bricks after adding time for laying common bond pattern is blf .
tblf
Substitute 701 hrs for .
Clb 701 29
= $20329
Here, the cost of laying bricks by helper is Ch and the labor time required by helper for laying
t
bricks after adding time for laying common bond pattern is hf .
thf
Substitute 460 hrs for .
Ch 460 22
= $10120
Here, the cost of material required for the work is Cmc , the cost of bricks required for the work is
CB , the cost of mortar required for the work is CM and the cost of wall ties required for the work
is Cwt .
Here, the cost of labor required for the work is CL , the cost of laying bricks by helper is Ch and
the cost of laying bricks by mason is Clb .
Here, the cost of equipment required for the work is CE , the cost of mortar mixer required for the
work is Cmm and the rental cost of scaffolding is Crcs .
Compute the total cost of material, labor and equipment required for the work.
CMLE Cmc CL CE
Here, the total cost of material, labor and equipment required for the work is CMLE , the cost of
material required for the work is Cmc , the cost of labor required for the work is CL and the cost of
equipment required for the work is CE .
$62,330.55
Therefore, the total cost of material, labor and equipment required for the work is .
Compute the cost of material, labor and equipment for 1000 bricks.
c pb (CMLE / Tb ) 1000
c
Here, the cost of material, labor and equipment for 1000 bricks is pb , the total cost of material,
labor and equipment required for the work is CMLE and total number of bricks required for the
construction of walls of the building without adding waste is Tb .
Therefore, the cost of material, labor and equipment for 1000 bricks is $1599 .