Professional Documents
Culture Documents
It
likewise prays that the October 25, 2006
Decision[4] of the CIAC Arbitral Tribunal be
1) G.R. No. 192725 August 9, 2017 CE reinstated.
Construction Corporation vs. Araneta
Center Inc The CIAC Arbitral Tribunal October 25, 2006
Decision awarded a total sum of
P217,428,155.75 in favor of petitioner CE
Construction Corporation (CECON). This sum
[ G.R. No. 192725, August 09, 2017 ] represented adjustments in unit costs plus
CE CONSTRUCTION CORPORATION, interest, variance in take-out costs, change
PETITIONER, VS. ARANETA CENTER INC., orders, time extensions, attendance fees,
RESPONDENT. contractor-supplied equipment, and costs of
arbitration. This amount was net of the
DECISION countervailing awards in favor of respondent
LEONEN, J.: Araneta Center, Inc. (ACI), for defective and
A tribunal confronted not only with ambiguous incomplete works, permits, licenses and other
contractual terms but also with the total absence advances.[5]
of an instrument which definitively articulates
the contracting parties' agreement does not act in The assailed Court of Appeals April 28, 2008
excess of jurisdiction when it employs aids in Decision modified the CIAC Arbitral Tribunal
interpretation, such as those articulated in October 25, 2006 Decision by awarding a net
Articles 1370 to 1379 of the Civil Code. In so amount of P82,758,358.80 in favor of CECON.
[6]
doing, a tribunal does not conjure its own The Court of Appeals July 1, 2010 Amended
contractual terms and force them upon the Decision adjusted this amount to
parties. P93,896,335.71.[7]
After mediation failed, an arbitral tribunal was The CIAC Arbitral Tribunal noted that while
constituted through a March 16, 2005 Order of ACI's initial invitation to bidders was for a
the CIAC. It was to be composed of Dr. Ernesto lump-sum design-and-construct arrangement,
S. De Castro, who acted as Chairperson with the way that events actually unfolded clearly
Engr. Reynaldo T. Viray and Atty. James S. indicated a shift to an arrangement where the
Villafranca as members.[54] designs were contingent upon ACI itself.
Considering that the premise for CECON's
ACI filed a Motion for Reconsideration of the August 30, 2002 lump-sum offer of
CIAC March 16, 2005 Order. This was denied in P1,540,000.00 was no longer availing, CECON
the Order dated March 30, 2005. [55] was no longer bound by its representations in
respect of that lump-sum amount. It may then
In the Order dated April 1, 2005, the CIAC claim cost adjustments totalling P16,429,630.74,
Arbitral Tribunal set the preliminary conference as well as values accruing to the various change
on April 13, 2005.[56] orders issued by ACI, totalling P159,827,046.94.
[61]
The Court of Appeals held ACI liable to On the CIAC Arbitral Tribunal's award for
CECON for the sum of P12,672,488.36 for overhead costs and profits under day work, the
miscellaneous change orders, which it construed Court of Appeals held that it was improper to
to be "separate contracts that have been entered grant this award based on stipulations on day
into at the time [ACI] required them."[79] It works pertaining "only to 'materials' and not to
likewise held ACI liable for P1,132,946.17 equipment."[87]
representing the balance of 12 other partially
paid change orders.[80] Finally, the Court of Appeals held that CECON
was not entitled to costs of litigation considering
The Court of Appeals noted that CECON was that "no premium is to be placed on the right to
not entitled to time extensions because the litigate"[88] and since ACI could not be faulted
arrangement between ACI and CECON had for delays.
never been altered. Consequently, it was not
entitled to acceleration co ts, additional The dispositive portion of the assailed Court of
overhead, ru1d reimbursement for extending the Appeals April 28, 2008 Decision read:
Contractor's All Risk Insurance.[81] Conversely, WHEREFORE, based on all the foregoing, the
the Court of Appeals held CECON liable for Decision of the Arbitral Tribunal is modified as
delays thereby entitling ACI to liquidated follows:
damages corresponding to 10% of the supposed
contract sum of P1,540,000,000.00, or a. AWARD TO CECON
P15,400,000.00.[82]
NO. ISSUE Pesos (PHP)
Also on account of the supposed lump-sum Cost
1 10,266,628.00
arrangement, the Court of Appeals held that Adjustment
CECON was not entitled to attendance fees on Take Out
contract amounts increased by change order 2 Cost of 3,811,289.70
works.[83] It also stated that the rate for Equipment
attendance fees, overhead, and profit for
Change
subcontractors' works remained subject to the 3 99,119,200.09
Orders
original contract documents based on ACI's
original invitation to bidders and had never been a. Approved
altered.[84] Change 1,132,946.17
Orders
Regarding attendance fees, the Court of Appeals b. [Schematic
proffered that the work attributed to Drawings] to
80,108,761.60
subcontractors was merely work done by [Construction
CECON itself, thereby negating the need for Drawings]
attendance fees.[85] c. 12,672,488.30
Miscellaneous
Concerning take-out costs, the Court of Appeals
Change I - AWARD:
Orders
a. AWARD TO CE CONSTRUCTION, INC.
d. Change
5,205,004.02
Order No. 11 NO. ISSUE PESOS (PhP)
Equipment Additional costs spent on
[4]
Supplied by 1,127,486.50 1 10,266,628.00
rebars.
Owner
Increase in the costs of
114,324,605.00 cement and formworks
Total 2 5,205,004.02
(sic) falling under cost-bearing
b. AWARD TO ARANETA change.
NO. ISSUE Pesos (PHP) Representing
undervaluation of
[5] Liquidated 3 respondent's works in the1,209,782.50
15,400,000.00
Damages supply and installation of
Defective and G.I. sheets.
[6]
Incomplete 3,000,000.00 Representing Miscellaneous
Works 4 27,601,469.32
Change Orders.
Bookmarking
6,980,000.00 5 Drilling of Holes 4,543,450.00
Granite Tiles
Permits, Licenses [Schematic Drawings] to
6 80,108,761.60
[7]
and Other 6,186,246.23 [Construction Drawings]
Advances [7] Installation of equipment
1,127,486.50
31,566,246.20 supplied by owner.
Total
(sic) TOTAL 130,062,581.94
In addition, CECON is directed to submit all
required. close-out documents within thirty (30) b. AWARD TO ARANETA CENTER, INC.
days from receipt of this Decision. 1 Liquidated Damage (sic) 20,000,000.00
The parties shall bear their own costs of Defective and Incomplete
2 3,000,000.00
arbitration and litigation. Works
Bookmarking Granite
3 6,980,000.00
SO ORDERED.[89] Tiles
Acting on CECON's Motion for Permits, Licenses and
Reconsideration, the Court of Appeals issued its 4 6,186,246.23
other Advances
Amended Decision on July 1, 2010.[90] This
Amended Decision increased the award for TOTAL 36,166,246.23
miscellaneous change orders to P27,601,469.32; II - COMPUTATION:
reinstated awards for undervalued works in AWARD TO CE
supplying and installing G.I. sheets worth 130,062,581.94
CONSTRUCTION, INC.
P1,209,782.50[91] and for the drilling of holes
and application of epoxy worth P4,543,456.00; LESS
[92]
and deleted the award for takeout costs.[93] AWARD TO ARANETA
36,166,246.23
CENTER, INC.
The dispositive portion of the assailed Court of
Appeals July 1, 2010 Amended Decision read: BALANCE PAYABLE
WHEREFORE, Our Decision dated 28 April BY ARANETA TO93,896,335.71
2008 is hereby modified as follows: CECON
matter of the characterization of the contract
SO ORDERED.[94] between CECON and ACI. Upon its
Aggrieved at the Court of Appeals' ruling, characterization of the contract as one for a
CECON tiled the present Petition insisting on lump-sum fixed price, the Court of Appeals
the propriety of the CIAC Arbitral Tribunal's deleted much of the CIAC Arbitral Tribunal's
conclusions and findings.[95] It prays that the monetary awards to CECON and awarded
assailed Court of Appeals decisions be reversed liquidated damages to ACI.
and that the CIAC Arbitral Tribunal October 25,
2006 Decision, as modified by its December 28, On initial impression, what demands resolution
2006 Order, be reinstated.[96] is the issue of whether or not the Court of
Appeals erred in characterizing the contractual
ACI counters that the Court of Appeals July 1, arrangement between petitioner CE Construction
2010 Amended Decision must be upheld. [97] Corporation and respondent Araneta Center, Inc.
as immutably one for a lump-sum fixed price.
ACI insists on the inviolability of its supposed
agreement with CECON, as embodied in the However, this is not merely a matter of applying
contract documents delivered to contractors and deriving conclusions from cut and dried
alongside the original offer to bid. It cites contractual provisions. More accurately, what is
specific provisions of these documents such as on issue is whether or not the Court of Appeals
valuation rules and required notices for correctly held that the CIAC Arbitral Tribunal
extensions and changes, reckoning of losses and acted beyond its jurisdiction in holding that the
expenses, the ensuing liquidated damages for price of P1,540,000,000.00 did not bind the
defects, cost-bearing changes and provisional parties as an immutable lump-sum. Subsumed in
sums,[98] which define parameters for permissible this issue is the matter of whether or not the
changes and for reckoning corresponding costs Court of Appeals correctly ruled that CECON
and liabilities. However, it did not attach any of was rightfully entitled to time extensions and
these documents to its Comment or that intervening circumstances had made ACI
Memorandum. It also cites statutory provisions- liable for cost adjustments, increases borne by
Articles 1715[99] and 1724[100] of the Civil Code- change orders, additional overhead costs,
on CECON's liabilities and the primacy of extended contractor's all risk insurance
stipulated contract prices.[101] coverage, increased attendance fees vis-a-vis
subcontractors, and arbitration costs which it
By the inviolability their agreement, ACI insists awarded to CECON.
on the supposed immutability of the stipulated
contract sum and on the impropriety of the This Court limits itself to the legal question of
CIAC Arbitral Tribunal in writing its own terms the CIAC Arbitral Tribunal's competence.
for ACI and CECON to follow.[102] It faults the Unless any of the exceptional circumstances that
CIAC Arbitral Tribunal for erroneously warrant revisiting the factual matter of the
reckoning the sums due to CECON, particularly accuracy of the particulars of every item
in relying on factual considerations that run awarded to the parties is availing, this Court
afoul of contractual stipulations and on bases shall not embark on its own audit of the amounts
such as industry practices and standards, which owing to each.
supposedly should not have even been I
considered as the parties have already adduced
their respective evidence.[103] It insists upon This Court begins by demarcating the
CECON's fault for delays and defects, making it jurisdictional and technical competence of the
liable for liquidated damages.[104] CIAC and of its arbitral tribunals.
I.A
Though nominally modifying the CIAC Arbitral
Tribunal October 25, 2006 Decision, the Court The Construction Industry Arbitration
of Appeals actually reversed it on the pivotal Commission was a creation of Executive Order
No. 1008, otherwise known as the Construction Republic Act No. 9184 or the Government
Industry Arbitration Law.[105] At inception, it was Procurement Reform Act, enacted on January
under the administrative supervision of the 10, 2003, explicitly recognized and confirmed
Philippine Domestic Construction the competence of the CIAC:
Board[106] which, in turn, was an implementing Section 59. Arbitration. - Any and all disputes
agency of the Construction Industry Authority of arising from the implementation of a contract
the Philippines (CIAP).[107] The CIAP is covered by this Act shall be submitted to
presently attached to the Department of Trade arbitration in the Philippines according to the
and Industry.[108] provisions of Republic Act No. 876, otherwise
known as the "Arbitration Law": Provided,
The CIAC was created with the specific purpose however, That, disputes that are within the
of an "early and expeditious settlement of competence of the Construction Industry
disputes"[109] cognizant of the exceptional role of Arbitration Commission to resolve shall be
construction to "the furtherance of national referred thereto. The process of arbitration shall
development goals."[110] be incorporated as a provision in the contract
that will be executed pursuant to the provisions
Section 4 of the Construction Industry of this Act: Provided, That by mutual agreement,
Arbitration Law spells out the jurisdiction of the the patties may agree in writing to resort to
CIAC: alternative modes of dispute resolution.
Section 4. Jurisdiction. - The CIAC shall have (Emphasis supplied)
original and exclusive jurisdiction over disputes Arbitration of construction disputes through the
arising from, or connected with, contracts CIAC was formally incorporated into the
entered into by parties involved in construction general statutory framework on alternative
in the Philippines, whether the dispute arises dispute resolution through Republic Act No.
before or after the completion of the contract, or 9285, the Alternative Dispute Resolution Act of
after the abandonment or breach thereof. These 2004 (ADR Law). Chapter 6, Section 34 of ADR
disputes may involve government or private Law made specific reference to the Construction
contracts. For the Board to acquire jurisdiction, Industry Arbitration Law, while Section 35
the parties to a dispute must agree to submit the confirmed the CIAC's jurisdiction:
same to voluntary arbitration. CHAPTER 6
ARBITRATION OF CONSTRUCTION
The jurisdiction of the CIAC may include but is DISPUTES
not limited to violation of specifications for
materials and workmanship; violation of the Section 34. Arbitration of Construction
terms of agreement; interpretation and/or Disputes: Governing Law. - The arbitration of
application of contractual time and delays; construction disputes shall be governed by
maintenance and defects; payment, default of Executive Order No. 1008, otherwise known as
employer or contractor and changes in contract the Construction Industry Arbitration Law.
cost.
Section 35. Coverage of the Law. - Construction
Excluded from the coverage of this law are disputes which fall within the original and
disputes arising from employer-employee exclusive jurisdiction of the Construction
relationships which shall continue to be covered Industry Arbitration Commission (the
by the Labor Code of the Philippines. "Commission") shall include those between or
Though created by the act of a Chief Executive among parties to, or who are otherwise bound
who then exercised legislative powers by, an arbitration agreement, directly or by
concurrently with the Batasang Pambansa, the reference whether such parties are project
creation, continuing existence, and competence owner, contractor, subcontractor, fabricator,
of the CIAC have since been validated by acts of project manager, design professional, consultant,
Congress, quantity surveyor, bondsman or issuer of an
insurance policy in a construction project.
Electronics v. Technology Electronics Assembly
The Commission shall continue to exercise and Management Pacific[113] distinguished
original and exclusive jurisdiction over construction arbitration, as well as voluntary
construction disputes although the arbitration is arbitration pursuant to Article 219(14) of the
"commercial" pursuant to Section 21 of this Act. Labor Code,[114] from commercial arbitration. It
I.B ruled that commercial arbitral tribunals are not
quasi-judicial agencies, as they are purely ad hoc
The CIAC does not only serve the interest of bodies operating through contractual consent
speedy dispute resolution, it also and as they intend to serve private, proprietary
facilitates authoritative dispute resolution. Its interests.[115] In contrast, voluntary arbitration
authority proceeds not only from juridical under the Labor Code and construction
legitimacy but equally from technical expertise. arbitration operate through the statutorily vested
The creation of a special adjudicatory body for jurisdiction of government instrumentalities that
construction disputes presupposes distinctive exist independently of the will of contracting
and nuanced competence on matters that are parties and to which these parties submit. They
conceded to be outside the innate expertise of proceed from the public interest imbuing their
regular courts and adjudicatory bodies respective spheres:
concerned with other specialized fields. The Voluntary Arbitrators resolve labor disputes and
CIAC has the state's confidence concerning the grievances arising from the interpretation of
entire technical expanse of construction, defined Collective Bargaining Agreements. These
in jurisprudence as "referring to all on-site works disputes were specifically excluded from the
on buildings or altering structures, from land coverage of both the Arbitration Law and the
clearance through completion including ADR Law.
excavation, erection and assembly and
installation of components and equipment."[111] Unlike purely commercial relationships, the
relationship between capital and labor are
Jurisprudence has characterized the CIAC as a heavily impressed with public interest. Because
quasi-judicial, administrative agency equipped of this. Voluntary Arbitrators authorized to
with technical proficiency that enables it to resolve labor disputes have been clothed with
efficiently and promptly resolve conflicts; quasi-judicial authority.
[The CIAC] is a quasi-judicial agency. A quasi-
judicial agency or body has been defined as an On the other hand, commercial relationships
organ of government other than a court and other covered by our commercial arbitratjon laws are
than a legislature, which affects the rights of purely private and contractual in nature. Unlike
private parties through either adjudication or labor relationships, they do not possess the same
rule-making. The very definition of an compelling state interest that would justify state
administrative agency includes its being vested interference into the autonomy of contracts.
with quasi-judicial powers. The ever increasing Hence, commercial arbitration is a purely private
variety of powers and functions given to system of adjudication facilitated by private
administrative agencies recognizes the need for citizens instead of government instrumentalities
the active intervention of administrative wielding quasi-judicial powers.
agencies in matters calling for technical
knowledge and speed in countless controversies Moreover, judicial or quasi-judicial jurisdiction
which cannot possibly be handled by regular cannot be conferred upon a tribunal by the
courts. The CIAC's primary function is that of a parties alone. The Labor Code itself confers
quasi-judicial agency, which is to adjudicate subject-matter jurisdiction to Voluntary
claims and/or determine rights in accordance Arbitrators.
with procedures set forth in E.O. No. 1008.[112]
The most recent jurisprudence maintains that the Notably, the other arbitration body listed in
CIAC is a quasi-judicial body. This Court's Rule 43 the Construction Industry Arbitration
November 23, 2016 Decision in Fruehauf Commission (CIAC) - is also a government
agency attached to the Department of Trade and utilized in the settlement of disputes if requested
Industry. Its jurisdiction is likewise conferred by by any of the parties or by the Arbitral Tribunal.
statute. By contrast, the subject matter If the request for an expert is done by either or
urisdiction of commercial arbitrators is by both of the parties, it is necessary that the
stipulated by the parties.[116](Emphasis supplied, appointment of the expert be confirmed by the
citations omitted) Arbitral Tribunal.
Consistent with the primacy of technical
mastery, Section 14 of the Construction Industry Whenever the parties request for the services of
Arbitration Law on the qualification of an expert, they shall equally shoulder the
arbitrators provides: expert's fees and expenses, half of which shall be
Section 14. Arbitrators. - A sole arbitrator or deposited with the Secretariat before the expert
three arbitrators may settle a dispute. renders service. When only one party makes the
request, it shall deposit the whole amount
.... required.
II
Arbitrators shall be men of distinction in whom
the business sector and the government can have Consistent with CIAC's technical expertise is the
confidence. They shall not be permanently primacy and deference accorded to its decisions.
employed with the CIAC. Instead, thy shall There is only a very narrow room for assailing
render services only when called to arbitrate. For its rulings.
each dispute they settle, they shall be given fees.
Section 8.1 of the Revised Rules of Procedure Section 19 of the Construction Industry
Governing Construction Arbitration establishes Arbitration Law establishes that CIAC arbitral
that the foremost qualification of arbitrators awards may not be assailed, except on pure
shall be technical proficiency. It explicitly questions of law:
enables not only lawyers but also "engineers, Section 19. Finality of Awards. - The arbitral
architects, construction managers, engineering award shall be binding upon the parties. It shall
consultants, and businessmen familiar with the be final and inappealable except on questions of
construction industry" to serve as arbitrators: law which shall be appealable to the Supreme
Section 8.1 General Qualification of Arbitrators. Court.
- The Arbitrators shall be men of distinction in Rule 43 of the 1997 Rules of Civil Procedure
whom the business sector and the government standardizes appeals from quasi-judicial
can have confidence. They shall be technically agencies.[118] Rule 43, Section 1 explicitly lists
qualified to resolve any construction dispute CIAC as among the quasi judicial agencies
expeditiously and equitably. The Arbitrators covered by Rule 43.[119] Section 3 indicates that
shall come from different professions. They may appeals through Petitions for Review under Rule
include engineers, architects, construction 43 are to "be taken to the Court of Appeals ...
managers, engineering consultants, and whether the affoeal involves questions of fact, of
businessmen familiar with the construction law, or mixed questions of fact and law." [120]
industry and lawyers who are experienced in
construction disputes. (Emphasis supplied) This is not to say that factual findings of CIAC
Of the 87 CIAC accredited arbitrators as of arbitral tribunals may now be assailed before the
January 2017, only 33 are lawyers. The majority Court of Appeals. Section 3's statement
are experts from construction-related professions "whether the appeal involves questions of fact,
or engaged in related fields. [117] of law, or mixed questions of fact and law"
merely recognizes variances in the disparate
Apart from arbitrators, technical experts aid the modes of appeal that Rule 43 standardizes: there
CIAC in dispute resolution. Section 15 of the were those that enabled questions of fact; there
Construction Industry Arbitration Law provides: were those that enabled questions of law, and
Section 15. Appointment of Experts. - The there were those that enabled mixed questions
services of technical or legal experts may be fact and law. Rule 43 emphasizes that though
there may have been variances, all appeals under is not an artifice for the parties to undermine the
its scope are to be brought before the Court of process they voluntarily elected to engage in. To
Appeals. However, in keeping with the prevent this Court from being a party to such
Construction Industry Arbitration Law, any perversion, this Court's primordial inclination
appeal from CIAC arbitral tribunals must remain must be to uphold the factual finqings of arbitral
limited to questions of law. tribunals:
Aware of the objective of voluntary arbitration
Hi-Precision Steel Center, Inc. v. Lim Kim Steel in the labor field, in the construction industry,
Builders, Inc.[121] explained the wisdom and in any other area for that matter, the Court
underlying the limitation of appeals to pure will not assist one or the other or even both
questions of law: parties in any effort to subvert or defeat that
Section 19 makes it crystal clear that questions objective tbr their private purposes. The Court
of fact cannot be raised in proceedings before will not review the factual findings of an arbitral
the Supreme Court - which is not a trier of facts tribunal upon the artful allegation that such
- in respect of an arbitral award rendered under body had "misapprehended the facts" and will
the aegis of the CIAC. Consideration of the not pass upon issues which are, at bottom,
animating purpose of voluntary arbitration in issues of fact, no matter how cleverly disguised
generaland arbitration under the aegis of the they might be as "legal questions." The parties
CIAC in particular, requires us to apply here had recourse to arbitration and chose the
rigorously the above principle embodied in arbitrators themselves; they must have had
Section 19 that the Arbitral Tribunal's findings confidence in such arbitrators. The Court will
of fact shall be final and unappealable. not, therefore, permit the parties to relitigate
before it the issues of facts previously presented
Voluntary arbitration involves the reference of a and argued before the Arbitral Tribunal, save
dispute to an impartial body, the members of only where a very clear showing is made that, in
which are chosen by the parties themselves, reaching its factual conclusions, the Arbitral
which parties freely consent in advance to abide Tribunal committed an error so egregious and
by the arbitral award issued after proceedings hurtful to one party as to constitute a grave
where both parties had the opportunity to be abuse of discretion resulting in lack or loss of
heard. The basic objective is to provide a speedy jurisdiction. Prototypical examples would be
and inexpensive method of settling disputes by factual conclusions of the Tribunal which
allowing the parties to avoid the formalities, resulted in deprivation of one or the other party
delay, expense and aggravation which of a fair opportunity to present its position
commonly accompany ordinary litigation, before the Arbitral Tribunal, and an award
especially litigation which goes through the obtained through fraud or the corruption of
entire hierarchy of courts. [The Construction arbitrators. Any other, more relaxed, rule would
Industry Arbitration Law] created an arbitration result in setting at naught the basic objective of
facility to which the construction industry in the a voluntary arbitration and would reduce
Philippines can have recourse. The arbitration to a largely inutile institution.
[123]
[Construction Industry Arbitration Law] was (Emphasis supplied, citations omitted)
enacted to encourage the early and expeditious Thus, even as exceptions to the highly restrictive
settlement of disputes in the construction nature of appeals may be contemplated, these
industry, a public policy the implementation of exceptions are only on the nanowest of grounds.
which is necessa and important for the Factual findings of CIAC arbitral tribunals may
realization of national development goals.[122] be revisited not merely because arbitral tribunals
Consistent with this restrictive approach, this may have erred, not even on the already
Court is duty-bound to be extremely watchful exceptional grounds traditionally available in
and to ensure that an appeal does not become an Rule 45 Petitions.[124] Rather, factual findings
ingenious means for und rmining the integrity of may be reviewed only in cases where the CIAC
arbitration or for conveniently setting aside the arbitral tribunals conducted their affairs in a
conclusions arbitral processes make. An appeal haphazard, immodest manner that the most basic
integrity of the arbitral process was imperiled. on the given set of circumstances. Once it is
In Spouses David v. Construction Industry and clear that the issue invites a review of the
Arbitration Commission:[125] evidence presented, the question posed is one of
We reiterate the rule that factual findings of fact.[128]
construction arbitrators are final and conclusive It further explained that an inquiry into the true
and not reviewable by this Court on appeal, intention of the contracting parties is a legal,
except when the petitioner proves affirmatively rather than a factual, issue:
that: (1) the award was procured by corruption, On the surface, the instant petition appears to
fraud or other undue means; (2) there was merely raise factual questions as it mainly puts
evident partiality or corruption of the arbitrators in issue the appropriate amount that is due to
or of any of them; (3) the arbitrators were guilty HRCC. However, a more thorough analysis of
of misconduct in refusing to postpone the the issues raised by FFCCl would show that it
hearing upon sufficient cause shown, or in actually asserts questions of law.
refusing to hear evidence pertinent and material
to the controversy; (4) one or more of the FFCCI primarily seeks from this Court a
arbitrators were disqualified to act as such under determination of whether [the] amount claimed
section nine of Republic Act No. 876 and by HRCC in its progress billing may be enforced
willfully refrained from disclosing such against it in the absence of a joint measurement
disqualifications or of any other misbehavior by of the former's completed works. Otherwise
which the rights of any party have been stated, the main question advanced by FFCCI is
materially prejudiced; or (5) the arbitrators this: in the absence of the joint measurement
exceeded their powers, or so imperfectly agreed upon in the Subcontract Agreement, how
executed them, that a mutual, final and definite will the completed works of HRCC be verified
award upon the subject matter submitted to them and the amolfnt due thereon be computed?
was not made.[126] (Citation omitted)
Guided by the primacy of CIAC's technical The determination of the foregoing question
competence, in exercising this Court's limited entails an interpretation of the terms of the
power of judicial review, this Court proceeds to Subcontract Agreement vis-a-vis the respective
rule on whether or not the Court of Appeals rights of the parties herein. On this point, it
erred in its assailed decisions. should be stressed that where an interpretation
III of the true agreement between the parties is
involved in an appeal, the appeal is in effect an
Properly discerning the issues in this case inquiry of the law between the parties, its
reveals that what is involved is not a mere matter interpretation necessarily involves a question of
of contractual interpretation but a question of the law.
CIAC Arbitral Tribunal's exercise of its powers.
III.A Moreover, we are not called upon to examine the
probative value of the evidence presented before
F.F. Cruz v. HR Construction[127] distinguished the CIAC. Rather, what is actually sought from
questions of law, properly cognizable in appeals this Court is an interpretation of the terms of the
from CIAC arbitral awards, from questions of Subcontract Agreement as it relates to the
fact: dispute between the parties.[129] (Emphasis
A question of law arises when there is doubt as supplied)
to what the law is on a certain state of facts, Though similarly concerned with "an
while there is a question of fact when the doubt interpretation of the true agreement between the
arises as to the truth or falsity of the alleged parties,"[130] this case is not entirely congruent
facts. For a question to be one of law, the same with F.F. Cruz.
must not involve an examination of the
probative value of the evidence presented by the In F.F. Cruz, the parties' agreement had been
litigants or any of them. The resolution of tbe clearly set out in writing. There was a definitive
issue must rest solely on what the law provides
instrument which needed only to be consulted to nature. As a consequence, the Contract
ascertain the parties' intent: Documents expressly prohibit any adjustment of
In resolving the dispute as to the proper the contract sum due to any changes or
valuation of the works accomplished by HRCC, fluctuations in the cost of labor, materials or
the primordial consideration should be the terms other matters.[133] (Citations omitted)
of the Subcontract Agreement. It is basic that if Upon its characterization of the contract as one
the tem1s of a contract are clear and leave no for the lump-sum, fixed price of
doubt upon the intention of the contracting P1,540,000,000.00, the Court of Appeals faulted
parties, the literal meaning of its stipulations the CIAC Arbitral Tribunal for acting in excess
shall control.[131] of jurisdiction as it supposedly countermanded
Thus, this Court concluded: the parties' agreement, or worse, conjured its
Pursuant to the terms of payment agreed upon own tenns for the parties' compliance. [134]
by the parties, FFCCI obliged itself to pay the
monthly progress billings of HRCC within 30 It was the Court of Appeals, not the CIAC
days from receipt of the same. Additionally, the Arbitral Tribunal, that committed serious error.
monthly progress billings of HRCC should
indicate the extent of the works completed by it, To rule that the CIAC Arbitral Tribunal
the same beinff essential to the valuation of the modified the parties' agreement because it was
amount that FFCCI would pay to HRCC.[132] indisputably one for a lump-sum, fixed price of
III.B P1,540,000,000.00 is begging the question. The
Court of Appeals used a conclusion as a premise
In this case, there is no established contract that to support itself. It erroneously jumped to a
simply required interpretation and application. conclusion only to plead this conclusion in
support of points that should have made up its
The assailed Court of Appeals April 28, 2008 anterior framework, points that would have been
Decision implies that all that had to be done to the ones to lead to a conclusion. It then used this
resolve the present controversy was to apply the abortive conclusion to injudiciously dispose of
supposedly clear and unmistakable terms of the the case.
contract between ACI and CECON. It even
echoes the words of F.F. Cruz: The Court of Appeals took the parties'
It is a legal principle of long standing that when contractual relation as a revealed and
the language of the contract is explicit, leaving preordained starting point. Then, it dismissed
no doubt as to the intention of the parties, the every prior or subsequent detail that contradicted
courts may not read into it any other intention this assumption. It thereby conveniently
that would contradict its plain import. The clear terminated the discussion before it even began.
terms of the contract should never be the subject III.C
matter of interpretation. Neither abstract justice
nor the rule of liberal interpretation justifies the There was never a meeting of minds on the price
creation of a contract for the parties which they of P1,540,000,000.00. Thus, that stipulation
did not make themselves or the imposition upon could not have been the basis of any obligation.
one party to a contract or obligation not assumed
simply or merely to avoid seeming hardships. The only thing that ACI has in its favor is its
Their true meaning must be enforced, as it is to initial delivery of tender documents to
be presumed that the contracting parties know prospective bidders. Everything that transpired
their scope and effects. after this delivery militates against ACI's
position.
....
Before proceeding to a consideration of the
The Contract Documents expressly characterize circumstances that negate a meeting of minds,
the construction contract between [ACI] and this Court emphasizes that ACI would have this
CECON as "lump-sum" and "fixed price" in Court sustain claims premised on supposed
inviolable documents. Yet, it did not annex constitutes a counter-offer.
copies of these documents either to its Comment
or to its Memorandwn. Acceptance made by letter or telegram does not
bind the offerer except from the time it came to
ACI leaves this Court compelled to rely purely his knowledge. The contract, in such a case, is
on their packaged presentation and in a bind, presumed to have been entered into in the place
unable to verify even the accuracy of the syntax where the offer was made. (Emphasis supplied)
of its citations. This Court cannot approve of this Subsequent events do not only show that there
predicament. To cursorily acquiesce to ACI's was no meeting of minds on CECON's initial
overtures without due diligence and offered contract sum of P1,449,089,174.00 as
substantiation is being overly solicitous, even stated in its August 30, 2002 bid. They also
manifestly partisan. show that there was never any meeting of minds
on the contract sum at all.
ACI and its counsel must have fully known the
importance of equipping this Court with a In accordance with Article 1321 of the Civil
reliable means of confirmation, especially in a Code,[135] an offeror may fix the time of
case so steeped in the sway of circumstances. acceptance. Thus, CECON's August 30, 2002
ACI's omission can only work against its cause. offer of P1,449,089,174.00 "specifically stated
that its bid was valid for only ninety (90) days,
By delivering tender documents to bidders, ACI or only until 29 November 2002."[136] November
made an offer. By these documents, it specitled 29, 2002 lapsed and ACI failed to manifest its
its terms and defined the parameters within acceptance of CECON's offered contract sum.
which bidders could operate. These tender
documents, therefore, guided the bidders in It was only sometime after November 29, 2002
formulating their own offers to ACI, or, even that ACI verbally informed CECON that the
more fundamentally, helped them make up their contract was being awarded to it. Through a
minds if they were even willing to consider telephone call on December 7, 2002, ACI
undertaking the proposed project. In responding informed CECON that it may commence
and submitting their bids, contractors, including excavation works. However, there is no
CECON, did not peremptorily become indication that an agreement was reached on the
subservient to ACI's terms. Rather, they made contract sum in any of these conversations. ACI,
their own representations as to their own CECON, the CIAC Arbitral Tribunal, and the
willingness and ability. They adduced their own Court of Appeals all concede that negotiations
counter offers, although these were already persisted.
tailored to work within ACI's parameters.
Still without settling on a contract sum, even the
These exchanges were in keeping with Article object of the contract was subjected to multiple
1326 of the Civil Code: modifications. Absent a concurrence of consent
Article 1326. Advertisements for bidders are and object, no contract was perfected. [137]
simply invitations to make proposals, and the
advertiser is not bound to accept the highest or An office tower atop Part A was included in
lowest bidder, unless the contrary appears. CECON's scope of works and the contract sum
The mere occurrence of these exchanges of increased to P1,582,810,525.00. Price
offers fails to satisfy the Civil Code's fluctuations were conceded after this and the
requirement of absolute and unqualified project cost was again adjusted to
acceptance: P1,613,615,244.00. Thereafter, CECON agreed
Article 1319. Consent is manifested by the to extend a discount and reduced its offered
meeting of the offer and the acceptance upon the project cost to P1,540,000,000.00.[138]
thing and the cause which are to constitute the
contract. The offer must be certain and the After all these, ACI demurred on the tenns of its
acceptance absolute. A qualified acceptance own tender documents and changed the project
from one encompassing both design and even realize or remotely reference CECON's
construction to one that was limited to most recent P1,594,631,418.00 stipulation but
construction. insisted on the passe offer of P1,540,000,000.00
from the past year.
Though not pertaining to the object of the
contract itself but only to one (1) of its many ACI's supposed acceptance was not an effective,
facets, ACI also removed from CECON's scope unqualified acceptance, as contemplated by
of works the acquisition of elevators, escalators, Article 1319 of the Civil Code. At most, it was a
chillers, generator sets, indoor substations, counter-offer to revert to P1,540,000,000.00.
cooling towers, pumps, and tanks. However,
much later, ACI reneged on its own and opted to ACI's June 2, 2003 letter stated an undertaking:
still obtain pumps, tanks, and cooling towers "This notwithstanding, formal contract
through CECON. documents embodying these positions will
shortly be prepared and forwarded to you for
It is ACI's contention that the offered project execution."[143] Through this letter, ACI not only
cost of P1,540,000,000.00 is what binds the undertook to deliver documents, it also admitted
parties because its June 2, 2003 letter indicated that the final, definitive terms between the
acceptance of this offered amount. parties had yet to be articulated in writing.
It has been established that the original tender, Neither requisite avails in this case. Yet again,
request for proposal and award is for a design ACI is begging the question. It is precisely the
and construct contract. The contract documents crux of the controversy that no price has been
are therefore associated for said system of set. Article 1724 does not work to entrench a
construction. When Respondent decided to disputed price and make it sacrosanct.
change and take over the design, such as the Moreover, it was ACI which thn1st itself upon a
change from concrete to structural steel framing, situation where no plans and specifications were
"take-out" equipment from the contract and immediately agreed upon and from which no
modify the [mechanical, electrical and plumbing deviation could be made. It was ACI, not
w]orks, the original scope of work had been CECON, which made, revised, and deviated
drastically changed. To tie down the Claimant to from designs and specifications.
the tmit prices for the proposal for a different V.C
scope of work would be grossly unfair. This
Tribunal will hold that unit price adjustment The CIAC Arbitral Tribunal also merely held
could be allowed but only for change orders that ACI to account for its voluntarily admitted
were not in the original scope of work, such as adjustments. The CIAC Rules of Procedure
the change order from concrete to structural pennit deviations from technical rules on
framing, the [mechanical, electrical and evidence, including those on admissions. Still,
plumbing w]orks, [schematic drawings to common sense dictates that the principle that
construction drawings] and the Miscellaneous "[t]he act, declaration or omission of a party as
Change Order Works.[151] to a relevant fact may be given in evidence
V.B against him"[153] must equally hold true in
administrative or quasi-judicial proceedings as
Contrary to ACI's oft-repeated argument, [152] the they do in court actions. Certainly, each must be
CIAC Arbitral Tribunal correctly found that ACI held to account for his or her own voluntary
had gained no solace in statutory provisions on declarations. It would have been plainly absurd
the immutability of prices stipulated between a to disregard ACI's reneging on its own
contractor and a landowner. Article 1724 of the admissions:
Civil Code reads: Respondent has agreed to the price increase in
Article 1724. The contractor who undertakes to structural steel and after some negotiation paid
build a structure or any other work for a the agreed amount. Respondent also agreed to
stipulated price, in conformity with plans and the price increase in the reinforcing bars and
specifications agreed upon with the land-owner, instructed the Claimant to bill it accordingly. To
can neither withdraw from the contract nor the Tribunal, such action is an acknowledgment
demand an increase in the price on account of of the price increase. Respondent can make the
the higher cost of labor or materials, save when case that said agreement is conditional, i.e., the
there has been a change in the plans and Complaint must be withdrawn. To the Tribunal,
specifications, provided: the conditionality falls both ways. The Claimant
has as much interest to agree to a negotiated absurdity and injustice to insist on the payment
price increase so that it can collect payments for of an amount the consideration of which has
the claims. The conditionalities do not change been reduced to a distant memory. ACI's
the basis for the quantity and the amotmt. The invocation of Article 1724 is useless as the
process of the negotiation has arrived at the premises for its application are absent. ACI's
price difference and quantities. The Tribunal position is an invitation for this Court to lend its
finds the process in arriving at the Joint imprimatur to unjust enrichment enabled by the
Manifestation, a fair determination of the unit gradual wilting of what should have been a
price increase. This holding will render the reliable contractual relation. Basic decency
discussions on Exhibit JJJJ, and the demand of impels this Court to not give in to ACI's
the burden of proof of the Respondent advances and instead sustain the CIAC Arbitral
superfluous.[154] Tribunal's conclusion that the amount due to
This absurdity is so patent that the Court of CECON has become susceptible to reasonable
Appeals was still compelled to uphold awards adjustment.
premised on ACI's admissions, even as it VI
reversed the CIAC Arbitral Tribunal decision on
the primordial issue of the characterization of The Arbitral Tribunal's award must be
the contractual arrangement between CECON reinstated.
and ACI: VI.A
As stated, the contract between [ACI] and
CECON has not been amended or revised. The With the undoing of the foundation for the Court
Arbitral Tribunal had no power to amend the of Appeal's fallacious, circular reasoning, its
contract to provide that there be allowed price monetary awards must also necessarily give way
and/or cost adjustment removing the express to the reinstatement of the CIAC Arbitral
stipulation that the Project is for a lump sum or Tribunal's awards.
fixed price consideration. Accordingly, this
Court removes the award for additional costs The inevitable changes borne by ACI's own
spent by CECON on cement and formworks due trifling actions justify, as a consequence,
to price increases or removing the award for compensation for cost adjustments and the
these items in the total amount of ensuing change orders, additional overhead costs
PhP5,598,338.20. Since CECON is not entitled for the period of extension, extended coverage
to its claim for price increase, it is likewise not for contractor's all-risk insurance, and
entitled to the award of the interest rate of 6% attendance fees for auxiliary services to
per annum. subcontractors whose functions were also
necessarily prolonged. ACI's frivolity on the
With regard however to the additional costs for acquisition of elevators, escalators, chillers,
the rebars due to price increases. this Court finds generator sets, indoor substations, cooling
that CECON is entitled to the amount of towers, pumps, and tanlcs also vindicates
PhP10,266,628.00 representing the additional compensation for the works that remained under
costs spent by CECON for rebars due to price CECON's account. ACI's authorship of the
increases, notwithstanding the Arbitral causes of delay supports time extensions
Tribunal's excess of jurisdiction in amending the favoring CECON and, conversely, discredits
contract between the parties because [ACI] and liquidated damages benefitting ACI.
CECON had in fact agreed that CECON was
entitled to such an amount and that [ACI] would This Court upholds the Arbitral Tribunal's
pay the same. This agreement was made in the awards on each of the items due to CECON, as
parties' Joint Manifestation of Compliance dated well as on its findings relating to CECON's
March 30, 2004 which they filed with th Arbitral countervailing liabilities.
Tribunal ("Joint Manifestation").[155]
No extraordinary technical or legal proficiency In fulfilling its task, the CIAC Arbitral Tribunal
is required to see that it would be the height of was equipped with its technical competence,
adhered to the rigors demanded by the CIAC agreement must be construed accordingly.
Rules of Procedure, and was endowed with the
experience of exclusively presiding over 19 ....
months of arbitral proceedings, examining
object and documentary evidence, and probing Section 19. Interpretation according to usage. -
witnesses. An instrument may be construed according to
VI.B usage, in order to determine its true character.
[157]
(Emphasis supplied)
Within the CIAC Arbitral Tribunal's technical Equally availing is the following principle. This
competence was its reference to prevailing is especially tlue of the remuneration due to
industry practices, a much-bewailed point by CECON, considering that stipulations for
ACI.[156] This reference was made not only remuneration are devised for the benefit of the
desirable but even necessary by the absence of person rendering the service:
definitive governing instruments. Moreover, this Section 17. Of two constn.1ctions, which
reference was made feasible by the CIAC preferred. - When the terms of an agreement
Arbitral Tribunars inherent expertise in the have been intended in a different sense by the
construction industry. different parties to it, that sense is to prevail
against either party in which he supposed the
This reference was not only borne by practical other understood it, and when different
contingencies and buttressed by recognized constructions of a provision are otherwise
proficiency, it was also sanctioned by the equally proper, that is to be taken which is the
statutory framework of contractual interpretation most favorable to the party in whose favor the
within which the CIAC Arbitral Tribunal provision was made.[158]
operated. Thus, the following principles VI.C
governed the interpretation of the change orders,
requests, and other communications, which had In appraising the CIAC Arbitral Tribunal's
effectively been surrogates of a single definite awards, it is not the province of the present Rule
instrument executed by the parties. 45 Petition to supplant this Court's wisdom for
the inherent technical competence of and the
From the Civil Code: insights drawn by the CIAC Arbitral Tribunal
Article 1375. Words which may have different throughout the protracted proceedings before it.
significations shall be understood in that which The CIAC Arbitral Tribunal perused each of the
is most in keeping with the nature and object of parties' voluminous pieces of evidence. [159] Its
the contract. members personally heard, observed, tested, and
propounded questions to each of the witnesses.
Article 1376. The usage or custom of the place Having been constituted solely and precisely for
shall be borne in mind in the interpretation of the the purpose of resolving the dispute between
ambiguities of a contract, and shall fill the ACI and CECON for 19 months, the CIAC
omission of stipulations which are ordinarily Arbitral Tribunal devoted itself to no other task
established. than resolving that controversy. This Court has
From the Revised Rules on Evidence, the the benefit neither of the CIAC Arbitral
following have been made applicable even Tribunal's technical competence nor of its
outside regular litigation by Article 1379 of the irreplaceable experience of hearing the case,
Civil Code: scrutinizing every piece of evidence, and
Section 14. Peculiar signification of terms. - The probing the witnesses.
terms of a writing are presumed to have been
used in their primary and general acceptation, True, the inhibition that impels this Court admits
but evidence is admissible to show that they of exceptions enabling it to embark on its own
have a local, technical, or otherwise peculiar factual inquiry. Yet, none of these exceptions,
signification, and were so used and understood which are all anchored on considerations of the
in the particular instance, in which case the CIAC Arbitral Tribunal's integrity and not
merely on mistake, doubt, or conflict, is competence to pontificate on technical matters.
availing. These include things such as fluctuations in
prices of materials from 2002 to 2004, the
This Court finds no basis for casting aspersions architectural and engineering consequences -
on the integrity of the CIAC Arbitral TribunaL with their ensuing financial effects - of shifting
There does not appear to have been an from reinforced concrete to structural steel, the
undisclosed disqualification for any of its three feasibility of rectification works for defective
(3) members or proof of any prejudicial installations and fixtures, the viability of a given
misdemeanor. There is nothing to sustain an schedule of rates as against another, the audit of
allegation that the parties' voluntarily selected changes for every schematic drawing as revised
arbitrators were conupt, fraudulent, manifestly by construction drawings, the proper mechanism
partial, or otherwise abusive. From all for examining discolored and mismatched tiles,
indications, it appears that the CIAC Arbitral the minutiae of installing G.I. sheets and sealing
Tribunal extended every possible opportunity for cracks with epoxy sealants, or even unpaid sums
each of the parties to not only plead their case for garbage collection.
but also to arrive at a mutually beneficial
settlement. This Court has ruled, precisely, that The CIAC Arbitral Tribunal acted in keeping
the arbitrators acted in keeping with their lawful with the law, its competence, and the adduced
competencies. This enabled them to come up evidence; thus, this Court upholds and reinstates
with an otherwise definite and reliable award on the CIAC Arbitral Tribunal's monetary awards.
the controversy before it. VII
Inventive, hair-splitting recitals of the supposed It does not escape this Court's attention that this
imperfections in the CIAC Arbitral Tribunal's controversy has dragged on for more than 13
execution of its tasks will not compel this Court years since CECON initially sought to avail of
to supplant itself as a fact-finding, technical arbitration.
expert.
The CIAC Arbitral Tribunal noted that ACI
ACI's refutations on each of the specific items consumed a total of 840 days filing several
claimed by CECON and its counterclaims of motions and manifestations, including at least
sums call for the point by point appraisal of eight (8) posturings at pursuing settlement. [160] It
work, progress, defects and rectifications, and added, however, that ACI repeatedly failed to
delays and their causes. They are, in truth, respond to CECON's claims during meetings
invitations for this Court to engage in its own thereby constraining CECON to file motions to
audit of works and corresponding financial proceed after repeatedly being dangled hope of
consequences. In the alternative, its refutations an early resolution.[161] It appeared that ACI was
insist on the application of rates, schedules, and more interested in buying time than in effecting
other stipulations in the same tender documents, a consummate voluntary settlement.
copies of which ACI never adduced and the
efficacy of which this Court has previously The CIAC Arbitral Tribunal October 25, 2006
discussed to be, at best, doubtful. Decision should have long brought this matter to
an end. This Court does not fault ACI for
This Court now rectifies the error made by the availing of remedies. Yet, this Court also notes
Court of Appeals. By this rectification, this that even in proceedings outside of the CIAC
Court does not open the doors to an inordinate Arbitral Tribunal, ACI seems to not have been
and overzealous display of this Court's authority sufficiently conscientious of time.
as a final arbiter.
In this Court alone, ACI sought extensions to
Without a showing of any of the exceptional file its Comment no less than five (5) times.
[162]
circumstances justifying factual review, it is It sought several other extensions in the
neither this Court's business nor in this Court's filing of its Memorandum.[163]
delivered until well after the project's intended
It also does not escape this Court's attention that completion date.
while ACI's arguments have perennially pleaded
the supposed primacy and itnmutability of This Court commenced its discussion by
stipulations originally articulated in the tender underscoring that arbitration primarily serves the
documents, it never bothered to annex any of need of expeditious dispute resolution. This
these documents either to its Comment or to its interest takes on an even greater urgency in the
Memorandum. Without these and other context of construction projects and the national
supporting materials, this Court is left in the interest so intimately tied with them. ACI's
uneasy predicament of merely relying on ACI's actions have so bogged down its contractor.
self-stated assertions and without means of Nearing 13 years after the Gateway Mall's
verifying even the syntax of its citations. completion, its contractor has yet to be fully and
properly compensated. Not only have ACI's
While presumptions of good faith may be actions begotten this dispute, they have hyper-
indulged, the repercussions of ACI's vacillation extended arbitration proceedings and dragged
cannot be denied. courts into the controversy. The delays have
virtually bastardized the hopes at expeditious
Even if this Court were to ignore the delays and effective dispute resolution which are
borne by ACI's procedural posturing, this Court supposedly the hallmarks of arbitration
is compelled to hearken to ACI's original faults. proceedings.
These are, after all, what begot these
proceedings. These are the same original faults For these, in addition to sustaining each of the
which so exasperated CECON; it was left with awards due to CECON arising from the facets of
no recourse but to seek the intervention of the project, this Court also sustains the CIAC
CIAC. Arbitral Tribunal's award to CECON of
arbitration costs. Further, this Court imposes
These faults began as soon as bidders responded upon respondent Araneta Corporation, Inc. the
to ACI's invitation. In CECON's case, its burden of bearing the costs of what have
communicated time for the validity of its offer mutated into a full-fledged litigation before this
lapsed without confinnation from ACI. ACI only Court and the Court of Appeals.
verbally responded and only after CECON's
communicated timeframe. It told CECON to WHEREFORE, the Petition is GRANTED.
commence excavation works but failed to The assailed April 28, 2008 Decision and July 1,
completely deliver the project site until five (5) 2010 Amended Decision of the Court of Appeals
months later. It engaged in protracted in CA-G.R. SP No. 96834 are REVERSED and
negotiations, never confirming acceptance until SET ASIDE. The Construction Industry
the tenth month, after bidders had submitted Arbitration Commission Arbitral Tribunal
their offers. By then, ACI's supposed acceptance October 25, 2006 Decision in CIAC Case No.
could not even identify CECON's most recent 01-2004 is REINSTATED.
quoted price. It undertook to process and deliver
formal documents, yet this controversy already Legal interest at the rate of six percent (6%) per
reached this Court and not a single page of those annum is imposed on the award from the finality
documents has seen the light of day. It has of this Decision until its full satisfaction.
repeatedly added and taken from CECONs scope
of works but vigorously opposed adjustments Costs against respondent.
that should have at least been given reasonable
consideration, only to admit and partially SO ORDERED.
stipulate on thern. In taking upon itself the task
of designing, it took its time in delivering as
many as 1,675 construction drawings to
CECON, more than 600 of which were not