(58803) 5 4 16 1273.6
14 D/Truck(58804) 5 5 16 1592
14 D/Truck(57038) 5 4 16.7 1329.32
Total 31640.36 3299.376
1 Grader(60025) 1 8.17 1115.00 9109.55 foreman 1 0.50 12 6 45.83 274.98
2 Grader(59992) 1 8 1115.00 8920 Laborer 10 1.00 12 120 8.27 992.4
3 Grader(0097) 1 7.83 1140.85 8932.8555 operator 3 1.00 12 36 43.89 1580.04
4 Grader(59998) 1 9 1140.85 10267.65
Borrow 5 Roller(0814) 1 4.92 810.00 3985.2
Placing(14+720- 6 Roller(0292) 1 5.67 812.00 4604.04
14+960-15+380- 7 Roller(58837) 1 5.5 810.00 4455 71,231.52 17,807.88 89,039.39 32.72 1,740.00 56,932.80 -32,106.59
15+580)
8 Roller(0483) 1 4 810.00 3240
9 Roller(0620) 1 5.58 810.00 4519.8
10 W/truck(59804) 1 11.5 300.00 3450
11 W/truck(59808) 1 11.5 300.00 3450
12 W/truck(59831) 1 11.5 300.00 3450
Total 68,384.10 2,847.42 -
1 Grader(0538) 1 0 1115.00 0 foreman 1 0.50 12 6 45.83 274.98
2 Grader(0166) 1 0 1115.00 0 Laborer 10 1.00 12 120 8.27 992.4
3 Grader(59992) 1 0 1115.00 0 operator 3 1.00 12 36 43.89 1580.04
Sub base Placing
(19+960-20+100) 4 Roller(61308007) 1 0 810.00 0
2,847.42 711.86 3,559.28 32.72 1,740.00 56,932.80 53,373.53
5 Roller(0483) 1 0 810.00 0
6 W/truck(59804) 1 0 300.00 0
7 W/truck(59831) 1 0 300.00 0
Total - 2,847.42 -
1 Loader(0544) 1 0 649 0 Laborer 2 1.00 12 24 8.27 198.48
No. D/Truck Km No.Trip Capacity operator 2 1.00 12 24 43.89 1053.36
Waste 1 D/Truck(28854) 5 0 18 0
Haulling(17+400-
17+420) 2 D/Truck(27593) 5 0 16 0 1251.84 312.96 1,564.80 26.42 - - -1,564.80
3 D/Truck(47608) 5 0 16 0
4 D/Truck(62147) 5 0 14 0
Total 0 1251.84
Total Sum 357,003.41 #REF! #REF!
Activity Total Direct 25% Unit Rate Excuted Amount Net Amount
Equipment No of Workin Man Hour Hourly Cost Over Head Total Cost
Description Description U.F Working Hourly Rate Amount Trade Worker U.F g Hour F=(D*G) Indexed Amount Material Unit Quantity (I) Unit(J)Cost Amount (m) Quantity (n) o=(m*n)
Hour (A) (B) C=(A*B) H=(F*G) Description K=(I*J) L=(C+H+K) Cost
(With Plate No) s (D) (E) Rate(G)
No
1 Loader(58546) 1.00 12 579.00 6948 Foreman 3 1.00 12 36 43.46 1564.56 cement qtl 15.80 185 2922.743056
2 Mixer(59976) 1.00 11.5 250 2875 Laborer 100 1.00 12 1200 8.27 9924 sand m3 3.41 350 1194.375
Masonry 3 Mixer(79412) 1.00 11.5 250 2875 Mason 40 1.00 12 480 22.78 10934.4 stone m3 9.10 500 4550
construction 4 Mixer(00542) 1.00 11.5 250 2875 carpenter 4 1.00 12 48 22.78 1093.44 55,615.12 13,903.78 69,518.90 1,207.77 13.00 15,701.01 -53,817.89
5 Mixer(05157) 1.00 11.5 250 2875 Laborer Foreman 4 1.00 12 48 13.13 630.24
6 W/ truck (59802) 1.00 11 300 3300 operator 2 1.00 12 24 43.89 1053.36
Total 21,748.00 25,200.00 8,667.12
1 Mixer(78080) 0.50 11.5 250 1437.5 Foreman 1 0.33 12 3.96 43.46 172.1016 cement qtl 10.64 185 1968.4
2 W/ truck (58998) 0.50 11 300 1650 Laborer 15 1.00 12 180 8.27 1488.6 sand m3 1.18 350 411.6
Pipe production
(19+500) 3 operator 1 0.50 12 6 43.89 263.34 Aggregate m3 2.80 600 1680
16,021.66 4,005.41 20,027.07 2,113.22 7.00 14,792.54 -5,234.53
4 Mason 5 1.00 12 60 22.78 1366.8 R.bar ton 0.22 21740 4,763.23
5 Barbender 3 1.00 12 36 22.78 820.08
Total 3,087.50 4,110.92 8,823.23
1 Loader(34686) 1.00 3 579.00 1737 Foreman 1 0.33 12 3.96 43.46 172.10 cement qtl 12.25 185 2266.472
Ditch cover 2 Mixer(78080) 0.50 11.5 250 1437.5 Laborer 15 1.00 12 180 8.27 1488.6 sand m3 1.35 350 473.928
production 3 W/ truck (58998) 0.50 11 300 1650 operator 1 0.50 12 6 43.89 263.34 Aggregate m3 3.22 600 1934.4
(19+500) 27,089.02 6,772.26 33,861.28 420.00 62.00 26,040.00 -7,821.28
4 Mason 5 1.00 12 60 22.78 1366.8 R.bar ton 0.62 21740 13,478.80
5 Barbender 3 1.00 12 36 22.78 820.08
Total 4,824.50 4,110.92 18,153.60
1 Loader(58552) 1.00 2.5 579.00 1447.5 Foreman 0 1.00 0 0 43.46 0
Backfill using 2 Roller(58834) 1.00 5 550 2750 Laborer 3 1.00 12 36 8.27 297.72
imported
material 3 Excavator(58756) 1.00 0 1326 0 operator 3 1.00 12 36 43.89 1580.04
7,882.82 1,970.71 9,853.53 88.26 16.00 1,412.16 -8,441.37
(7+384) 4 Loader(58546) 0.30 0 579 0 Laborer Foreman 1 1.00 12 12 13.13 157.56
Base course 1 Crusher(45023) 1 8.25 3600 29700 foreman 1 0.25 12 3 45.83 137.49
crushing 2 Loader(58545) 1 11 579 6369 operator 2 1.00 17 34 43.89 1492.26
(5+000) 39584.31 9896.0775 49,480.39 179.95 - - -49,480.39
3 Laborer 19 1.00 12 228 8.27 1885.56
Total 36069 3515.31
Activity Total Direct 25% Unit Rate Excuted Amount Net Amount
Equipment Working Hourly Rate Amount No of Workin Man Hour Hourly Amount Material Unit Cost Amount Cost Over Head Total Cost
Description Description hy Trade Worker U.F g Hour Indexed Unit Quantity (I) L=(C+H+K) Cost (m) Quantity (n) o=(m*n)
(With Plate No) Hour (A) (B) C=(A*B) s (D) (E) F=(D*G) Rate(G) H=(F*G) Description (J) K=(I*J)
No
1 Grader(60200) 1 12 1115.00 13380 foreman 1 0.60 12 7.2 45.83 329.976
Borrow 2 Grader(0538) 1 5.5 1140.90 6274.95 Laborer 12 1.00 12 144 8.27 1190.88
Placing(6+820- 3 Roller(0498) 1 10.5 810.00 8505 operator 3 1.00 12 36 43.89 1580.04
7+000-6+200-
6+340-7+700- 4 Roller(0292) 1 0 812.00 0
41,243.85 10,310.96 51,554.81 32.72 1,380.00 45,153.60 -6,401.21
7+900-7+000- 5 Roller(0283) 1 7 812.00 5684
7+360) 6 W/truck(60122) 1 8.83 300.00 2649
7 W/truck(59813) 1 5.5 300.00 1650
Total 38,142.95 3,100.90 -
1 Dozer(0676) 1 8.17 1900 15523 foreman 1 0.20 12 2.4 45.83 109.992
Rock excavation
(4+700-4+900) 2 Laborer 1 1.00 12 12 8.27 99.24
15732.232 3933.058 19,665.29 155.16 155.23 24,085.49 4,420.20
3
Total 15523 209.232
1 Excavator(1149) 1 3.58 1474 5276.92 foreman 1 0.60 12 7.2 45.83 329.976
Cut to waste No. D/Truck Km No.Trip Capacity 1650
(7+720-7+760- 1 D/Truck(59752) 5 0 14 0
7+820-7+860) 7256.896 1814.224 9,071.12 45.09 #REF! #REF! #REF!
2 D/Truck(59777) 5 0 14 0
3 D/Truck(59731) 5 0 14 0
Total 6926.92 329.976
1 Loader(0905) 1 4.25 649 2758.25 foreman 1 0.60 12 7.2 45.83 329.976
No. D/Truck Km No.Trip Capacity operator 3 1.00 12 36 43.89 1580.04
1 D/Truck(53834) 5 3 16.7 996.99
2 D/Truck(58805) 5 1 16 318.4
3 D/Truck(58806) 5 3 16 955.2
4 D/Truck(47608) 5 4 17.9 1424.84
Borrow Haulling
(10+200) 5 D/Truck(32939) 5 2 14 557.2
13458.096 3364.524 16,822.62 33.33 441.70 14,721.86 -2,100.76
6 D/Truck(54263) 5 2 14 557.2
7 D/Truck(57995) 5 2 14 557.2
4 D/Truck(62147) 5 3 14 835.8
5 D/Truck(27593) 5 3 14 835.8
6 D/Truck(28263) 5 4 14 1114.4
7 D/Truck(58982) 5 2 16 636.8
Total 11548.08 1910.016
1 Loader(0905) 1 4.58 649 2972.42 foreman 1 0.60 12 7.2 45.83 329.976
No. D/Truck Km No.Trip Capacity Laborer 10 1.00 12 120 8.27 992.4
1 D/Truck(53834) 5 5 16.7 1661.65 operator 3 1.00 12 36 43.89 1580.04
2 D/Truck(58805) 5 5 16 1592
3 D/Truck(58806) 5 5 16 1592
4 D/Truck(47608) 5 5 17.9 1781.05
5 D/Truck(32939) 5 6 14 1671.6
Sub base haulling
(10+200) 6 D/Truck(54263) 5 6 18 2149.2 24107.216 6026.804 30,134.02 83.34 916.20 76,356.11 46,222.09
7 D/Truck(57995) 5 5 13.8 1373.1
8 D/Truck(62147) 5 7 14 1950.2
9 D/Truck(27593) 5 7 14 1950.2
10 D/Truck(28263) 5 5 14 1393
11 D/Truck(58982) 5 2 14 557.2
12 D/Truck(59769) 5 1 14 278.6
13 D/Truck(28854) 5 1 14.2 282.58
Total 21204.8 2902.416
1 Loader(0266) 1 0 649 0 foreman 1 0.60 12 7.2 45.83 329.976
No. D/Truck Km No.Trip Capacity Laborer 1 1.00 12 12 8.27 99.24
1 D/Truck(59752) 5 0 14 0 operator 3 1.00 12 36 43.89 1580.04
2 D/Truck(58979) 5 0 16 0
Waste haulling
(7+600) 3 D/Truck(59912) 5 0 16 0
2009.256 502.314 2,511.57 83.34 - - -2,511.57
4 D/Truck(59933) 5 0 14 0
5 D/Truck(58980) 5 0 16 0
6 D/Truck(60117) 5 0 16 0
7 D/Truck(58979) 5 0 16 0
Total 0 2009.256
1 Excavator(0789) 1 3.17 1474 4672.58 foreman 1 0.60 12 7.2 45.83 329.976
2 Excavator(1149) 1 4.42 1474 6515.08 Laborer 14 1.00 12 168 8.27 1389.36
3 Dozer(58829) 1 10 2500.9 25009 operator 3 1.00 12 36 43.89 1580.04
4 Loader(0544) 1 7.33 649 4757.17
No. D/Truck Km No.Trip Capacity 0
1 D/Truck(58805) 5 7 16 2228.8
2 D/Truck(54263) 5 9 18 3223.8
3 D/Truck(28263) 5 7 14 1950.2
Cut to waste
(9+480-9+540- 4 D/Truck(27593) 5 9 14 2507.4
9+480-9+520- 6 D/Truck(32939) 5 8 14 2228.8
9+500-9+540- 74351.956 18587.989 92,939.95 45.09 #REF! #REF! #REF!
9+500-9+540) 7 D/Truck(58806) 5 7 16 2228.8
8 D/Truck(47608) 5 8 17.9 2849.68
9 D/Truck(27958) 5 8 14 2228.8
10 D/Truck(53834) 5 7 16.7 2326.31
11 D/Truck(57995) 5 8 13.8 2196.96
12 D/Truck(62147) 5 8 14 2228.8
13 D/Truck(59777) 5 8 14 2228.8
14 D/Truck(59759) 5 1 14 278.6
15 D/Truck(58982) 5 5 14 1393
Total 71052.58 3299.376
1 Loader(0396) 1 1 649 649 foreman 1 0.60 12 7.2 45.83 329.976
No. D/Truck Km No.Trip Capacity Laborer 14 1.00 12 168 8.27 1389.36
1 D/Truck(58805) 5 1 16 318.4 operator 3 1.00 12 36 43.89 1580.04
3 D/Truck(27958) 5 1 14 278.6
5 D/Truck(27593) 5 1 14 278.6
Borrow Material 6 D/Truck(58806) 5 3 16 955.2
Haulling(10+200) 7 D/Truck(32939) 5 1 14 278.6 9546.246 2386.5615 11,932.81 33.33 281.30 9,375.73 -2,557.08
3 D/Truck(47608) 5 1 17.9 356.21
4 D/Truck(47608) 5 0 17.9 0
5 D/Truck(28263) 5 1 14 278.6
6 D/Truck(54263) 5 1 18 358.2
7 D/Truck(59924) 5 6 14 1671.6
Total 6246.87 3299.376
1 Loader(0968) 1 0 649 0 Laborer 2 1.00 12 24 8.27 198.48
No. D/Truck Km No.Trip Capacity operator 2 1.00 12 24 43.89 1053.36
Waste 1 D/Truck(62148) 5 0 18 0
Haulling(11+500-
11+540) 2 D/Truck(58803) 5 0 16 0 1251.84 312.96 1,564.80 26.42 - - -1,564.80
3 D/Truck(34761) 5 0 13.8 0
4 D/Truck(28793) 5 0 13.9 0
Total 0 1251.84
1 Grader(55656) 1 9 1141 10268.1 foreman 1 0.25 12 3 45.83 137.49
Borrow 2 Grader(0166) 1 7.5 1115 8362.5 Laborer 10 1.00 12 120 8.27 992.4
Placing(12+800- 3 Grader(59990) 1 6 1115 6690 operator 3 1.00 12 36 43.89 1580.04
12+900-12+220-
12+400-12+020- 4 Roller(0552) 1 8.92 810 7225.2 44,107.48 11,026.87 55,134.35 32.72 1,740.00 56,932.80 1,798.45
12+100-10+460- 5 Roller(0148) 1 7.75 697 5401.75
10+740)
6 W/Truck(59807) 1 11.5 300 3450
7 W/Truck(60122) 1 0 300 0
Total 41,397.55 2,709.93 -
1 Loader(1376) 1 0 649 0 foreman 1 0.25 12 3 45.83 137.49
2 Loader(0266) 1 0 649 0 Laborer 10 1.00 12 120 8.27 992.4
No. D/Truck Km No.Trip Capacity operator 3 1.00 12 36 43.89 1580.04
1 D/Truck(28793) 5 0 13.9 0
2 D/Truck(34083) 5 0 13.6 0
3 D/Truck(34761) 5 0 13.8 0
4 D/Truck(44662) 5 0 16.5 0
Borrow Haulling
(15+720-16+020) 5 D/Truck(53411) 5 0 17.6 0
2709.93 677.4825 3,387.41 83.34 - - -3,387.41
6 D/Truck(57038) 5 0 16.7 0
7 D/Truck(32940) 5 0 14 0
8 D/Truck(27783) 5 0 14 0
9 D/Truck(29177) 5 0 14 0
10 D/Truck(16834) 5 0 12.4 0
11 D/Truck(62148) 5 0 14 0
12 D/Truck(59754) 5 0 14 0
Total 0 2709.93
1 Loader(0396) 1 0 649 0 foreman 1 0.60 12 7.2 45.83 329.976
No. D/Truck Km No.Trip Capacity Laborer 14 1.00 12 168 8.27 1389.36
1 D/Truck(62148) 5 3 14 835.8 operator 3 1.00 12 36 43.89 1580.04
2 D/Truck(57038) 5 4 16.7 1329.32
3 D/Truck(53411) 5 3 17.6 1050.72
4 D/Truck(32940) 5 4 14 1114.4
5 D/Truck(27783) 5 4 14 1114.4
Caping Material 6 D/Truck(28793) 5 3 13.9 829.83
Haulling(16+360- 7 D/Truck(34761) 5 4 13.8 1098.48
16+600) 21728.766 5432.1915 27,160.96 33.33 926.10 30,866.91 3,705.96
8 D/Truck(29177) 5 4 14 1114.4
9 D/Truck(16834) 5 4 12.4 987.04
10 D/Truck(58804) 5 4 16 1273.6
11 D/Truck(58803) 5 4 16 1273.6
12 D/Truck(59754) 5 5 14 1393
13 D/Truck(59755) 5 10 14 2786
14 D/Truck(58978) 5 5 14 1393
15 D/Truck(59759) 5 3 14 835.8
Total 18429.39 3299.376
1 Loader(0968) 1 10.58 649 6866.42 foreman 1 0.60 12 7.2 45.83 329.976
2 Loader(1376) 1 6.25 649 4056.25 Laborer 14 1.00 12 168 8.27 1389.36
3 Loader(0266) 1 7.33 649 4757.17 operator 3 1.00 12 36 43.89 1580.04
No. D/Truck Km No.Trip Capacity
1 D/Truck(53411) 5 4 17.6 1400.96
2 D/Truck(27783) 5 4 14 1114.4
3 D/Truck(32940) 5 5 14 1393
4 D/Truck(62148) 5 5 14 1393
Sub base haulling
(13+720- 5 D/Truck(34761) 5 5 13.8 1373.1
14+040) 6 D/Truck(28793) 5 3 13.9 829.83 38710.066 9677.5165 48,387.58 83.34 991.50 82,631.61 34,244.03
7 D/Truck(16834) 5 4 12.4 987.04
8 D/Truck(29177) 5 5 14 1393
9 D/Truck(58803) 5 5 16 1592
10 D/Truck(57038) 5 4 16.7 1329.32
11 D/Truck(58804) 5 6 16 1910.4
12 D/Truck(59754) 5 6 14 1671.6
13 D/Truck(59755) 5 6 14 1671.6
14 D/Truck(58978) 5 6 14 1671.6
Total 35410.69 3299.376
1 Grader(60025) 1 6.5 1115.00 7247.5 foreman 1 0.50 12 6 45.83 274.98
2 Grader(59992) 1 0 1115.00 0 Laborer 10 1.00 12 120 8.27 992.4
3 Grader(0097) 1 6.5 1140.85 7415.525 operator 3 1.00 12 36 43.89 1580.04
4 Grader(59998) 1 7.5 1140.85 8556.375
Borrow 5 Roller(0814) 1 3.08 810.00 2494.8
Placing(14+360- 6 Roller(0292) 1 5.67 812.00 4604.04
14+400-15+940- 7 Roller(58837) 1 5 810.00 4050 57,285.66 14,321.42 71,607.08 32.72 1,740.00 56,932.80 -14,674.28
16+260)
8 Roller(0483) 1 5 810.00 4050
9 Roller(0620) 1 7 810.00 5670
10 W/truck(59804) 1 11.5 300.00 3450
11 W/truck(59808) 1 11.5 300.00 3450
12 W/truck(59831) 1 11.5 300.00 3450
Total 54,438.24 2,847.42 -
1 Grader(0538) 1 0 1115.00 0 foreman 1 0.50 12 6 45.83 274.98
2 Grader(0166) 1 0 1115.00 0 Laborer 10 1.00 12 120 8.27 992.4
3 Grader(59992) 1 0 1115.00 0 operator 3 1.00 12 36 43.89 1580.04
Sub base Placing
(19+960-20+100) 4 Roller(61308007) 1 0 810.00 0
2,847.42 711.86 3,559.28 32.72 1,740.00 56,932.80 53,373.53
5 Roller(0483) 1 0 810.00 0
6 W/truck(59804) 1 0 300.00 0
7 W/truck(59831) 1 0 300.00 0
Total - 2,847.42 -
1 Loader(0544) 1 0 649 0 Laborer 2 1.00 12 24 8.27 198.48
No. D/Truck Km No.Trip Capacity operator 2 1.00 12 24 43.89 1053.36
Waste 1 D/Truck(28854) 5 0 18 0
Haulling(17+400-
17+420) 2 D/Truck(27593) 5 0 16 0 1251.84 312.96 1,564.80 26.42 - - -1,564.80
3 D/Truck(47608) 5 0 16 0
4 D/Truck(62147) 5 0 14 0
Total 0 1251.84
Total Sum 446,998.43 #REF! #REF!
Activity Total Direct 25% Unit Rate Excuted Amount Net Amount
Equipment No of Workin Man Hour Hourly Cost Over Head Total Cost
Description Description U.F Working Hourly Rate Amount Trade Worker U.F g Hour F=(D*G) Indexed Amount Material Unit Quantity (I) Unit(J)Cost Amount (m) Quantity (n) o=(m*n)
Hour (A) (B) C=(A*B) H=(F*G) Description K=(I*J) L=(C+H+K) Cost
(With Plate No) s (D) (E) Rate(G)
No
1 Loader(58546) 1.00 12 579.00 6948 Foreman 3 1.00 12 36 43.46 1564.56 cement qtl 15.80 185 2922.743056
2 Mixer(59976) 1.00 11.5 250 2875 Laborer 100 1.00 12 1200 8.27 9924 sand m3 3.41 350 1194.375
Masonry 3 Mixer(79412) 1.00 11.5 250 2875 Mason 40 1.00 12 480 22.78 10934.4 stone m3 9.10 500 4550
construction 4 Mixer(00542) 1.00 11.5 250 2875 carpenter 4 1.00 12 48 22.78 1093.44 55,615.12 13,903.78 69,518.90 1,207.77 13.00 15,701.01 -53,817.89
5 Mixer(05157) 1.00 11.5 250 2875 Laborer Foreman 4 1.00 12 48 13.13 630.24
6 W/ truck (59802) 1.00 11 300 3300 operator 2 1.00 12 24 43.89 1053.36
Total 21,748.00 25,200.00 8,667.12
1 Mixer(78080) 0.50 11.5 250 1437.5 Foreman 1 0.33 12 3.96 43.46 172.1016 cement qtl 10.64 185 1968.4
2 W/ truck (58998) 0.50 11 300 1650 Laborer 15 1.00 12 180 8.27 1488.6 sand m3 1.18 350 411.6
Pipe production
(19+500) 3 operator 1 0.50 12 6 43.89 263.34 Aggregate m3 2.80 600 1680
16,021.66 4,005.41 20,027.07 2,113.22 7.00 14,792.54 -5,234.53
4 Mason 5 1.00 12 60 22.78 1366.8 R.bar ton 0.22 21740 4,763.23
5 Barbender 3 1.00 12 36 22.78 820.08
Total 3,087.50 4,110.92 8,823.23
Prepared By:________________________________________________ Checked By:_________________________________________________ Approved BY:_________________________________________________
1 Loader(34686) 1.00 3 579.00 1737 Foreman 1 0.33 12 3.96 43.46 172.10 cement qtl 12.25 185 2266.472
Ditch cover 2 Mixer(78080) 0.50 11.5 250 1437.5 Laborer 15 1.00 12 180 8.27 1488.6 sand m3 1.35 350 473.928
production 3 W/ truck (58998) 0.50 11 300 1650 operator 1 0.50 12 6 43.89 263.34 Aggregate m3 3.22 600 1934.4
(19+500) 27,089.02 6,772.26 33,861.28 420.00 62.00 26,040.00 -7,821.28
4 Mason 5 1.00 12 60 22.78 1366.8 R.bar ton 0.62 21740 13,478.80
5 Barbender 3 1.00 12 36 22.78 820.08
Total 4,824.50 4,110.92 18,153.60
1 Loader(58552) 1.00 2.5 579.00 1447.5 Foreman 0 1.00 0 0 43.46 0
Backfill using 2 Roller(58834) 1.00 5 550 2750 Laborer 3 1.00 12 36 8.27 297.72
imported
material 3 Excavator(58756) 1.00 0 1326 0 operator 3 1.00 12 36 43.89 1580.04
7,882.82 1,970.71 9,853.53 88.26 16.00 1,412.16 -8,441.37
(7+384) 4 Loader(58546) 0.30 0 579 0 Laborer Foreman 1 1.00 12 12 13.13 157.56
5 Roller(58842) 1.00 3 550 1650
Total 5,847.50 2,035.32 -
1 Excavator(1149) 1 0 1474 0
No. D/Truck Km No.Trip Capacity
1 D/Truck(58978) 5 0 8 0 Laborer 0 1.00 0 0 8.27 0
Excavation for
open drain 2 D/Truck(59758) 5 0 8 0 foreman 1 0.50 0 0 43.46 0
(8+020-8+180) 3 D/Truck(59731) 5 0 8 0 operator 6 1.00 0 0 43.89 0 0 0 - 92.72 - - 0.00
4 D/Truck(59752) 5 0 8 0
5 D/Truck(59940) 5 0 8 0
6 D/Truck(58982) 5 0 8 0
Total 0 0
1 Loader(58555) 1.00 0 579.00 0 Foreman 1 1.00 0 0 43.46 0
pipe Installation 2 Excavator(58756) 1.00 0 1326 0 Laborer 15 1.00 0 0 8.27 0
(0+611) 3 operator 2 1.00 0 0 43.89 0 - - - 775.79 - - 0.00
4 Mason 5 1.00 0 0 22.78 0
Total - - -
Base course
crushing 1 Crusher(45023) 1 7.92 3600 28512 foreman 1 0.25 12 3 45.83 137.49
(5+000) 32027.31 8006.8275 40,034.14 179.95 - - -40,034.14
2 Loader(58545) 0.33 0 579 0 operator 2 1.00 17 34 43.89 1492.26
Total 28512 3515.31
Concrete Aggregate 1 Crusher(39502) 1 5.83 3600 20988 foreman 0 0.25 12 3 45.83 137.49
crushing (5+000) 27014.73 6753.6825 33,768.41 336.59 96.00 32,312.64 -1455.7725
2 Loader(58545) 1 10 579 5790 operator 0 1.00 12 0 43.89 0
Total 26778 236.73
Total Sum 252,017.53 129,229.68 -122,787.85
4 D/Truck(62147) 5 0 14 0
Total 0 1251.84
Total Sum 416,852.86 #REF! #REF!
Total 0 625.92
1 Wagon drill 1 0 1200 0 Laborer 4 1.00 11.5 11.5 8.27 95.105 Dynamite
Quary rock 2 Air compresor 1 0 450 0 operator 3 1.00 11.5 34.5 43.89 1514.205 Blasting caps
Production 3 Dozer(60005) 1 9 2272 20448
(5+000) 22546.77875 5636.694688 28,183.47 122.34 270.00 33,031.80 4,848.33
4 Excavator(58533) 1 0 1326 0 Quary foreman 1 0.25 11.5 2.875 34.05 97.89375
5 powder man 1 1.00 11.5 11.5 34.05 391.575
Total 20448 2098.77875
1 Excavator(58533) 1 0 1326 0 Laborer 1 1.00 12 12 8.27 99.24
2 Loader(58545) 0.33 0 579 0 foreman 1 0.25 12 3 45.83 137.49
Quary rock
Hauling (5+000) 3 D/Truck(59751) 1 10.33 550 5681.5
11599.73 2899.9325 14,499.66 37.66 594.00 22,370.04 7,870.38
4 D/Truck(60111) 1 0 550 0
5 D/Truck(59785) 1 10.33 550 5681.5
Total 11363 236.73
Base course
crushing 1 Crusher(45023) 1 9.58 3600 34488 foreman 1 0.25 12 3 45.83 137.49
(5+000) 44470.74 11117.685 55,588.43 179.95 - - -55,588.43
2 Loader(58545) 0.5 11.17 579 6467.43 operator 2 1.00 17 34 43.89 1492.26
Total 40955.43 3515.31
Concrete
Aggregate 1 Crusher(39502) 1 9.67 3600 34812 foreman 0 0.25 12 3 45.83 137.49
crushing 38282.445 9570.61125 47,853.06 336.59 160.00 53,854.40 6001.34375
(5+000) 2 Loader(58545) 0.5 11.17 579 3233.715 operator 0 1.00 12 0 43.89 0
Total 38045.715 236.73
Total Sum 299,146.84 181,000.64 -118,146.20
Activity Total Direct 25% Unit Rate Excuted Amount Net Amount
Equipment No of Workin Hourly Cost Over Head Total Cost
Working Hourly Rate Amount
g Hour Man
Hour Amount Material
Unit Quantity (I) Unit(J)Cost
Description Amount (m) Quantity (n) o=(m*n)
Description U.F Trade Worker U.F
(With Plate No) Hour (A) (B) C=(A*B) s (D) (E) F=(D*G) Indexed
Rate(G) H=(F*G) Description K=(I*J) L=(C+H+K) Cost
No
1 Loader(58546) 1.00 12 579.00 6948 Foreman 3 1.00 12 36 43.46 1564.56 cement qtl 15.80 185 2922.743056
2 Mixer(59976) 1.00 11.5 250 2875 Laborer 100 1.00 12 1200 8.27 9924 sand m3 3.41 350 1194.375
Masonry 3 Mixer(79412) 1.00 11.5 250 2875 Mason 40 1.00 12 480 22.78 10934.4 stone m3 9.10 500 4550
construction 4 Mixer(00542) 1.00 11.5 250 2875 carpenter 4 1.00 12 48 22.78 1093.44 55,615.12 13,903.78 69,518.90 1,207.77 13.00 15,701.01 -53,817.89
5 Mixer(05157) 1.00 11.5 250 2875 Laborer Foreman 4 1.00 12 48 13.13 630.24
6 W/ truck (59802) 1.00 11 300 3300 operator 2 1.00 12 24 43.89 1053.36
Total 21,748.00 25,200.00 8,667.12
Total 0 625.92
1 Wagon drill 1 0 1200 0 Laborer 4 1.00 11.5 11.5 8.27 95.105 Dynamite
Quary rock 2 Air compresor 1 0 450 0 operator 3 1.00 11.5 34.5 43.89 1514.205 Blasting caps
Production 3 Dozer(60005) 1 9.5 2272 21584
(5+000) 23682.77875 5920.694688 29,603.47 122.34 180.00 22,021.20 -7,582.27
4 Excavator(58533) 1 0 1326 0 Quary foreman 1 0.25 11.5 2.875 34.05 97.89375
5 powder man 1 1.00 11.5 11.5 34.05 391.575
Total 21584 2098.77875
1 Excavator(58533) 1 0 1326 0 Laborer 1 1.00 12 12 8.27 99.24
2 Loader(58545) 0.33 0 579 0 foreman 1 0.25 12 3 45.83 137.49
Quary rock
Hauling (5+000) 3 D/Truck(59751) 1 11 550 6050
18111.73 4527.9325 22,639.66 37.66 581.00 21,880.46 -759.20
4 D/Truck(60111) 1 7.17 550 3943.5
5 D/Truck(59785) 1 14.33 550 7881.5
Total 17875 236.73
Base course
crushing 1 Crusher(45023) 1 9.42 3600 33912 foreman 1 0.25 12 3 45.83 137.49
(5+000) 37613.5139 9403.378475 47,016.89 179.95 - - -47,016.89
2 Loader(58545) 0.5 16.67 11.17 186.2039 operator 2 1.00 17 34 43.89 1492.26
Total 34098.2039 3515.31
Concrete
Aggregate 1 Crusher(39502) 1 16.33 3600 58788 foreman 1 0.25 12 3 45.83 137.49
crushing 63850.695 15962.67375 79,813.37 336.59 261.00 87,849.99 8036.62
(5+000) 2 Loader(58545) 0.5 16.67 579 4825.965 operator 0 1.00 12 0 43.89 0
Total 63613.965 236.73
Total Sum 323,418.04 242,721.65 -80,696.39
Activity Total Direct 25% Unit Rate Excuted Amount Net Amount
Equipment Working Hourly Rate Amount No of Workin Man Hour Hourly Amount Material Unit Cost Amount Cost Over Head Total Cost
Description Description U.F Trade Worker U.F g Hour Indexed Unit Quantity (I) (m) Quantity (n) o=(m*n)
Hour (A) (B) C=(A*B) F=(D*G) Rate(G) H=(F*G) Description (J) K=(I*J) L=(C+H+K) Cost
(With Plate No) s (D) (E)
No
1 Loader(58546) 1.00 12 579.00 6948 Foreman 3 1.00 12 36 43.46 1564.56 cement qtl 15.80 185 2922.743056
2 Mixer(59976) 1.00 11.5 250 2875 Laborer 100 1.00 12 1200 8.27 9924 sand m3 3.41 350 1194.375
Masonry 3 Mixer(79412) 1.00 11.5 250 2875 Mason 40 1.00 12 480 22.78 10934.4 stone m3 9.10 500 4550
construction 4 Mixer(00542) 1.00 11.5 250 2875 carpenter 4 1.00 12 48 22.78 1093.44 55,615.12 13,903.78 69,518.90 1,207.77 13.00 15,701.01 -53,817.89
5 Mixer(05157) 1.00 11.5 250 2875 Laborer Foreman 4 1.00 12 48 13.13 630.24
6 W/ truck (59802) 1.00 11 300 3300 operator 2 1.00 12 24 43.89 1053.36
Total 21,748.00 25,200.00 8,667.12
1 Mixer(78080) 0.50 11.5 250 1437.5 Foreman 1 0.33 12 3.96 43.46 172.1016 cement qtl 10.64 185 1968.4
2 W/ truck (58998) 0.50 11 300 1650 Laborer 15 1.00 12 180 8.27 1488.6 sand m3 1.18 350 411.6
Pipe production
(19+500) 3 operator 1 0.50 12 6 43.89 263.34 Aggregate m3 2.80 600 1680
16,021.66 4,005.41 20,027.07 2,113.22 7.00 14,792.54 -5,234.53
4 Mason 5 1.00 12 60 22.78 1366.8 R.bar ton 0.22 21740 4,763.23
5 Barbender 3 1.00 12 36 22.78 820.08
Total 3,087.50 4,110.92 8,823.23
1 Loader(34686) 1.00 3 579.00 1737 Foreman 1 0.33 12 3.96 43.46 172.10 cement qtl 12.25 185 2266.472
Ditch cover 2 Mixer(78080) 0.50 11.5 250 1437.5 Laborer 15 1.00 12 180 8.27 1488.6 sand m3 1.35 350 473.928
production 3 W/ truck (58998) 0.50 11 300 1650 operator 1 0.50 12 6 43.89 263.34 Aggregate m3 3.22 600 1934.4
(19+500) 27,089.02 6,772.26 33,861.28 420.00 62.00 26,040.00 -7,821.28
4 Mason 5 1.00 12 60 22.78 1366.8 R.bar ton 0.62 21740 13,478.80
5 Barbender 3 1.00 12 36 22.78 820.08
Total 4,824.50 4,110.92 18,153.60
1 Loader(58552) 1.00 2.5 579.00 1447.5 Foreman 0 1.00 0 0 43.46 0
Backfill using 2 Roller(58834) 1.00 5 550 2750 Laborer 3 1.00 12 36 8.27 297.72
imported
material 3 Excavator(58756) 1.00 0 1326 0 operator 3 1.00 12 36 43.89 1580.04
7,882.82 1,970.71 9,853.53 88.26 16.00 1,412.16 -8,441.37
(7+384) 4 Loader(58546) 0.30 0 579 0 Laborer Foreman 1 1.00 12 12 13.13 157.56
5 Roller(58842) 1.00 3 550 1650
Total 5,847.50 2,035.32 -
1 Excavator(1149) 1 0 1474 0
No. D/Truck Km No.Trip Capacity
1 D/Truck(58978) 5 0 8 0 Laborer 0 1.00 0 0 8.27 0
Excavation for 2 D/Truck(59758) 5 0 8 0 foreman 1 0.50 0 0 43.46 0
open drain
(8+020-8+180) 3 D/Truck(59731) 5 0 8 0 operator 6 1.00 0 0 43.89 0 0 0 - 92.72 - - 0.00
4 D/Truck(59752) 5 0 8 0
5 D/Truck(59940) 5 0 8 0
6 D/Truck(58982) 5 0 8 0
Total 0 0
1 Loader(58555) 1.00 0 579.00 0 Foreman 1 1.00 0 0 43.46 0
pipe Installation 2 Excavator(58756) 1.00 0 1326 0 Laborer 15 1.00 0 0 8.27 0
(0+611) 3 operator 2 1.00 0 0 43.89 0 - - - 775.79 - - 0.00
4 Mason 5 1.00 0 0 22.78 0
Total - - -
Total 0 625.92
1 Dozer(59282) 1 0 2272 0 Laborer 1 1.00 11.5 12 8.27 99.24
Borrow operator 1 1.00 11.5 12 43.89 526.68
Production
(0+800) 625.92 156.48 782.40 27.00 - - -782.40
Total 0 625.92
1 Wagon drill 1 0 1200 0 Laborer 4 1.00 11.5 11.5 8.27 95.105 Dynamite
Quary rock 2 Air compresor 1 0 450 0 operator 3 1.00 11.5 34.5 43.89 1514.205 Blasting caps
Production 3 Dozer(60005) 1 0 2272 0
(5+000) 2098.77875 524.6946875 2,623.47 122.34 - - -2,623.47
4 Excavator(58533) 1 0 1326 0 Quary foreman 1 0.25 11.5 2.875 34.05 97.89375
5 powder man 1 1.00 11.5 11.5 34.05 391.575
Total 0 2098.77875
1 Excavator(58533) 1 0 1326 0 Laborer 1 1.00 12 12 8.27 99.24
2 Loader(58545) 0.33 0 579 0 foreman 1 0.25 12 3 45.83 137.49
Quary rock
Hauling (5+000) 3 D/Truck(59751) 1 0 550 0
236.73 59.1825 295.91 37.66 - - -295.91
4 D/Truck(60111) 1 0 550 0
5 D/Truck(59785) 1 0 550 0
Total 0 236.73
Base course
crushing 1 Crusher(45023) 1 0 3600 0 foreman 1 0.25 12 3 45.83 137.49
(5+000) 3515.31 878.8275 4,394.14 179.95 - - -4,394.14
2 Loader(58545) 0.33 0 11.17 0 operator 2 1.00 17 34 43.89 1492.26
Total 0 3515.31
Concrete 1 Crusher(39502) 1 0 3600 0 foreman 0 0.25 12 3 45.83 137.49
Aggregate
crushing 236.73 59.1825 295.91 336.59 - - -295.91
(5+000) 2 Loader(58545) 0.33 0 579 0 operator 0 1.00 12 0 43.89 0
Total 0 236.73
Total Sum 138,983.66 38,865.00 -100,118.66
Activity Total Direct 25% Unit Rate Excuted Amount Net Amount
Equipment No of Workin Hourly Cost Over Head Total Cost
Description Description U.F Working Hourly Rate Amount Trade Worker U.F g Hour Man Hour Indexed Amount Material Unit Quantity (I) Unit Cost Amount (m) Quantity (n) o=(m*n)
Hour (A) (B) C=(A*B) F=(D*G) Rate(G) H=(F*G) Description (J) K=(I*J) L=(C+H+K) Cost
(With Plate No) s (D) (E)
No
1 Loader(58546) 1.00 12 579.00 6948 Foreman 3 1.00 12 36 43.46 1564.56 cement qtl 15.80 185 2922.743056
2 Mixer(59976) 1.00 11.5 250 2875 Laborer 100 1.00 12 1200 8.27 9924 sand m3 3.41 350 1194.375
Masonry 3 Mixer(79412) 1.00 11.5 250 2875 Mason 40 1.00 12 480 22.78 10934.4 stone m3 9.10 500 4550
construction 4 Mixer(00542) 1.00 11.5 250 2875 carpenter 4 1.00 12 48 22.78 1093.44 55,615.12 13,903.78 69,518.90 1,207.77 13.00 15,701.01 -53,817.89
5 Mixer(05157) 1.00 11.5 250 2875 Laborer Foreman 4 1.00 12 48 13.13 630.24
6 W/ truck (59802) 1.00 11 300 3300 operator 2 1.00 12 24 43.89 1053.36
Total 21,748.00 25,200.00 8,667.12
1 Mixer(78080) 0.50 11.5 250 1437.5 Foreman 1 0.33 12 3.96 43.46 172.1016 cement qtl 10.64 185 1968.4
2 W/ truck (58998) 0.50 11 300 1650 Laborer 15 1.00 12 180 8.27 1488.6 sand m3 1.18 350 411.6
Pipe production
(19+500) 3 operator 1 0.50 12 6 43.89 263.34 Aggregate m3 2.80 600 1680
16,021.66 4,005.41 20,027.07 2,113.22 7.00 14,792.54 -5,234.53
4 Mason 5 1.00 12 60 22.78 1366.8 R.bar ton 0.22 21740 4,763.23
5 Barbender 3 1.00 12 36 22.78 820.08
Total 3,087.50 4,110.92 8,823.23
1 Loader(34686) 1.00 3 579.00 1737 Foreman 1 0.33 12 3.96 43.46 172.10 cement qtl 12.25 185 2266.472
Ditch cover 2 Mixer(78080) 0.50 11.5 250 1437.5 Laborer 15 1.00 12 180 8.27 1488.6 sand m3 1.35 350 473.928
production 3 W/ truck (58998) 0.50 11 300 1650 operator 1 0.50 12 6 43.89 263.34 Aggregate m3 3.22 600 1934.4
(19+500) 27,089.02 6,772.26 33,861.28 420.00 62.00 26,040.00 -7,821.28
4 Mason 5 1.00 12 60 22.78 1366.8 R.bar ton 0.62 21740 13,478.80
5 Barbender 3 1.00 12 36 22.78 820.08
Total 4,824.50 4,110.92 18,153.60
1 Loader(58552) 1.00 2.5 579.00 1447.5 Foreman 0 1.00 0 0 43.46 0
Backfill using 2 Roller(58834) 1.00 5 550 2750 Laborer 3 1.00 12 36 8.27 297.72
imported
material 3 Excavator(58756) 1.00 0 1326 0 operator 3 1.00 12 36 43.89 1580.04
7,882.82 1,970.71 9,853.53 88.26 16.00 1,412.16 -8,441.37
(7+384) 4 Loader(58546) 0.30 0 579 0 Laborer Foreman 1 1.00 12 12 13.13 157.56
5 Roller(58842) 1.00 3 550 1650
Total 5,847.50 2,035.32 -
1 Excavator(1149) 1 0 1474 0
No. D/Truck Km No.Trip Capacity
1 D/Truck(58978) 5 0 8 0 Laborer 0 1.00 0 0 8.27 0
Excavation for 2 D/Truck(59758) 5 0 8 0 foreman 1 0.50 0 0 43.46 0
open drain
(8+020-8+180) 3 D/Truck(59731) 5 0 8 0 operator 6 1.00 0 0 43.89 0 0 0 - 92.72 - - 0.00
4 D/Truck(59752) 5 0 8 0
5 D/Truck(59940) 5 0 8 0
6 D/Truck(58982) 5 0 8 0
Total 0 0
1 Loader(58555) 1.00 0 579.00 0 Foreman 1 1.00 0 0 43.46 0
pipe Installation 2 Excavator(58756) 1.00 0 1326 0 Laborer 15 1.00 0 0 8.27 0
(0+611) 3 operator 2 1.00 0 0 43.89 0 - - - 775.79 - - 0.00
4 Mason 5 1.00 0 0 22.78 0
Total - - -