Professional Documents
Culture Documents
R. L. Puro
Mill Superintendent,
L. M. Ames
The Thompson Mill
Mill Engineer,
The International Nickel Company Annual General Meeting, Montreal, April, 1964
of Canada, Ltd.,
Manitoba Division fransactions, Volume LXVll, 1964, pp. 243-248
ABSTRACT Introduction
HE Thompson mill began ·operating in 1960 and
The Thompson mill of The International Nickel Com-
pany of Canada, Limited, began operating in 1960, treat-
ing a sulphide ore having a copper-to-nickel ratio of ap-
T is now milling at a rate of 6,000 tons per day.
Its maximum rated capacity is 6,600 tons per day,
proximately 1 to 15. and this can be doubled without major additions or
Ore is crushed in an underground jaw crusher, set at structural alterations to the existing building. The
6 inches, and hoisted directly into the mill's coarse ore
bins. It is crushed to 1-in. size in cone crushers, and general flowsheet is shown in Figure 1.
ground to 65 mesh in a rod and pebble mill grinding cir- Ore is crushed, ground and subjected to a froth
cuit. The ground ore is then subjected to froth flotation,
producing a nickel concentrate, a copper concentrate and flotation process, producing a nickel concentrate,
sand fill. The nickel concentrate is pumped to the smelter. a copper concentrate and tailing. The nickel con-
The copper concentrate is dewatered, dried and shipped centrate is pumped to the smelter for dewatering
to Copper Cliff. Sand recovered from the flotation tailings and further processing. The copper concentrate is
is used as fill material underground, and the slime frac-
tion is pumped to the disposal area. dewatered, dried and loaded into box cars for ship-
MINE HOIST
~
ORE BIN
~
WASTE SLIMES TAILINGS OISPOSA.l
' AREA
~OCK SCREENS
(,
TRIPPER CONVEYOR
~~---!..__
l -i SA.ND
' ~')RUNS
EJ H
FINE
ORE BIN
FINE
ORE BIN
l 8f01 SHORT HEAD
CONE CRUSHERS
z
0
~
UNDERGROUND
BACKFILL
lrntl l
®®® SCAVENGERS
CONE
llJ
CLASSIFIERS
NICKEL
CONCENTRATE
TO SMELTER
THICKENER
fl
SECTION THROUGH CRUSHERS SECTION THROUGH FINE ORE BINS, Mill AISLE & FLOTATION AREA
(1) Coarse ore from the Thompson mine (15) Conveyor to fine ore mills
(2) Coarse ore from outside source (16) Grinding mill
(3) Thompson coarse ore bin (17) Mill discharge sump
(4) Outside coarse ore bin (18) Cyclone classifiers
(5) Belt feeders (19) 10-ton hoist
(6) 6- by 14-ft. screen (20) 35-ton crane
(7) 7-ft. standard crusher (21) Flotation head sump
(8) 5- by 8-ft. screen (22) Pulp distributor
(9) 7-ft. short-head crusher (23) Scavenger ce'lls
(10) Collecting conveyor (24) Rougher flotation cells
(11) Conveyor to fine ore bins (25) Copper flotation cells
(12) Tripper (26) Nickel concentrate sump
(13) Fine ore bin (27) Flotation tailing sump
(14) Feeders to conveyor (28) 5-ton crane
Sandfill Recovery
Flotation tailing is deslimed in a three-stage cy-
clone classifier circuit and used as fill material un-
derground. The slimes are pumped to the tailing
disposal area. Maximum sand recovery is essential
because of the low ratio of concentration. Sand re-
eovery is 84 per cent, and the percolation rate is
in excess of 4 inches per hour. The screen analyses
appear in Table VI.
Sand is stored in a steel tank with a capacity of
2,300 dry tons. The tank overflow, containing slimes,
is decanted to the waste sump. The tank has three
outlets, from which the rate of pour is regulated by
4-in. rubber flex valves. Water spigots in the dis-
charge line permit pulp density control - general-
ly 50 to 60 per cent solids by weight. Water jets are
located around each pouring outlet to control hang-
up. Sand is poured underground through 5.875-in.
bore holes connected to 6.0-in. reinforced rubber
hoses. Figure 8.-A centrifugal separator.