Professional Documents
Culture Documents
GES K.01
INDEX
1.1 Introduction 4
1.2 Other NOC Specifications 4
1.3 Data Sheets 5
2.0 DEFINITIONS 5
2.1 Technical 5
2.2 Contractual 5
3.0 DESIGN 6
4.0 MATERIALS 16
5.0 INSPECTION 17
5.1 Procedures 17
5.2 Inspection Method/Scope 17
5.3 Nameplates 18
6.0 TESTING 18
7.0 DOCUMENTATION 20
7.1 Introduction 20
7.2 Schedules and Reports 20
7.3 Data and Calculations 21
7.4 Drawings 21
7.5 Final Records, Documents & Manuals 21
GENERAL ENGINEERING SPECIFICATION GES K.01
CENTRIFUGAL COMPRESSORS (API 617) Page 3 of 23
Rev 0 1999
DATA SHEETS
1.1 Introduction
1.1.1 This specification covers the general requirements for design, fabrication, inspection and testing for skid
mounted centrifugal compressors.
1.1.2 This specification applies to equipment for refineries, onshore oil and gas installations, and processing
facilities including items purchased either directly or as a part of a package.
1.1.3 The Vendor/Contractor shall comply fully with the provisions laid down in the specification. Any
exception must be authorised in writing by the Owner.
1.1.4 In the event of any conflict between this specification and the Data Sheets, or with any of the applicable
Codes and Standards, the Vendor/Contractor shall inform the Owner in writing and receive written
clarification before proceeding with the work.
1.1.5 This specification is based on API Standard 617. The following centrifugal compressors are excluded from
this specification:
(a) Fans or blowers which produce a pressure of less than 5 psig (34.5 kPag), these are covered by
NOC Specification GES K.02.
(b) Integrally geared centrifugal air compressors, these are covered by GES K.06.
1.1.6 This specification also includes for the related drivers, lubricating systems, controls, instrumentation,
control panels and other auxiliary equipment. The Vendor/Contractor shall resolve all engineering issues
relating to the associated equipment and shall be responsible for the complete package unit design.
1.1.7 This General Engineering Specification will form part of the Purchase Order/Contract.
1.2.1 The following NOC Specifications may form an integral part of this specification and any exceptions shall
be approved in advance by the Owner.
GES A.04 - Noise Level Criteria and Noise Control of Mechanical Equipment
GES M.05 - Lubrication, Shaft Sealing and Control Oil Systems for Rotating Equipment
(API 614)
The technical data supplied by the Owner for the equipment is provided on the API Standard 617 Data
Sheets which form part of this specification.
The Vendor/Contractor shall complete the data sheets with the remaining information and submit them with
his proposal.
Prior to shipment, the Vendor/Contractor shall submit a complete set of "As-Built" Data Sheets.
2.0 DEFINITIONS
2.1 Technical
The technical terms used in this specification additional to those defined in API 617 are as follows:-
Maximum and minimum operating pressures and temperatures are the extreme suction or discharge
pressures and temperatures which can be reached under the most adverse combinations of speed, or suction
and discharge conditions. These extreme conditions can coincide with the maximum working pressure
case.
2.2 Contractual
Owner
The oil and gas company, an associate or subsidiary, who is the end user of the equipment and facilities.
Vendor
Sub-Contractor
A company awarded a contract by a contractor to do part of the work awarded to the Contractor.
Inspection Authority
The organisation representing the Owner, or Contractor that verifies that the equipment and facilities have
been designed, constructed, inspected and tested in accordance with the requirements of this specification
and the Purchase Order/Contract.
Inspector
A qualified individual representing the Owner, Vendor/Contractor or the assigned Inspection Authority,
who verifies that the equipment and facilities have been designed, constructed, inspected and tested in
accordance with the requirements of this specification and the Purchase Order/Contract.
3.0 DESIGN
3.1.1 The design shall comply with this specification and the following Codes and Standards.
Centrifugal compressors shall conform to API 617, "Centrifugal Compressors for Petroleum, Chemical and
Gas Service Industries" 6th Edition 1995, as amended by this NOC Specification.
Additionally, centrifugal compressors in sour service shall comply with MR-01-75, "Sulphide Stress
Corrosion Resistant Metallic Materials for Oil Field Equipment".
3.1.2 The following Codes an Standards, together with the references therein shall be deemed to form part of this
specification. All recommendation shall apply unless specifically modified herein.
3.1.3 Unless specified otherwise in the Purchase Order/Contract, the current editions of the Codes and Standards
at the time of the order should be used.
3.2.1 In API 617, paragraphs are marked with a bullet (•) if the Owner has to make a decision or provide
information. Where possible, these decisions have been made, such paragraphs are marked "*" in this
specification.
3.2.2 The following paragraph numbers refer to API 617, Sixth Edition, February 1995, which is a part of this
GENERAL ENGINEERING SPECIFICATION GES K.01
CENTRIFUGAL COMPRESSORS (API 617) Page 7 of 23
Rev 0 1999
General Engineering Specification.
2.1 General
2.1.1 Add:
The compressor unit shall be designed for safe, reliable, continuous, unattended operation
at all operating conditions specified in the Data Sheets.
2.1.2 For gas turbine driven compressors, the package responsibility shall be assumed by the
gas turbine vendor.
2.1.4 Add:
In applications where compressors will operate in parallel the minimum head rise from
the rated point to the predicted surge shall be 8 percent.
2.1.5 Add:
Except that site temperatures will be modified by high ambient conditions specified.
2.1.9* The type of installation (indoors/outdoors, heated/unheated, etc) will be specified on the
Data Sheets, along with details of the site environment and ambient conditions.
2.1.10 * The sound pressure level measured at 3.3 ft (1 m) from the surface of the equipment shall not
exceed 95 dB(A).
2.1.14 * The Vendor/Contractor's representative shall (a) observe a check of the piping performed by
parting the flanges, (b) check alignment at the operating temperature, and (c) be present
during the initial alignment check.
2.1.17 * Where temperatures allow it the compressors shall be suitable for field run on air.
2.1.19 When electric induction motor drivers are furnished with direct online start facilities, the
compressor train shall be capable of withstanding momentary high torque overloads equal
to four times motor nameplate rating. The suitability of this rating shall be confirmed by
Owner after final electrical system characteristics are defined.
GENERAL ENGINEERING SPECIFICATION GES K.01
CENTRIFUGAL COMPRESSORS (API 617) Page 8 of 23
Rev 0 1999
In addition, for synchronous motor drives, the compressor train shall also be capable of
withstanding the peak oscillatory torque values predicted by the system transient torsional
analysis of the motor starting.
2.2 Casings
2.2.8 Add:
2.2.9 Add:
Casings shall be radially split for gas with molecular weight lower than 15, and when the
maximum working pressure is greater than 580 psig (4 MPag).
2.3.5 If an entering side-stream flow exceeds 15% of the total flow to the impeller, the entrance
passage shall minimise the disturbance at the impeller inlet. In this instance, entrance
through a standard spaced diaphragm section is prohibited. Providing extra space
between adjacent wheels is an acceptable method of introducing side-streams.
Connections covered by ASME B16.5 or API 605 are preferred. Other connections
require the Owner's approval and if approved, the Vendor/Contractor shall supply all
mating flanges, including studs and nuts.
2.4.3.2 * Individual stage drains if required will be detailed on the Data Sheets.
Add:
Drain connections shall be flanged. Angle valves shall not be used in drains.
2.4.3.5 Screwed connections are not acceptable; socket or butt welded flanged nipples shall be
used.
GENERAL ENGINEERING SPECIFICATION GES K.01
CENTRIFUGAL COMPRESSORS (API 617) Page 9 of 23
Rev 0 1999
2.4.3.6 Delete this paragraph and replace by:
Pipe nipples shall not be more than 6 inches (150 mm) in length. Pipe nipples shall be a
minimum of schedule 160 for 1 inch (25 mm) and smaller and a minimum of schedule 80
for 1½ inch (40 mm) and larger. Each pipe nipple shall be provided with a welding-neck,
socket-weld, or slip-on flange.
2.5.3 "The Vendor/Contractor shall review and approve the piping stress analysis"
2.7.1.2 Add:
The compressor shall be designed so that only one impeller will make contact with the
diaphragm in the event of a thrust-bearing failure.
If the process gas will cause deterioration of the lube oil qualities, bearings shall be
isolated from the shaft seal by a ventilated air space and have labyrinths or other closures
to prevent contamination, or an interchange of sealing oil or gas and lube oil.
2.8.1 Add:
"Unless otherwise specified shaft seals and seal oil systems shall be suitable for exposure
to maximum casing working pressure and temperature or settle out pressure where
specified"
2.8.2 * Shaft sleeves shall be accessible for inspection and replacement, without removing the
top half of the casing of an axially split compressor, or the heads of a radially split unit.
2.8.3 * Shaft seals shall preferably be the self-acting gas type (2.8.3.5). If the Vendor/Contractor
is unable to provide this type, he shall propose an alternative type complying with
paragraph 2.8.3, for the approval of the Owner.
2.8.3.2 * Add:
"The seals shall incorporate a lock-up feature to prevent gas leakage from the compressor
on loss of seal oil pressure, The Vendor/Contractor shall propose the seal features to
achieve this"
GENERAL ENGINEERING SPECIFICATION GES K.01
CENTRIFUGAL COMPRESSORS (API 617) Page 10 of 23
Rev 0 1999
2.8.4 Add:
For low temperature services, seals shall have provision for maintaining seal oil above its
pour point temperature at the inner seal drain.
The Data Sheets will specify whether buffer gas is required in normal operation.
"The Vendor/Contractor shall specify if buffer gas injection is essential for compressor
"run-in" on air or any other operating condition. When buffer gas injection is required
continuously the Vendor/Contractor shall supply the complete buffer gas automatic
control system including inlet strainer. If buffer gas is used for "run-in" only, a hand
control valve without pressure alarm is acceptable. Piping downstream of the strainer
shall be stainless steel. The Vendor/Contractor shall specify the buffer gas flow rate at
new, and at two times new labyrinth clearances".
"The provision of a seal buffer gas system shall be considered in the following
applications or when recommended by the Vendor/Contractor.
(a) Refrigeration service, where sub-atmospheric suction pressure might allow air
in-leakage through the contaminated seal oil drain.
(b) Sour gas service, to prevent sludge formation in the contaminated oil annulus.
(c) Low suction pressure service, to assure successful operation of automatic drain
pots and to avoid contamination of the compressed gas.
When buffer-gas injection is required, the Vendor/Contractor shall supply the complete
buffer gas control system and shall state the buffer gas requirements."
"With the exception of compressors in air service, compressor sealing design shall ensure
positive pressure at the seals, under all startup and operating conditions, including
negative suction pressure during air "run-in" operation".
2.9 Dynamics
2.9.1.8 Add:
The torsional and lateral vibration analyses shall consist of the following items as a
minimum:
(a) tabulation of all natural frequencies up to two times the maximum operating
speed of the highest speed shaft,
(b) schematic sketch showing all the inertias and spring constants used in the
calculations,
(d) tabulation of the shaft stresses including any stress concentration factors for the
shape of byways and short circuit stresses for motor driven units,
(e) shaft material yield stress and ultimate shear stress, fatigue limit in shear,
material alloy analysis and heat treatment.
GENERAL ENGINEERING SPECIFICATION GES K.01
CENTRIFUGAL COMPRESSORS (API 617) Page 11 of 23
Rev 0 1999
2.9.2.3 Add:
For compressors driven through gears, both the gear and compressor
Vendors/Contractors shall perform an independent analysis on the complete train using
basic equipment dimension and stiffness data. If the results of these independent
torsional analysis differ by more than 3 percent the compressor Vendor/Contractor shall
resolve these discrepancies. Results of these studies shall be submitted to the Owner for
approval.
2.10.3* The seal-oil and lube-oil systems shall normally be combined. Separate oil systems shall
be provided when accidental oil contamination would cause deterioration of the oil
lubricating properties. Separate oil systems shall, therefore, be provided for:
(c) heavy refrigerating gases such as propane and ethane and oil-soluble gases.
2.11.5 Impellers
2.11.5.1 Add:
The Vendor/Contractor shall qualify a welding procedure for impellers with welded
joints for each material used.
2.11.5.3 Add:
2.11.5.4 For impellers with welded joints where a maximum Rockwell C22 hardness applies, the welding
procedure shall specify any heat treatment used after completion of welding to achieve
acceptable hardness values.
GENERAL ENGINEERING SPECIFICATION GES K.01
CENTRIFUGAL COMPRESSORS (API 617) Page 12 of 23
Rev 0 1999
The manufacturer shall verify that the maximum allowable hardness has not been
exceeded. A mock-up weldment is acceptable for this purpose. This mock-up shall be
prepared using the maximum thickness of materials to be joined for impeller
construction. Joint details, welding process, filler metal and heat treatment shall be
identical to that used for the construction of the impellers. The joint shall be cross-
sectioned transversely, and a traverse made over the cross section to determine hardness
of the base metal, weld metal and heat affected zone. This traverse shall be made 1/16in.
(1.5 mm) from the top and parallel to the face of the weld. It is not necessary to repeat
this test provided that the welding and heat treatment procedures are not changed.
2.11.5.5 Maximum stress at maximum speed shall not exceed 70 percent of the impeller yield strength.
3.1 Drivers
3.1.2* Anticipated process variations which may affect drive sizing will be specified on the Data
Sheets.
The compressor package shall be capable of starting with the compressor casing
pressurised to the normal suction pressure unless otherwise stated on the Data Sheets.
The Vendor/Contractor shall state any mechanical limitations which affect the ability to
operate at high or low ambient temperatures and up to 105% of the speed. Variable
speed drivers must be suitable for all operating conditions and for driving the compressor
up to maximum continuous speed.
3.1.4 * Steam turbine drivers shall conform to GES K10 or GES K.11.
General purpose steam turbines are used for low power applications, where the steam
does not exceed 700 psig (4.8 MPag) and 750°F (400°C), and the speed is less than 6,000
RPM.
Special purpose steam turbines are used for high power applications in critical service
where there is no spare unit. The Owner shall decide whether GES K.10 or GES K.11
applies.
Electric motor drivers shall conform to GES L.11 and GES L.12 as applicable.
The motor power rating shall be at least 115 percent of the greatest power (including
gear, or other losses, as applicable) required for any of the specified operating conditions.
Compressors driven by induction motors shall be rated at the actual motor speed for the
rated load conditions.
The gas turbine rated power at maximum ambient air temperature stated on the Data
Sheets shall be at least 110 percent of the greatest power (including gear, or other losses,
as applicable) required for any of the specified operating conditions.
GENERAL ENGINEERING SPECIFICATION GES K.01
CENTRIFUGAL COMPRESSORS (API 617) Page 13 of 23
Rev 0 1999
For gas turbines, the Vendor/Contractor shall provide a starting arrangement using gas
expansion or electric motor starter or shall propose the best alternate. The
Vendor/Contractor shall specify all the utility requirements for the proposed starting
system.
3.1.8 Add:
Speed increases and reducers shall meet the requirements of GES M.04.
The gearbox rated power shall not be less than 110% of the maximum continuous power.
3.2.1 Add:
Non sparking coupling guards shall be supplied for the complete compression train
including the auxiliary consoles.
3.2.2 Add:
"Main drive couplings which operate above 1800 RPM shall be diaphragm or flexible
disc type with a retained spacer, except for gas turbines where gear type may be used
subjected to approval by the Owner.
Coupling rating and design shall be based on the maximum axial and radial misalignment
anticipated during transient and steady state conditions. However, the rating shall not
exceed the catalogue rating. The shaft end clearances during assembly shall be specified
by the Vendor/Contractor.
Coupling spacer piece natural frequency shall be at least 10% removed from any
specified operating speed, and from any multiply of any specified operating speed.
Shafts may have integral or removal hubs. Removal hubs shall be non-keyed, tapered,
hydraulically fitted with a minimum interference fit of 0.0015 in/in (mm/mm) of bore
diameter. Taper shall be ½ in/ft (0.042 mm/mm) on the diameter, unless otherwise
approved by the Owner.
For motor or steam turbine drive, the Vendor/Contractor shall furnish all couplings and
enclosures or guards. Guards shall be fabricated from reinforced non-sparking expanded
metal (preferably of brass material). Guards shall extend to the vertical line of the shaft
protrusion from the bearing housing or cover".
"Particular attention shall be given to couplings and their shrink fits for synchronous
motor driven compressors where transient torque variations from +5% to -1% of design
torque, can be expected. Torsional analysis shall be performed by the Vendor/Contractor
in sufficient time to permit establishing coupling design criteria and shall be submitted to
the Owner for review."
GENERAL ENGINEERING SPECIFICATION GES K.01
CENTRIFUGAL COMPRESSORS (API 617) Page 14 of 23
Rev 0 1999
3.3 Mounting Plates
Compressors, gears and drivers shall be mounted on full depth skid members. Lube oil
consoles shall be mounted on a skid. Oil reservoirs shall not be directly under the
compressor or power transmissions. All auxiliary items and connections shall be
accessible for maintenance.
Non-shrink epoxy grout will be used and the Vendor/Contractor shall precoat all the
grouting surfaces on the mounting plates with a catalysed epoxy primer applied to
degreased near-white metal.
3.3.2.1 The baseplate shall be extended to support all components, provided the dimensions do
not exceed the Owner's shipping limits. These limits are defined in GES A.03.
3.4.1.1 * The Vendor/Contractor shall review the Owner's overall control system and confirm its
compatibility with the Vendor/Contractor supplied compressor control system.
3.4.2.4 * For constant speed drive units, the control signal shall actuate an Owner supplied control valve in
the compressor inlet piping.
The Vendor/Contractor shall include an annunciated alarm point for all unit shutdowns.
GENERAL ENGINEERING SPECIFICATION GES K.01
CENTRIFUGAL COMPRESSORS (API 617) Page 15 of 23
Rev 0 1999
The instrument/control panels shall be free standing, floor mounted and off skid.
3.4.4.4 Add:
3.4.4.5 * Oil filled pressure gauges shall be provided in areas subject to vibration.
3.4.6.2* The hazardous area classification will be stated on the Data Sheets.
3.4.6.6* When electrical materials require tropicalisation it will be stated on the Data Sheets.
3.4.7.2 * Vibration and axial position monitors and calibrated in accordance with GES M.06 shall be
provided.
3.4.7.4 * Bearing temperature monitors and calibrated in accordance with GES M.06, shall be provided.
"The Vendor/Contractor shall be responsible for the entire train vibration monitoring
system including probes, signal conditioners, monitors and all interconnecting wiring.
The Vendor/Contractor shall install 2 sleeve mounted radial proximity probes
approximately 90° apart inboard on each radial bearing and one sleeve mounted axial
proximity probe within 10 inches (25 mm) of the thrust collar. A key phasor shall be
provided on both motor and compressor shafts if a gearbox is used. The gearbox shall
have an accelerometer mounted on the high speed shaft. Probes shall be located so that
oil spillage is minimised on changeout.
All oscillator detectors and wiring shall be provided. Probe lead wire shall be enclosed in
a separate conduit independent of other electrical wiring."
3.5.1.4 Add:
The balance line shall be provided with orifice flanges, pitot tube connections or other
means of measuring flow. The flanges shall permit removal for inspection and cleaning.
3.5.1.6 * A buffer gas manifold shall be supplied if the compressor seal requires a supply of buffer gas (see
comments to paragraph 2.8.7).
3.5.1.10 All piping shall be designed with sufficient flexibility not to imposed undue strain on nozzles or
connections. Where disassembly is required for maintenance, forged steel unions or
flanges shall be provided in the lines.
Threaded socket welded connections shall only be used for connections NPS 1½ inch
(40mm) and less. For NPS 2 inch (50mm) and larger only welded connections are
acceptable. Threaded connections shall be welded. Relief valves shall be of flanged
construction."
4.0 MATERIALS
The Vendor/Contractor shall provide materials in accordance with paragraphs 2.11.1, 2.11.2, 2.11.3 and
Appendix 'B' of API 617, as amended below:
2.11 Materials
2.11.1.7* The Data Sheets will indicate if hydrogen sulphide is present in the process gas.
2.11.1.8* The Data Sheets will indicate if corrosive agents are present in the process gas, the
process stream and the environment,
"Nodular iron casings are not acceptable for flammable or toxic service.
2.11.2.10 * Proposed connection designs shall be submitted to the Owner for agreement before
fabrication.
"Materials and thicknesses not covered by the code shall not be used."
4.2.1 Materials shall be identified by references to ASTM, AISI type numbers etc., and not by reference to the
manufacturer's code number.
4.2.2 Pressure retaining steel castings shall be in accordance with ASTM A-216 WCB. Pressure containing steel
forgings shall be in accordance with ASTM A-395.
GENERAL ENGINEERING SPECIFICATION GES K.01
CENTRIFUGAL COMPRESSORS (API 617) Page 17 of 23
Rev 0 1999
5.0 INSPECTION
5.1 Procedures
5.1.1 The inspection requirements are covered by the document "General Conditions of Purchase" which forms
part of the Purchase Order/Contract. Additional requirements are given below.
5.1.2 The Vendor/Contractor shall allow the Inspector free access to all areas of manufacture, fabrication,
assembly and testing.
The Vendor/Contractor shall furnish the Inspector with all reasonable functions, to satisfy himself that the
equipment, including Sub-Contactors materials, is fabricated and tested in accordance with the relevant
code and this specification.
5.1.3 The Vendor/Contractor always has the responsibility to provide adequate quality control and inspection of
equipment and materials. Any inspection by Owner or his Inspector shall not relieve the
Vendor/Contractor of these responsibilities or those under his guarantees.
5.1.4 Inspection shall be in accordance with API 617, Sixth Edition and this specification. All inspection
activities to be performed, including any special requirements, shall be agreed with the Owner and shall be
incorporated within the agreed Quality Control Plan provided by the Vendor/Contractor. The Quality
Control Plan shall be co-ordinated with and shall include the quality plans of major Sub-Contractors. The
Vendor/Contractor shall submit procedures for all applicable NDT techniques for approval by the Owner
before production commences.
5.1.5 All operators of NDT equipment shall have thorough knowledge of the operation of the equipment to be
used and shall hold an appropriate certificate of competence, which is to be agreed by the Owner.
5.2.1 All items of plant and equipment referenced within this specification shall be subject to inspection by the
Owner or its nominated agency. The Vendor/Contractor shall furnish the Owner's Inspector with all
reasonable facilities, to satisfy themselves that the equipment is fabricated and tested in accordance with the
relevant code and this specification. All inspection activities to be performed including any special
requirements, shall be agreed with the Owner and shall be incorporated within the agreed Quality Control
Plan provided by the Vendor/Contractor.
5.2.2 The Owner's inspection will include, but not be limited to, the following:
(e) inspection of equipment supplied by Sub-Contractors e.g. driver, gear units, lube oil pumps,
coolers, filters, control panels and other equipment;
(g) witness the shop test of control panels and control systems;
(h) witness the mechanical run test and examination of compressor bearings and seals after the test;
(a) The Vendor's/Contractor's Quality Control Plan shall propose the parts to be
examined and the type of examination usually performed, for the approval of the
Owner.
(b) The radiographic and other inspection of materials shall be carried out as
specified below:
Support leg attachment welds and the welds in the end covers of vertically split casings
shall be examined by the magnetic particle method; or if made of non-magnetic materials
then examination shall be by the dye penetrent method.
4.2.1.5 * Spot checks on cleanliness will be made during the course of manufacture.
4.2.1.6* Hardness testing of ferrous materials will be required when NACE MR 01-75 conditions apply.
5.3 Nameplates
6.0 TESTING
Required tests are listed in comments to API para 4.1 and additionally will be listed in the Data Sheets and
agreed in the Quality Control Plan.
Testing shall be carried out in accordance with paragraph 4.3 of API 617, as amended below:
4.3.6.1 * A performance test according to ASME PTC 10, Class III is required. Performance curves for
capacity, discharge pressure and brake horsepower shall be developed from
surge to 115% of normal capacity at 100% speed. Curves shall be based on the test
results. There shall be a minimum of 6 points taken. Reynolds No. correction shall not
be applied to test results.
4.3.6.2 * A complete unit test, including all components such as gears, drivers where possible and
auxiliaries, is preferred.
4.3.6.5 * A helium test shall be carried out if the compressor is in hydrogen service, or if the process gas is
of similar low molecular weight.
4.3.6.8 * The gas test shall be carried out after the post-test inspection.
GENERAL ENGINEERING SPECIFICATION GES K.01
CENTRIFUGAL COMPRESSORS (API 617) Page 19 of 23
Rev 0 1999
4.3.6.11 * Spare parts shall be subject to the Vendor/Contractor's standards tests, but complying
with paragraph 4.3.6.7. If a spare rotor is supplied along with the main unit a separate
additional mechanical running test of the overall unit shall be carried out. A separate
additional performance test with the spare rotor fitted is not required.
6.2.1 The Vendor/Contractor shall submit his test procedures in writing for approval, prior to the start of the
testing programme.
6.2.2 Testing shall comply with paragraphs 4.1 and 4.3 of API 617, as amended below:
- selected NDT,
- balancing,
- hydrostatic,
- mechanical running,
- casing pressure test,
- performance test,
- assembled compressor gas leakage,
- complete unit test,
- auxiliary equipment tests,
- post-test inspection of bearings and seals.
4.3 Testing
"No type of preservative or paint shall be allowed to cover any joint, mechanical or
welded, before the pressure test is completed."
"Test pressure gauges shall be of the direct reading type and shall be periodically
calibrated. The certificate of calibration shall be presented to the Owner's Inspector prior
to the commencement of tests."
4.3.4.2.5 * Lube oil and seal oil inlet pressures and temperatures shall be varied during the four hour
run at maximum continuous speed (paragraph 4.3.4.2.3).
"The actual weight of the coupling shall be simulated by the addition of weights to the
compressor rotor during the mechanical running test when the contract coupling is not
used."
4.3.4.3.3 * Filtered and unfiltered vibration level data, presented in polar form, is not required.
4.3.4.3.6 * Tape recordings of real time vibration data are not required.
4.3.4.4.1 * Shaft end seals shall be inspected, following a successful running test.
4.3.5.3 * The casing shall be pressurised for 30 minutes and a soap bubble test carried out.
GENERAL ENGINEERING SPECIFICATION GES K.01
CENTRIFUGAL COMPRESSORS (API 617) Page 20 of 23
Rev 0 1999
6.3 Test Certificates
The Vendor/Contractor shall carry out at site a fully pressurised performance test on the installed
compressor/driver package. The Owner shall witness and approve the results of these tests.
6.5 Start-Up
6.5.1 The Vendor/Contractor shall be responsible for complete start-up until unit is accepted as operational by
the Owner. The Vendor/Contractor shall be responsible for the supply of a competent serviceman for the
duration of the checking, start-up and run-on period.
6.5.2 The Vendor/Contractor will supply for start-up, all lubricating fluids, including oil, grease and coolants as
required by the unit. The Vendor/Contractor shall recommend amount and type of lubrication and cooling
fluids for subsequent operation.
7.0 DOCUMENTATION
7.1 Introduction
7.1.1 This section covers the documentation required for the design, selection, fabrication, inspection and testing
for all the equipment, components and services to be provided against this specification.
7.1.2 The detailed list of documents that are required is included with the Purchase Order/Contract.
7.1.3 The documents as listed may be considered as a minimum requirement. All details to confirm compliance
with the relevant specifications, and to allow a full and continued appraisal to be made of the
Vendor/Contractor's proposals and interpretations of the ordered equipment, should be submitted in
accordance with the schedule specified in the Purchase Order/Contract.
7.1.4 All documentation (drawings, calculations, Data Sheets, etc.) shall be produced by the Vendor/Contractor
in an electronic format that is compatible with that used by the Owner and shall be agreed at the
commencement of the contract.
7.1.5 Any production or procurement undertaken by the Vendor/Contractor which is prior to the relevant
documentation being submitted and reviewed by the Owner is at the Vendors/Contractors risk.
7.1.6 On all documentation the Purchaser Order/Contract number, equipment title, tag number and project name
shall be quoted.
7.1.7 All documentation shall be checked and signed by the checker before submission.
7.2.1 The Vendor/Contractor shall submit with his proposal a preliminary Quality Control Plan.
GENERAL ENGINEERING SPECIFICATION GES K.01
CENTRIFUGAL COMPRESSORS (API 617) Page 21 of 23
Rev 0 1999
7.2.2 The Vendor/Contractor shall include with his proposal documentation a statement of proposed Sub-
contractors, a document submission schedule for all documents based on a review cycle of three weeks and
an outline programme for procurement and production activities.
7.2.3 The Vendor/Contractor shall incorporate any revisions agreed with the Owner during the enquiry review
stage and submit revised tender documentation for approval.
7.2.4 Monthly reports shall be submitted by the Vendor/Contractor detailing design, procurement, production
and documentation activities. The format of which shall be agreed with the Owner.
7.3.1 The Vendor/Contractor shall supply with his proposal completed Data Sheets containing all the relevant
information necessary for appraisal of the design by the Owner.
7.3.2 Project specific instructions will be issued to the Vendor/Contractor with the Purchase Order/Contract,
which describes the data and calculations to be submitted, and the methods of submission.
7.3.3 The Vendor/Contractor shall be responsible for obtaining approvals from the Inspection Authority.
7.3.4 All calculations shall be carried out in a clear and logical manner. Where conditions involve the use of
formulae or methods not specified in the Design Code, the source of these formulae or methods shall be
clearly referenced.
7.3.5 Computer calculations will only be acceptable if all input is shown, together with calculated values of
intermediate terms and factors and options chosen, as well as final calculated dimensions, stresses or other
values and the computer program has been validated to the satisfaction of the Owner.
7.3.6 Calculations and drawings that are interdependent, i.e. foundation loading and equipment footprint, shall be
presented for appraisal together.
7.4 Drawings
7.4.1 The drawings listed with the Purchase Order/Contract shall be sent by the Vendor/Contractor to the Owner
and the Inspection Authority for review and approval.
7.4.2 The components and process to produce the ordered equipment shall be shown in sufficient detail to be
fully appraised eg, casing drawings, shall as a minimum, show the position of all through thickness welds,
together with material thicknesses and specifications, clearly indicating the welding procedure
specification which is applicable to each weld.
7.4.3 General arrangement drawings shall be to scale and show the relative location and main dimensions of all
components including elevations and orientations of nozzles, lifting lugs, nameplates and supports.
7.4.4 Detail drawings which may be included on the general arrangement shall include thicknesses and
dimensions of all components, weld details, machining and surface finish requirements, gasket and
nameplate details.
7.5.1 Two (2) copies of the Data Dossier shall be supplied, and shall be a record of the manufacturing process. It
shall contain the following:
7.5.2 Six (6) sets of the Installation, Operations and Maintenance Manual shall be specifically compiled for the
equipment supplied. A compendium of manufacturer's data for a range of like products is not acceptable.
The Manual shall contain the following:
The Manuals shall be presented in A4 format, and be securely bound in heavy duty 4 ring binders.
7.5.3 The Vendor/Contractor shall produce "as built" documents revised to indicate field changes.
7.5.4 The Vendor/Contractor shall supply one set of mylar original drawings.
7.5.5 In addition to the 'hard copies' required under the contract, copies of the electronic records shall be issued
to the Owner for all approved documentation, this forming part of the Vendor's/Contractor's contractual
obligations.
Surface preparation, painting and painting materials shall be in accordance with GES X.01, GES X.02 and
GES X.03.
8.2 Spares
The Vendor/Contractor shall submit with his proposal, a priced list of recommended spares for
commissioning, start-up and two years operation, for review by the Owner.
8.3.2 After mechanical completion at the works, the compressors shall be left in a clean dry condition.
8.3.3 The Vendor/Contractor shall be responsible for loading and anchoring the compressors to prevent damage
during shipment. This shall be done at the Vendor/Contractor's works, and may be achieved by firmly
fixing the equipment to wooden pallets or crates, as part of an approval packing procedure.
The equipment shall be prepared for export shipment by sea. Shipment as non-
containerised deck cargo is not permissible.
The probable storage period will be specified in the order/enquiry and will extend from
the time of despatch to the time of unpacking at site. If the storage period is not stated, a
minimum period of 24 months shall be assumed.
Painting shall comply with GES X.01, GES X.02 and GES X.03.
4.4.3.10 The spare rotor shall be suitably crated for export shipment.
4.3.3.11* The fit-up and assembly of machine mounted piping, intercoolers and so forth, shall be
completed in the Vendor/Contractor's shop prior to shipment.
4.4.3.13 The top of forced draft air cooler tube bundles shall be covered with 5/16" (8 mm) minimum
thickness plywood prior to shipment to prevent damage to fins.
8.4 Shipping
The equipment shall not leave the Vendor's/Contractor's works for shipment until the release certificate has
been approved by the Owner's Inspector.
8.5 Warranty
8.5.1 The Vendor/Contractor shall provide manufacturer's written guarantees of compressor and driver
performance.
8.5.2 The Vendor/Contractor shall warrant all materials and services supplied against any defect for a minimum
of 12 months after commissioning or 24 months from the date of delivery to site, whichever is the shorter
period, or for the period stipulated in the Purchase Order/Contract.
8.5.3 Should any item be found defective, the Vendor/Contractor shall be responsible for all costs associated
with restoring the equipment to the standard specified by the Purchase Order/Contract.
S:\NOC9077\ADMIN\SPECIFICATIONS\K-SERIES\K-01\GESK01RF