You are on page 1of 47

ES/079

Rev 0 1988

REVISION STATUS PAGE


REVISION REVISION DETAILS REVISED REF. IND
No/DATE* BY:
0/July 1988

* THIS DOCUMENT SHOULD BE REVIEWED WITHIN ONE YEAR OF THE LAST REVISION DATE.
HOWEVER, THE USER OF THIS DOCUMENT MUST ALWAYS CONSULT THE APPOINTED CUSTODIAN
FOR ADVICE ON VALIDITY AND CURRENCY.

Page 2 of 47
ES/079
Rev 0 1988

CONTENTS
Para Page
PREFACE 5
GLOSSARY 6
1 INTRODUCTION AND GENERAL REQUIREMENTS 7
1.1 Compliance with this Standard 7
1.2 Alternative Supply 7
1.3 Selection of Options 7
1.4 Technical Audit 7
1.5 Selection of “Bought-Out” Items and Use of Sub-Contractors 7
1.6 Quality Assurance 8
1.7 Vendor Experience Qualification 8
1.8 Material Traceability 8
1.9 Unconventional Manufacturing Methods 8
1.10 Correction of Design/Manufacturing Errors 9
1.11 Acceptance Tests 9
1.12 Weight Control 9
1.13 Conflicting Requirements 9
1.14 Reliability 9
2 DESIGN AND MANUFACTURING REQUIREMENTS 11
2.1 Scope and Configuration 11
2.2 General Design 12
2.3 Package Components 13
2.4 Interconnecting Piping and Valves 16
2.5 Control and Instrumentation 17
2.6 Electrical Requirements 19
2.7 Inspection and Testing 21
2.8 Nameplate 22
2.9 Painting 22
3 PREPARATION FOR SHIPMENT AND STORAGE 23
3.1 General 23
3.2 Minimum Requirements for Utility Compressed Air Packages 24
3.3 Tagging of Equipment 25
3.4 Packing for Transportation and Storage 25
4 WEIGHT CONTROL 27
4.1 Information with Proposal 27
4.2 Information Following an Order 27
4.3 Weight Control During Manufacture 27
5 DOCUMENTATION 28
5.1 Technical Manuals 28
5.2 Data Sheets 29
5.3 Other Documentation 29
5.4 Information Required with Proposal 30
6 REFERENCE DOCUMENTS 31
6.1 Legislation and Other Related Documents 31
6.2 British Standards 31
6.3 Other National/International Standards 31
6.4 Shell Expro Documents 32
6.5 SIPM Documents 32
6.6 SIPC Documents 32

Page 3 of 47
ES/079
Rev 0 1988

Para Page
7 APPENDICES 33
7.1 WEIGHT/CENTRE OF MASS DATA SHEET 33
7.2 SPARE PARTS LIST AND INTERCHANGEABILITY RECORD 34
7.3 DOCUMENTATION REQUIREMENTS SCHEDULE – UTILITY COMPRESSED AIR
PACKAGES 39
7.4 EQUIPMENT NOISE LEVEL DATA SHEET 40
7.5 SCHEDULE OF ESSENTIAL TESTS AND INSPECTIONS: UTILITY COMPRESSED AIR
PACKAGE 41
7.6 FIGURE 1: EQUIPMENT NOZZLE PROTECTION PLATE FOR FF, RF AND RTJ
FLANGES 42
7.7 UTILITY COMPRESSED AIR SYSTEM OPERATION 43
7.8 UTILITY COMPRESSED AIR PACKAGE – DATA SHEETS 46

Page 4 of 47
ES/079
Rev 0 1988

PREFACE
This Standard is intended to be used as a purchasing standard for utility compressed air packages to
be supplied to Shell Expro for service on offshore installations. It covers the minimum technical
requirements for packages which include either oil injected or oil free rotary compressors driven by
electric motors, air driers(s) and the associated separation and filtration equipment.
The intention is to specify packages based on manufacturers' standard designs, modified with the
minimum requirements considered necessary to ensure reliable operation in an offshore environment.
The Vendor shall be responsible for conducting an analysis of the standard system and providing
confidence that any major potential weaknesses have been eliminated.
This Standard may be used by Shell Expro directly or by Agents Consultants or Contractors acting on
its behalf.
The Standard shall be used as it stands and shall not be re-issued under a different cover or modified
in any other way. When it is necessary to supplement or modify the Standard, this shall be done by
suitable notes contained in the order (or enquiry) or the data sheets attached thereto and not by
making any change to the Standard itself.
Significant modifications or any intent to use a different standard or specification in addition to, or
instead of, this Standard shall be discussed with Shell Expro Central Engineering Department, Head
of Mechanical Equipment Engineering.
In preparing Sections 3 and 5 of this Standard, the requirements of the following Shell Expro
documents have been taken into account and incorporated where appropriate:
ES/087 Preservation and Protection of Mechanical Equipment
ES/002 Standards for Vendor Documents

Page 5 of 47
ES/079
Rev 0 1988

GLOSSARY

Within the context of this Standard the following words shall have the meanings stated:

“must/shall” indicates a mandatory requirement.


“should” indicates a preferred course of action.
“may” indicates one acceptable course of action.
SIPM Shell Internationale Petroleum Maatschappij B.V.
Shell Shell U.K. Ltd.
Shell Expro Shell U.K. Exploration and Production
Purchaser The organisation responsible who carry out the purchasing function, eg Shell
Expro or a Shell Expro appointed contractor, Consultant or Agent.
Vendor The supplier of materials or equipment - not necessarily the Manufacturer.
Manufacturer The company responsible for the manufacture - not necessarily the Vendor.
Contractor The Shell Expro appointed main Contractor for a defined piece of work.
Sub-contractor A company awarded a contract by a Contractor to do part of the work awarded
to the Contractor by Shell Expro. The work of the Sub-contractor is carried out
under the direction and control of the Contractor. Under its model contracts
Shell Expro has the right to review all proposed Sub-contractors, and sub-
contractors.

Nominated A term having a special legal meaning applicable to the unusual case where
Sub-contractor the terms and conditions of the contract between Shell Expro and the
(to be used with Contractor provide that special terms and conditions apply to any Sub-
extreme caution) contractor that is nominated by Shell Expro. Shell Expro model contracts avoid
use of the term “nominated”.

Consultant A company awarded a contract by Shell Expro for the company to advise or
give guidance on specific subjects. The Scope of Work may include instructions
to act as an Agent for Shell Expro (see Agent).
Agent The legal status of any person or company authorised by Shell Expro to act on
Shell Expro's behalf on the matters specified in the agency agreement or
contract. Third parties can usually rely on the Agent as acting on behalf of and
with the authority of Shell Expro, provided that the Agent acts within the scope
of his apparent authority from Shell Expro.

Page 6 of 47
ES/079
Rev 0 1988

1 INTRODUCTION AND GENERAL REQUIREMENTS


1.1 Compliance with this Standard
A potential Vendor shall state, in writing in the proposal, any requirements of this Standard with which
he is unable to comply.
A potential Vendor shall bring to the attention of the Purchaser any requirements of this Standard,
which in his opinion, are not in accordance with good engineering practice or are otherwise not
suitable for the application in question.
Except as allowed for above, it shall be assumed that the Vendor agrees with, and will abide by, the
requirements of this Standard completely.
Where other specifications and Standards are referred to in this Standard, it is the potential Vendor's
responsibility to obtain such documents and familiarise himself with the requirements thereof.
Documents of Shell origin will be supplied on application to the Purchaser.
1.2 Alternative Supply
At the enquiry stage, in addition to offering equipment conforming to this Standard, a potential Vendor
is free to offer alternative equipment, where such equipment has been proven to give satisfactory
service in closely similar applications. A potential Vendor shall clearly explain in the proposal the
extent to which such an alternative offer deviates from this Standard.
1.3 Selection of Options
Certain clauses in this Standard or any associated Standards may require the Purchaser to make a
selection between various options. When the Purchaser has omitted to make such a selection in the
enquiry or order, this omission shall be brought to the attention of the Purchaser by the Vendor. At the
enquiry stage, a potential Vendor may assume a particular option but shall clearly state such an
assumption in the proposal.
1.4 Technical Audit
Shell Expro reserves the right, through the Purchaser, to review and check any part of the design of
the equipment supplied, using their own expert or an independent specialist/consultant employed for
the purpose. The Vendor and/or Manufacturer shall release to such an expert or specialist all the
necessary drawings, or other information, to enable him to make such check calculations or analyses
as he may consider necessary. However, the expert or specialist shall, if so required by the Vendor,
give a written undertaking not to divulge such information or drawings to any other party except as is
necessary to satisfactorily complete the review or check.
In the event of a conflict between any calculations, analyses or recommendations made by the expert
or specialist and the corresponding calculations, analyses etc.. made by the Vendor, every effort shall
be made to resolve such a conflict and arrive at a mutually acceptable solution.
Where mutual agreement cannot be reached in the extreme, the Purchaser shall have the right to
insist that any modifications, additional calculations or additional tests recommended by the specialist
shall be made.
However, in the event that the Purchaser does overrule the Vendor in this way, it is clearly accepted
that the Vendor's responsibilities, both contractually and in relation to the costs of any modifications,
additional tests etc., shall be limited to the extent indicated by the Vendor's calculations/design, unless
it can be shown either at the time or subsequently by, for example the analysis of test results that the
Vendor's calculations/designs were in error.
1.5 Selection of “Bought-Out” Items and Use of Sub-Contractors
Except for standard fasteners and other small items which are covered by internationally recognised
standards, the Purchaser shall be given details of all “bought-out”, including the proposed supplier of
the items. The Purchaser shall also be given details of the Vendor's intent to employ sub-contractors
to partly or wholly manufacture any part of the equipment. This information shall be disclosed to the
Purchaser as soon as possible, in any case before the sub-orders for such items are placed.

Page 7 of 47
ES/079
Rev 0 1988

The Purchaser shall have the right to request that a nominated supplier, sub-contractor and/or type of
equipment be substituted for the Vendor's initial selection, for reasons of rationalisation, past
experience in similar service technical superiority or other reasons. Where such requests are made
before or at the time of placing the order, they shall be considered mandatory. Requests for
substitutions made after the order shall not be refused by the Vendor without good technical reasons.
Alternatively the Purchaser may, at the outset, nominate sub-suppliers form whom certain items shall
be obtained.
1.6 Quality Assurance
The Vendor shall maintain a quality system in accordance with BS 5750 Part 1.
1.7 Vendor Experience Qualification
Utility compressed air package shall comprise equipment and components selected from
Vendors’/manufacturers' standard ranges.
Prototype equipment will not be considered.
Each potential Vendor shall state in the proposal where a package (or individual item included therein)
being offered is of a size, type or method of manufacture, which is not in satisfactory service. The
extent to which the package offered differs from or is an extrapolation of proven experience, shall be
disclosed.
1.8 Material Traceability
The Vendor shall have an effective system of part numbering. The part number shall completely define
the part including the material of which it is made. For example, two items which are dimensionally
identical but are made from different material, shall have different part numbers. All parts except
standard fasteners, gaskets and other small parts where it is not practicable, shall be indelibly marked
with the appropriate part number.
The Vendor and all sub-Vendors shall maintain an effective system to assure that all parts and
ancillaries are manufactured from the correct materials.
This system shall satisfy the following requirements:
• material and accompanying Certificates of Compliance or Manufacturer's Certificates shall be
checked on receipt by the Vendor for compliance with the specified requirements;
• the grade of material shall be positively identified by marking or recording throughout
manufacture.
NOTE: Certificate of Compliance and Manufacturers' Certificates shall be as defined in
DIN50049. Copies of certificates are acceptable provided they are signed and dated
by a responsible person in the Vendor's or sub-Vendor's inspection department
certifying them as true copies.
Certain components are required to be traceable. These will be specified on the data sheets or
otherwise will be as indicated in Appendix 5 of this Standard.
The Purchaser shall have the right to review inspect and monitor the operations of these materials
control systems.
The final “as-built” revision of the data sheet shall correctly state the material of all important
components and formal issue of this data sheet revision shall constitute certification by the Vendor
that these details are correct.
1.9 Unconventional Manufacturing Methods
The Manufacturer shall declare his intention to use any unconventional methods to manufacture or
fabricate any item or component.
In this context, an unconventional method is a method of manufacture which the particular
Manufacturer has not used for closely similar items for a sufficient period for the items to have been
proved satisfactory in service. For example, fabrication by welding of components which hitherto have
been cast or otherwise made from one solid piece.

Page 8 of 47
ES/079
Rev 0 1988

1.10 Correction of Design/Manufacturing Errors


In the event of any design or manufacturing error, faulty material or accidental damage, the
component to question shall be replaced.
Where it is proposed to recover the component rather than replace it, the method of repair shall
submitted to the Purchaser to obtain Shell Expro's approval. Further, additional tests or calculations
may be required to prove the effectiveness of the repair and that there will be no detrimental effect on
the serviceability of the equipment.
1.11 Acceptance Tests
Mechanical running tests and performance test, when called for, may be attended by the Purchaser
and/or Shell Expro engineers or appointed Consultants.
If required the attending engineer may sign an acceptance certificate. However, signing such a
document signifying or implying approval in any way shall only indicated that the engineer is satisfied
with the conduct of the test. It shall not be construed to mean agreement that the equipment
necessarily complies with the conditions of the order or to relieve the Vendor of his contractual
liabilities in any way.
1.12 Weight Control
For all offshore applications the Vendor shall provide an initial estimate of and shall subsequently
monitor the weight of the equipment he is supplying in accordance with Section 4 of this Standard.
1.13 Conflicting Requirements
Any case of apparent conflict between the requirements of this Standard and any other relevant
document shall be brought to the Purchaser's notice. Unless otherwise agreed the following
descending order of precedence shall apply:
(1) The order (or where no order has yet been placed the enquiry document) and any schedule
specification or data/requisition sheet attached thereto.
(2) This Standard.
(3) Other Shell Standards as referenced herein or in the data/requisition sheet or order (or enquiry).
(4) Other API, ASME, ANSI, BSI, ISO Codes or Standards etc.. as appropriate.
1.14 Reliability
(1) The Vendor shall demonstrate that the reliability/availability aspects of the utility compressed air
package being proposed have been considered in a disciplined and structured manner. The
object of this consideration shall be:
• to estimate the overall reliability/availability of the total package in relation to the duty or
duties which it is intended to perform;
• to identify those components of the package which make a major contribution to
unreliability/unavailability;
• to provide confidence that major potential weaknesses in the package have been
eliminated.
The Vendor shall provide evidence of the reliability/availability of the package with the proposal.
(2) An acceptable procedure to satisfy the above requirements would comprise:
• construct a reliability block diagram such that each “block” represents an item component
or sub-system for which meaningful reliability data can be provided:
• identify the potential failure modes of the “blocks” and the consequence of such failures
on the performance of the package;
• by using a fault tree or equivalent alternative method compute the overall
unreliability/unavailability of the package and identify significant contributors;
• propose modification for consideration by the Purchaser to improve the design.

Page 9 of 47
ES/079
Rev 0 1988

(3) The Vendor shall declare the data used, the sources thereof and any assumption made. The
Purchaser may wish to review this data and discuss its applicability to the particular equipment.
The Vendor may be required to substantiate any data that is not within the public domain.
(4) In making assessments of availability, the Vendor will need to estimate times-to-restore. For the
purpose of making such estimates, the Vendor may assume, unless otherwise stated, that the
spares holding is in accordance with normal recommendations for the service. The Vendor
should also neglect any delay caused by factors not directly related to the Utility Compressed
Air Package unless a basis for estimating the extent of such delays is provided by the
Purchaser. In the case of failure modes which make a significant contribution to the overall
unavailability, the Vendor may be required to demonstrate that the assumed times to restore
can be achieved.
(5) The overall availability of the complete utility compressed air system to supply compressed air
to specification, as predicted by the analysis shall not be less than 99.9%, or such other value
as may be specified or agreed. The complete utility compressed air system consists of a
number of packages operating in parallel or as standby as specified in this Standard and the
order/enquiry. There will normally be 2 or 3 packages.
(6) The potential Vendor shall include, in the proposal, an extended warranty based on either of the
following principles. Any additional cost for the extended warranty shall be shown separately.
The potential Vendor shall provide details of the facilities available for servicing/repairing the
packages. In either case routine maintenance (such as oil changes) and the time and costs of
transportation offshore will not be included in the downtime or cost analyses.
• vendor's warranty for the packages shall be extended to at least 5 years from
commissioning on the basis of a service/breakdown contract at a fixed annual price to be
agreed at the time of the order; such that a repair service will be provided at no further
cost to the Purchaser/Operator in the event of equipment failure during the agreed
warranty period. If the package fails to achieve the specified availability in any one year,
the fixed price for that year shall be reduced in accordance with an agreed formula;
• the warranty shall initially be extended to cover a trial period of a duration agreed by
Purchaser and Vendor. The package shall substantially achieve the specified availability
for this warranty period. If the package does not achieve the specified availability over the
trail period, the warranty shall be further extended until the specified availability has been
demonstrated over a period equivalent in length to the initial trial period.
The details of the warranty will be specified in the order/enquiry.

Page 10 of 47
ES/079
Rev 0 1988

2 DESIGN AND MANUFACTURING REQUIREMENTS


2.1 Scope and Configuration
2.1.1 Minimum Requirements
This standard establishes the minimum requirements for equipment to provide utility air on offshore
installations, for use as plant and instrument air. The equipment shall be supplied in packaged units
complete with all necessary auxiliaries and controls. The operating conditions duty and quantities will
be specified in the order/enquiry.
2.1.2 Vendor's Scope of Supply
The Vendor shall provide, as a minimum, the equipment listed below for each utility compressed air
package. Any other equipment required shall be indicated by the Vendor and included in the proposal.
(1) Single stage or two-stage rotary compressor(s) with integral drive gears and timing gears where
required.
(2) Oil separator for oil injected compressors.
(3) Condensate separator; installed downstream of, or combined with, the aftercooler.
(4) Intercooler (where required), aftercooler and oil cooler.
(5) Electric motor driver, coupling and guard, (if required).
(6) Control system and instrumentation.
(7) Lube oil system.
(8) Inlet air filter and silencer.
(9) Baseplate.
(10) Equipment condition monitoring system.
(11) Control panel(s).
(12) Acoustic enclosure.
(13) Filter coalescer installed downstream of the condensate separator.
(14) Instrument air drier installed downstream of the filter coalescer.
(15) After-filter : installed downstream of the air drier.
(16) Interconnecting piping and valves.
(17) Special tools and fixtures.
Air receivers are not in the Vendor's scope of supply unless specified in the order/enquiry.
2.1.3 Mounting
The utility compressed air packages shall be either 2 x 100% or 3 x 50% capacity units, as specified in
the order/enquiry. The complete utility compressed air system is defined as the 2 or 3 packaged units
specified.
Each packaged unit shall be mounted on a single baseplate. If necessary the package mode status
control panel may be supplied separately for wall or floor mounting. However, the preferred
arrangement is for this panel to be mounted on one of the package enclosures.
Alternative arrangements where the complete utility compressed air system (2 or 3 packaged units as
specified) are mounted on a single baseplate within a single enclosure may be offered. In this case,
however, there shall be no overall penalty with respect to space and weight and it must be possible to
maintain safely non-operating equipment whilst the compressor(s) are running.

Page 11 of 47
ES/079
Rev 0 1988

2.2 General Design


2.2.1 Complete Package
The complete package will be located either in an air conditioned room or a semi-open marine
environment, as specified in the order/enquiry.
The equipment (including auxiliaries) covered by this standard shall be suitable for the specified
operating conditions in the specified environment and shall be designed and constructed for
continuous unattended, uninterrupted operation for periods of at least 25 000 hours, except for minor
routine servicing operations such as oil and filter cartridge changing. It is recognised that this is a
design criterion as actual uninterrupted operation for this period of time involves factors beyond the
Vendor's control, and will not necessarily be achieved.
The package duty and specific requirements are shown on the data sheets included in the requisition.
A specimen copy of the utility compressed air package data sheets are included as Appendix 8 of this
Standard.
2.2.2 Design and Construction
The utility compressed air package shall be designed and constructed in accordance with BS 6244
(ISO 5388) as amended and supplemented by this Standard.
2.2.3 Noise Control
Utility Compressed Air Packaged shall be designed to minimise the generation of noise, and shall not
exceed the noise limits given in the following clauses:
(1) General
All definitions, notations, measuring equipment, measuring procedures, test reporting,
calculation methods and calculating procedures shall be in accordance with EEMUA
publications 140 and 141.
(2) Noise Limits
The compressor, gears and motor driver and other noise generating components of the
package shall be housed in an acoustic enclosure. The noise generated by the package,
measured at any location 1 metre from the surface of the enclosures, or the sound power level,
shall not exceed the limits stated on the “Noise Level Data Sheet”, a specimen copy of which is
attached as Appendix 4 of this Standard.
Where no limits have been specified, the sound pressure limit in dB re 20 x 10-6 Pa for the
package shall 83dB(A).
If the equipment produces impulsive noise, the above limit shall be reduced by dB(A). Impulsive
noise is defined as noise where the rise time is very short (a few milliseconds).
The above requirements apply in the absence of reverberation and background noise from
other sources and for all operating conditions.
(3) Information to be Submitted with the Proposal.
The Vendor shall complete Table 2 of the Shell Expro “Equipment Noise Level Data Sheet” (see
Appendix 4 of this Standard), providing the following information:
• the best estimate of the noise level to be expected from the compressor without the
acoustic enclosure;
• the expected noise levels outside the acoustic enclosure;
• the noise levels outside the acoustic enclosure that the Vendor is prepared to guarantee.

2.2.4 Oil Reservoirs and Housing


Oil reservoirs and housing which enclose moving lubricated parts; such as bearings, shaft seals,
highly polished parts, instrument and control elements, shall be designed to minimise the entrance of
moisture, dust and other foreign matter during periods of operation and idleness.

Page 12 of 47
ES/079
Rev 0 1988

2.2.5 Maintenance
All equipment shall be designed to permit rapid and economical maintenance. Major parts, such as
casing components and bearing housing shall be designed (shouldered and/or dowelled) to ensure
accurate alignment on reassembly. Shaft seals and bearings shall be accessible for inspection and
replacement with the minimum of disassembly.
2.2.6 Air Quality
Unless otherwise stated in the order/enquiry the air quality shall be as defined below:
• maximum allowable particle size: 1 micron (100% filtration efficiency);
• maximum oil content (droplets and vapour): 0.05 ppm (w/w) at 21°C;
• dew point at operating pressure measured at the drier outlet : at least 10°C below the minimum
design ambient temperature specified in the order/enquiry.
2.2.7 Outlet Air Pressure
The required outlet air pressure stated in the order/enquiry shall be the pressure at the outlet of the
after-filter. This pressure shall be attainable with a dirty filter coalescer and after-filter.
2.2.8 Lifting System
The Vendor shall design and provide a suitable system for lifting the complete package unit. Four
lifting points shall be provided, located so that the unit can be lifted from a single hook using equal
length slings, without fouling the installation. The unit shall remain substantially horizontal while being
lifted.
2.3 Package Components
2.3.1 Compressor and Driver
(1) The compressor shall be to the manufacturer's standard proven design and construction,
coupled either directly or via integral gears to an electric motor driver. The compressor shall be
either a single-stage oil-injected screw or vane type, complete with oil separation equipment, or
a two stage (intercooled) oil-free screw or lobe.
(2) The motor shall be rated for not less than 110% of the total compressor absorbed power at
rated discharge pressure under the most adverse inlet temperature. The motor shall comply
with DEP.33.66.05.31Gen and shall be suitable for the area classification specified in the
order/enquiry. Unless otherwise specified, the motor starter, supply cable and gland will be
provided by the Purchaser.
The motor type shall be as stated on the data sheets and shall be obtained from one of the
Vendors listed in the order/enquiry.
2.3.2 Coolers
(1) The coolant supplied to the package will be either sea water, cooling medium or air, as specified
in the order/enquiry. Cooling medium is a mixture of potable water, mono-ethylene glycol,
corrosion and scale inhibitors.
(2) Coolers shall be provided for the following duties, as applicable:
• intercooling two-stage compressors only;
• aftercooling;
• oil cooling for lubrication and air coolant;
• Other duties necessary for compressor operation; eg bleed-off cooler if required for
capacity control.
Cooling duties may be combined to suit Vendor standard configurations. Air cooler fans shall be
directly driven by either the main compressor driver motor or by an auxiliary motor.

Page 13 of 47
ES/079
Rev 0 1988

(3) Where sea water is specified as the coolant the coolers shall be constructed from the following
materials:
Shell and Tube Exchangers;
Tubes: 70/30 or 90/10 Cu Ni to BS2871; Part 3 CN107 and CN102 respectively.
Tube plates: 70/30 or 90/10 Cu Ni to BS2875, CN107 and CN102 respectively.
Channels and Headers: leaded gun metal or nickel aluminium bronze to BS1400, LG2C or
LG4C or AB2C.
Titanium may also be used, but not in conjunction with copper alloys.
Plate Exchangers;
Plates: Titanium.
2.3.3 Filter Coalescer
(1) The filter coalescer shall be sized to handle the maximum capacity of the compressor
connected to it.
(2) The filter coalescer shall be sized be of the replaceable cartridge type, designed to permit
continuous operation on full load for 4000 hours.
The filter vessel shall be designed, constructed and tested in accordance with Shell Expro
Standard ES/205.
The filter coalescer shall be fitted with either an automatic float trap or a timed pneumatically or
electrically operated drain valve with isolation and manual by pass.
2.3.4 Air Drier
(1) The drier shall be sized to handle the maximum capacity of the compressor connected to it.
(2) The air drier(s) shall be of the adsorption type requiring no energy source from outside the
package. Drier vessels of welded construction shall be designed, constructed and tested in
accordance with Shell Expro Standard ES/205. Drier vessels of proprietary design are
acceptable subject to approval by the Purchaser, and provided they are designed in accordance
with the requirements of BS 5169, BS 5500 or ASME VIII Div.1.
Air drier unit(s) shall be self-contained; complete with vessels, desiccant, valves,
interconnecting piping, automatic moisture removal and control systems, and any other
equipment necessary for drier operation.
(3) Driers with twin vessels holding granulated desiccant, and operating through one vessel while
the other is regenerating, shall additionally be designed in accordance with the following:
• to minimise desiccant attrition the drier shall be arranged to dry air with a downward flow
and regenerate with an upward flow. Alternative designs which include devices to prevent
desiccant attrition while drying with an upward flow may be acceptable, subject to
approval by the Purchaser.
• depressurisation time shall be no less than 15 seconds and controlled by an orifice;
• the outlet for vessel depressurisation and desiccant regeneration air shall be fitted with an
exhaust silencer to limit the noise level to 83dB(A) measured at 1m from the air vent;
• the switching valves shall be of proven design with satisfactory operating experience over
a minimum of 300 000 cycles.

Page 14 of 47
ES/079
Rev 0 1988

2.3.5 After-Filter
(1) The after-filter shall be sized to handle the maximum capacity of the compressor connected to it
and shall be designed to remove solids carried over the air drier.
(2) The filter element shall be of the replaceable cartridge type, designed to permit continuous
operation on full load for 4000 hours. The filter design shall be such that the element can be
changed in less than one hour.
The filter vessel shall be designed constructed and tested in accordance with Shell Expro
Standard ES/205.
The filter shall be fitted with a manual drain valve.
2.3.6 Baseplate
(1) The Vendor's standard baseplate shall be used where suitable for supporting all the equipment
specified and providing the following requirements are met:
• the baseplate shall be designed such that water cannot collect and stagnate within the
baseframe confines. It shall be assumed that the package will be installed directly on the
decking;
• the baseplate shall be supplied with the following equipment at each support point:
• mounting plate suitable for welding to the supporting steel structure. The
mounting plate shall be a minimum of 200mm square and 40mm thick drilled and
tapped to accept the holding-down stud. The actual plate thickness shall be
determined so as to ensure adequate thread engagement with the holding-down
stud, with the nut at the appropriate torque,
• holding-down stud, nut and washer in accordance with BS3692 and BS4320.
Where there are space restrictions with a particular baseframe design, a bolt may
be used in place of the stud and nut subject to approval by the Purchaser,
• shim pack of assorted thicknesses, to a total thickness of 15mm. Shims shall
straddle the holding-down stud/bolt and shall be manufactured from AISI 316
stainless steel.
• two earthing bosses shall be provided, at diagonally opposite locations. Each earthing
boss shall consist of a 50mm diameter bar x 50mm long. A central hole tapped M10 x
30mm deep is to be machined before welding the bar into position with a 6mm
continuous fillet weld. The face of the boss is to be machined square. The thread and
machine face shall be left unpainted;
• the baseplate shall be capable of sustaining a horizontal acceleration of 0.7g in any
direction, and 2.0g vertically during transportation/lifting without exceeding the normal
allowable stresses by more than 30%, and without subjecting any internal nozzles on
equipment within the package to loads greater than the design loads.
(2) A baseplate in accordance with Shell Expro Standard ES/179 shall be supplied under the
following circumstances:
• the Vendor's standard baseplate is not suitable for supporting the specified equipment
arrangement and/or does not comply with paragraph 2.3.6(1) above;
• the 2 (or 3) packaged units specified are to be mounted on a single baseplate.

Page 15 of 47
ES/079
Rev 0 1988

2.3.7 Acoustic Enclosure


(1) The acoustic enclosure shall be designed to reduce the noise generated by the Utility
Compressed Air Package to the levels defined in Section 2.2.3 of this Standard.
(2) The outer surface of the enclosure shall be either stainless steel or glass reinforced plastic
(GRP), of a grade suitable for the operating conditions, and the construction shall be suitable for
the operating conditions, and the construction shall be suitable for installation in an open marine
environment. The enclosure shall be designed to prevent the ingress of water from the direct
impingement of a seawater washdown hose, with special attention to the following:
• door seals;
• inlet and outlet grills; which shall be protected with louvres or inverted “cans” if the
openings are in the enclosure roof;
• instrument and control panels which are mounted flush with the enclosure surface.
(3) For stainless steel enclosures the acoustic panels shall be formed with an outer facing of
stainless steel sheet, acoustic media and a lining of perforated stainless or galvanised steel
sheet. Internal stiffening shall be fitted as appropriate.
(4) Acoustic medium shall be inert, non-combustible and non-hygroscopic. Enclosure panels shall
be easily dismountable and simple to re-assemble to facilitate equipment maintenance and
change-out. The enclosure and baseplate assembly shall be sufficiently rigid to withstand
transportation and handling in the module/integrated deck fabrication yard.
2.4 Interconnecting Piping and Valves
2.4.1 Piping
Piping design and fabrication outside the compressor acoustic enclosures should comply with
ANSI.B31.1 or equivalent. Piping within the acoustic enclosure may be designed and fabricated in
accordance with the piping standards normally used by the Vendor. If stainless steel or copper tubing
is proposed it shall be in accordance with recognised National or International standards.
The Vendor shall submit, with the proposal, complete details of the piping in the package both inside
and outside the enclosure, including specifications, materials, sizes and fittings/flanges.
The number of flanges, fittings and valves in the piping system shall be kept to a minimum.
Purchaser's piping connections shall be grouped at the edge of the package and shall terminate with
flanges to ANSI.B16.5. All terminations, other openings and any piping despatched separately to the
package, shall be identified with corrosion resistant metal tags as to their service and duty.
2.4.2 Flange Finish
All ANSI 150lb rated flanges of nominal size 24 inch and smaller, and other surfaces to which flanges
are to be connected, shall be machined as follows:
• the gasket contact surface shall be finished by a continuous spiral groove generated by 1.6mm
radius round-nosed tool at feed rate of between 0.7 and 0.9mm per revolution, to achieve an
average arithmetic roughness height value (CLA) of between 6.3 and 12.5 microns.
2.4.3 Valves
(1) The Vendor shall submit with the proposal details of all relief valves and control valves in the
system; including manufacturer, model number, rating, size and materials of construction.
(2) There shall preferably be no block valves between individual items of equipment within the
package. Valve actuators and operators shall clearly indicate the open and closed positions.
Automatic condensate drains shall be provided at all low points in the system.
(3) Each stage of compression shall be provided with a safety relief valve. Additional valves shall
be installed to protect the downstream equipment where necessary to comply with the
applicable design codes.
Connections shall be provided at the package limits for relief valves external to the acoustic
enclosure. Relief valves installed within the enclosure may discharge locally.

Page 16 of 47
ES/079
Rev 0 1988

2.5 Control and Instrumentation


2.5.1 Control Systems
(1) The utility compressed air package shall be supplied with a control system designed for fully
automatic control. The system shall be based on fully modulated compressor intake throttling,
automatic loading and unloading (with an overriding control to prevent the compressor running
unloaded for extended periods), or a combination or both systems.
(2) The Vendor shall submit full details of the control system with the proposal. The system detailed
design shall be developed jointly by the Vendor and Purchaser to suit the specific installation
requirements.
(3) The expected system operation is given in Appendix 7 for the different methods of capacity
control. The operating pressures will be advised in the order/enquiry.
(4) A water content analyser of the lithium chloride type (or equivalent) shall be provided
downstream of the air drier(s). The analyser shall measure water content of the instrument air
and shall provide local indication and a high humidity alarm.
(5) The compressor control system shall include provision for signals from the fire and gas panel to
stop and inhibit running of the compressor as may be necessary in a hazardous situation.
2.5.2 Control Panels
Where possible, the instrumentation specified below shall be accommodated on the compressor
enclosure or on a panel associated with the drier as appropriate. Where this is not possible, a
separate free-standing control panel shall be provided for the complete utility compressed air system.
Package status control panel(s) shall be provided for the air system to enable each compressor to be
set in duty mode, standby mode and emergency standby mode as applicable. This may either be
integral with the control panels, or a separate panel suitable for wall or floor mounting.
The panel or panels shall be designed and constructed to prevent the ingress of water from the direct
impingement of a seawater washdown hose.
Instrument and control cabling shall terminate in junction boxes located within the acoustic enclosure
or the control panel as appropriate.

Page 17 of 47
ES/079
Rev 0 1988

2.5.3 Instrumentation
Unless otherwise specified in the order/enquiry, the following instrumentation shall be supplied with
the Utility Compressed Air Package. The Vendor shall also include any other instrument functions
considered necessary for the unattended, continuous operation of all components provided with the
package.

FUNCTION INDICATION ALARM TRIP


Air intake filter differential pressure I H (1)
Lube Oil filter differential pressure I H
Oil reclaimer oil level (2) I L LL
Oil reclaimer scavenge flow (2) I L (1)
Oil reclaimer differential pressure (2) I H
Oil reclaimer pressure (2) I H (1) HH
Oil reclaimer temperature (2) I H HH
Compressor discharge temperature (each stage) I H (1) HH
Intercooler and aftercooler discharge temperature I H (1) HH
Filter coalescer differential pressure I H
Drier inlet pressure I
After-filter differential pressure I H
Package outlet pressure I HH
Running Status (each compressor) I
Mode status (3) I
Drier discharge moisture content I H
Running hours indicator I
Lube oil temperature I H
Lube oil pump discharge pressure I L (1) LL

(1) Required only for unmanned installations, where specified in the order/enquiry.
(2) Oil injected screw compressors. Only the applicable functions should be included with oil
injected vane compressors.
(3) Duty, standby, emergency standby; as applicable.

Symbols: I: indication required


H: high HH : high high
L: Low LL : low low

In addition, the air drier shall be provided with all instrumentation necessary for automatic operation.
Separate contacts shall be provided for remote indication of a common alarm, a common shutdown
and compressor running status for each package.

Page 18 of 47
ES/079
Rev 0 1988

2.6 Electrical Requirements


2.6.1 General
(1) The electrical equipment shall be designed to prevent danger to personnel by the most
appropriate means, eg interlocking, insulation enclosed equipment and warning labels.
Inspection and acceptance of equipment will include consideration of these aspects whether a
particular safety feature is specified or not.
(2) The electrical installation shall comply with I.E.E. Recommendations for the Electrical and
Electronic Equipment of Mobile and Fixed Offshore Installations and be subject to the conditions
of Factories Act (Electricity Regulations) and the Health and Safety at Work etc. Act 1974.
(3) The Vendor is required to provide and install wiring and electrical equipment in a neat
accessible and robust manner. All components, supports and interconnecting wiring shall be
substantial enough, or so protected to perform the intended duty as well as withstand the
rigours of maintenance activity without damage or distortion.
2.6.2 Electrical Supply
(1) The electrical system voltages, frequencies and rating of equipment will be as specified on the
data sheets.
(2) The Vendor's attention is drawn to the levels of harmonic distortion of the supply voltages and
current waveforms. Details of any harmonic distortion levels will be stated in the data sheets.
(3) The supply for all anti-condensation space heaters shall be wired to a common terminal box for
the Purchaser or Contractor to connect form a remote supply. A 2-pole local isolator shall be
provided by the Vendor adjacent to each heater. The power supply to heaters will be single
phase unless otherwise specified.
(4) Automatic start controls for motors shall be so designed that in the event of power failure, the
motor will not automatically re-start on restoration power. Under no circumstances must it be
possible to inhibit the stopping of a motor.
(5) Unless otherwise specified in the order/enquiry, main power will be cabled directly to the motors
and control circuits will be cabled to the remote control units.
Where the Vendor is required to supply package mounted starters, the Purchaser will cable
direct to these units and no interposing terminal boxes are required.
The Vendor shall liaise with the purchaser to ensure that gland plates are drilled and tapped to
suit incoming Purchaser connections.
(6) The package shall be provided with a means of isolating the power supply ('stop' push button),
located within easy reach of the compressor drive motor.
2.6.3 Cabling
(1) The Vendor shall provide and install all electrical cabling for connecting the various components
forming the Utility Compressed Air Package. The Vendor shall advise in the proposal, if any
special cables are required.
(2) Insulation level of low voltage power and control cables shall be 600/1000 volt grade.
Power cables shall be rated in accordance with the IEE Recommendations for the Electrical and
Electronic Equipment of Mobile and Fixed Offshore Installations. The potential Vendor shall
state, in the proposal, the derating factor employed. To provided mechanical robustness cable
conductors shall be of the stranded type with a minimum cross sectional area of 1.5mm².
(3) Cable support shall be by either ladder rack, or heavy duty type tray. Power cables shall be
suitably segregated form low power instrument cables to prevent electro-magnetic interference.
Cable support systems shall not be mounted in a manner that will cause obstructions or prevent
easy access round equipment for operating and maintenance activities.
Cables shall be strapped to trays using insulated stainless steel cable ties.
(4) Where conduit is the only practicable way of routing cables, all necessary boxes and sealing
compounds shall be supplied. Where conduit is proposed, this shall be stated by the Vendor in
the proposal. Only hot dipped galvanised solid drawn metal conduit is acceptable.

Page 19 of 47
ES/079
Rev 0 1988

(5) Cables shall not be routed above machinery requiring maintenance lifting equipment, on the top
of oil tanks, or fastened to process pipes or vessels. All on-skid cabling shall be carefully routed
and fixed into place to avoid stress on cable termination's and mechanical damage.
2.6.4 Terminal Points
(1) The Vendor shall provide suitable terminal boxes or termination points for all the Purchaser's
cable connections and shall state the size of terminal being provided. Boxes shall be positioned
for ease of access and such that the minimum cable bending radii are not violated.
(2) Terminal boxes for separately mounted control panels (where applicable) shall preferably have
detachable undrilled gland plates for the Purchaser's cable connections. Gland plates provided
for the Purchaser's use shall be separate from those used by the Vendor's cabling such that
they may be detached and drilled on site without disconnecting 'on-skid' installed cabling.
Where screwed entries are required they shall be threaded ISO MIO. The Vendor shall liaise
with the Purchaser to determine the thread size.
(3) The position of the Purchaser's cable entries shall be shown clearly on the general arrangement
drawings.
Where the Vendor terminates 'on-skid' control cables into control panels or junction boxes the
cables cores shall be neatly loomed around the panel such that any core may reach the furthest
point of termination.
(4) The Vendor shall provide terminals and terminal boxes of adequate dimensions to
accommodate all 'field' wiring to be supplied by the Purchaser and terminated on the package.
The Vendor shall liaise with the Purchaser to confirm dimensions and types of 'field' cables.
(5) Power and control cable conductor termination's shall, for cores up to and including 4mm² csa,
be terminated on screw clamp/pressure plate type equipment terminals. For cores greater than
4mm² cross sectional area, tinned copper compression lugs shall be utilised for terminating the
individual cores. MICC cables shall be terminated in accordance with the Manufacturer's
recommendations
Cables shall be identified by attaching plastic cable tags, marked with the cable number. These
shall be of the Critchley Unilabel type or approved equivalent. Cores of all cables shall be
identified with ferrules displaying the number shown on the wiring diagrams.
Circuits and terminals operating at different voltage levels and/or performing different functions
shall be segregated by an insulation barrier. Intrinsically safe circuits must be completely
segregated. Removable transparent cover plates with warning labels shall be provided over
terminals operating above 50 volts a.c.
2.6.5 Earthing
Earthing within the package shall be the Vendor's responsibility. All sections of steel enclosures,
electrical equipment and the baseplate shall be connected electrically to each other to form a
continuous low impedance path to earth.
2.6.6 Protection
All electrical equipment shall be adequately protected against overloading, short circuit and earth
faults. Protective devices will normally be provided by the Purchaser. The Vendor shall provide details
of any recommended protection devices with the proposal.

Page 20 of 47
ES/079
Rev 0 1988

2.7 Inspection and Testing


2.7.1 Inspection
(1) General
All equipment covered by this Standard shall be subject to inspection at the Vendor's works and
at the works of any sub-vendor or sub-contractor, by the purchaser's engineers or by a
consultant or agent acting on behalf of the Purchaser.
The Purchaser and/or his agent shall therefore be permitted access to the equipment at all
reasonable times.
The above requirements shall be drawn to the attention of any sub-vendor or sub-contractor
and shall be made a condition of any sub-order or sub-contract.
(2) Specific Inspection
Certain tests and inspection shall be witnessed by the Purchaser and/or his agent and shall be
considered “hold points” in the manufacture. These tests and inspections will be listed on the
“Schedule of Essential Tests and Inspections”, a specimen copy of which is attached as
Appendix 5 of this Standard.
2.7.2 Testing
The following tests shall be performed and the Purchaser given the opportunity to witness them:
(1) Hydrostatic Tests
Pressure vessels shall be tested in accordance with the applicable code. All other pressure
containing parts (casings, coolers, piping system and valves) shall be subjected to a hydrostatic
test at a pressure of not less than 12 times the maximum working pressure of the utility
compressed air package. The test fluid shall be fresh water containing a corrosion inhibitor.
The pressure shall be held for a sufficient period of time to permit complete examination of the
parts under pressure. This period shall not be less than 30 minutes. Any leakage shall be the
cause for rejection.
(2) Motor Tests
Electric motors shall be tested in accordance with Shell DEP.33.66.05.31-Gen.
(3) Control Panel Test
The local compressor control panel shall be fully functionally tested at the
Vendor's/manufacturer's works. All remote signals, both incoming and outgoing, shall be
simulated and the specified local/remote annunciation requirements demonstrated.
(4) Compressor Performance Test
The bare compressor shall be subjected to a performance test at the Vendor's works, in
accordance with BS 1571: Part 1 (ISO 1217) or BS 1571: Part 2. The Vendor shall advise if the
standard test procedure is to a different standard/specification. Details of the test procedure
shall be submitted with the proposal.
(5) Package Performance Test
Each complete utility compressed air package shall be subjected to an extended 8 hours
performance test at the Vendor's works to verify mechanical integrity. All slave equipment shall
be identified prior to the test and shall be used only with the approval of the Purchaser. The
Vendor shall submit the test procedure with the proposal.
The parameters listed below shall be recorded at half-hourly intervals during the test:
• ambient air pressure and temperature (wet and dry bulb);
• discharge air pressure for each stage of compression;
• discharge air temperature for each stage of compression before and after the cooler;
• free air delivered from the package;
• lube oil pressure;

Page 21 of 47
ES/079
Rev 0 1988

• lube oil temperature before and after cooler;


• motor speed;
• absorbed power;
• pressure at package plant air outlet and instrument air outlet connections;
• dew point at package instrument air outlet connection;
• moisture content at package plant air outlet connection.
In addition, noise levels outside the enclosure, with the drier operating, shall be measured
during the test.
Following a satisfactory test run all sensing device actuation's shall be simulated and all modes
of operations and malfunction protection shall be demonstrated.
Should the test reveal any faults or no-compliances, the Purchaser reserves the right to instruct
the Vendor to carry out remedial work and repeat the extended test.
2.8 Nameplate
Nameplates of 18 Cr-8Ni stainless steel or Monel type material shall be furnished, securely attached
by stainless steel or Monel pins to the compressor casing and acoustic enclosure. The nameplate(s)
shall be stamped with the following information in the English language with the data in SI units.
Purchaser's name Casing hydrostatic test pressure bar g
Purchaser's order number Compressor speed (rpm)
Equipment serial number Compressor and motor model/frame number
Capacity (Nm³/h) Manufacturer of compressor and motor
Relief valve set pressure (bar) Year of manufacture
Motor rated power (kW) Project Tag Number
In addition to being stamped on the nameplate, the compressor serial number shall be plainly stamped
on the casing and the relief valve set pressure shall be stamped on the valve body.
2.9 Painting
Stainless steel panels and equipment of aluminium bronze, cupro nickel and stainless steel shall not
be painted. All other equipment shall be painted in accordance with ES/011.
Alternatively, equipment located within the acoustic enclosure may be painted in accordance with the
Vendor's standard for a marine environment subject to approval by the Purchaser. The Vendor shall
submit details of the standard procedure, for review and approval, with the proposal. Details shall
include surface preparation, paint materials/application/thicknesses and the manufacturer's data
sheets.

Page 22 of 47
ES/079
Rev 0 1988

3 PREPARATION FOR SHIPMENT AND STORAGE


3.1 General
(1) This section describes the minimum procedure to be followed by Vendors and Manufacturers to
ensure the adequate preservation and protection of their mechanical equipment during
transportation and storage prior to unpacking at the module fabrication yard, or any other
manufacturing or fabricating facility that may be specified in the order/enquiry. Procedures for
extended storage (cocooning) of mechanical equipment are not described in this Standard. If
required, such procedures will be covered separately in the order/enquiry, or an attachment
thereto.
(2) THE VENDOR/MANUFACTURER SHALL PRODUCE A DETAILED PRESERVATION AND
PROTECTION PROCEDURE FOR THE PACKAGED UNITS, INCORPORATING THE
REQUIREMENTS OF THIS STANDARD.
Different preservation methods or deviations to the methods described here may be proposed
by the Vendor but shall only be used with the approval of the Purchaser.
The preservation and protection procedures shall also be applied to equipment which is to be
shipped directly to an offshore location; either during initial construction/hook-up, or as
spare/replacement units during operational periods. Any additional preservation/protection
requirements for sea transit or offshore storage shall be advised by the equipment
Vendor/Manufacturer.
(3) Unless otherwise specified, the equipment will be installed on a Shell Expro offshore
installation. Equipment preservation and protection shall be adequate to enable the equipment
to be delivered without suffering damage or deterioration, stored at the module fabrication yard
(or other place of storage that may be specified) for a period and then installed in a module (or
in the open) during the construction phase. The probable storage period will be specified in the
order/enquiry for the equipment and will extend form time of despatch to the time of unpacking
at the fabrication yard. If the storage period is not stated in the order/enquiry, a minimum period
of 12 months shall be assumed. The construction will normally last for a 6-12 month period.
Following construction the module containing the equipment will be transported by barge to the
platform location for final installation, hook-up and process/utility commissioning.
(4) It is recognised that some or all of the preservation and protection applied to the equipment by
the Vendor will, of necessity, be removed at the fabrication yard during equipment installation
and hook-up. If applicable, temporary preservation will then be applied to the equipment for the
sea transit, installation and hook-up phases to ensure adequate protection up to the time of
offshore process/utility commissioning.
The Vendor shall advise the Purchaser of any special measures or precautions which should be
taken during this period.
(5) As long as the equipment packaging and protection remains unopened and undamaged, and is
correctly handled in accordance with the Vendor's marking and shipping instructions, then it
shall remain the responsibility of the Vendor that the equipment supplied remains in the same
condition as when accepted by the Purchaser ex-works.
If the Vendor so wishes, this responsibility may be conditional on the Vendor being allowed to
inspect the equipment preservation/protection at intervals (to be agreed between the Vendor
and Purchaser) and on the Purchaser acting on any reasonable recommendations made by the
Vendor following such inspection visits. Such activities carried out under the Vendor's
supervision, or with the Vendor's approval, shall not relieve the Vendor of his liabilities as
described above.
(6) All items containing preservations an inhibitors shall have prominent warning labels or tags
securely attached advising of procedures cautions, toxicity of materials, hazards, necessity for
removal prior to placing in service and any other salient cautioning factors. When VPI powders
are used inside equipment , red tags shall be attached to the outside indicating the quantity of
bags inside. All materials and procedures shall comply with the Health and Safety at Work Act
etc., 1974. The Guide to Shell Lubricants published by SIPC Ltd. Provides guidance on the use
of Shell preservatives.

Page 23 of 47
ES/079
Rev 0 1988

(7) All flanged openings shall be provided with gasketted metal protection plates in accordance with
Figure 1 of this Standard. Plastic or wooden plates/closures are not acceptable. The purpose of
these special plates is to enable them to be left in position whilst pipe connections are made.
(8) All open ends of drains, vents, instrument tubing and small bore piping connections shall be
capped or plugged with metal caps or plugs, as applicable. Threaded caps and plugs shall be
used for threaded connections. Grease fittings shall be protected with plastic caps.
(9) Any item of equipment protected internally with a desiccant shall be prominently labelled or
tagged “WARNING- DESICCANT INSIDE”. Desiccant shall be placed in a bag or other suitable
container so as to prevent it dispersing inside the equipment during transit or installation. The
drying of equipment prior to the application of preservative may be done by wiping dry or air
drying. However, all inaccessible areas shall be air dried.
When appropriate, the Vendor shall calculate the amount of desiccant required following the
guidelines on the use of desiccants laid down in BS 1133 Section 19.
NOTE: Desiccant should be not used in combination with Shell VPI Powders.
(10) Warning labels and tags shall be secured with stainless steel wire or rivets (as appropriate), in
such a way that they will remain attached during transit and storage for 12 months under
adverse conditions. Labels and tags shall preferably be of stainless steel, and lettering shall be
a minimum of 10mm high.
(11) Stress corrosion cracking can result when stainless steel equipment is in contact with salt water
at temperatures greater than 50°C. The residual stress in welded equipment can be sufficient to
promote stress corrosion cracking. Extra precautions shall be taken when preserving stainless
steel equipment which will be subjected to a saline environment whether during operation,
transit or installation.
3.2 Minimum Requirements for Utility Compressed Air Packages
(1) All exposed shafts, machined and polished surfaces, shall be thoroughly cleaned coated with
Shell Fluid SDC and wrapped with heavy-gauge plastic sheeting secured with tape. Shell
Ensues Fluids are described in the Guide to Shell Lubricants published by SIPC Ltd. Shaft
entries to bearing housing and casing shall be wrapped with heavy-duty tape to prevent the
ingress of dirt, dust and moisture.
(2) It should be noted that alkaline solvents must not be used to clean no-ferrous metals especially
aluminium, tin and zinc, and alloys thereof. Most alkaline cleaners are also liable to attack paint.
Alkaline solvents should be used with caution on highly finished surfaces, as they may damage
the surface or cause staining. Finger sweat on fine-machined surfaces shall be removed with
methanol.
(3) The major components of the package (compressor motor drier(s) filters etc.) shall be
preserved in accordance with the Vendor's/manufacturer's standard procedures for the
environment.
(4) Piping system internals within packaged units and any section piping (including spool pieces)
which are to be dispatched or handled separately shall be flushed and properly drained and
dried internally and then preserved with VPI powder or a desiccant. For stainless steel piping
systems, refer also to Section 3.1(11) of this Standard.
Flanged openings of piping system within packaged units and separate sections of piping shall
be closed in accordance with Section 3.1(7) of this Standard.
(5) Valves shall be preserved together with, and in the same manner as the piping system in which
they are incorporated, or by the same procedure applying to the mechanical equipment with
which they are associated.
Valves shall be left slightly open to avoid metal-to-metal contact; diaphragm valves should
always be left in the fully open position.
Valve packing shall be left in place. Valve spindles shall be thoroughly cleaned, coated with
Shell Ensis Fluid of the appropriate grade (at least Shell Ensis Fluid SDC) and wrapped with
heavy-duty plastic sheeting or tape.

Page 24 of 47
ES/079
Rev 0 1988

(6) Control panels and instruments shall be sealed to ensure they are watertight, a suitable
desiccant (eg silica gel) placed inside and then they shall be shrink-wrapped with at least 2
layers of heavy-duty film (0.2 mm thick). The faces of control panels and instruments shall be
protected with plywood at least 6mm thick. Electrical and instrument junction boxes (and other
equipment) shall be sealed to ensure they are watertight, with a suitable desiccant (eg silica gel)
placed inside.
Electrical wiring shall be terminated and adequately supported. No wires shall be left exposed.
Note that desiccant must not be used in combination with Shell VPI powders.
(7) It is essential to thoroughly flush out Shell Ensis Fluids before filling equipment with the service
oils, as Ensis Fluids or other silicone-based fluids, even in trace quantities, may cause serious
deterioration in the service oil.
3.3 Tagging of Equipment
(1) Before despatch, the Vendor shall mark on, or securely attach to the equipment, as list of the
specific oils greases and rust preventatives used to protect the equipment. The list shall include
external as well as internal treatment/oils used, giving Manufacturers and type number, the
locations where each has been applied, method of removal and details of special precautions to
be taken during periods of storage.
(2) Before despatch, the Vendor shall mark on, or securely attach to the consignment, any special
handling and/or storage instructions. These instructions shall include notification of any
electrical, instrumentation or other components not suitable for long-term outdoor storage and
any special handling instruction for catalysts and chemicals.
(3) Each package shall be tagged with a stainless steel tag secured with stainless steel wire. The
tag shall contain the following information in lettering of 10mm height minimum:
• Shell U.K. Exploration and Production;
• Purchaser (if not Shell Expro);
• Project Name and Number;
• Purchase Order Number;
• Item Number/Project Tag Number;
• Overall size and weight.
(4) The Vendor shall comply with any additional instructions for tagging specified in the
order/enquiry.
3.4 Packing for Transportation and Storage
(1) Whenever possible, the package shall be packed for despatch by erecting suitable protective
covers, panels, boxes, etc., on and within the confines of the package. The arrangement shall
be such as to enable the package to be placed in position without removing such protection.
Also the protection should allow access to connecting flanges and other Purchaser connections.
Any items not mounted on the package shall be boxed suitable for export. This shall require the
equipment to be packed in stout wooden boxes with the lids securely fastened by nailing,
screwing or strapping.
Alternatively the package may be shipped on a wooden or steel pallet. The equipment shall be
fastened to the pallet with strapping. Strapping shall comply with BS 1133 Section 15 and shall
be stainless steel or plastic-coated steel, of minimum width 12.5mm, thickness 0.27mm.
Stainless steel strapping shall be prevented from rubbing directly on the equipment.
Wooden boxes shall comply with BS 1133 Section 8 and any shipping regulations or other
instructions included in the order/enquiry. The boxes shall be marked on at least two sides and
top with the same information listed in Section 3.3(3) of this Standard, together with the
Purchaser's name and the delivery address.
Wooden containers shall be manufactured of flame-retardent timber. Steel boxes and
proprietary re-usable boxes are acceptable.

Page 25 of 47
ES/079
Rev 0 1988

Consideration should be given to the further use of such boxes to provide protection for the
equipment at the fabrication yard during the equipment installation and module construction
phases. This may be done by providing removable covers over the termination position and
panels, such that the package can be connected up at the fabrication yard without removing the
complete box.
All boxes shall contain a vapour barrier material.
A list of contents, in a waterproof enclosure, shall be attached to the outside of the box, or
equipment if on a pallet, and a duplicate list enclosed with the contents.
(2) All fragile items such as control panels, instruments and small piping/tubing shall be adequately
supported and glass faces covered with polythene and plywood, which shall be at least 6.0mm
thick. Vendors shall note the requirements given in Section 3.2(6) of this Standard.
(3) Whether boxed or strapped to a pallet for shipment, all equipment shall be adequately
supported so as to prevent damage during transit and lifting. The lifting points shall be clearly
indicated.
(4) If it is necessary to remove any items from the equipment package for shipment, they shall be
tagged boxed and labelled in accordance with the requirements stated here for the equipment
package.

Page 26 of 47
ES/079
Rev 0 1988

4 WEIGHT CONTROL
The vendor shall comply with the following requirements for all equipment to be installed on an
offshore facility.
4.1 Information with Proposal
A potential Vendor shall provide in the quotation, the estimated total installed operating weight of each
package to be supplied, including all ancillaries and appurtenances regardless of whether they are
supplied loose or installed on the unit.
The weight estimate shall have an upward tolerance of 10%.
Prior to placing the order, a Vendor may be required to guarantee his weight estimate with the above
tolerance.
4.2 Information Following an Order
Within 28 days of receipt of an order (or some other period as specified) the Vendor shall supply the
following information:
• the weight and position of the centre of mass of each package:
• as intended to be shipped including packing, temporary shipping constraints, lifting
equipment, etc.,
• as installed including all ancillaries, appurtenances, etc.,
• in operation, ie including the normal contents of process fluids lubricants etc.;
• the weight of any ancillary or appurtenance to be shipped separately;
• the weight of any component or item included in a package greater than 200kg or 25% of the
total weight of the package, whichever is the lesser (defined as a “major” component).
The above information shall be provided on a “Weight/Centre-of-Mass Data Sheet” a specimen of
which is attached as Appendix 1 of this Standard.
4.3 Weight Control During Manufacture
The Vendor shall operate a Weight Control Programme and shall notify the Purchaser at any time if
information becomes available, indicating that the weight of the complete pump unit or any major
component differs from the data provided under Section 4.2 by more than 5% of the total weight.
The Vendor shall weigh all components or ancillaries as they are completed in his shops or received
from Sub-vendors.
When all significant components have been completed or received, the Vendor shall review his initial
weight estimates and confirm or modify the data by reissuing the “Weight/Centre-of-Mass Data Sheet”.
This shall be done not later than one month prior to the agreed shipment data.
On completion of each complete package, the Vendor shall weigh it and again revise his initial
estimates if necessary and re-issue the “Weight/Centre-of-Mass Data Sheet” certified final.

Page 27 of 47
ES/079
Rev 0 1988

5 DOCUMENTATION
5.1 Technical Manuals
5.1.1 General
Technical Manuals shall be provided and shall incorporate both Vendor and sub-vendor data.
Technical Manuals shall be in accordance with BS 4884 Part 1 and Part 2. In addition, they shall meet
the requirements of this Standard.
Vendors shall submit the Manual Index to the Purchaser prior to the manual being issued for review
and approval.
The manual shall be divided into nine information categories (parts) as given below:
• Part 1 Leading Particulars (including data sheets);
• Part 2 Installation;
• Part 3 Commissioning;
• Part 4 Operation;
• Part 5 Maintenance;
• Part 6 Parts Data, including Spare Parts List and Interchangeability Record (SPIR) forms
(shown in Appendix 2 of this Standard);
• Part 7 Drawings;
• Part 8 Lubrication;
• Part 9 Fault Finding/Correction Procedures
Within the Parts of the manual listed above, information shall be comprehensive and specific to the
scope of supply with non-relevant information clearly edited out. Information required under Parts 6 to
9 is self-evident and no further requirements are stated here. However, for other parts, details are
given below of the minimum information they shall contain.
5.1.2 Part 1 - Leading Particulars (including data sheets)
This shall include all main characteristics of the equipment including sizes, weight, supply
requirements, environmental and loading limitations, performance data, operating parameters, etc..
Details of suppliers and UK Agents shall be stated. A copy of the final issue of the appropriate
equipment data sheets shall be included.
5.1.3 Part 2 - Installation
This shall contain sufficient information to enable correct initial installation. Contents shall include (as
appropriate to the scope of supply):
• lifting, transportation, handling, unpacking and any special installation requirements;
• method of installation including alignment, mounting/support details and use of special support
equipment or tools;
• ex-works preservation status including handling/disposal instructions for any fluids or
compounds used for preservation or inhibition;
• details to enable connection of all utility services including any techniques required for certified
intrinsically safe equipment.
5.1.4 Part 3 - Commissioning
This shall contain sufficient information to enable correct commissioning and recommissioning after
major overhaul to be carried out. Contents shall include (as appropriate):
• procedures for preparation for initial operation including flushing, cleaning, lubrication,
introduction of any medium etc.;
• precommissioning checks;

Page 28 of 47
ES/079
Rev 0 1988

• measures necessary to maintain equipment integrity between initial commissioning (which may
be carried out onshore) and initial operation;
• recommissioning checks and test procedures following shutdown.
5.1.5 Part 4 - Operation
This shall include sufficient data for operators not familiar with the equipment to operate it in a safe
manner. Contents shall include:
• operating procedures for the various modes (manual/auto/remote) as applicable, and covering
start-up, steady state running, shutdown, emergency shutdown, and fault conditions.
Procedures shall include operational limitations, precautions and method of operating control
devices;
• diagrams identifying controls and adjustments.
5.1.6 Part 5 - Maintenance
This shall include sufficient planned, preventative and corrective maintenance data to support
equipment maintenance in the workshop and Purchaser's maintenance planned procedures. Contents
shall include:
• maintenance schedules indicating recommended minimum and maximum periods for
implementation of routine tests and preventative maintenance. Recommendations shall be
based upon stated role of equipment, and on the general requirement for most equipment to
operate continuously for long periods;
• all routine maintenance and test procedures;
• corrective maintenance procedure, including equipment removal, dismantling, overhaul,
assembly, replacement, repair, test and calibration. This information shall be supported by
diagrams/drawings (particularly where removal/replacement procedures are complicated) with
positive location of control points, adjustment points, test points etc.;
• specified cleaning methods and materials;
• fits/clearances and tolerances (baseline and maximum);
• details of access/lifting requirements including weights of all components requiring mechanical
lifting/handling facilitates for removal and replacement;
• list of tools required for maintenance, both standard and special, and diagrams of test rigs to be
used;
• safety precautions where necessary.
5.2 Data Sheets
Data sheets of approved form shall constitute the prime means of communicating details of the
equipment between Purchaser and Vendor. Unless otherwise agreed, Shell Expro and SIPM Data
Sheets shall be used. Specimens of some of the sheets to be used for the package are attached as
Appendices 1, 4 and 8 of this Standard.
The final issue of these data sheets, copies of which shall be in the Technical Manual (See Section
5.1), shall accurately record details of the equipment as delivered:
5.3 Other Documentation
Other documents, certificates, drawings, and data shall be supplied by the Vendor at the times and in
the form and quantities specified in the Documentation Requirements Schedule attached as Appendix
3 of this Standard. The Vendor shall also supply the documentation specified in other applicable
standards and specifications (eg ES/205).

Page 29 of 47
ES/079
Rev 0 1988

5.4 Information Required with Proposal


This Section summarises the sections in this Standard, which require the Vendor of the Utility
Compressed Air Package to submit information with the proposal in addition to the data and
documentation specified in the order/enquiry and/or necessary to describe the equipment being
offered. Listed below are the section numbers and key words describing the type of information
required. The list may be used for checking that all the required data has been submitted or received
as appropriate.

Section Key Word(s)


1.14 (1) Reliability/availability
1.14 (6) Extended warranty
2.2.3 (3) Noise
2.4.1 Details of piping
2.4.3. Details of valves
2.5.1.(2) Control system
2.6.3.(1) Special cables
2.6.3.(2) Power cable derating factor
2.6.3.(4) Conduit
2.6.6 Electrical protection
2.7.2.(4) Test procedure - compressor
2.7.2(5) Test procedure - package
2.9 Painting
4.1 Weight data

Page 30 of 47
ES/079
Rev 0 1988

6 REFERENCE DOCUMENTS
The following Standards, Codes and Specifications shall, to the extent specified herein, form a part of
this Standard. Except where a specific edition or revision is identified by date or revision/edition
number, the edition in effect at the time of the contract shall govern.
6.1 Legislation and Other Related Documents
Health and Safety Work etc., Act 1974
Factories Act (Electricity Regulations).
6.2 British Standards
BS1133 Packaging code
Section 8 Wooden containers
Section 15 Tensional strapping
Section 19 Use of desiccants in packaging
BS1400 Specification for Copper Alloy Ingots and Copper Alloy and High Conductivity
Copper Castings
BS1571 Testing of Positive Displacement compressors and exhausters
Part 1 Acceptance Tests (equivalent to ISO 1271)
Part 2 Methods for simplified acceptance testing for air compressors and exhausters
BS2871 Specification for Copper and Copper Alloys,
Part 3 Tubes. Tubes for Heat exchangers
BS2875 Specification for Copper and Copper Alloys, Plate.
BS3692 ISO metric precision hexagon bolts, screws and nuts
BS4320 Metal washers for general engineering purposes
BS4884 Technical Manuals
Part 1 Content
Part 2 Presentation
BS5169 Fusion welded steel air receivers
BS5500 Unfired fusion welded pressure vessels
BS5750 Quality systems
Part 1 Specification for design development, production, installation and servicing
Part 4 Guide to the use of BS5750: Part 1
BS6244 Code of Practice for stationary air compressors (equivalent to ISO 5388)
6.3 Other National/International Standards
ASME VIII Div. 1 Boiler and Pressure Vessel Code
ANSI B16.5 Steel Pipe Flanges and Fittings
ANSI B31.3 Chemical Plant and Petroleum Refinery piping
DIN 50049 Materials testing Certificates
EEMUA
Publication No. 140 Noise Procedure Specification
Publication No. 141 Guide to the Use of Noise Procedure Specification
IEE Recommendations for the Electrical and Electronic equipment of Mobile and
Fixed Offshore Installations

Page 31 of 47
ES/079
Rev 0 1988

6.4 Shell Expro Documents


6.4.1 Engineering Reference Documents
Standards
ES/011 Painting and Coating of Offshore Structures
ES/179 Baseframes for packaged units
ES/205 Non-critical pressure vessels
Manual
EM/012 Engineering Standard Forms: Data Sheets/Requisitions/Data
Requisitions
Data Sheets
EM/012-06-001 Equipment Noise Level Data Sheet
EM/012-06-002 Weight/Centre of Mass Data Sheet
EM/012-06-015 Utility Compressed Air Package Data/Requisition Sheet
(Sheets 1 and 2)
Shell Expro Drawings
U-22598-A2 (Figure 1) Equipment Nozzle Protection Plate for F.F., R.F. and R.T.J.
Flanges
6.5 SIPM Documents
6.5.1 SPIR Sheets
8384 Spare Parts List and Interchangeability Record (Sheet 1)
8692 Spare Parts List and Interchangeability record (sheet 2)
DEP 33.66.05.31-Gen Electric Motors - Three Phase Cage Induction Type
6.6 SIPC Documents
Guide to Shell Lubricants SIPC Marketing Publication 84/18 December 1984

Page 32 of 47
ES/079
Rev 0 1988

7 APPENDICES
7.1 WEIGHT/CENTRE OF MASS DATA SHEET

WEIGHT / CENTRE OF MASS DATA SHEET


EQUIPMENT DESCRIPTION INFORMATION STATUS
(TICK AS NECESSARY)

TENDER EST.
DESIGN EST
HEAVIEST COMPONENT TO BE HANDLED DURING MAINTENANCE: DESIGN UPDATE
DESCRIPTION WEIGHT KG AS SUPPLIED

WEIGHT DATA (KG)


NOTES:
1. ONE SHEET SHALL BE COMPLETED FOR EACH SEPARATELY INSTALLED SKID OR ITEM.
2. AS SUPPLIED EQUIPMENT SHALL BE WEIGHED BY VENDOR AND WITNESSED BY PURCHASER OR NOMINEE.
3. VENDOR SHALL PROVIDE CURRENT CALIBRATION CERTIFICATE OF WEIGHING EQUIPMENT CALIBRATION METHODS
SHALL BE TO BS 1610: 1967.
4. VENDOR SHALL SUBMIT DESIGN UPDATE FOR SIGNIFICANT CHANGES IN WEIGHT.

DRY KG OPERATING KG TEST KG

OTHER DESCRIPTION
TEMPORARY KG
WEIGHTS

CERTIFIED FINAL WEIGHT DATE NAME COMPANY


SHELL INSPECTOR
VENDOR

DIMENSIONAL DATA (MM)


NOTES:
1. EQUIPMENT ORIENTATION ON EACH SKID OR ITEM TO BE INDICATED.
2. C of G CO-ORDINATES TO BE CLEARLY SHOWN ON G.A. DRAWINGS.
'L' OVERALL SIZES
'X' DIMENSION 'L'
DIMENSION 'W'
DIMENSION 'H'
C of M
'W'

'Y'
CENTRE OF MASS
DIMN DRY OPERATING
PLAN
'X'
'Y'
'Z'
C of M
'H'
'Z'

ELEVATION

Rev.
letter
Date
Sign.
Sheet No. cont'd on Sheet No.
Eng by: Equipm. No.
Principle Req No.
Drawing No. 46834 EM/012-06-002 Rev 0, 1st ISSUE 10/87

Page 33 of 47
ES/079
Rev 0 1988

7.2 SPARE PARTS LIST AND INTERCHANGEABILITY RECORD


THE COMPLETION OF SPIR FORMS
The SPIR form consists of a main sheet and a continuation sheet, format A3. A specimen of each
sheet is attached to this guide.
The manufacturer/supplier is requested to complete columns 1 to 13, 15 and 19 of the form as
described below. All information should be given in the English language.

Column 1 - EQUIPMENT REG. OR TAG NO.


Enter the same equipment registration - or tag number for each piece of
equipment as stated in the requisition - or purchase order.
Column 2 - MANUFACTURER'S MODEL OR TYPE
State model, type or other positive identification reference of the
equipment/instrument ordered.
Column 3 - MANUFACTURER'S SERIAL NO.
State serial number or other identification reference of the equipment/instrument
ordered.
Column 4 - NO. OF UNITS
Enter the total number of pieces of identical equipment/instruments as quoted in
columns 1, 2 and 3.
Column 5 - NUMBER OF PARTS PER UNIT
For each unit or group of identical units, enter in the appropriate space the
number of parts fitted in each unit of equipment/instrument.
Column 6 - REQUISITION/MODEL REF NO.
State purchasing company's requisition or order reference number.
Column 7 - TOTAL NUMBER OF IDENTICAL PARTS INSTALLED
Enter the total number of identical parts covered by the equipment specified. In
the case of identical units multiply the quantity of column 5 by the number of units
given in column 4.
Column 8 - DESCRIPTION OF PARTS
List all parts which should be carried in stock for initial and normal operation
including slow-wearing parts. If an item is interchangeable between two or more
units it should be listed only once, refer to columns 10A and 10B.
Column 9 - DRAWING NUMBER
For each part in column 8 enter the manufacturer's parts list and/or drawing
number. Documents referred to should always be attached to the SPIR form by
the manufacturer or supplier.
Column 10A - MANUFACTURER'S PART NUMBER
Enter the manufacturer's unique reference number or other information which
specifically identifies each part in the manufacturer's organisation.
Column 10B - SUPPLIER'S PART NUMBER
Enter the supplier's unique identification number of all items from third party
manufacturers (“bought-out” items) such as ball bearings, oil seals, mechanical
seals, gaskets, couplings, instruments, electrical parts, fuses, relays etc.
NOTES FOR 10A, 10B:
In view of the wide variety of systems in use for identification of parts, it is not
possible to lay down firm rules for completion of these columns.

Page 34 of 47
ES/079
Rev 0 1988

Manufacturers/suppliers should give whatever identification system they use to


positively identify parts and to show interchangeability with other existing
equipment.
Manufacturer's/supplier's final cross-sectional drawings, Worksop drawings and
real part numbers may not always be available in the early stage of manufacture.
This should not delay the completion of the SPIR form and subsequent ordering.
(See column 13 and 15 below). In such cases it is recommended that reference is
made to manufacturer's documentation which is readily available, such as
pamphlets, brochures, exploded views, typical drawings of similar equipment, in
which the parts can be identified. As soon as final drawings etc. become available
the SPIR form should be revised immediately.
Column 11 - MATERIAL SPECIFICATION
Enter material specification in terms of full international standards and accepted
conventions, not manufacturer's or sub-manufacturer's reference.
Column 12 - REMARKS
Note supplier's name for items shown in column 10B
Column 13 - INITIAL SPARE PARTS RECOMMENDED BY MANUFACTURER
Enter Manufacturer's/supplier's recommended quantities of initial spare parts.
Initial spare parts are to safeguard the operation of equipment during the running-
in, starting-up period and the first year of operation.
Column 15 - SPARE PARTS FOR NORMAL OPERATING RECOMMENDED BY
MANUFACTURER
Enter Manufacturer's/supplier's recommended quantities of normal spare parts.
Spare parts for normal operation should adequately cover the requirements of day
to day maintenance for a period of two year operation following the initial
operation (running-in, starting-up, period and the first year of operation).
Column 19 - APPROXIMATE. UNIT PRICE
State the ex-works price per piece of each part in the currency shown at the top of
the column.

SPARE PARTS LIST AND INTERCHANGEABILITY RECORD:


The SIPM SPIR sheets listed below occupy the pages following:
Main Sheet : No. 86.84
Cont. Sheet : No. 86.92

Page 35 of 47
SPIR NUMBER : 30
SPARE PARTS LIST AND INTERCHANGEABILITY RECORD MESC GROUP : 31
1
AUTHORISED FOR PURCHASE BY
: 32

OR TAG No.
For explanation of columns MANUFACTURER'S/SUPPLIER'S SPARE PARTS DATA
REQUIRED ON SITE DATE : 33

EQUIPMENT REG.
see sheet 3
DESCRIPTION OF PARTS MATERIAL DRAWING No. SUPPLIER OR PART NUMBER MESC NUMBER Spare Parts Spare Parts
Recommended Recommended
SPECIFICATION INCL. POS. No. REMARKS by Manufacturer by:
MANUFACTURER SUPPLIER

MODEL OR TYPE
ITEM NUMBER
:
3

SERIAL No.
CURRENCY:
COMMISSIONING
CRITICAL
COMMISSIONING
CRITICAL
QUANTITY TO BE ORDERED

UNIT OF MEASURE
UNIT PRICE:
DATE
DELIVERY TIME IN WEEKS
INITIAL
NORMAL OPERATION
INITIAL
NORMAL
PHYSICAL STOCK

TOTAL No OF IDENTICAL PARTS INSTALLED


4 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

UNITS
No OF MANUFACTURER'S MANUFACTURER'S
1
2
3
4
5
6
7
8
9
ES/079

10
Rev 0 1988

Page 36 of 47
11
12
5 13
14
15
16

NUMBER OF PARTS PER UNIT


17
18
19
20
21
22
23
24
25
NOTES: 36 REMINDER: EQUIPMENT STATUS OF SPIR 34
MANUFACTURERS TO ATTACH TO THIS FORM MANUFACTURER REVISION
ALL DRAWINGS AND PARTS LISTS
SUPPLIER DATE
6
FOCAL POINT MANUFACTURER/SUPPLIER 35 PROJECT SIGNATURE

ORDER REF. No.


INCLUDING PHONE NUMBER
PLANT SHEET No. OF

MESC No EQUIPMENT
7 CLASSIFICATION OF EQUIPMENT COMPANY REQUISITION No.
DEP 70.10.90.81-Gen., Sheet 1, 11/90 (illu5580622)
SPIR NUMBER :

MESC GROUP :

EQUIPMENT :

OR TAG No.
MANUFACTURER:

SUPPLIER :

PROJECT :

PLANT :

MODEL OR TYPE
COMPANY :

NOTES

SERIAL No.
REMARKS

UNITS
No OF MANUFACTURER'S MANUFACTURER'S EQUIPMENT REG.
1 1
2 2
3 3
4 4
5 5
6 6
7 7
8 8
9 9
10 10
11 11

Page 37 of 47
12 12
ES/079

CONTINUATION SHEET
13 13
Rev 0 1988

14 14
15 15
16 16
17 17

NUMBER OF PARTS PER UNIT


18 18

SPARE PARTS LIST AND INTERCHANGEABILITY RECORD


19 19
20 20
21 21
22 22
23 23
24 24
25 25
STATUS OF SPIR

REVISION

DATE

SIGNATURE

ORDER REF. No.


SHEET No. OF

MESC No EQUIPMENT
REQUISITION No.
DEP 70.10.90.81-Gen., Sheet 2, 11/90 (illu5580624)
SPARE PARTS LIST AND INTERCHANGEABILITY RECORD
THE COMPLETION OF THE SPIR FORM(S) BY MANUFACTURER(S) / SUPP LIER(S)

The SPIR form consists of a main sheet and continuation shee ts, format A3. The completed forms shall be distributed Manufacturer's supplier's final cross-sectional drawings, wo rkshop drawings and real part numbers
on A3 formats as specified in the Purchase Order. The manufa cturer / supplier is requested to complete all the may not always be available in the early stage of manufactur e.
columns, except the bold faced columns of the form, as descr ibed below. This should not delay the completion of the SPIR form and su bsequent ordering.
All information shall be clearly stated in English language.
Column 16 MESC NUMBER OF SPARE PARTS
Explanation of Column No. If known to be filled in by manufacturer.

Column 1 EQUIPMENT REG. or TAG No. Column 17 UNIT OF MEASURE


Enter the equipment registration - or tag number for each pi ece of equipment as stated in the For example: pc = piece, st = set. The build-up of a set sha ll be explained in column 10.
requisition - or the purchase order.
Column 18 APPROXIMATE UNIT PRICE
Column 2 MANUFACTURER'S MODEL or TYPE State the ex-works price per piece of each part in the curre ncy shown at the top of the column.
State model, type or other positive identification reference of the equipment / instrument ordered.
Column 19 DELIVERY TIME IN WEEKS
Column 3 MANUFACTURER'S SERIAL No.
State serial number or other unique identification reference of the equipment / instrument ordered. Column 20 COMMISSIONING SPARE PARTS RECOMMENDED BY MANUFACTURER
Commissioning Spare Parts are required to prepare the equipm ent ready for start up.
Column 4 No. OF UNITS
Enter the total number of pieces of identical equipment / in struments as quoted in columns 1, 2 and 3. Column 21 INITIAL SPARE PARTS RECOMMENDED BY MANUFACTURER
Initial spare parts are to safeguard the operation of equipm ent during the running-in and starting-up
Column 5 NUMBER OF PARTS PER UNIT periods and the first year of operation.
For each unit or group of identical units, enter in the appr opriate space the number of parts fitted in
each unit of equipment / instrument. Column 22 SPARE PARTS FOR NORMAL OPERATION RECOMMENDED BY MANUFACTURER
Spare parts for normal operation should adequately cover the requirements of the day-to-day
Column 6 MESC NUMBER EQUIPMENT / ORDER REFERENCE No. maintenance for a period of two years following the initial operation.
If known, filled in by manufacturer.
Column 23 CRITICAL SPARE PARTS
Column 7 CLASSIFICATION OF EQUIPMENT Based on manufacturers experience.
v = vital, e = essential, a = auxiliary.
Column 24 COMMISSIONING SPARE PARTS RECOMMENDED BY SPARE PARTS ADVISOR OF OPCO.
Column 8 TOTAL NUMBER OF IDENTICAL PARTS INSTALLED
Enter the total number of identical parts covered by the equ ipment specified. In the case of identical Column 25 INITIAL SPARE PARTS RECOMMENDED BY SPARE PARTS ADVISOR OF OP CO.
units multiply the quantity of column 5 by the number of uni ts given in column 4.
Column 26 SPARE PARTS FOR NORMAL OPERATION RECOMMENDED BY SPARE PARTS ADVISOR OF OPCO.
ES/079

Column 9 ITEM NUMBER OF PARTS


Column 27 CRITICAL SPARE PARTS
Rev 0 1988

Column 10 DESCRIPTION OF PARTS Based on OpCo's experience.

Page 38 of 47
List all parts which should be carried in stock for initial and normal operation, including slow-wearing
parts. Column 28 PHYSICAL STOCK TO BE FILLED IN BY MATERIALS DEPARTMENT OF OP CO
If an item is interchangeable between two or more units it s hould be listed only once (refer to If a part is an existing stock item, the actual stock quanti ty shall be mentioned.
columns 14, 15).
Column 29 QUANTITY TO BE ORDERED TO BE FILLED IN BY MATERIALS DEPARTME NT OF OPCO
Column 11 MATERIAL SPECIFICATION Taking into account the new established min / max stock leve ls.
Enter material specification in terms of full International Standards and accepted conventions, not
manufacturer's or sub-manufacturer's reference, including ma terial certificates if required. Column 30 SPIR NUMBER
Enter the SPIR registration / filing number.
Column 12 DRAWING NUMBER (including POS No.)
For each part in column 10, enter the manufacturer's parts l ist and / or drawing number. Column 31 MESC GROUP
Documents referred to must always be attached to the SPIR fo rm by the manufacturer or supplier. Refer coding schedule of the GENERAL INDEX TO MESC.

Column 13 NAME SUPPLIERS AND / OR REMARKS Column 32 AUTHORISED FOR PURCHASE


Note supplier's name for items shown in column 15. Enter name of responsible person.

Column 14 MANUFACTURER'S PART NUMBER Column 33 REQUIRED ON SITE DATE


Enter the manufacturer's unique reference number or other in formation which specifically identifies In case the SPIR form is used for purchase enter the require d on-site date.
each part in the manufacturer's organisation.
Column 34 STATUS / REVISION OF SPIR LIST
Column 15 SUPPLIER'S PART NUMBER f = final, p = preliminary. Revisions to be marked as o = or iginal a, b, c etc.
Enter the supplier's unique identification number of items f rom third party manufacturers ('bought-
out items) such as ball bearings, oil seals, mechanical seal s, gaskets, couplings, instruments, Column 35 MANUFACTURER'S FOCAL POINT
electrical parts, fuses, relays etc. Including tel. no. to be filled in.

NOTES FOR 14, 15: Column 36 NOTES


In view of the wide variety of systems in use for identifica tion of parts, it is not possible to lay down Information not covered in previous columns to be filled in here.
firm rules for completion of these columns.
Manufacturers / suppliers should give whatever identificatio n system they use to positively identify NOTE: FOR DEFINITIONS E.T.C. REFER DEP 70.10.90.11-GEN.
parts and to show interchangeability with other existing equ ipment. 'SPARE PARTS FOR INITIAL AND NORMAL OPERATION'.

DEP 70.10.90.81-Gen., Sheet 3, 11/90 (illu5580625)


ES/079
Rev 0 1988

7.3 DOCUMENTATION REQUIREMENTS SCHEDULE – UTILITY COMPRESSED AIR PACKAGES


See sub-sections 5.3 of this Standard

DOCUMENTATION REQUIREMENTS SCHEDULE - UTILITY COMPRESSED AIR PACKAG


DOCUMENT APPROVED BY APPROVAL OR INCLUDE IN
CODE DOCUMENT TITLE PURCHASER'S REVIEW BY TECHNICAL
INSPECTOR PURCHASER MANUAL
(NOTE 1) (NOTE 2) (NOTE 3)

D01 CERTIFIED AS-BUILT DRAWINGS X (X) YES


D03 ARRANGEMENT DRAWINGS showing: X YES
- all customer connections
- foundation support loads
- allowable nozzle loads
D04 ASSEMBLY DRAWINGS identifying: (X) YES
- all replaceable parts
D11 PIPING AND INSTRUMENT DRAWINGS (NOTE 4) (X) YES
D14 ELECTRICAL INTERCONNECTION DIAGRAMS (X) YES
D22 PANEL DRAWINGS (NOTE 5) (X) YES
E03 DRIVER PERFORMANCE CURVE (NOTE 6) (X) YES
G05 WEIGHT/CENTRE OF MASS DATA SHEET (X) -
WEIGHT/CENTRE OF MASS DATA SHEET FINAL ISSUE (X) -
G06 EQUIPMENT DATA SHEETS (X) -
EQUIPMENT DATA SHEETS FINAL ISSUE X (X) YES
M03 S.P.I.R. (X) YES
M09 TECHNICAL MANUAL INITIAL DRAFT X
TECHNICAL MANUAL FINAL ISSUE (X)
P06 PRESERVATION AND PROTECTION PROCEDURE (X) X YES
MANUFACTURER'S CERTIFICATES X
INSPECTOR'S RELEASE NOTES X (X)
DETAILS OF SUB-SUPPLIERS (X)

X = COMPLETE VERIFICATION/CHECK
NOTES: (X) = REVIEW ONLY

1. DOCUMENT CODE TO APPEAR ON EACH DOCUMENT


2. DOCUMENT REQUIRING APPROVAL OR REVIEW SHALL BE FORWARDED TO THE PURCHASER AT THE ADRESS SHOWN ON
DOCUMENT TRANSMITTAL SHEET.
3. TECHNICAL MANUALS SHALL BE SUBMITTED TO THE PURCHASER
4. FOR AIR, OIL AND COOLING SYSTEMS, AS APPROPRIATE
5. FOR SEPARATE CONTROL PANEL AND/OR PANELS HOUSED WITHIN ACOUSTIC ENCLOSURES
6. EFFICIENCY AND POWER FACTOR vs LOAD AND SPEED/TORQUE AND CURRENT vs SPEED/SAFE LOCKED ROTOR TIME CUR
ALL AT 100% AND 80% VOLTAGE, AND 100% AND 80% FREQUENCY.
7. THE VENDOR SHALL ALSO SUPPLY DOCUMENTATION SPECIFIED IN OTHER APPLICABLE STANDARDS (EG. ES/205)

(illu5580254)

Page 39 of 47
ES/079
Rev 0 1988

7.4 EQUIPMENT NOISE LEVEL DATA SHEET

Design book No. : page


EQUIPMENT NOISE LEVEL DATA SHEET Contr. Job No. :
Order No. :

NOISE LIMITS NOT TO BE EXCEEDED:


The noise generated by the equipment shall not exceed the more stringent of the noise limits given in the table below,
for any of the conditions of operation, for which the equipment may normally be expected to be used.

Octave band centre frequencies Hz REMARKS:


TABLE 1 dB(A)
63 125 250 500 1k 2k 4k 8k
Maximum sound pressure level, dB re 20 Pa at any OR
location 1m from equipment surface
Maximum sound power level, dB re 1pW (total
noise emitted by equipment)

If the equipment emits impulsive or narrow band noise reduce above limits by 5dB.
INFORMATION TO BE SUBMITTED WITH THE TENDER.
a. Expected sound pressure and sound power levels of the equipment with no special silencing or sound attenuation
measures applied. The position of the maximum shall be defined. See Table 2.
b. Expected sound pressure and sound power levels after the application of silencing and/or sound attenuation
measures. These levels shall not be greater than those specified above. See Table 2.
c. Details of all silencing/sound attenuation measures required to achieve the expected levels in 'b', including the
effect on cost, performance and programme, if any.
d. Sound pressure and sound power levels which the Vendor is prepared to guarantee after the application of
silencing/sound attenuation measures as described in 'c'. See Table 2.
e. Details of the basis for noise data, eg. measurement on actual/similar equipment, calculation, extrapolation, etc.
f. Details of any characteristic noise components such as narrow band or impulsive noise.
g. Completed data/requisition sheets of any silencers and/or acoustic enclosures.
Narrow Impulsive
Octave band centre frequencies Hz band band Silencing
TABLE 2 Condition noise noise measures
state state taken
63 125 250 500 1k 2k 4k 8k dB(A) yes or no yes or no
Maximum sound Unsilenced
pressure level dB re
20 Pa at 1m distance Silenced
from equipment
surface Guarantee
Unsilenced
Sound power level
dB re 1pW Silenced

Guarantee

REMARKS:

Made by Date Equipment : Rev


letter
Checked by Date Plant : Date
Sign.
Appr. by Date Consignee :
Sheet No. of
Eng. by: Equip. No.
Principal: Req. No.
Drawing No. 45959 EM/012-06-001 Rev. 0 06/87 (illu5580146)

Page 40 of 47
7.5
SCHEDULE OF ESSENTIAL Project: Item: Item/Tag No:
TESTS AND INSPECTIONS Manufacturer: Manufacturer's Ref. No:
UTILITY COMPRESSED AIR PACKAGE: SHELL EXPRO STANDARD ES/079
Description Execution of Test/Inspection Certificate/Test Curve/Report Comments
By Witnessed By By Reviewed By In Manual
Hydrostatic Pressure Test Vendor Inspector Vendor - Yes
Motor Tests Vendor Inspector Vendor - Yes
Control Panel Test Vendor Inspector Vendor - Yes
Compressor Performance Test Vendor Inspector Vendor - Yes
Package Performance Test Vendor Inspector & Purchaser Vendor - Yes

Material Test for Casing Vendor - Vendor Inspector No


Shaft or Sub- or Sub-
Rotors Vendor Vendor
Certificate of
Compliance for Casing Vendor/ Purchaser No
Final issue of Data
Shaft - - Inspector Sheets will signify
Rotors compliance

Dynamic balancing of Rotors Vendor Inspector Vendor Purchaser Yes


Inspection Release
- No Note will signify

Page 41 of 47
Dimensional Check of Inspector Inspector Purchaser
ES/079

Purchaser Interfaces compliance


Rev 0 1988

Final Weight Check Vendor Inspector Vendor Purchaser Yes


Inspection Release
Check of Preservation Inspector - - - No Note will signify
compliance

Note: Revision 0 1 2 3 4
By
Date
(illu5580256)
SCHEDULE OF ESSENTIAL TESTS AND INSPECTIONS: UTILITY COMPRESSED AIR PACKAGE
50mm
7.6
FABRICATION
1. Protection plate shall be the same material type
CORROSION as the vessel and of the following thickness:
RESISTANT TAG
OPENING THICKNESS

20" NB 6.0mm
20" NB 10.0mm
2. Thickness of full face rubber gasket
RUBBER GASKET shall be 3.0mm.
(SEE NOTE 2) 3. Straight distance between studs shall not
5-10mm exceed 380mm.

100mm
PIPING SPOOL 4. Holes for alignment of piping spool flange
HOLD-DOWN STUD shall be 4.0mm larger than the standard
(SEE NOTE 5) bolt diameter.
5. Diameter of hold-down studs shall be 6.0mm
less than the equipment nozzle standard bolt
diameter. The minimum number of studs shall
be 4.
FLANGE PCD EQUIPMENT NOZZLE
ASSEMBLY
a. Closure to be water and airtight.
Ensure that plate is not bent or
GE distorted during tightening.
F L AN
OF b. Spot weld after assembly.
O/D
c. Stud shall be welded to plate (bolts shall not
be used).
ES/079

d. Outer face of plate shall be flat.


Rev 0 1988

Page 42 of 47
e. Protection plates for nozzles on vessels or
casings pressurised with nitrogen shall
additionally be bolted through the alignment
holes. The through bolts shall be removed
immediately prior to installation.

INSTALLATION
SEE NOTE a - If possible, piping shall be fitted with
DISTANCE BETWEEN ADJACENT the protection plate in position.
HOLES FOR ALIGNMENT SEE NOTE b
HOLD-DOWN STUDS
OF PIPING SPOOL - Protection plates shall preferably be
(SEE NOTE 3 AND e) TAB WASHER
FLANGE (SEE NOTE 4) removed immediately prior to final
HOLES SHOWN OUT OF SEE NOTE c piping assembly. Removal of plates on
POSITION vessels and casings pressurised with
nitrogen shall be witnessed by
vendor's representative.

Drawing No. U-25438 AI


(illu5580320)
FIGURE 1: EQUIPMENT NOZZLE PROTECTION PLATE FOR FF, RF AND RTJ FLANGES
ES/079
Rev 0 1988

7.7 UTILITY COMPRESSED AIR SYSTEM OPERATION


(1) General
This section describes the expected system operation for utility compressed air packages.
Where 3 x 50% capacity packages are specified the status of each package will nominally be
selected as duty mode standby mode and emergency standby mode. Where 2 x 100% capacity
packages are specified the status will be duty mode and standby mode.
The system operation will be based on either fully modulated compressor intake throttling
automatic loading and unloading or a combination of both.
The operating pressures for the utility air system will be given in the order/enquiry and will
depend on the selected compressor's rated discharge pressure and the control system
characteristics. Typical system set pressures are given at the end of this Appendix as a guide to
interpreting the following descriptions.
(2) Fully Modulated Compressors
Refer to Figure 2.
When the utility air consumption is within the capacity of the selected duty compressor the
compressor regulator will control the volume of air delivered to maintain a stable delivery
pressure in response to the output signal from the pressure controller in the logic system. The
system pressure will vary between P1 and P2.
When the utility air consumption rises above the capacity of the duty compressor or on failure of
the duty compressor the system pressure will fall below P2. The selected standby machine will
start-up automatically when the system pressure falls to P3. Line E-F represents the
proportional band setting for the standby compressor. the system will operate along line C-D for
an air consumption ranging from Q3 to Q4 and along line D-F for an air consumption ranging
from Q4 to Q2. On failure of the duty compressor the system pressure will be between P5 and
P4. If the utility air consumption then falls so that the pressure in the instrument air header rises
to P6 and provided that the standby compressor has been off load for approximately 10 minutes
the standby compressor should shutdown automatically. The 10 minute delay is to avoid the
machine tripping in and out during fluctuating load operation.
If the system pressure falls below P7 the low pressure alarm will be activated and a priority
control valve (by others) in the plant air supply line will start to restrict the flow of plant air to
maintain instrument air supply pressure. If the system pressure falls further to P8 the low low
pressure alarm will be activated and the emergency standby compressor will start and the plant
air supply will by completely shut off. Surface Process Shutdown shall be initiated when the
system pressure falls to P9.
(3) Loading/Unloading Compressors
The above scheme also applies for on/off loading compressors the only difference being that
the system pressure will oscillate around the set-pressure for the duty compressor if Q is less
than Q1 and around the set-pressure for the standby compressor if Q is less than Q2 but
greater than Q1.
(4) Combined System
A combined modulating and on/off loading system is also acceptable whereby the standby
compressor always goes on full load and the duty compressor takes the extra load for utility air
consumptions above the capacity of one compressor.
Refer to Figure 2.
When the utility air consumption is within the capacity of the selected duty compressor the
system will approximately operated along line A-B with the pressure ranging from P1 to P2.
When the utility air consumption rises above the capacity of the duty compressor or on failure of
the duty compressor the system pressure will fall below P2. The selected standby machine will
start-up when the pressure fall to P3.

Page 43 of 47
ES/079
Rev 0 1988

The standby compressor will discharge its full capacity because it is set to operate on full load
and rotary compressors can be regarded as constant flow machines for compressed air
applications in a 5-10 bar output range. set pressure of the standby compressor will be P4
above P2 ( being the lowest system pressure when only the duty compressors is on line). The
compressor regulator/logic system fed from the instrument air header will then modulate the
duty compressor until and equilibrium pressure is reached along line AB eg PX for consumption
QX.
Should the utility air consumption then fall so that the pressure in the instrument air header
reaches P4 the standby machine will run unloaded. If it has operated on zero load for
approximately 10 minutes the standby compressor will shutdown automatically.
(5) Typical Operating Pressure Levels

Combine Modulating and On/off


Modulating Control
Pressure Level Control
NCNS SNS NCNS SNS
P1 9.0 8.0 9.0 8.0
P2 8.6 7.6 8.4 7.4
P3 8.55 7.55 8.1 7.1
P4 8.7 7.8 8.7 7.7
P5 8.3 7.4 7.7 6.8
P6 8.75 7.85 6.9 6.3
P7 8.7 6.8 4.0 4.0
P8 6.9 6.3 - -
P9 4.0 4.0 - -

Notes: 1. Pressures are in bar g.


2. NCNS is Northern and Central North Sea.
SNS is Southern North Sea.
3. Above figures are based on normal operating pressure in the distribution system of 8.3
bar g for NCNS and 7.3 bar g for SNS a receiver operating pressure of 9 bar g for
NCNS and 8 bar g for SNS (allowing 0.7 bar pressure drop between the receiver and
distribution system at design quantity of continuous air and clean conditions).

Page 44 of 47
ES/079
Rev 0 1988

LEGEND
P1 A Q 1 = Consumption equivalent to capacity of one
compressor.
P6 E Q 2 = Consumption equivalent to capacity of two
SYSTEM PRESSURE

P4 C compressors.
D P 1 = Upper limit of duty compressors proportional
P2 B control band.
P3 P 2 = Lower limit of duty compressors proportional
control band.
P5 F P 3 = Start standby compressor.
P7 P 4 = Upper limit of standby compressors proportional
control band.
P 5 = Lower limit of standby compressors proportional
G control band.
P8 H P 6 = Shut down standby compressor.
P9 P 7 = Initiate plant air supply shutoff and low pressure
alarm.
P 8 = Shut off plant air supply, start emergency standby
compressor and initiate low low pressure alarm.
P 9 = Minimum air pressure for operation of instruments
Initiate surface process shutdown.
Q3 Q1 Q4 Q2 GH = Emergency standby compressor characteristic.
CONSUMPTION

MODULATING CONTROL

P1 A

LEGEND
P4
PX Q 1 = Consumption equivalent to capacity of one
SYSTEM PRESSURE

compressor.
Q 2 = Consumption equivalent to capacity of two
compressors.
P2 P 1 = Upper limit of duty compressors proportional
B control band.
P3 P 2 = Lower limit of duty compressors proportional
control band.
P 3 = Start standby compressor.
P 4 = Set pressure for standby compressor
P5
P 5 = Initiate plant air supply shutoff and low pressure
alarm.
P 6 = Shut off plant air supply, start emergency standby
G compressor and initiate low pressure alarm.
P6 H P 7 = Minimum air pressure for operation of instruments
Initiate surface process shutdown.
P7 GH = Emergency standby compressor characteristic.

Q1 QX Q2
CONSUMPTION

COMBINED MODULATING-ON/OFF CONTROL (illu5580258)

Figure 2 System Operation for Utility Air Systems

Page 45 of 47
ES/079
Rev 0 1988

7.8 UTILITY COMPRESSED AIR PACKAGE – DATA SHEETS

Data/requisition sheet for Document No :


Requisition No :
UTILITY COMPRESSED AIR PACKAGES Order No :
Package equipment No Number required:
OPERATING DATA
Operation : continuous/intermittent/parallel Package outlet pressure : bar abs.
Entrainment : solids/liquids/no Aftercooler outlet temperature : o
C
Corrosive : o
: yes/no/due to Maximum allowable temperature of compression C
Hazardous duty : yes/no Estimated isentropic power : kW
Operating modes : duty/standby/emergency standby

COMPRESSOR OPERATING CONDITIONS COMPRESSOR DRIVE


Condition Normal Rated Type : Electric motor Enclosure :
Flow rate (wet) : kg/s Estimated absorbed power/installed power : / kW
o
Capacity (at 1 bar abs. 15 C, dry) : Nm 3/h Electrical supply : V/50/60Hz/3 Phase
Motor speed/number of poles : rpm
Inlet pressure : bar abs. Refer to data sheet number : (UMA 175/175A)
o
Inlet temperature : C INSPECTIONS/TESTS
Relative humidity : % Required Witnessed
Mol. weight at inlet : Shop inspection yes yes/no
Cp/Cv at inlet : Hydrostatic test yes yes/no
Cp at inlet : kJ/kg.K Compression performance yes yes/no
Z (compressibility factor) at inlet : Control panel yes yes/no
Discharge pressure : bar abs. Package performance test yes yes/no
First stage discharge pressure : bar abs.
Discharge temperature : o yes/no
C yes/no
o
First stage discharge temperature : C LOCATION
General : indoor/outdoor/under roof/partial sides
Offshore/subsea : Saline atmosphere
SCOPE OF SUPPLY AND CONFIGURATION o
Ambient temperature : maximum/minimum / C
Baseplate : combined with filter coalescer/drier/after filter
Acoustic enclosure : housing coalescer/drier/filter
Coupling make/type : IP area classification : safe/division
Inlet filter/silencer : yes -temperature class : gas group :
Intercooler : yes/no COOLING
Aftercooler : yes Type : Air/cooling medium/seawater
Condensate separator : yes Air cooling : Refer to Data Sheet No. (EM/012-06-014)
Filter coalescer/mounting : Yes. Combined/separate baseplate Water cooling : Refer to Data Sheet No.
Air drier/mounting : Yes. Combined/separate baseplate (EM/012.06.007 for Plate Exch'rs; DEP 31.21.00.93-Gen for Shell/Tube Exch'
After filter/mounting : Yes. Combined/separate baseplate
Control panel : Separate/integral with enclosure

Air receiver : yes/no


Compressor control panel type :
- capacity modulation (suction throttling) ADDITIONAL REQUIREMENTS
- two step (load/unload)
- combination system
EQUIPMENT NUMBERS
Compressor
Motor
Drier
Filters
Packages shall be in accordance with Shell Expro Standard ES/079
REMARKS ON REVISIONS

Made by Date EQUIPMENT : Rev.


letter

Checked by Date PLANT : Date

Sign.
Appr. by Date CONSIGNEE:
Sheet No. 1 of 2
Eng. by : Equipm. No.

Principal : Req. No.

(illu5580259) EM/012-06-015 REV.0 02/88

Page 46 of 47
ES/079
Rev 0 1988

Data/requisition sheet for Document No :


Requisition No :
UTILITY COMPRESSED AIR PACKAGES Order No :
Package equipment No Number required:
INSTRUMENTATION MATERIAL SPECIFICATIONS
FUNCTION INDICATION ALARM TRIP PART
Air intake filter differential pressure I H Compressor - casing
Lub oil filter differential pressure I H - lining
Oil reclaimer oil level (1) I L LL - rotors
Oil reclaimer differential pressure (1) I H - seals
Oil reclaimer pressure (1) I H HH Piping/tubing
Compressor discharge temperature (2) I H HH
Filter coalescer differential pressure I H Oil separator vessel
Drier inlet pressure I Cond. separator vessel
After filter differential pressure I H Drier vessel(s)
Package outlet pressure I HH Filter coalescer vessel
Running status (each compressor) I After filter vessel
Mode status (3) I Acoustic enclosure
Drier discharge moisture content I H AIR DRIER
Running hours indicator I Make/model :
Lub oil temperature I H Design code :
o
Lub oil pump discharge pressure I LL LL Design pressure : bar(g) at temperature C
Hydrostatic test pressure : bar(g)
Corrosion allowance : mm
NOTES: (1) Oil injected compressors only Design capacity : Nm3/h
o
(2) Each stage Pressure dew point : C
(3) Duty, standby, emergency standby as appropriate Desiccant :
Quantity per vessel/section : kg
Operating pressure : bar(g)
: o
Inlet temperature C
Cycle time : min
Noise level 1m from vent : dB(A)

FILTER COALESCER AFTER FILTER


Make/model Make/model :
Capability - particle size at 100% efficiency : micron Capability - particle size at 100% efficiency : micron
- particle size at % efficiency : micron - particle size at % efficiency : micron
- oil/moisture removal : w/w ppm Design code :
o
Design code : Design pressure : bar(g) at temperature C
o
Design pressure : bar(g) at temperature C Hydrostatic test pressure : bar(g)
Hydrostatic test pressure : bar(g) Corrosion allowance : mm
Corrosion allowance : mm Design capacity : Nm3/h
Design capacity : Nm3/h Maximum differential pressure: bar
Maximum differential pressure: bar Element material/construction
Element material/construction:

CONDENSATE SEPARATOR OIL SEPARATOR


Manufacturer : Manufacturer :
Design code : Design code :
o o
Design pressure : bar(g) at temperature C Design pressure : bar(g) at temperature C
Corrosion allowance : mm Corrosion allowance : mm
Separation capability : Separation capability :

Made by Date EQUIPMENT : Rev.


letter

Checked by Date PLANT : Date

Sign.
Appr. by Date CONSIGNEE :
Sheet No. 2 of 2
Eng. by : Equipm. No.

Principal : Req. No.

(illu5580260) EM/012-06-015 REV.0 02/88

Page 47 of 47

You might also like