Project Variation

Project Variation to

Shell DEP 31.29.02.30

Centrifugal Pumps (Amendments / Supplements to ISO 13709)

I 27 Aug 13 Approved for Design FW FW FW


H 19 Mar 13 Approved for Design FW FW FW
G 29 Sep 09 Approved for Design CPR CPR ACW
F 03 Sep 09 Approved for Design CPR CPR ACW
E 25 Feb 09 Approved for Design CPR CPR ACW
D 11 June 08 Approved for Design CPR CPR ACW
C 01 May 08 Approved for Design CPR CPR ACW
B 27 Dec 06 Approved for Design CPR CPR ACW
A 13 Sep 06 Approved for Design CPR CPR ACW
CHKD
Rev. Date Description Orig. Approved By Client Approval
By

Kuwait National Petroleum Company (K.S.C.)


Clean Fuels Project 2020
Kuwait

Fluor Limited
Fluor Project No. A2WD
Sugar Land, Texas

CONTRACT NO. PROJECT VARIATION NO. REV. NO.

NRP/PMC-0001/CNSL 31.29.02.30-P6000CFP-000-PV I

31.29.02.30-P6000CFP-000-PV_I.DOC
Kuwait National Petroleum Company (K.S.C.) 31.29.02.30-P6000CFP-000-PV
Clean Fuels Project 2020 REV I, 27 Aug 2013
KNPC Contract No. NRP/PMC-0001/CNSL Page 2 of 24
Fluor Project No. A2WD

Project Variation

Record of Revisions
Rev. No. Date Description

A 13 Sep 06 Approved for Design


Identical to Project Variation 31.29.02.30-P4001NRP-00-PV, Rev B with
updated PV references.
B 27 Dec 06 Approved for Design
Revised and corrected header on all pages.
Corrected font on all pages.
No other changes.
C 01 May 08 Approved for Design.
Added clause 6.2.2.a.
Revised 6.2.14.
Added paragraph 6.3.21.
D 11 June 08 Approved for Design.
Changed paragraph number 6.3.21 to paragraph number 6.3.1 and revised
wording to clarify intent.
E 25 Feb 09 Approved for Design
Revised paragraph 6.1.9 so that power limitations for use of general purpose
gears matches those found in P6000CFP.000.10.29.007 and 31.29.60.30-
P6000CFP-000-PV.
F 03 Sep 09 Approved for Design
Revised paragraph 6.1.3 regarding motor sizing for pumps operating in
parallel.
Revised paragraph 8.3.1.5 regarding the requirement for a basket type strainer
to be furnished on the suction of vertical pumps.
G 29 Sep 09 Approved for Design
Corrected paragraph number shown in Rev. F revision description above.
H 19 Mar 13 Approved for Design
Updated as marked to reflect SHELL DEP Version 33
This document has been substantially revised, therefore changes have not been
highlighted
I 27 Aug 13 Approved for Design
Revised paragraphs 7.4.2.2 and 7.4.2.3 regarding instrumentation requirements
versus machine driver power.

31.29.02.30-P6000CFP-000-PV_I.DOC
Kuwait National Petroleum Company (K.S.C.) 31.29.02.30-P6000CFP-000-PV
Clean Fuels Project 2020 REV I, 27 Aug 2013
KNPC Contract No. NRP/PMC-0001/CNSL Page 3 of 24
Fluor Project No. A2WD

Project Variation

DEP 31.29.02.30-Gen, Centrifugal Pumps (amendments / supplements to ISO 13709) dated Feb 2011, is adopted
for the Clean Fuels Project (CFP) subject to the modification noted in this project variation. This PV (Project
Variation) shall be included, as a requirement, wherever DEP 31.29.02.30-Gen is referenced in any other project
documents, including all DEPs.

In general, the requirements stated in this PV have precedence over, and supersede those in the Shell DEPs. Any
discrepancy between this PV and other Clean Fuels Project documents shall be brought to the attention of the
Company for review and direction.

References in DEP 31.29.02.30-Gen to other Design and Engineering Practices (specifications, guidelines, etc.)
shall be amended, superseded, or otherwise revised by the associated PV of a given DEP, where available.

31.29.02.30-P6000CFP-000-PV_I.DOC
Kuwait National Petroleum Company (K.S.C.) 31.29.02.30-P6000CFP-000-PV
Clean Fuels Project 2020 REV I, 27 Aug 2013
KNPC Contract No. NRP/PMC-0001/CNSL Page 4 of 24
Fluor Project No. A2WD

Project Variation

TABLE OF CONTENTS

Record of Revisions ............................................................................................................................ 2 


PART I INTRODUCTION ......................................................................................................... 5 
1.1 Scope ........................................................................................................................... 5 
1.4 Cross-references .......................................................................................................... 5 
PART III PUMPS FOR NON-ESSENTIAL SERVICE AND SPARED PUMPS FOR ESSENTIAL
SERVICE (AMENDMENTS/SUPPLEMENTS TO ISO 13709) ....................................... 6 
4. GENERAL .................................................................................................................. 6 
5. REQUIREMENTS ...................................................................................................... 6 
6. BASIC DESIGN .......................................................................................................... 6 
7. ACCESSORIES......................................................................................................... 11 
8. INSPECTION, TESTING AND PREPARATION FOR SHIPMENT ......................... 13 
9. SPECIFIC PUMP TYPES ......................................................................................... 16 
PART IV PUMPS FOR VITAL SERVICE AND UNSPARED PUMPS FOR ESSENTIAL
SERVICE (AMENDMENTS/SUPPLEMENTS TO ISO 13709) ..................................... 20 
8. INSPECTION, TESTING AND PREPARATION FOR SHIPMENT ......................... 20 
PART V REFERENCES ........................................................................................................... 21 
APPENDIX 1 MATERIAL SELECTION ........................................................................................... 23 

APPENDICES
ANNEX P Scope of Inspection and Testing.............................................................................................. 24

31.29.02.30-P6000CFP-000-PV_I.DOC
Kuwait National Petroleum Company (K.S.C.) 31.29.02.30-P6000CFP-000-PV
Clean Fuels Project 2020 REV I, 27 Aug 2013
KNPC Contract No. NRP/PMC-0001/CNSL Page 5 of 24
Fluor Project No. A2WD

Project Variation

PART I INTRODUCTION

1.1 Scope
This PV shall be used in conjunction with data sheets 31.29.02.93-H-P6000CFP-000-PV and
31.29.02.93-V-P6000CFP-000-PV
Pump selection shall comply with 31.29.02.11-P6000CFP-000-PV.

1.4 Cross-references
Other documents referenced by this PV are listed in (Part V) in this document.

31.29.02.30-P6000CFP-000-PV_I.DOC
Kuwait National Petroleum Company (K.S.C.) 31.29.02.30-P6000CFP-000-PV
Clean Fuels Project 2020 REV I, 27 Aug 2013
KNPC Contract No. NRP/PMC-0001/CNSL Page 6 of 24
Fluor Project No. A2WD

Project Variation

PART III PUMPS FOR NON-ESSENTIAL SERVICE AND SPARED PUMPS FOR ESSENTIAL
SERVICE (AMENDMENTS/SUPPLEMENTS TO ISO 13709)

4. GENERAL

4.2 Classification and designation

4.2.2 Pump designations and description


4.2.2.1 ADD TO THIS CLAUSE:
Pump type OH1 shall not be used.
4.2.2.5 DELETE CLAUSE AND REPLACE WITH:
Pump type OH5 shall not be used.
ADD NEW CLAUSE:
4.2.2.19 The following pump types shall not be used: Two-stage overhung, double suction overhung and Built-
in Mechanical Seal.

5. REQUIREMENTS
ADD NEW CLAUSE:
5.3.3 In the case of conflicting requirements between documents relating to the enquiry or order, the
following hierarchy of documents shall apply:
- upper level: applicable regulations
- second level: purchase order and variations thereto;
- third level: data/requisition sheets and drawings;
- fourth level: this PV / DEP 31.29.02.30-Gen

6. BASIC DESIGN
6.1.4 REPLACE THE FIRST SENTENCE OF THIS CLAUSE BY:
Pumps with constant-speed drivers shall be capable of developing at least a 3 m (10 ft) or 5 percent
head increase (whichever is greater) at rated conditions, when a new impeller(s) (larger diameter)
and/or new diffuser(s) is installed. This criteria may not be met by special overbores of cases or
diffusers. Impeller diameters less than published minimum diameters are not acceptable.
6.1.6 ADD TO THIS CLAUSE:
Note: For variable speed applications the Pump Supplier is responsible for checking MAWP and shaft
horsepower ratings at maximum continuous speed.
6.1.7 ADD TO THIS CLAUSE:
The pump supplier is responsible for checking in all instances that the seal arrangement, axial thrust
load and bearing life is in compliance with this standard.
6.1.11 REPLACE CLAUSE BY:

31.29.02.30-P6000CFP-000-PV_I.DOC
Kuwait National Petroleum Company (K.S.C.) 31.29.02.30-P6000CFP-000-PV
Clean Fuels Project 2020 REV I, 27 Aug 2013
KNPC Contract No. NRP/PMC-0001/CNSL Page 7 of 24
Fluor Project No. A2WD

Project Variation

Pumps shall have stable head/capacity curves which continuously rise by at least 5 % from rated
capacity to shut-off. The gradient of the tangent to the curve shall continuously decrease from 125 %
of the best efficiency point to minimum continuous stable flow and shall remain positive. If parallel
operation is specified, the head rise from rated point to shutoff shall be at least 10 %.

Discharge orifice shall not be used as a means for providing continuous rise to shut-off. Unless
otherwise specified, head rise from rated flow to shut-off of more than 20% requires the approval of
the Principal.

6.1.12 ADD TO THIS CLAUSE


Viscous performance must be checked.
6.1.14 Noise Control
ADD NEW CLAUSE
6.1.14.2 Limits
The Contractor shall comply with DEP 31.10.00.31-Gen.
6.1.17 ADD TO THIS CLAUSE:
The need for cooling is to maintain lube oil temperatures in an acceptable temperature range. Bearing
housing cooling by axial shaft mounted fan with shroud is preferred and should be utilized when
pumping temperature exceeds 100°C. Water cooling of bearing housing shall be provided when fan
cooling is not sufficient to maintain proper oil temperature. Mechanical seal coolers shall be provided
when required to meet vapor pressure and sealing pressure margin.

The use of cooling water on the bearing bracket is left to the discretion of the pump supplier, but the
API requirements for bearing life shall be met.
ADD NEW CLAUSE:
6.1.36 Pumps shall not be provided with inducers, unless approved by the Principal.

6.3 Pressure casings


6.3.2 REPLACE “IF SPECIFIED” IN THE 2ND SENTENTENCE OF THIS CLAUSE BY “UNLESS
OTHERWISE SPECIFIED”
6.3.4 ADD TO THIS CLAUSE:
The supplier shall state the source for the material properties, and this source shall be an organization
recognized in material selection.
The materials selected shall either meet the required ASTM material specified in table H-2 or be
equivalent materials to the ASTM grades.

6.3.9 ADD TO THIS CLAUSE:


d. Boiler feed water pumps at a rated discharge pressure above 10,000 kPa (1450 psig).
e. One and two-stage pumps in process units.
6.3.10 ADD TO THIS CLAUSE:

31.29.02.30-P6000CFP-000-PV_I.DOC
Kuwait National Petroleum Company (K.S.C.) 31.29.02.30-P6000CFP-000-PV
Clean Fuels Project 2020 REV I, 27 Aug 2013
KNPC Contract No. NRP/PMC-0001/CNSL Page 8 of 24
Fluor Project No. A2WD

Project Variation

The supplier shall use solid metal, metal-clad or confined and compression restricted, spiral-wound
metal or non-asbestos-filled gaskets conforming to ASME B16.20 for design temperatures over 177C
(350F). O-rings shall not be used under these conditions.
6.3.14 ADD TO THIS CLAUSE:
Studs are required; cap screws are not acceptable.

6.4 Nozzle and pressure casing connections


6.4.2 Suction and discharge nozzles
6.4.2.2 REPLACE THIS CLAUSE BY:
Cast iron shall not be used.
6.4.2.7 ADD NEW CLAUSE:

End suction top discharge pumps shall be self venting type by the arrangement of discharge nozzle.

6.4.3 Auxiliary connections


6.4.3.1 ADD TO THIS CLAUSE:
Threaded connections to the pressure casing shall not be used, except that the seal gland connection
may be threaded.
6.4.3.4 ADD TO THIS CLAUSE:
Connections welded to the case shall not limit the MAWP of the case. These welds are pressure
boundary welds, not piping welds.

Note: This happens when Austenitic stainless steel piping is used on C-6 pump cases, using the same
flange rating. Connections using a different material grade are acceptable only if the connection
flanged rating is increased to a higher pressure rating, for example using a 600# flanged drain
connection on a 300# R.F. C-6 pump.

6.4.3.7 ADD TO THIS CLAUSE:


Pipe Threads shall be in accordance with ASME B1.20.1.
6.4.3.8 ADD TO THIS CLAUSE:
Cylindrical threads are not acceptable.

6.4.3.11 ADD TO THIS CLAUSE:


Openings shall not be furnished unless they are essential, in which case they shall be located away
from high-velocity areas. The only allowed exception is the casing drain. The provision and location
of openings shall be identified in the vendor’s proposal and shall be subject to the approval of the
Principal. All openings furnished and not connected to piping shall be closed with a flange in
accordance with (5.4.3.4).
ADD TO THIS CLAUSE:
Balance lines and their connections shall be flanged. Unions shall not be used.

31.29.02.30-P6000CFP-000-PV_I.DOC
Kuwait National Petroleum Company (K.S.C.) 31.29.02.30-P6000CFP-000-PV
Clean Fuels Project 2020 REV I, 27 Aug 2013
KNPC Contract No. NRP/PMC-0001/CNSL Page 9 of 24
Fluor Project No. A2WD

Project Variation

6.4.3.12 ADD TO THIS CLAUSE:


Connections to be in accordance with ASME B16.1 or ASME B16.5 as applicable.

6.4.3.14 ADD TO THIS CLAUSE:


All pumps shall be supplied with a low point casing drain. Pumps shall be supplied with multiple
drain points in the suction area and cross over if required to drain the pump case as completely as
possible. The supplier shall indicate on the outline drawing the liquid which will not self drain.

6.6 Rotors
ADD THIS CLAUSE:
6.6.1.1 Cast iron and bronze impellers with peripheral velocities exceeding 60 m/sec (200 ft/sec) are not
acceptable.
ADD THIS CLAUSE:

6.6.1.2 Cast iron impellers and/or wear rings applied at pumping temperatures above 200°C (400°F) are not
acceptable.
6.6.10.e.1 REPLACE THIS CLAUSE:
For areas to be observed by radial vibration probes, 25 percent of the allowed peak-to-peak vibration
amplitude or 0.25 mil, whichever is less.

6.7 Wear rings and running clearances


6.7.1 REPLACE THE LAST SENTENCE IN THIS CLAUSE BY:
Renewable front and back case and impeller wear rings are required for all pumps.

6.8 Mechanical shaft seals


6.8.1 ADD TO THIS CLAUSE BY:
Unless otherwise specified, pumps shall be equipped with mechanical seals. All mechanical seals
SHALL [PS] be in accordance with 31.29.00.33-P6000CFP-000-PV.

6.9 Dynamics
6.9.1 General
6.9.1.3 ADD TO THIS CLAUSE:
Single-stage overhung pumps (types OH2 and OH3) require the approval of the Principal if the
impeller tip speed exceeds 62.5 m/sec. If alternative shaft diameters are available, the larger shaft shall
be supplied.
6.9.2 Torsional analysis
6.9.2.10 ADD TO THIS CLAUSE:
Whenever a torsional analysis is performed, the manufacturer shall furnish a detailed report that
includes the requirements of 6.9.2.10a – 6.9.2.10e.

31.29.02.30-P6000CFP-000-PV_I.DOC
Kuwait National Petroleum Company (K.S.C.) 31.29.02.30-P6000CFP-000-PV
Clean Fuels Project 2020 REV I, 27 Aug 2013
KNPC Contract No. NRP/PMC-0001/CNSL Page 10 of 24
Fluor Project No. A2WD

Project Variation

6.9.4 Balancing

6.9.4.1 ADD TO THIS CLAUSE:


Shafts are not considered as a component and are not required to be balanced. The shaft machining
operation provides an inherent balance.

6.10 Bearings and bearing housings


6.10.1 Bearings
6.10.1.3 ADD TO THIS CLAUSE:
Ball bearings shall be in accordance with ABMA 20 Group 3.
6.10.2 Bearing Housings
6.10.2.2 ADD TO THIS CLAUSE:
Constant level oilers shall be Trico "Optomatic" (or Principal authorized equal).
6.10.2.6 ADD TO THIS CLAUSE:
Bearing housings shall be supplied with Protech or INPRO bearing Isolators.

6.10.2.10 ADD TO THIS CLAUSE:


The bearing housing of pumps supplied with anti-friction bearings shall be supplied with a flat surface
with a threaded hole in accordance with Fig. 31 through 33.

6.11 Lubrication
6.11.2 ADD TO THIS CLAUSE:
Oil flingers are acceptable only in constant speed service. Flingers and/or oil rings shall be metallic.

6.12 Materials
6.12.1 General
6.12.1.2 REPLACE THIS CLAUSE BY:
The material specification of all components shall be clearly stated in the vendor’s proposal. The
vendor shall supply materials in accordance with Table H.2 using ASTM material designations.
Equivalent materials to the ASTM grades listed may be supplied using the other International table
H.2 grades if approved by the Principal (KNPC). The Supplier shall provide the necessary equivalence
data. The materials selected shall either meet the required ASTM material specified in table H-2 or be
equivalent materials to the ASTM grades. Equivalent materials shall be identified by reference to
applicable International Standards; including the material grade (Tables H.2 and H.3 may be used for
guidance).

6.12.1.4 DELETE SHELL DEP CLASE AND ADD THE FOLLOWING TO API 610:
Minor or unidentified parts other than static gaskets, O-rings, or shaft packing shall be metallic.
Plastic, phenolic, or similar materials are not acceptable.

31.29.02.30-P6000CFP-000-PV_I.DOC
Kuwait National Petroleum Company (K.S.C.) 31.29.02.30-P6000CFP-000-PV
Clean Fuels Project 2020 REV I, 27 Aug 2013
KNPC Contract No. NRP/PMC-0001/CNSL Page 11 of 24
Fluor Project No. A2WD

Project Variation

6.12.3 Welding
6.12.3.3 ADD TO THIS CLAUSE:
Welding procedures (PQRs, WPSs and weld maps) for fabricated casings shall be submitted to the
Buyer for review and acceptance prior to fabrication.

6.12.3.4e1 ADD TO THIS CLAUSE:


Liquid penetrant or magnetic particle examination is required for all auxiliary connections.

6.12.3.4e2 ADD TO THIS CLAUSE:


One hundred percent radiographic examination of attachment welds for suction and discharge nozzles
is required.

6.12.4 REPLACE 2ND SENTENCE OF THIS CLAUSE IN SHELL DEP 31.29.02.30-GEN BY:
If this temperature is 0 °C (32 °F) or below, the materials of pressure-containing parts shall comply
with 30.10.02.31-P6000CFP-000-PV.

7. ACCESSORIES

7.1 Drivers
7.1.1 REPLACE THIS CLAUSE IN SHELL DEP 31.29.02.30-Gen BY:
Electric motor drivers shall be in accordance with 33.66.05.31- P6000CFP-000-PV.
7.1.4 DELETE CLAUSE FROM SHELL DEP 31.29.02.30-Gen AND REPLACE THE 1ST SENTENCE
OF API 610 WITH THE FOLLOWING:
Motors shall have power ratings, excluding the service factor (if any), at least equal to the percentages
of power at pump rated conditions given in TABLE 12. When the installation consists of two 50
percent flow pumps operating in parallel the motor power rating shall be sufficient for operation at
any point on the performance curve including end-of-curve. The motors for certain other pumps may
also need to be sized for the end-of-curve case. These situations will be noted on the pump data sheet.
7.1.7 DELETE CLAUSE FROM SHELL DEP 31.29.02.30-Gen
7.1.9 Delete “at Normal Steam Conditions” from the second sentence of this clause in API 610.
7.1.10 ADD TO THIS CLAUSE:
Gears in services operating at absorbed power above 1500 kW (2000 hp) shall be in accordance with
31.29.00.32- P6000CFP-000-PV.

ADD NEW CLAUSE:


7.1.11 Internal combustion engines shall comply with EEMUA 107 if located in an area classified as Zone 1
or Zone 2.

7.2 Couplings and guards


7.2.2 ADD TO THIS CLAUSE:
a) Corrosion resistant material shall be defined as austenitic stainless steel.
31.29.02.30-P6000CFP-000-PV_I.DOC
Kuwait National Petroleum Company (K.S.C.) 31.29.02.30-P6000CFP-000-PV
Clean Fuels Project 2020 REV I, 27 Aug 2013
KNPC Contract No. NRP/PMC-0001/CNSL Page 12 of 24
Fluor Project No. A2WD

Project Variation

7.2.4 DELETE CLAUSE FROM SHELL DEP 31.29.02.30-Gen AND REPLACE API 610 CLAUSE BY:
Pumps (except vertical high speed) with drivers rated above 1 MW or pump speeds greater than or
equal to 4000 rpm shall be supplied with API-671 couplings in accordance with 31.29.00.36-
P6000CFP-000-PV.
7.2.7 ADD TO THIS CLAUSE:
The minimum service factor for couplings shall be 1.25, the service factor for couplings complying
with API-671, shall be per API-671.
7.2.14 REPLACE SHELL DEP CLAUSE WITH THE FOLLOWING:
Guards shall be made of aluminium or aluminium alloys with a maximum content of 2 % magnesium
or 0.2 % copper or other spark resistant material approved by the Principal.

7.3 Baseplates
7.3.1 ADD TO THIS CLAUSE:
When full top decking is specified on the data sheet it shall be defined as meaning that the top surface
of the base plate is completely covered with steel plate. Grout fill and vent holes as described in 7.3.10
below shall be included in this design.
7.3.10 DELETE SHELL DEP CLAUSE AND ADD THE FOLLOWING TO API 610:
Baseplates shall be designed per paragraph 7.3.13. Baseplates shall have grout fill and vent holes for
non-shrink cement grout fill. The pump supplier shall not consider the grout, which will be added in
the field, for structural stiffness in the baseplate design. The baseplates shall have features to prevent
liquid accumulation inside.
Drain-rim or drain-pan baseplates with raised lip shall be specified. Baseplate drains shall be
connected to the drain system. Lube oil consoles shall be separate from the pump baseplate, located
adjacent to the pump.

7.4 Instrumentation
7.4.1 ADD TO THIS CLAUSE:
If supplied, the gauges shall comply with 32.31.09.31- P6000CFP-000-PV or 31.29.00.33-
P6000CFP-000-PV.
7.4.2 VIBRATION, POSITION AND TEMPERATURE DETECTORS
7.4.2.2 ADD TO THIS CLAUSE:
When hydrodynamic thrust/radial bearings are provided, multistage pumps of driver power 1000 kW
and larger shall be provided with two radial vibration probes at each bearing housings, two axial
probes at the thrust end and a one-event-per revolution probe.
7.4.2.3 ADD TO THIS CLAUSE:
When hydrodynamic thrust/radial bearings are provided, multistage pumps of driver power 1000 kW
and larger shall be provided with two bearing metal detectors in each radial bearing, three bearing
metal detectors in active side of the thrust bearing and two bearing metal detectors in inactive side of
thrust bearing
7.4.2.4 ADD TO THIS CLAUSE:

31.29.02.30-P6000CFP-000-PV_I.DOC
Kuwait National Petroleum Company (K.S.C.) 31.29.02.30-P6000CFP-000-PV
Clean Fuels Project 2020 REV I, 27 Aug 2013
KNPC Contract No. NRP/PMC-0001/CNSL Page 13 of 24
Fluor Project No. A2WD

Project Variation

When vibration probes and bearing temperature detectors are provided, vendor shall provide vibration
and temperature monitor in accordance with API-670.
7.5 Piping and appurtenances
7.5.1 General
7.5.1.2 ADD TO THIS CLAUSE:
Flange gaskets shall be nonasbestos filled. Center support ring and inner metal ring shall be Type 304
or 316 stainless steel. Carbon steel slip-on flanges are not permitted for lubricating oil piping.

7.5.1.7 ADD TO THIS CLAUSE:


Cadmium plated fasteners are not acceptable.

7.5.2 Auxiliary process fluid piping


7.5.2.6 ADD TO THIS CLAUSE:
Pump casing drains and vents shall be provided with valves.

7.5.2.8 DELETE SHELL DEP CLAUSE AND ADD TO THIS CLAUSE:


Flanged piping joints shall be supplied for all auxiliary piping except for seal gland connections.
Socket welded construction is acceptable, socket-welded unions are not allowed. The seal flush
connection to the pump case shall be welded construction and be heat treated with the pump case.
Flush piping shall be supplied with paddle orifices, orifice unions are not allowed.
ADD NEW CLAUSE:
7.5.3.4 Manifold inlet and outlet valves shall be located at the edge of the baseplate opposite the driver.
ADD NEW CLAUSE:
7.5.3.5 Threaded plain steel pipe (ASTM A106), carbon steel fittings (ASTM A105), carbon steel valves,
carbon steel sight flow indicators shall be used for all cooling water piping. Copper tubing and brass
fittings are not acceptable.

8. INSPECTION, TESTING AND PREPARATION FOR SHIPMENT

8.1 General
8.1.1 ADD TO THIS CLAUSE;
Scope of witnessed inspection and testing is attached as Annex P.

8.3 Testing
8.3.1.2 REPLACE THIS CLAUSE BY:
At least 6 weeks before the first scheduled running test, the vendor shall submit to the purchaser, for
his review and comment, detailed procedures for all running tests and all specified optional tests,
including acceptance criteria for all monitored parameters. Any exceptions to the specified test
requirements shall be stated in the original proposal.

31.29.02.30-P6000CFP-000-PV_I.DOC
Kuwait National Petroleum Company (K.S.C.) 31.29.02.30-P6000CFP-000-PV
Clean Fuels Project 2020 REV I, 27 Aug 2013
KNPC Contract No. NRP/PMC-0001/CNSL Page 14 of 24
Fluor Project No. A2WD

Project Variation

8.3.2 Hydrostatic test


8.3.2.6 ADD TO THIS CLAUSE:
Piping shall be in accordance with ASME B31.3.

8.3.2.8 ADD TO THIS CLAUSE:


To prevent deposition of chlorides as a result of evaporative drying, all residual liquid shall be
removed from the equipment by flushing with chloride-free water, alcohol, petroleum distillate or
suitable flushing solution. Hot air drying is unacceptable.

8.3.2.12 ADD TO THIS CLAUSE:


Segmental hydrotesting of any pressure casing design is not acceptable.

8.3.2.15 REPLACE THIS CLAUSE:

Cooling passages and components, including jackets for bearings, seal chambers, oil coolers and seal
coolers, shall be tested at 1.5 times the cooling water design pressure or 10.5 bar, whichever is higher.

8.3.3 Performance test


8.3.3.2b ADD TO THIS CLAUSE:
8.3.3.2 b (Addition) The Vendor shall advise the Purchaser and state in the test procedures when a
substitute seal is required during the performance test if needed to prevent damage to the contract seal
or if the contract seals are not compatible with the test fluid. The Supplier shall include the cost of the
test seals in the pump base price.
8.3.3.3a ADD TO THIS CLAUSE:
Bearing temperatures and vibration readings shall not be taken at shutoff.

8.3.3.7 ADD TO SUB-CLAUSE a):


Any filing, grinding or other reworking of impellers, volute lips, suction splitters, etc. to meet the
guaranteed performance shall be described in the test report, engineering file, and parts manual in
sufficient detail to permit obtaining replacement parts similarly reworked.

8.3.3.7b ADD TO THIS CLAUSE:

Multistage pumps shall be retested if they are dismantled for any reason except inspection.

8.3.4 Optional tests


8.3.4.3 NPSH required test
8.3.4.3.2 ADD TO THIS CLAUSE:
The NPSHR test will determine the actual NPSHR at a 3% head drop, and NPSHR curve “knees” will
be developed and submitted in accordance with Hydraulic Institute (ANSI/HI 1.6-1994). An NPSHR
test that only demonstrates the quoted NPSHR value is not acceptable.

31.29.02.30-P6000CFP-000-PV_I.DOC
Kuwait National Petroleum Company (K.S.C.) 31.29.02.30-P6000CFP-000-PV
Clean Fuels Project 2020 REV I, 27 Aug 2013
KNPC Contract No. NRP/PMC-0001/CNSL Page 15 of 24
Fluor Project No. A2WD

Project Variation

8.3.4.4 Complete unit test


8.3.4.4.1 ADD TO THIS CLAUSE:

If a complete unit test is specified, only the motor driven unit shall be subject to the complete unit test
requirement. Steam Turbine driven pumps are exempt from the complete unit test requirement. Motor
driven pump complete unit tests shall be run with the job lube oil system, not a shop lube oil system.

8.3.4.6 Auxiliary equipment test


ADD TO THIS CLAUSE:

Completely assembled pressurized lube oil systems shall be given a functional mechanical test at the
lube oil system supplier's shop or the pump Seller's shop prior to shipment. Test shall show successful
operation of all alarms and shutdowns. Flow rate at required pressure shall be verified by
measurement. This test is in addition to the complete unit test.

8.4 Preparation For Shipment


8.4.2.2 ADD TO THIS CLAUSE:
Auxiliary process fluid piping shall be completely drained, dried and coated with suitable rust
preventative.

ADD NEW CLAUSE:

8.4.2.10 Mechanical seals, carbon rings and other sealing devices shall be installed for shipment.
8.4.5 REPLACE THIS CLAUSE BY:
(Substitution) Each item shall be tagged and impression stamped with the following information:

 Equipment Item No.


 Equipment Serial No.

Tags shall be stainless steel. Tags shall be attached to each component with stainless steel wire.

This tagging is in addition to the equipment nameplate.

Components shipped separately shall be tagged or marked with the equipment item number for which
they are intended. Equipment shipped in fully enclosed containers shall also include the above
information marked on the outside of the container.

Equipment containing insulating oils, anti-freeze solutions or other fluids shall be prominently tagged
at openings to indicate the nature of the contents and shipping and storage precautions.

31.29.02.30-P6000CFP-000-PV_I.DOC
Kuwait National Petroleum Company (K.S.C.) 31.29.02.30-P6000CFP-000-PV
Clean Fuels Project 2020 REV I, 27 Aug 2013
KNPC Contract No. NRP/PMC-0001/CNSL Page 16 of 24
Fluor Project No. A2WD

Project Variation

9. SPECIFIC PUMP TYPES

9.1 Single stage overhung pumps

9.1.1 Horizontal (Type OH2) Single stage overhung pumps


9.1.1.4 ADD TO THIS CLAUSE
Overhung pumps with impeller peripheral velocities exceeding 81 m/sec (265 ft/sec) are not
acceptable.

Single stage overhung pumps shall meet the following maximum L3/D4 values:
L = Distance in mm (in.) from the centerline of the impeller to the centerline of the first radial bearing.
D = Shaft Diameter in mm (in) at the seal chamber.

Single Volute Pumps: L3/D4 maximum value is 3560 (140).

Double Volute Pumps:


Discharge Nozzle Size mm Maximum Impeller Diameter mm L3/D4 Maximum
(in) (in)
80 (3) 432 (17) 2550 (100)
100 (4) 660 (26) 2550 (100)
150 (6) 660 (26) 2030 (80)
200 (8) 660 (26) 2030 (80)
250 (10) 660 (26) 1015 (40)
300 (12) 660 (26) 760 (30)
350 (14) 660 (26) 500 (20)
400 (16) 740 (29) 500 (20)

9.1.2 Vertical In-line (Type OH3) pumps


9.1.2.2 ADD TO THIS CLAUSE
Vertical in-line pumps shall be provided with a baseplate with anchor-bolt holes.
9.1.2.9 ADD THIS CLAUSE
The requirements stated in 9.1.1.4 above for OH2 pumps for impeller peripheral velocity and for
maximum L3/D4 values also apply to type OH3 pumps.
9.1.3 Integral gear driven (Type OH6) pumps
ADD NEW CLAUSE

31.29.02.30-P6000CFP-000-PV_I.DOC
Kuwait National Petroleum Company (K.S.C.) 31.29.02.30-P6000CFP-000-PV
Clean Fuels Project 2020 REV I, 27 Aug 2013
KNPC Contract No. NRP/PMC-0001/CNSL Page 17 of 24
Fluor Project No. A2WD

Project Variation

9.1.3.9 All OH6 type pumps shall be supplied with a start-up pre-lube pump which will be
interlocked with the main motor drive, to provide pre-lube to the gearbox, before startup.
The pre-lube pump shall be supplied by the pump manufacturer.

9.2 Between-bearing pumps (types BB1 to BB5)


9.2.4 Dynamics
9.2.4.1 Lateral analysis
9.2.4.1.2 REPLACE THE FIRST SENTENCE OF THIS CLAUSE BY:
The first wet critical speed for multistage pumps shall be at least 20% above the pump maximum
continuous speed. Pump rotors shall be classically stiff. Seller shall perform and provide a lateral
analysis on all multistage between bearing pumps with variable speed drivers.

9.2.7 Testing
9.2.7.5 ADD TO THIS CLAUSE:
Hydrodynamic radial bearings shall be removed (rolled out, bearings are not disassembled), inspected
by the Buyer or his representative, and re-placed after the performance test is complete. Any galling
or metal transfer, or rubs which result in grooving or heat discoloration will be cause for rejection.
The dressing of these surfaces by filing, honing, sanding, or any other polishing method without
resolving the cause is unacceptable. The cause must be determined, the bearing repaired and the
pump successfully retested and disassembled for inspection before final acceptance and release for
shipment. Minor scuffs and scratches and minor cosmetic repairs to these is not a cause for retest.

9.3 Vertically-suspended pumps


9.3.1 General
9.3.1.3 REPLACE SHELL DEP 31.29.02.30-Gen REQUIRMENT WITH THE FOLLOWING
Vertically suspended pumps shall meet the following requirements:

a. Bowls shall be flanged, have metal-to-metal rabbeted fits and be bolted with studs and nuts.
Stacked bowls secured by tie bolting and threaded bowls are not acceptable.

b. Column sections shall be flanged and piloted, incorporate bearing spiders and rabbeted fits for all
column sizes, and be bolted with studs and nuts. Integral bearing spiders shall be furnished with
replaceable inserts in the bearing retainer.

c. All pump discharge column pipe sections shall be flanged with a rabbet fit for proper alignment.
ADD NEW CLAUSE:
9.3.1.4 Double casing vertically suspended pumps shall have the suction and discharge nozzles located above
the mounting flange, with centerlines on the same elevation and 1800 apart.

ADD NEW CLAUSE:

9.3.1.5 Vertical, single casing pumps type VS-1, VS-2, VS-3, VS-4 and VS-5 shall be provided with a
cylindrical basket type strainer attached to the inlet nozzle or bell. Openings in the strainer shall be
31.29.02.30-P6000CFP-000-PV_I.DOC
Kuwait National Petroleum Company (K.S.C.) 31.29.02.30-P6000CFP-000-PV
Clean Fuels Project 2020 REV I, 27 Aug 2013
KNPC Contract No. NRP/PMC-0001/CNSL Page 18 of 24
Fluor Project No. A2WD

Project Variation

small enough to prevent the intake of solid particles that might damage the pump. The material of the
strainer shall be type 316 stainless steel. Other materials may be used if dictated by the pumping
service and approved by the Principal.

9.3.3 Rotors
9.3.3.2 ADD TO THIS CLAUSE:
When 2 piece or more shafts are approved and supplied, shaft couplings shall be keyed.

9.3.5 Dynamics
ADD TO THIS CLAUSE:
Seller shall submit an analysis of the structure and acceptance criteria for Buyer's review prior to
fabrication of pump.

9.3.8 Accessories
9.3.8.3 Mounting plates
9.3.8.3.5 REPLACE SHELL DEP REQUIRMENT WITH THE FOLLOWING:
Mounting plates shall be supplied. The plate shall be at least 50 mm (2 in) thick. The mounting plate
shall be drilled and tapped holes for mounting the pump, and the corresponding fasteners. The
mounting plate shall be supplied with a minimum of 4 anchor bolt holes, through-drilled, for securing
the mounting plate to the foundation. Anchor bolts will be furnished by the purchaser. If required,
grout holes and vent holes shall be provided. The bottom side and sides of the mounting plate (which
will be in contact with the grout) shall be sandblasted to SSPC SP 10 and coated with epoxy primer.
The top surface (and bottom surface of pump plate) unpainted and coated with a rust inhibitor.
1. The mounting plate shall be provided with vertical levelling screws at least 13 mm (0.5 in) in
diameter and at least 150 mm (6 in) long. Vertical levelling screws shall be located adjacent to
each anchor bolt (minimum 4) location. Corners of mounting plates shall be rounded to a radius of
at least 50 mm (2 in).
2. All vertical VS6 and VS7 type pumps in hydrocarbon service shall be supplied with an independent
liner. The liner shall be designed to be installed directly in concrete and shall be robust enough to
act as the inner form for concrete, as shown in Figure I-2.
9.3.10 Single-case diffuser (VS1) and volute (VS2) pumps
9.3.10.5 ADD TO THIS CLAUSE:
Line shafting shall not be furnished with sleeves under the bearings.
9.3.13 Double-casing diffuser (VS6) and volute (VS7) pumps
ADD TO THIS CLAUSE:
9.3.13.2 The inner casings of Types VS6 and VS7 pumps shall be hydrostatically tested at 1.5 times their
MAWP.

10 Vendor’s Data
10.3 Contract Data
10.3.2.1 ADD TO THIS CLAUSE:
31.29.02.30-P6000CFP-000-PV_I.DOC
Kuwait National Petroleum Company (K.S.C.) 31.29.02.30-P6000CFP-000-PV
Clean Fuels Project 2020 REV I, 27 Aug 2013
KNPC Contract No. NRP/PMC-0001/CNSL Page 19 of 24
Fluor Project No. A2WD

Project Variation

The dimensional outline drawing shall indicate a maximum fabrication tolerance of +/- 3 mm (1/8 in)
for pump suction and discharge nozzle face or centerline locations, referenced from the centerline of
the nearest baseplate anchor bolt hole. The same criteria applies to turbine inlet and exhaust nozzles
locations. The centerline of baseplate anchor bolt hole locations shall indicate a fabrication tolerance
of +/- 3 mm (1/8 in) from a common reference point on the baseplate.
Seller shall be required to add to his drawings all notes and data requested by Buyer including
equipment item numbers of various components, connection points, and locations, instrumentation,
and other data as required by Buyer.

10.3.2.2 ADD TO THIS CLAUSE:


Performance test curve shall be reviewed and given written approval by the Principal prior to the
pump being released for shipment.

10.3.4.2 ADD TO THIS CLAUSE:


Upon request, a list of interchangeable spare parts shall also be provided. This list shall include all
equipment furnished by the Seller for the Project as well as any Seller's existing equipment at Project
jobsite location.

10.3.5.3 ADD TO THIS CLAUSE:


Seller shall furnish lubrication data prior to issuance of the Operating, Maintenance, and Technical
Data Manual.

ANNEX G - MATERIALS CLASS SELECTION GUIDANCE


SHELL DEP requirement is not applicable for this point.
ANNEX H - MATERIALS AND MATERIAL SPECIFICATIONS FOR CENTRIFUGAL PUMP PARTS
SHELL DEP requirement is not applicable for this point.
Table H-1 - Materials for Pump Parts
REPLACE: Material Classes S-1 through S-4 shall use AISI 4140 for shafting.
ANNEX L - VENDOR DRAWING AND DATA REQUIREMENTS
DESCRIPTION
Pump
Z. ADD Completed ISA (Instrument Society of America) data sheets shall be furnished by the vendor as
contract data for review.

31.29.02.30-P6000CFP-000-PV_I.DOC
Kuwait National Petroleum Company (K.S.C.) 31.29.02.30-P6000CFP-000-PV
Clean Fuels Project 2020 REV I, 27 Aug 2013
KNPC Contract No. NRP/PMC-0001/CNSL Page 20 of 24
Fluor Project No. A2WD

Project Variation

PART IV PUMPS FOR VITAL SERVICE AND UNSPARED PUMPS FOR ESSENTIAL SERVICE
(AMENDMENTS/SUPPLEMENTS TO ISO 13709)

8. INSPECTION, TESTING AND PREPARATION FOR SHIPMENT

8.3 Testing
8.3.3 Performance test
8.3.3.2 DELETE “When Specified” FROM SHELL DEP
8.3.4 Optional Tests
8.3.4.4 Complete unit test
DELETE “When specified” FROM SHELL DEP

31.29.02.30-P6000CFP-000-PV_I.DOC
Kuwait National Petroleum Company (K.S.C.) 31.29.02.30-P6000CFP-000-PV
Clean Fuels Project 2020 REV I, 27 Aug 2013
KNPC Contract No. NRP/PMC-0001/CNSL Page 21 of 24
Fluor Project No. A2WD

Project Variation

PART V REFERENCES

ADD TO THIS PART:

In this PV, reference is made to the following publications:


NOTES: 1. Unless specifically designated by date, the latest issue of each publication shall be used together with any
amendments/supplements/revisions/project variations thereto.

SHELL STANDARDS AND PROJECT VARIATIONS


Non-metallic materials – Selection and application DEP 30.10.02.13-Gen
Metallic materials - prevention of brittle fracture 30.10.02.31-P6000CFP-000-PV
Noise control DEP 31.10.00.31-Gen.
Manual Pumps-Type Selection 31.29.02.11-P6000CFP-000-PV
Petroleum and natural gas industries – high-speed 31.29.00.32-P6000CFP-000-PV
special purpose gear units
Shaft sealing systems for centrifugal and rotary 31.29.00.33-P6000CFP-000-PV
pumps (amendments/supplements to API 682)
Flexible couplings for mechanical power 31.29.00.36-P6000CFP-000-PV
transmission - special purpose applications
Data sheets for centrifugal pumps 31.29.02.93-H-P6000CFP-000-PV
31.29.02.93-V-P6000CFP-000-PV
Lubrication, shaft-sealing and control oil systems and 31.29.60.32-P6000CFP-000-PV
auxiliaries for petroleum, chemical and gas industry
services (amendments/supplements to API 614)
Instrumentation for equipment packages 32.31.09.31-P6000CFP-000-PV
Electric machines - cage-induction types 33.66.05.31-P6000CFP-000-PV
(amendments/ supplements to IEC 60034-1)
Guide for the selection of jointing MESC INF 85/115
Recommended packing makes and styles MESC SPE 85/200
AMERICAN STANDARDS
Standard specification for castings, iron-chromium- ASTM A 890
nickel-molybdenum corrosion-resistant, duplex
(austenitic/ferritic) for general application
Issued by:
American Society for Testing and Materials
1916 Race Street, Philadelphia
19103, USA

BRITISH STANDARDS
Noise procedure specification EEMUA 140

31.29.02.30-P6000CFP-000-PV_I.DOC
Kuwait National Petroleum Company (K.S.C.) 31.29.02.30-P6000CFP-000-PV
Clean Fuels Project 2020 REV I, 27 Aug 2013
KNPC Contract No. NRP/PMC-0001/CNSL Page 22 of 24
Fluor Project No. A2WD

Project Variation

Recommendations for the protection of diesel EEMUA 107


engines for use in zone 2 hazardous areas
Issued by:
Engineering Equipment and Materials Users Association.
45 Beech Street
London EC2Y 8AD
UK

31.29.02.30-P6000CFP-000-PV_I.DOC
Kuwait National Petroleum Company (K.S.C.) 31.29.02.30-P6000CFP-000-PV
Clean Fuels Project 2020 REV I, 27 Aug 2013
KNPC Contract No. NRP/PMC-0001/CNSL Page 23 of 24
Fluor Project No. A2WD

Project Variation

APPENDIX 1 MATERIAL SELECTION


SHELL DEP shall not be applied in this appendix

31.29.02.30-P6000CFP-000-PV_I.DOC
Kuwait National Petroleum Company (K.S.C.) 31.29.02.30-P6000CFP-000-PV
Clean Fuels Project 2020 REV I, 27 Aug 2013
KNPC Contract No. NRP/PMC-0001/CNSL Page 24 of 24
Fluor Project No. A2WD

Project Variation

ADD NEW ANNEX


Annex P (Normative)
Scope of Inspection and Testing

Witnessed By
Description By Vendor Remarks
Contractor Company
1. Chemical & Physical Properties of √ In accordance with
Pump Parts this PV
2. NDE of Pump Parts √   In accordance with
this PV
3. Dynamic Balancing √  
4. Residual Unbalance Test √   If required by API
5. Hydrostatic Test √ √ 
6. Performance Test √ √ √
7. Performance Test of Spare Rotor √ √ √
and Inner Casing Assemblies
8. NPSH Test √ √ √ If required by this
PV
9. Complete Unit Test including 4- √ √ √
Hour Mechanical Run Test
10. Inspection of Hydrodynamic √ √ √
Bearings after Test
11. Shop Verification of Unbalance √ √ √ If required by this
Response Analysis PV
12. Sound Level Test √ √ √
13. Bearing Housing Resonance Test √ √ √ If Driver > 150kW
for Single-stage Overhung Pumps
14. Resonance Test for Vertically √ √ √
Suspended Pumps
15. Visual and Dimensional Inspection √ √ √
16. Painting Inspection √ √ √
17. Final Inspection √ √ √