Form: IRDP

Original : October, 2009AD


Remade : August, 2016AD
Remade : December, 2016AD
1st Revised: August, 2020AD

Government of People’s Republic of Bangladesh


Ministry of Water Resources

Revised Development Project Proposal (IRDP)

Re-excavation of Kumar River (1st Revised)


Revised development Project Table/Proposal (IRDP)
(For Full GOB Financing Project)

1.0 Project Headline Re-excavation of Kumar River (1st Revised)


2.1 Entrepreneurial Ministry of Water Resources/ Bangladesh Water
Ministry/Division Development Board
2.2 Implementing Agency Ministry of Water Resources/ Bangladesh Water
Development Board
2.3 The concerned Department of Agriculture, Water and Palasni
department of the Institutions
Planning Commission
3.0 Project objectives and goals (Including beneficiaries):
(Must be written in the form of bullets points. Must include
Amount/Percentage)
 The main objective of the Project is the
development of drainage system, flood control
and navigability system of 23580 hector area
by re-excavation of 72,700 km with excavator
and 57,931 km with dredger of Kumar River.
 To create opportunity for navigation.
 Reduce poverty in project areas by improving
farm / land development and creating
employment opportunities through
development of water resources management
4.0 Project’s implementation
period

DPP type Project Starting date Project Ending date


Original July/2016 December/ 2016
Revised (1st) July/2016 June/2022
5.1 Estimated cost of the Project (in Lakh)

Original Revised Revised Difference


Approved Estimated Estimated (3-2/4-3)
Cost cost (1st cost (2nd
Revised) Revised) In Tk. In percent
1 2 3 4 5 6
Total 25081.67 26313.56 - 1231.89 4.91
GOB 25081.67 26313.56 -
Own money - - - - -
Other (Must - - - - -
include)
5.2 Type and source of funding (in lakhs)
Source
GOB Own Financing Other
Type
(Foreign Currency) (Foreign Currency) (Must Include)
1 2 3 4
Loan - - -
Grants 26313.56 (0.00) - -
Equity - - -
Others(Must include) - - -
Total 26313.56 - -
5.3 Foreign Exchange rate (source: Bangladesh Bank) : Not applicable

6.0 Project’s year-wise amount of money (in lakh)

Fiscal Year Project Cost


Revisions GOB Own money (Foreign Others Total
(Foreign Currency)
Currency)
Year-1 (2016- 1st revised 24.24 - - 24.24
17) (0.00) (0.00)
Original 7532.93 - - 7532.93
(0.00) (0.00)
Year-2 (2017- 1st revised 1342.78 - - 1342.78
18) (0.00) (0.00)
Original 9553.64 - - 9553.64
(0.00) (0.00)
Year-3 (2018- 1st revised 2483.40 - - 2483.40
19) (0.00) (0.00)
Original 7995.10 - - 7995.10
(0.00) (0.00)
Year-4 (2019- 1st revised 2994.31 - - 2994.31
20) (0.00) (0.00)
Original 0.00 - - 0.00 (0.00)
(0.00)
Year-5 (2020- 1st revised 7966.50 - - 7966.50
21) (0.00) (0.00)
Original 0.00 - - 0.00 (0.00)
(0.00)
Year-6 (2021- 1st revised 11422.33 - - 11422.33
22) (0.00) (0.00)
Original 0.00 - - 0.00 (0.00)
(0.00)
Total 1st revised 26313.56 - - 26313.56
(0.00) (0.00)
Original 25081.67 - - 25081.67
(0.00) (0.00)
7.0 Project Area:

Division District Sub-district/City


Corporation/Municipality
Original Revised Original Revised Original Revised
1 2 3 4 5 6
Dhaka Dhaka Faridpur Faridpur Faridpur Sadar, Faridpur Sadar,
Vanga, Saltha, Vanga, Saltha,
Nagarkanda and Nagarkanda and
Bowalmari Bowalmari

10. Financial and economic analysis (Financial and economic analysis included)
0 (Accounts must be attached)
10. Net Project Value (NPV)
1
(1) Financial Tk. : 19484.13 lakh
(2) Economical Tk. : 16366.54 lakh
10. Benefit Cost Ratio (BCR))
2
(1) Financial 2.24:1.00
(2) Economical 2.06.100
10. Internal Rate of Returns (IRR)
3
(1) Financial 51.98%
(2) Economical 43.28%
11. The reason for the project revision  The project titled "Excavation of Kumar
0 must be explained logically River" was approved by ECNEC on
10/11/2018. In order to implement the
physical works of the project in DPM
method, the contract was executed on
04-02-2018 AD after giving work order
to Dockyard Road and Engineering
Works Ltd. of Bangladesh Navy on 10-
01-2017 AD. The contract value of the
physical works of the project is Rs.
According to the agreement, the
implementation of the project at the field
level was started from 11-02-2018 AD. It
is to be noted that after the approval of
the project, there has been a delay of
about 1 year and 3 months to start the
work in DPM system at the field level.
Moreover, although the project was
approved on 10.11.2018, the
implementation period has been seen to
start from 01 July 2018, so much so that
more than 4 months have been included
in the implementation period. Excavator
mobilization for river / canal re-
excavation work in Faridpur city area
was started by the excavator by
February / 18 after the agreement.
Dredging work was also started by 2
dredgers (1 18 '' and 1 20 ") from
November 2016. However, due to early
rains in 2016, the progress of river re-
excavation work by excavators has been
hampered. It was not possible to take it
to the desired level. In addition,
numerous illegal installations on both
the banks of the river / canal have
hampered the progress of the work due
to dredged material management
problems in the river dredging work and
the progress of the work could not be
taken to the desired level. Except for the
increase, it is reported to be 31.12.2020
AD. But since last March, 2020, due to
the outbreak of Bangladesh Global
Epidemic Corona Virus, the government
has announced lockdown and ban on
public movement in various places and
all mining projects in the project area.
They left and went to their respective
homes, so it was not possible to achieve
the desired target even during the time
described in the project . As at least 2
more dry seasons are required to carry
out the remaining physical works under
the project, a proposal has been sent to
describe the period till June, 2022 AD.
 Under the approved DPP project,
dredging works ranging from 16.80 km
to 61.010 km and 54.510 km are
available in Kumar river chain. However,
after the approval of the project, BIWTA
has carried out dredging work on the
chain of Kumar River from 50.98 km to
61.010 km and 20.033 km. As a result,
the revised length of Kumar River
dredging in the project described is
34.46 km.

12. The cumulative cost of the project and 6844.78 lakh Taka (45%) (till 09.08.2020
0 the actual progress (%) must be paid (up AD)
to date) (in lakhs).

13.0 Log Frame:

Brief description Objective verification Through verification Important


indicator Hypothesis
Program’s Goal:  Reducing the risk of  Five Year Wari
 Achieving lasting flood and National Rolling Plan
development of the waterlogging through Evaluation Report.
project area. proper water  National Environment
 Protecting life and management. Report.
property from flood.  Ensuring the safety of  Local/National
 Reviving small human and natural Business report.
economy. resources.  BBS Report.
 Reviving business
activities.
Project’s Objective:  Ensuring the safety of
 Reducing the risk of human and natural
flood and waterlogging resources due to flood
and increasing and waterlogging.
navigability  Improving cropping
 Ensuring the protection Intensity from
important archeological 154.16% to 178.08%.
building.  Development of
 Development of Fisheries
sustainable socio-  Financial: 51.98%
economic system  Economic: 43.28%
Output: Construction work to be
completed on June 30,
2022AD:
 Re-excavation of source  1.42 km
of Kumar river
 Re-excavation of Kumar  3.935 km
river
 Dredging on the Kumar  38.891 km
River
 Mandartala canal re-  9.095 km
excavated
 Re-excavation of Mara  58.25 km
Kumar river
 Dredging of Mara  19.04 km
Kumar river
 Building Regulator  1
 RCC ghats and girls'
changing houses  61
 Walkway and related
beautification work  3500 km
Input:

 Removal of soil by re-


excavation
 Removal of soil by
dredging
 Regulator
 Skilled manpower and
manpower
 Pre-construction
activities
 Recruitment of
qualified engineers and
other officers