Professional Documents
Culture Documents
Note:
*Rental rates are used to calculate the cost of ERCC dump trucks
*Contract rates are used to calculate the cost of ERCC machineries other than dump trucks
13/2/2014
Cost Revenue Net amount Net %
Material Production 345,149.85 260,933.00 -84,216.85 -32.28%
Borrow/sub base production 245,480.62 188,055.00 -57,425.62 -30.54%
Quary rock production & haulling 39,662.28 6,854.12 -32,808.16 -478.66%
Base Course Crushing 24,446.79 21,594.00 -2,852.79 -13.21%
Concrete Agg. Crushing 35,560.16 44,429.88 8,869.72 19.96%
Earthwork 522,556.57 452,395.72 -70,160.85 -15.51%
Section 1 (0+000-21+900) 352,656.35 302,777.86 -49,878.48 -16.47%
Mulugeta Site 86,651.07 69,371.35 -17,279.73 -24.91%
Samuel site 67,964.19 41,192.51 -26,771.68 -64.99%
Kidus Site 198,041.09 192,214.01 -5,827.08 -3.03%
Section 2 (18+700-29+500) 169,900.23 149,617.86 -20,282.37 -13.56%
Henok Site / Feleke site 169,900.23 149,617.86 -20,282.37 -13.56%
Total 0 625.92
1 Wagon drill 1 0 1200 0 Laborer 4 1.00 11.5 11.5 8.27 95.105 Dynamite
Quary rock 2 Air compresor 1 0 450 0 operator 3 1.00 11.5 34.5 43.89 1514.205 Blasting caps
Production 3 Dozer(60005) 1 3.5 2272 7952
(5+000) 10050.77875 2512.694688 12,563.47 122.34 - - -12,563.47
4 Excavator(58533) 1 0 1326 0 Quary foreman 1 0.25 11.5 2.875 34.05 97.89375
5 powder man 1 1.00 11.5 11.5 34.05 391.575
Total 7952 2098.77875
1 Excavator(58533) 1 0 1326 0 Laborer 1 1.00 12 12 8.27 99.24
Quary rock 2 Loader(58545) 0.33 0 579 0 foreman 1 0.25 12 3 45.83 137.49
Hauling (5+000) 3 D/Truck(59785) 1 8.33 550 4581.5 4818.23 1204.5575 6,022.79 37.66 234.00 8,812.44 2,789.65
4 D/Truck(58982) 1 0 550 0
Total 4581.5 236.73
Material Loading 1 Loader(1376) 1 6.42 649 4166.58 Laborer 1 1.00 12 12 8.27 99.24
(5+000) 2 foreman 1 0.25 12 3 45.83 137.49
3 4403.31 1100.8275 5,504.14 27.00 - - -5,504.14
Activity Total Direct 25% Unit Rate Excuted Amount Net Amount
Description Cost Over Head Total Cost (m) Quantity (n) o=(m*n)
Prepared By:________________________________________________ Checked By:_________________________________________________ Approved BY:_________________________________________________
L=(C+H+K) Cost
No
Total Direct 25% Net Amount
Activity Equipment No of Workin Man Hour Hourly Cost Over Head Total Cost Unit Rate Excuted Amount
Description Working Hourly Rate Amount Amount Material Unit Cost Amount (m) Quantity (n) o=(m*n)
Description U.F Hour (A) (B) C=(A*B) Trade Worker U.F g Hour F=(D*G) Indexed H=(F*G) Description Unit Quantity (I) (J) K=(I*J) L=(C+H+K) Cost
(With Plate No) s (D) (E) Rate(G)
No
1 Loader(58546) 1.00 12 579.00 6948 Foreman 3 1.00 12 36 43.46 1564.56 cement qtl 15.80 185 2922.743056
2 Mixer(59976) 1.00 11.5 250 2875 Laborer 100 1.00 12 1200 8.27 9924 sand m3 3.41 350 1194.375
Masonry 3 Mixer(79412) 1.00 11.5 250 2875 Mason 40 1.00 12 480 22.78 10934.4 stone m3 9.10 500 4550
construction 4 Mixer(00542) 1.00 11.5 250 2875 carpenter 4 1.00 12 48 22.78 1093.44 55,615.12 13,903.78 69,518.90 1,207.77 13.00 15,701.01 -53,817.89
5 Mixer(05157) 1.00 11.5 250 2875 Laborer Foreman 4 1.00 12 48 13.13 630.24
6 W/ truck (59802) 1.00 11 300 3300 operator 2 1.00 12 24 43.89 1053.36
Total 21,748.00 25,200.00 8,667.12
1 Mixer(78080) 0.50 11.5 250 1437.5 Foreman 1 0.33 12 3.96 43.46 172.1016 cement qtl 10.64 185 1968.4
2 W/ truck (58998) 0.50 11 300 1650 Laborer 15 1.00 12 180 8.27 1488.6 sand m3 1.18 350 411.6
Pipe production
(19+500) 3 operator 1 0.50 12 6 43.89 263.34 Aggregate m3 2.80 600 1680
16,021.66 4,005.41 20,027.07 2,113.22 7.00 14,792.54 -5,234.53
4 Mason 5 1.00 12 60 22.78 1366.8 R.bar ton 0.22 21740 4,763.23
5 Barbender 3 1.00 12 36 22.78 820.08
Total 3,087.50 4,110.92 8,823.23
1 Loader(34686) 1.00 3 579.00 1737 Foreman 1 0.33 12 3.96 43.46 172.10 cement qtl 12.25 185 2266.472
Ditch cover 2 Mixer(78080) 0.50 11.5 250 1437.5 Laborer 15 1.00 12 180 8.27 1488.6 sand m3 1.35 350 473.928
production 3 W/ truck (58998) 0.50 11 300 1650 operator 1 0.50 12 6 43.89 263.34 Aggregate m3 3.22 600 1934.4
(19+500) 27,089.02 6,772.26 33,861.28 420.00 62.00 26,040.00 -7,821.28
4 Mason 5 1.00 12 60 22.78 1366.8 R.bar ton 0.62 21740 13,478.80
5 Barbender 3 1.00 12 36 22.78 820.08
Total 4,824.50 4,110.92 18,153.60
1 Loader(58552) 1.00 2.5 579.00 1447.5 Foreman 0 1.00 0 0 43.46 0
Backfill using 2 Roller(58834) 1.00 5 550 2750 Laborer 3 1.00 12 36 8.27 297.72
imported
material 3 Excavator(58756) 1.00 0 1326 0 operator 3 1.00 12 36 43.89 1580.04
7,882.82 1,970.71 9,853.53 88.26 16.00 1,412.16 -8,441.37
(7+384) 4 Loader(58546) 0.30 0 579 0 Laborer Foreman 1 1.00 12 12 13.13 157.56
5 Roller(58842) 1.00 3 550 1650
Total 5,847.50 2,035.32 -
1 Excavator(1149) 1 0 1474 0
No. D/Truck Km No.Trip Capacity
1 D/Truck(58978) 5 0 8 0 Laborer 0 1.00 0 0 8.27 0
Excavation for 2 D/Truck(59758) 5 0 8 0 foreman 1 0.50 0 0 43.46 0
open drain
(8+020-8+180) 3 D/Truck(59731) 5 0 8 0 operator 6 1.00 0 0 43.89 0 0 0 - 92.72 - - 0.00
4 D/Truck(59752) 5 0 8 0
5 D/Truck(59940) 5 0 8 0
6 D/Truck(58982) 5 0 8 0
Total 0 0
1 Loader(58555) 1.00 0 579.00 0 Foreman 1 1.00 0 0 43.46 0
pipe Installation 2 Excavator(58756) 1.00 0 1326 0 Laborer 15 1.00 0 0 8.27 0
(0+611) 3 operator 2 1.00 0 0 43.89 0 - - - 775.79 - - 0.00
4 Mason 5 1.00 0 0 22.78 0
Total - - -
Total 0 236.73
Base course 1 Crusher(45023) 1 9.33 3600 33588 foreman 1 0.25 12 3 45.83 137.49
crushing
(5+000) 43373.88 10843.47 54,217.35 179.95 - - -54,217.35
2 Loader(58545) 1 10.83 579 6270.57 operator 2 1.00 17 34 43.89 1492.26
Total 39858.57 3515.31
Concrete 1 Crusher(39502) 1 2.5 3600 9000 foreman 0 0.25 12 3 45.83 137.49
Aggregate 2 Loader(58545) 0.33 0 579 0 operator 0 1.00 12 0 43.89 0
crushing 9236.73 2309.1825 11,545.91 336.59 - - -11545.91
(5+000) 3 Laborer 1 1.00 12 12 8.27 99.24
Total 9000 236.73
Total Sum 205,074.44 117,974.40 -87,100.04
Activity Total Direct 25% Unit Rate Excuted Amount Net Amount
Equipment No of Workin Man Hour Hourly Cost Over Head Total Cost
Working Hourly Rate Amount Amount Material
Unit Quantity (I) Unit(J)Cost
Description Amount (m) Quantity (n) o=(m*n)
Description U.F Hour (A) (B) C=(A*B) Trade Worker U.F g Hour F=(D*G) Indexed H=(F*G) Description K=(I*J) L=(C+H+K) Cost
(With Plate No) s (D) (E) Rate(G)
No
1 Loader(58546) 1.00 12 579.00 6948 Foreman 3 1.00 12 36 43.46 1564.56 cement qtl 15.80 185 2922.743056
2 Mixer(59976) 1.00 11.5 250 2875 Laborer 100 1.00 12 1200 8.27 9924 sand m3 3.41 350 1194.375
Masonry 3 Mixer(79412) 1.00 11.5 250 2875 Mason 40 1.00 12 480 22.78 10934.4 stone m3 9.10 500 4550
construction 4 Mixer(00542) 1.00 11.5 250 2875 carpenter 4 1.00 12 48 22.78 1093.44 55,615.12 13,903.78 69,518.90 1,207.77 13.00 15,701.01 -53,817.89
5 Mixer(05157) 1.00 11.5 250 2875 Laborer Foreman 4 1.00 12 48 13.13 630.24
6 W/ truck (59802) 1.00 11 300 3300 operator 2 1.00 12 24 43.89 1053.36
Total 21,748.00 25,200.00 8,667.12
1 Mixer(78080) 0.50 11.5 250 1437.5 Foreman 1 0.33 12 3.96 43.46 172.1016 cement qtl 10.64 185 1968.4
2 W/ truck (58998) 0.50 11 300 1650 Laborer 15 1.00 12 180 8.27 1488.6 sand m3 1.18 350 411.6
Pipe production
(19+500) 3 operator 1 0.50 12 6 43.89 263.34 Aggregate m3 2.80 600 1680
16,021.66 4,005.41 20,027.07 2,113.22 7.00 14,792.54 -5,234.53
4 Mason 5 1.00 12 60 22.78 1366.8 R.bar ton 0.22 21740 4,763.23
Prepared By:________________________________________________ Checked By:_________________________________________________ Approved BY:_________________________________________________
Pipe production
(19+500) 16,021.66 4,005.41 20,027.07 2,113.22 7.00 14,792.54 -5,234.53
Total 0 625.92
1 Dozer(59282) 1 0 2272 0 Laborer 1 1.00 11.5 12 8.27 99.24 Dynamite
Borrow operator 1 1.00 11.5 12 43.89 526.68 Blasting caps
Production
(0+800) 625.92 156.48 782.40 27.00 920.00 24,840.00 24,057.60
Total 0 625.92
1 Wagon drill 1 0 1200 0 Laborer 4 1.00 11.5 11.5 8.27 95.105 Dynamite
Quary rock 2 Air compresor 1 0 450 0 operator 3 1.00 11.5 34.5 43.89 1514.205 Blasting caps
Production 3 Dozer(60005) 1 7.33 2272 16653.76
(5+000) 18752.53875 4688.134688 23,440.67 122.34 210.00 25,691.40 2,250.73
4 Excavator(58533) 1 0 1326 0 Quary foreman 1 0.25 11.5 2.875 34.05 97.89375
5 powder man 1 1.00 11.5 11.5 34.05 391.575
Total 16653.76 2098.77875
1 Excavator(58533) 1 0 1326 0 Laborer 1 1.00 12 12 8.27 99.24
2 Loader(58545) 0.33 0 579 0 foreman 1 0.25 12 3 45.83 137.49
Quary rock
Hauling (5+000) 3 D/Truck(59970) 1 11 550 6050
20036.73 5009.1825 25,045.91 37.66 - - -25,045.91
4 D/Truck(59785) 1 25 550 13750
4 D/Truck(59964) 1 0 550 0
Total 19800 236.73
Total 0 236.73
Base course 1 Crusher(45023) 1 4.33 3600 15588 foreman 1 0.25 12 3 45.83 137.49
crushing
(5+000) 23833.74 5958.435 29,792.18 179.95 - - -29,792.18
2 Loader(58545) 0.33 8.17 579 4730.43 operator 2 1.00 17 34 43.89 1492.26
Total 20318.43 3515.31
Concrete 1 Crusher(39502) 1 2.17 3600 7812 foreman 0 0.25 12 3 45.83 137.49
Aggregate 2 Loader(60049) 0.33 0.42 579 80.2494 operator 0 1.00 12 0 43.89 0
crushing 8128.9794 2032.24485 10,161.22 336.59 40.00 13,463.60 3302.37575
(5+000) 3 Laborer 1 1.00 12 12 8.27 99.24
Total 7892.2494 236.73
Total Sum 214,119.54 212,225.00 -1,894.54
Activity Total Direct 25% Unit Rate Excuted Amount Net Amount
Equipment Working Hourly Rate Amount No of Workin Man Hour Hourly Amount Material Unit Cost Amount Cost Over Head Total Cost
Description Description U.F Trade Worker U.F g Hour Indexed Unit Quantity (I) (m) Quantity (n) o=(m*n)
Hour (A) (B) C=(A*B) F=(D*G) Rate(G) H=(F*G) Description (J) K=(I*J) L=(C+H+K) Cost
(With Plate No) s (D) (E)
No
1 Loader(58546) 1.00 12 579.00 6948 Foreman 3 1.00 12 36 43.46 1564.56 cement qtl 15.80 185 2922.743056
2 Mixer(59976) 1.00 11.5 250 2875 Laborer 100 1.00 12 1200 8.27 9924 sand m3 3.41 350 1194.375
Masonry 3 Mixer(79412) 1.00 11.5 250 2875 Mason 40 1.00 12 480 22.78 10934.4 stone m3 9.10 500 4550
construction 4 Mixer(00542) 1.00 11.5 250 2875 carpenter 4 1.00 12 48 22.78 1093.44 55,615.12 13,903.78 69,518.90 1,207.77 13.00 15,701.01 -53,817.89
5 Mixer(05157) 1.00 11.5 250 2875 Laborer Foreman 4 1.00 12 48 13.13 630.24
6 W/ truck (59802) 1.00 11 300 3300 operator 2 1.00 12 24 43.89 1053.36
Total 21,748.00 25,200.00 8,667.12
1 Mixer(78080) 0.50 11.5 250 1437.5 Foreman 1 0.33 12 3.96 43.46 172.1016 cement qtl 10.64 185 1968.4
2 W/ truck (58998) 0.50 11 300 1650 Laborer 15 1.00 12 180 8.27 1488.6 sand m3 1.18 350 411.6
Pipe production
(19+500) 3 operator 1 0.50 12 6 43.89 263.34 Aggregate m3 2.80 600 1680
16,021.66 4,005.41 20,027.07 2,113.22 7.00 14,792.54 -5,234.53
4 Mason 5 1.00 12 60 22.78 1366.8 R.bar ton 0.22 21740 4,763.23
5 Barbender 3 1.00 12 36 22.78 820.08
Total 3,087.50 4,110.92 8,823.23
1 Loader(34686) 1.00 3 579.00 1737 Foreman 1 0.33 12 3.96 43.46 172.10 cement qtl 12.25 185 2266.472
Ditch cover 2 Mixer(78080) 0.50 11.5 250 1437.5 Laborer 15 1.00 12 180 8.27 1488.6 sand m3 1.35 350 473.928
production 3 W/ truck (58998) 0.50 11 300 1650 operator 1 0.50 12 6 43.89 263.34 Aggregate m3 3.22 600 1934.4
(19+500) 27,089.02 6,772.26 33,861.28 420.00 62.00 26,040.00 -7,821.28
4 Mason 5 1.00 12 60 22.78 1366.8 R.bar ton 0.62 21740 13,478.80
5 Barbender 3 1.00 12 36 22.78 820.08
Total 4,824.50 4,110.92 18,153.60
1 Loader(58552) 1.00 2.5 579.00 1447.5 Foreman 0 1.00 0 0 43.46 0
Backfill using 2 Roller(58834) 1.00 5 550 2750 Laborer 3 1.00 12 36 8.27 297.72
imported
material 3 Excavator(58756) 1.00 0 1326 0 operator 3 1.00 12 36 43.89 1580.04
7,882.82 1,970.71 9,853.53 88.26 16.00 1,412.16 -8,441.37
(7+384) 4 Loader(58546) 0.30 0 579 0 Laborer Foreman 1 1.00 12 12 13.13 157.56
5 Roller(58842) 1.00 3 550 1650
Total 5,847.50 2,035.32 -
1 Excavator(1149) 1 0 1474 0
No. D/Truck Km No.Trip Capacity
1 D/Truck(58978) 5 0 8 0 Laborer 0 1.00 0 0 8.27 0
Excavation for 2 D/Truck(59758) 5 0 8 0 foreman 1 0.50 0 0 43.46 0
open drain
(8+020-8+180) 3 D/Truck(59731) 5 0 8 0 operator 6 1.00 0 0 43.89 0 0 0 - 92.72 - - 0.00
4 D/Truck(59752) 5 0 8 0
5 D/Truck(59940) 5 0 8 0
6 D/Truck(58982) 5 0 8 0
Total 0 0
1 Loader(58555) 1.00 0 579.00 0 Foreman 1 1.00 0 0 43.46 0
pipe Installation 2 Excavator(58756) 1.00 0 1326 0 Laborer 15 1.00 0 0 8.27 0
(0+611) 3 operator 2 1.00 0 0 43.89 0 - - - 775.79 - - 0.00
4 Mason 5 1.00 0 0 22.78 0
Total - - -
Total 0 625.92
1 Dozer(59282) 1 0 2272 0 Laborer 1 1.00 11.5 12 8.27 99.24 Dynamite
Borrow operator 1 1.00 11.5 12 43.89 526.68 Blasting caps
Production
(0+800) 625.92 156.48 782.40 27.00 920.00 24,840.00 24,057.60
Total 0 625.92
1 Wagon drill 1 0 1200 0 Laborer 4 1.00 11.5 11.5 8.27 95.105 Dynamite
Quary rock 2 Air compresor 1 0 450 0 operator 3 1.00 11.5 34.5 43.89 1514.205 Blasting caps
Production 3 Dozer(60005) 1 7.25 2272 16472
(5+000) 18570.77875 4642.694688 23,213.47 122.34 210.00 25,691.40 2,477.93
4 Excavator(58533) 1 0 1326 0 Quary foreman 1 0.25 11.5 2.875 34.05 97.89375
5 powder man 1 1.00 11.5 11.5 34.05 391.575
Total 16472 2098.77875
1 Excavator(58533) 1 0 1326 0 Laborer 1 1.00 12 12 8.27 99.24
2 Loader(58545) 0.33 0 579 0 foreman 1 0.25 12 3 45.83 137.49
Quary rock
Hauling (5+000) 3 D/Truck(59970) 1 26 550 14300
31036.73 7759.1825 38,795.91 37.66 - - -38,795.91
4 D/Truck(59785) 1 30 550 16500
4 D/Truck(59964) 1 0 550 0
Total 30800 236.73
Total 0 236.73
Base course 1 Crusher(45023) 1 8.25 3600 29700 foreman 1 0.25 12 3 45.83 137.49
crushing
(5+000) 33215.31 8303.8275 41,519.14 179.95 - - -41,519.14
2 Loader(58545) 0.33 0 579 0 operator 2 1.00 17 34 43.89 1492.26
Total 29700 3515.31
Concrete 1 Crusher(39502) 1 13.42 3600 48312 foreman 0 0.25 12 3 45.83 137.49
Aggregate
crushing 2 Loader(60049) 0.33 6.25 579 1194.1875 operator 0 1.00 12 0 43.89 0
52179.06 13044.765 65,223.83 336.59 216.00 72,703.44 7479.615
(5+000) 3 Loader(58545) 0.33 12.75 579 2436.1425 Laborer 1 1.00 12 12 8.27 99.24
Total 51942.33 236.73
Total Sum 293,400.29 281,184.84 -12,215.45
Activity Total Direct 25% Unit Rate Excuted Amount Net Amount
Equipment Working Hourly Rate Amount No of Workin Man Hour Hourly Amount Material Unit Cost Amount Cost Over Head Total Cost
Description Description U.F Trade Worker U.F g Hour Indexed Unit Quantity (I) (m) Quantity (n) o=(m*n)
Hour (A) (B) C=(A*B) F=(D*G) Rate(G) H=(F*G) Description (J) K=(I*J) L=(C+H+K) Cost
(With Plate No) s (D) (E)
No
1 Loader(58546) 1.00 12 579.00 6948 Foreman 3 1.00 12 36 43.46 1564.56 cement qtl 15.80 185 2922.743056
2 Mixer(59976) 1.00 11.5 250 2875 Laborer 100 1.00 12 1200 8.27 9924 sand m3 3.41 350 1194.375
Masonry 3 Mixer(79412) 1.00 11.5 250 2875 Mason 40 1.00 12 480 22.78 10934.4 stone m3 9.10 500 4550
construction 4 Mixer(00542) 1.00 11.5 250 2875 carpenter 4 1.00 12 48 22.78 1093.44 55,615.12 13,903.78 69,518.90 1,207.77 13.00 15,701.01 -53,817.89
5 Mixer(05157) 1.00 11.5 250 2875 Laborer Foreman 4 1.00 12 48 13.13 630.24
6 W/ truck (59802) 1.00 11 300 3300 operator 2 1.00 12 24 43.89 1053.36
Total 21,748.00 25,200.00 8,667.12
1 Mixer(78080) 0.50 11.5 250 1437.5 Foreman 1 0.33 12 3.96 43.46 172.1016 cement qtl 10.64 185 1968.4
2 W/ truck (58998) 0.50 11 300 1650 Laborer 15 1.00 12 180 8.27 1488.6 sand m3 1.18 350 411.6
Pipe production
(19+500) 3 operator 1 0.50 12 6 43.89 263.34 Aggregate m3 2.80 600 1680
16,021.66 4,005.41 20,027.07 2,113.22 7.00 14,792.54 -5,234.53
4 Mason 5 1.00 12 60 22.78 1366.8 R.bar ton 0.22 21740 4,763.23
5 Barbender 3 1.00 12 36 22.78 820.08
Total 3,087.50 4,110.92 8,823.23
1 Loader(34686) 1.00 3 579.00 1737 Foreman 1 0.33 12 3.96 43.46 172.10 cement qtl 12.25 185 2266.472
Ditch cover 2 Mixer(78080) 0.50 11.5 250 1437.5 Laborer 15 1.00 12 180 8.27 1488.6 sand m3 1.35 350 473.928
production 3 W/ truck (58998) 0.50 11 300 1650 operator 1 0.50 12 6 43.89 263.34 Aggregate m3 3.22 600 1934.4
(19+500) 27,089.02 6,772.26 33,861.28 420.00 62.00 26,040.00 -7,821.28
4 Mason 5 1.00 12 60 22.78 1366.8 R.bar ton 0.62 21740 13,478.80
5 Barbender 3 1.00 12 36 22.78 820.08
Total 4,824.50 4,110.92 18,153.60
1 Loader(58552) 1.00 2.5 579.00 1447.5 Foreman 0 1.00 0 0 43.46 0
Backfill using 2 Roller(58834) 1.00 5 550 2750 Laborer 3 1.00 12 36 8.27 297.72
imported
material 3 Excavator(58756) 1.00 0 1326 0 operator 3 1.00 12 36 43.89 1580.04
7,882.82 1,970.71 9,853.53 88.26 16.00 1,412.16 -8,441.37
(7+384) 4 Loader(58546) 0.30 0 579 0 Laborer Foreman 1 1.00 12 12 13.13 157.56
5 Roller(58842) 1.00 3 550 1650
Total 5,847.50 2,035.32 -
1 Excavator(1149) 1 0 1474 0
No. D/Truck Km No.Trip Capacity
1 D/Truck(58978) 5 0 8 0 Laborer 0 1.00 0 0 8.27 0
Excavation for 2 D/Truck(59758) 5 0 8 0 foreman 1 0.50 0 0 43.46 0
open drain
(8+020-8+180) 3 D/Truck(59731) 5 0 8 0 operator 6 1.00 0 0 43.89 0 0 0 - 92.72 - - 0.00
4 D/Truck(59752) 5 0 8 0
5 D/Truck(59940) 5 0 8 0
6 D/Truck(58982) 5 0 8 0
Total 0 0
1 Loader(58555) 1.00 0 579.00 0 Foreman 1 1.00 0 0 43.46 0
pipe Installation 2 Excavator(58756) 1.00 0 1326 0 Laborer 15 1.00 0 0 8.27 0
(0+611) 3 operator 2 1.00 0 0 43.89 0 - - - 775.79 - - 0.00
4 Mason 5 1.00 0 0 22.78 0
Total - - -
Total 0 625.92
1 Dozer(59282) 1 0 2272 0 Laborer 1 1.00 11.5 12 8.27 99.24 Dynamite
Borrow operator 1 1.00 11.5 12 43.89 526.68 Blasting caps
Production
(0+800) 625.92 156.48 782.40 27.00 920.00 24,840.00 24,057.60
Total 0 625.92
1 Wagon drill 1 0 1200 0 Laborer 4 1.00 11.5 11.5 8.27 95.105 Dynamite
Quary rock 2 Air compresor 1 0 450 0 operator 3 1.00 11.5 34.5 43.89 1514.205 Blasting caps
Production 3 Dozer(60005) 1 2.92 2272 6634.24
(5+000) 8733.01875 2183.254688 10,916.27 122.34 60.00 7,340.40 -3,575.87
4 Excavator(58533) 1 0 1326 0 Quary foreman 1 0.25 11.5 2.875 34.05 97.89375
5 powder man 1 1.00 11.5 11.5 34.05 391.575
Total 6634.24 2098.77875
1 Excavator(58533) 1 0 1326 0 Laborer 1 1.00 12 12 8.27 99.24
2 Loader(58545) 0.33 0 579 0 foreman 1 0.25 12 3 45.83 137.49
Quary rock
Hauling (5+000) 3 D/Truck(59970) 1 36 550 19800
37086.73 9271.6825 46,358.41 37.66 - - -46,358.41
4 D/Truck(59785) 1 19 550 10450
4 D/Truck(59964) 1 12 550 6600
Total 36850 236.73
Material Loading 1 Loader(1376) 1 9.92 649 0 Laborer 1 1.00 12 12 8.27 99.24
(5+000) 2 foreman 1 0.25 12 3 45.83 137.49
3 236.73 59.1825 295.91 27.00 - - -295.91
Total 0 236.73
Base course 1 Crusher(45023) 1 0 3600 0 foreman 1 0.25 12 3 45.83 137.49
crushing
(5+000) 2 Loader(58545) 0.33 0 579 0 operator 2 1.00 17 34 43.89 1492.26 3515.31 878.8275 4,394.14 179.95 - - -4,394.14
Total 0 3515.31
Concrete 1 Crusher(39502) 1 9.58 3600 34488 foreman 0 0.25 12 3 45.83 137.49
Aggregate 2 Loader(60049) 0.33 0 579 0 operator 0 1.00 12 0 43.89 0
crushing 34724.73 8681.1825 43,405.91 336.59 155.00 52,171.45 8765.5375
(5+000) 3 Loader(58545) 0.33 0 579 0 Laborer 1 1.00 12 12 8.27 99.24
Total 34488 236.73
Total Sum 245,353.30 240,006.85 -5,346.45
Borrow
Placing(15+000-
15+300-14+460- 85,006.26 21,251.56 106,257.82 32.72 1,740.00 56,932.80 -49,325.02
14+720)
3 Grader(0097) 1 7.08 1141 8077
4 Grader(59998) 1 10 1141 11409
Borrow 5 Roller(0814) 1 7.92 810 6415
Placing(15+000- 6 Roller(0292) 1 6.58 812 5343
15+300-14+460- 7 Roller(58837) 1 6.5 810 5265 85,006.26 21,251.56 106,257.82 32.72 1,740.00 56,932.80 -49,325.02
14+720)
8 Roller(0483) 1 8.42 810 6820
9 Roller(0620) 1 9.58 810 7760
10 W/truck(59804) 1 11.5 300 3450
11 W/truck(59808) 1 11.5 300 3450
12 W/truck(59831) 1 11.5 300 3450
Total 83,738.88 1,267.38 -
1 Grader(0538) 1 0 1115.00 0 foreman 1 0.50 12 6 45.83 274.98
2 Grader(0166) 1 0 1115.00 0 Laborer 10 1.00 12 120 8.27 992.4
3 Grader(59992) 1 0 1115.00 0 operator 3 1.00 12 36 43.89 1580.04
Sub base Placing
(19+960-20+100) 4 Roller(61308007) 1 0 810.00 0
2,847.42 711.86 3,559.28 32.72 1,740.00 56,932.80 53,373.53
5 Roller(0483) 1 0 810.00 0
6 W/truck(59804) 1 0 300.00 0
7 W/truck(59831) 1 0 300.00 0
Total - 2,847.42 -
1 Loader(0544) 1 0 649 0 Laborer 2 1.00 12 24 8.27 198.48
No. D/Truck Km No.Trip Capacity operator 2 1.00 12 24 43.89 1053.36
Waste 1 D/Truck(28854) 5 0 18 0
Haulling(17+400-
17+420) 2 D/Truck(27593) 5 0 16 0 1251.84 312.96 1,564.80 26.42 - - -1,564.80
3 D/Truck(47608) 5 0 16 0
4 D/Truck(62147) 5 0 14 0
Total 0 1251.84
Total Sum #REF! #REF! #REF!
Activity Total Direct 25% Unit Rate Excuted Amount Net Amount
Equipment Working Hourly Rate Amount No of Workin Man Hour Hourly Amount Material Cost Over Head Total Cost
Description Description U.F Hour (A) (B) C=(A*B) Trade Worker U.F g Hour F=(D*G) Indexed H=(F*G) Description Unit Quantity (I) Unit(J)Cost Amount
K=(I*J) L=(C+H+K) Cost
(m) Quantity (n) o=(m*n)
(With Plate No) s (D) (E) Rate(G)
No
1 Loader(58546) 1.00 12 579.00 6948 Foreman 3 1.00 12 36 43.46 1564.56 cement qtl 15.80 185 2922.743056
2 Mixer(59976) 1.00 11.5 250 2875 Laborer 100 1.00 12 1200 8.27 9924 sand m3 3.41 350 1194.375
Masonry 3 Mixer(79412) 1.00 11.5 250 2875 Mason 40 1.00 12 480 22.78 10934.4 stone m3 9.10 500 4550
construction 4 Mixer(00542) 1.00 11.5 250 2875 carpenter 4 1.00 12 48 22.78 1093.44 55,615.12 13,903.78 69,518.90 1,207.77 13.00 15,701.01 -53,817.89
5 Mixer(05157) 1.00 11.5 250 2875 Laborer Foreman 4 1.00 12 48 13.13 630.24
6 W/ truck (59802) 1.00 11 300 3300 operator 2 1.00 12 24 43.89 1053.36
Total 21,748.00 25,200.00 8,667.12
1 Mixer(78080) 0.50 11.5 250 1437.5 Foreman 1 0.33 12 3.96 43.46 172.1016 cement qtl 10.64 185 1968.4
2 W/ truck (58998) 0.50 11 300 1650 Laborer 15 1.00 12 180 8.27 1488.6 sand m3 1.18 350 411.6
Pipe production
(19+500) 3 operator 1 0.50 12 6 43.89 263.34 Aggregate m3 2.80 600 1680
16,021.66 4,005.41 20,027.07 2,113.22 7.00 14,792.54 -5,234.53
4 Mason 5 1.00 12 60 22.78 1366.8 R.bar ton 0.22 21740 4,763.23
5 Barbender 3 1.00 12 36 22.78 820.08
Total 3,087.50 4,110.92 8,823.23
1 Loader(34686) 1.00 3 579.00 1737 Foreman 1 0.33 12 3.96 43.46 172.10 cement qtl 12.25 185 2266.472
Ditch cover 2 Mixer(78080) 0.50 11.5 250 1437.5 Laborer 15 1.00 12 180 8.27 1488.6 sand m3 1.35 350 473.928
production 3 W/ truck (58998) 0.50 11 300 1650 operator 1 0.50 12 6 43.89 263.34 Aggregate m3 3.22 600 1934.4
(19+500) 27,089.02 6,772.26 33,861.28 420.00 62.00 26,040.00 -7,821.28
4 Mason 5 1.00 12 60 22.78 1366.8 R.bar ton 0.62 21740 13,478.80
5 Barbender 3 1.00 12 36 22.78 820.08
Total 4,824.50 4,110.92 18,153.60
1 Loader(58552) 1.00 2.5 579.00 1447.5 Foreman 0 1.00 0 0 43.46 0
Backfill using 2 Roller(58834) 1.00 5 550 2750 Laborer 3 1.00 12 36 8.27 297.72
imported
material 3 Excavator(58756) 1.00 0 1326 0 operator 3 1.00 12 36 43.89 1580.04
7,882.82 1,970.71 9,853.53 88.26 16.00 1,412.16 -8,441.37
(7+384) 4 Loader(58546) 0.30 0 579 0 Laborer Foreman 1 1.00 12 12 13.13 157.56
5 Roller(58842) 1.00 3 550 1650
Total 5,847.50 2,035.32 -
1 Excavator(1149) 1 0 1474 0
No. D/Truck Km No.Trip Capacity
1 D/Truck(58978) 5 0 8 0 Laborer 0 1.00 0 0 8.27 0
Excavation for 2 D/Truck(59758) 5 0 8 0 foreman 1 0.50 0 0 43.46 0
open drain
(8+020-8+180) 3 D/Truck(59731) 5 0 8 0 operator 6 1.00 0 0 43.89 0 0 0 - 92.72 - - 0.00
4 D/Truck(59752) 5 0 8 0
5 D/Truck(59940) 5 0 8 0
6 D/Truck(58982) 5 0 8 0
Total 0 0
1 Loader(58555) 1.00 0 579.00 0 Foreman 1 1.00 0 0 43.46 0
pipe Installation 2 Excavator(58756) 1.00 0 1326 0 Laborer 15 1.00 0 0 8.27 0
(0+611) 3 operator 2 1.00 0 0 43.89 0 - - - 775.79 - - 0.00
4 Mason 5 1.00 0 0 22.78 0
Total - - -
Total 0 625.92
1 Dozer(59282) 1 0 2272 0 Laborer 1 1.00 11.5 12 8.27 99.24 Dynamite
Borrow operator 1 1.00 11.5 12 43.89 526.68 Blasting caps
Production
(0+800) 625.92 156.48 782.40 27.00 920.00 24,840.00 24,057.60
Total 0 625.92
1 Wagon drill 1 0 1200 0 Laborer 4 1.00 11.5 11.5 8.27 95.105 Dynamite
Quary rock 2 Air compresor 1 0 450 0 operator 3 1.00 11.5 34.5 43.89 1514.205 Blasting caps
Production 3 Dozer(60005) 1 8.5 2272 19312
(5+000) 21410.77875 5352.694688 26,763.47 122.34 255.00 31,196.70 4,433.23
4 Excavator(58533) 1 0 1326 0 Quary foreman 1 0.25 11.5 2.875 34.05 97.89375
5 powder man 1 1.00 11.5 11.5 34.05 391.575
Total 19312 2098.77875
1 Excavator(58533) 1 0 1326 0 Laborer 1 1.00 12 12 8.27 99.24
2 Loader(58545) 0.33 0 579 0 foreman 1 0.25 12 3 45.83 137.49
Quary rock
Hauling (5+000) 3 D/Truck(59970) 1 33 550 18150
23886.73 5971.6825 29,858.41 37.66 - - -29,858.41
4 D/Truck(59785) 1 10 550 5500
4 D/Truck(59964) 1 0 550 0
Total 23650 236.73
Material Loading 1 Loader(1376) 1 5.5 649 0 Laborer 1 1.00 12 12 8.27 99.24
(5+000) 2 foreman 1 0.25 12 3 45.83 137.49
3 236.73 59.1825 295.91 27.00 - - -295.91
Total 0 236.73
Base course 1 Crusher(45023) 1 7.33 3600 26388 foreman 1 0.25 12 3 45.83 137.49
crushing
(5+000) 2 Loader(58545) 0.33 9.67 579 5598.93 operator 2 1.00 17 34 43.89 1492.26 35502.24 8875.56 44,377.80 179.95 255.00 45,887.25 1,509.45
Activity Total Direct 25% Unit Rate Excuted Amount Net Amount
Equipment Working Hourly Rate Amount No of Workin Man Hour Hourly Amount Material Unit Cost Amount Cost Over Head Total Cost
Description Description U.F Trade Worker U.F g Hour Indexed Unit Quantity (I) (m) Quantity (n) o=(m*n)
Hour (A) (B) C=(A*B) F=(D*G) Rate(G) H=(F*G) Description (J) K=(I*J) L=(C+H+K) Cost
(With Plate No) s (D) (E)
No
1 Loader(58546) 1.00 12 579.00 6948 Foreman 3 1.00 12 36 43.46 1564.56 cement qtl 15.80 185 2922.743056
2 Mixer(59976) 1.00 11.5 250 2875 Laborer 100 1.00 12 1200 8.27 9924 sand m3 3.41 350 1194.375
Masonry 3 Mixer(79412) 1.00 11.5 250 2875 Mason 40 1.00 12 480 22.78 10934.4 stone m3 9.10 500 4550
construction 4 Mixer(00542) 1.00 11.5 250 2875 carpenter 4 1.00 12 48 22.78 1093.44 55,615.12 13,903.78 69,518.90 1,207.77 13.00 15,701.01 -53,817.89
5 Mixer(05157) 1.00 11.5 250 2875 Laborer Foreman 4 1.00 12 48 13.13 630.24
6 W/ truck (59802) 1.00 11 300 3300 operator 2 1.00 12 24 43.89 1053.36
Total 21,748.00 25,200.00 8,667.12
1 Mixer(78080) 0.50 11.5 250 1437.5 Foreman 1 0.33 12 3.96 43.46 172.1016 cement qtl 10.64 185 1968.4
2 W/ truck (58998) 0.50 11 300 1650 Laborer 15 1.00 12 180 8.27 1488.6 sand m3 1.18 350 411.6
Pipe production
(19+500) 3 operator 1 0.50 12 6 43.89 263.34 Aggregate m3 2.80 600 1680
16,021.66 4,005.41 20,027.07 2,113.22 7.00 14,792.54 -5,234.53
4 Mason 5 1.00 12 60 22.78 1366.8 R.bar ton 0.22 21740 4,763.23
5 Barbender 3 1.00 12 36 22.78 820.08
Total 3,087.50 4,110.92 8,823.23
1 Loader(34686) 1.00 3 579.00 1737 Foreman 1 0.33 12 3.96 43.46 172.10 cement qtl 12.25 185 2266.472
Ditch cover 2 Mixer(78080) 0.50 11.5 250 1437.5 Laborer 15 1.00 12 180 8.27 1488.6 sand m3 1.35 350 473.928
production 3 W/ truck (58998) 0.50 11 300 1650 operator 1 0.50 12 6 43.89 263.34 Aggregate m3 3.22 600 1934.4
(19+500) 27,089.02 6,772.26 33,861.28 420.00 62.00 26,040.00 -7,821.28
4 Mason 5 1.00 12 60 22.78 1366.8 R.bar ton 0.62 21740 13,478.80
5 Barbender 3 1.00 12 36 22.78 820.08
Total 4,824.50 4,110.92 18,153.60
1 Loader(58552) 1.00 2.5 579.00 1447.5 Foreman 0 1.00 0 0 43.46 0
Backfill using 2 Roller(58834) 1.00 5 550 2750 Laborer 3 1.00 12 36 8.27 297.72
imported
material 3 Excavator(58756) 1.00 0 1326 0 operator 3 1.00 12 36 43.89 1580.04
7,882.82 1,970.71 9,853.53 88.26 16.00 1,412.16 -8,441.37
(7+384) 4 Loader(58546) 0.30 0 579 0 Laborer Foreman 1 1.00 12 12 13.13 157.56
5 Roller(58842) 1.00 3 550 1650
Total 5,847.50 2,035.32 -
1 Excavator(1149) 1 0 1474 0
No. D/Truck Km No.Trip Capacity
1 D/Truck(58978) 5 0 8 0 Laborer 0 1.00 0 0 8.27 0
Excavation for 2 D/Truck(59758) 5 0 8 0 foreman 1 0.50 0 0 43.46 0
open drain
(8+020-8+180) 3 D/Truck(59731) 5 0 8 0 operator 6 1.00 0 0 43.89 0 0 0 - 92.72 - - 0.00
4 D/Truck(59752) 5 0 8 0
5 D/Truck(59940) 5 0 8 0
6 D/Truck(58982) 5 0 8 0
Total 0 0
1 Loader(58555) 1.00 0 579.00 0 Foreman 1 1.00 0 0 43.46 0
pipe Installation 2 Excavator(58756) 1.00 0 1326 0 Laborer 15 1.00 0 0 8.27 0
(0+611) 3 operator 2 1.00 0 0 43.89 0 - - - 775.79 - - 0.00
4 Mason 5 1.00 0 0 22.78 0
Total - - -