Matarbari USC Coal-Fired Power Project Currency : Bangladesh Taka (BDT)

Description / Specification for Total Price


No. Item 项目 Description / Specification for Subcontractor Measurement Criteria Unit Qt'y Unit Price
SINOHYDRO (Unit Price x Q'ty)

1.0 Earth Work


Excavation 开挖 For all kinds of soil For all kinds of soil - Duplication of volume due to overlapping area and structures shall
- Leveling, not be included.
compaction at final level. - Basis of slope ratio is 1H(horizontal):1V(vertical).
- Safety Precaution such as shoring, strutting, sheeting, bracing, - - For excavation less than 1.2m deep, basis of slope ratio is
safety handrail, calculation and slope protection for rainfall. Excavation plan & shop drawing 0.5H(horizontal):1V(vertical).
- Protection work such as geotextile for existing objects which for slope, level, area dimension. - Working space for concrete work will be secured max. 500mm
maybe encountered during the work. - Excavation start after Pile from the edge of lean concrete.
- Securing proper access way. driving complete - Working space for non-concrete work will be secured max. 300mm
- Dewatering of storm water and underground water encounter - Transport and temporary from the edge of material, structures.
1.1 during excavation(pump, hose, steel pipe, well pit, trench, etc). stockpiling inside plant M3 15,898 -
boundary.

Pile Head Cutting For piles between D400~D600 -Pile Head Cutting Machine
桩头切割 - Saw-cutting of PHC pile. shall be provided by
- Additional head cutting while excavation in basement such as SINOHYDRO
TG, Condensate, Lube oil, Cable Room, Trench, Misc. Pit etc.
1.2 - Disposal for head treatment, scrap piles to designated area inside EA 227 -
Project Boundary (Usual 1~2km, Max.3km)

Pile Head Reinforcement For piles between D400~D600


桩头钢筋 - Head reinforcing with rebar
1.3 stirrup for pile head treatment. EA 227 -
- Wire with plate supplying and installation for concrete placement.
Backfill Backfill with excavated selected soil including; -Excavator and hand compactor - The work quantity shall be the soil volume after compaction,
回填 - Reuse, soil filling with selected excavated soil inside stock piled. shall be provided by consolidation, and grading.
(This shall be approved by SINOHYDRO) SINOHYDRO. - Any volume existing in backfilling
- Necessary compaction test and inside transportation. -Compaction test area shall be deducted from
- Compaction in layers not exceeding 300mm thickness and Max. shall be done by SINOHYDRO. quantity calculation.
Density Test 95% (ASTM D698)
- Well-graded, non-expansive, granular material.
1.4 M3 4,682 -
- Backfilling in narrow area between pile and
structure shall be by
small equipment, manpower.
-Corporation with SINOHYDRO for test.

Disposal 余方弃置 Surplus soil after backfill - Unless specified or directed otherwise, all unnecessary excavated
- Disposal to the designated materials shall be transported and deposited to the suitable site at
dumping area inside the Project the
Boundary. subcontractor's own expense.
1.5 (Usual 1~2km, Max.3km) M3 11,216 -

- No spoil
material shall be dumped into
the river and/or sea.
Hard Core with Sand Fill For cable trench, underground sump pit, etc For cable trench, underground - The work quantity shall be the volume after spreading, compaction
填砂硬芯 - Horizontal layer thickness 100mm. sump pit, etc and leveling.
- BS 6031 or equivalent. - Crushed stone or natural
- Compaction, Grading. rubble shall be provide by
-Corporation with SINOHYDRO for test. SINOHYDRO.
- Stone size : 38mm crushed
fines.
1.6 M3 - -
- Horizontal layer thickness
100mm.
- BS 6031 or equivalent.

-Hand
compactor shall be provided by
SINOHYDRO.
Sheet Pile (Material) 板桩(材料 -For
Test shallHouse
Power be done by
basement
) - Supply sheet pile
- Sheet Pile Min. Size
400×100×10.5mm, Pile
1.7 Length=9M TON - -
- JIS A
5523, 5528 (SY295, SY390) or
equivalent.
Description / Specification for Total Price
No. Item 项目 Description / Specification for Subcontractor Measurement Criteria Unit Qt'y Unit Price
SINOHYDRO (Unit Price x Q'ty)

Sheet Pile (Driving & Pull-Out) 板桩(打入 For Power House basement
和拔出) - All work for sheet pile driving &
pull-out.
- Driving carried out after 1st
excavation.
-
1.8 Approx. Driving deep length = M - -
9M/PCS
- Shop drawing & calculation
shall be submitted and shall be
approved
by the owner.

Installation & Dismantling of Temporary 临时钢结构 For Power House basement


Steel Structure 安拆 - The unit price include
material, installation, removal,
welding & bolting.
- The unit price include
transportation cost.
1.9 - The quantity include wale, TON 60 -
strut, bracket, post pile & skrew
jack.
- The quantity shall be
calculated by the design weight
without loss rate.

Sub-Total -
2.0 Reinforced Concrete work
Lean Concrete 贫混凝土 - f'c=12 Mpa (compressive strength at 28 days). - f'c=12 Mpa (compressive - Concrete supply by SINOHYDRO.
strength at 28 days). - Terminal point for concrete supply is the mixer truck
- Concrete, pumpcrete (pump outlet chute at jobsite.
- Form work and cleaning of the rock. car), bobcat for pouring shall be - Only quantity indicated in the drawing.
- Dewatering if necessary. provided by SINOHYDRO.
2.1 - All auxiliary items and consumables for concrete work such as M3 228 -
PVC Sheet, vibrator etc. (By sub-
contractor).
- Pouring, vibrating, curing and strength test as per technical
specification and local regulation.
- Broom finish if necessary.

Plain Concrete 素混凝土 - f'c=17 Mpa (compressive strength at 28 days). - f'c=17 Mpa (compressive - Concrete supply by SINOHYDRO.
- Wire Mesh(#8-150x150). strength at 28 days). - Terminal point for concrete supply is the mixer truck
- Pouring, vibrating, curing and strength test as per technical - Concrete, pumpcrete (pump outlet chute at jobsite.
specification and local regulation. car), bobcat for pouring shall be - Only quantity indicated in the drawing.
- Less than 35℃ at Site provided by SINOHYDRO.
- All auxiliary items and consumables for concrete work such as
2.2 vibrator etc. (By sub-contractor). M3 - -
- All construction & other joint work (for isolation, construction, etc).
- Sleeve, drain slope if necessary.
- Steel trowel finish, broom finish.

Structural Concrete (25MPa) 结构混凝土 - f'c=25 Mpa (compressive strength at 28 days). - f'c=25 Mpa (compressive - Concrete supply by SINOHYDRO.
(25MPa) - Pouring, vibrating, curing and strength test as per technical strength at 28 days). - Terminal point for concrete supply is the mixer truck
specification and local regulation. - Concrete, pumpcrete (pump outlet chute at jobsite.
- Less than 35℃ at Site car), bobcat for pouring shall be - Only quantity indicated in the drawing
- All auxiliary items and consumables for concrete work such as provided by SINOHYDRO.
vibrator etc. (By sub-
contractor).
2.3 M3 4,309 -
- All construction & other joint work (for isolation, construction, etc)
including chipping work which should break the construction joint
area
- Sleeve, drain slope if necessary.
- Steel trowel finish, broom finish.

Structural Concrete (35MPa) 结构混凝土 - f'c=35 Mpa (compressive strength at 28 days) - f'c=35 Mpa (compressive - Concrete supply by SINOHYDRO.
(35MPa) strength at 28 days) - Terminal point for concrete supply is the mixer truck
- Pouring, vibrating, curing and strength test as outlet chute at jobsite.
per technical - Only quantity indicated in the drawing
specification and local regulation -
- Less than 35℃ at Site Concrete, pumpcrete (pump
- All auxiliary items and consumables for concrete work such as car), bobcat for pouring shall be
high frequency vibrator etc. (By sub-contractor) provided by SINOHYDRO.
2.4 - All construction & other joint work (for isolation, construction, etc) M3 - -
including chipping work which should break the construction joint
area
- Sleeve, drain slope if necessary.
- Steel trowel finish, broom finish
- Method Statement to get approval
for Mess Concrete and following Subcontractor requirement
Description / Specification for Total Price
No. Item 项目 Description / Specification for Subcontractor Measurement Criteria Unit Qt'y Unit Price
SINOHYDRO (Unit Price x Q'ty)

Re-bar Work 钢筋工程 -Transportation for bending ready rebar from SINOHYDRO - Bending, cutting as per bar - Reinforcing Rebar supply by SINOHYDRO (12m long without
Workshop to Construction Site. bending schedule. bending).
- Tying wire with mild steel of diameter - Rebar shall be provided by - All material handling after handing-over at SINOHYDRO laydown
approx. 1.5mm. SINOHYDRO. area.
- Welding where necessary or mechanical splice installation. - Material Transportation from SINOHYDRO's laydown to working
- Strength and proposition test work. area
- assembly, installation etc. as per bar bending by sub-contractor.
2.5 TON 454 -
schedule. - 3.0% of extra against bar bending schedule will be supplied.
- All consumables such as bar support / spacer/ wire for connection. (This extra quantity is not included in payment quantity)
- Bar-bending Schedule & Shop Drawing to be submitted and shall - Only Quantity indicated in the drawing will be paid except for loss
be confirmed by Subcontractor of rate as per bar bending schedule (Any losses, non-structural
pieces such as spacer, chair and others are not to be considered).

Normal Faced Form 普通混凝土模板 地下模板 For underground level (Hidden surface); - The work quantity shall be calculated using the dimensions
-Formwork and necessary indicated
supporting steel pipe and fittings shall be provided by subcontractor. on the drawings and the surface area of the forms to be in contact
- Normal Faced Form, wooden or metal shapes of form as required, with the placed concrete, excluding leveling concrete.
formtie, separator & all accessories and sealing of form tie hole.
- Shop drawing for fabrication, erection including calculation which
confirmed by Contractor
- Chamfer (15×15mm, 20×20mm, 30×30mm) at exposed corner. M2 7,914 -
- Marking, leveling, block out work.
- Opening, sleeve work, if necessary.
- Formwork shall be designed in accordance with ACI 347.
- Including all material, labor and equipment

Fair Faced Form 清水混凝土模板 地上模板 For above ground level (exposed surface); - The work quantity shall be calculated using the dimensions
-Formwork indicated
and necessary supporting steel pipe and fittings shall be provided on the drawings and the surface area of the forms to be in contact
by subcontractor. with the placed concrete, excluding leveling concrete.
- Normal Faced Form, wooden or metal shapes of form as required,
form tie, separator & all accessories and sealing of form tie hole.
- Shop drawing for fabrication, erection including calculation which
confirmed by Contractor
- Chamfer (15×15mm, 20×20mm, 30×30mm) at exposed corner. M2 2,427 -
- Marking, leveling, block out work.
- Opening, sleeve work, if necessary.
- Formwork shall be designed in accordance with ACI 347.
- Fair Surface Treatment.
- Including all material, labor and equipment

Scaffolding 脚手架 - Material of scaffolding - The work quantity shall be calculated using the dimensions
- Installaing & Removal of scaffolding with indicated
relative supporting as on the drawings
required
- Shop drawing or plan for erection including calculation which M2 5,814 -
confirmed by Contractor
- Including all
accessories
- Including all material, labor and equipment
Shoring Support 支撑支架 - Material of shoring support - The work quantity as a volumn (Width × Length × Height) shall be
- Installaing & re-shoring support calculated using the dimensions indicated on the drawings

- Shop M3 23,598 -
drawing for erection and shoring based on calculation
considering weight of fresh concrete which confirmed by
Contractor.
系统模板( - Including all material, labor and equipment
System Form (Turbine Generator For System Form is required - The work quantity shall be calculated using the dimensions
Structure) 汽轮发电机 such as TG Structure (Footing, indicated
结构) Pedestal, Top Deck Slab) on the drawings and the surface area of the forms to be in contact M2 - -
- Material of System Form, with the placed concrete, excluding leveling concrete.
wooden or metal shapes of form
as required,
Tutbine Generator Structure Support 发电机结构 -form
Material of shoring&support
tie, separator all - The work quantity as a volumn (Width × Length × Height) shall be
支架 accessories and sealing of form calculated using the dimensions indicated on the drawings
tie hole. -
Installaing
- Shop drawing& re-shoring support
for fabrication,
erection for system form based M3 - -
on
calculation considering weight
of fresh concrete which
confirmed - Shop drawing for
erection of shoring based on
by Contractor
Precast Concrete Trench Cover 预制混凝土 - Removable type precast concrete cover -Concrete and rebar shall be
沟盖 - Chamfer (15×15mm,
- Thickness : 200 mm provided by SINOHYDRO.
20×20mm, 30×30mm) at
- Cover handle and waterproofing sealant. M2 - -
exposed corner.
- Including all material, labor and equipment
- Marking, leveling, block out
work.
- Opening, sleeve work, if
necessary.
- Formwork shall be designed in
accordance with ACI 347.
- Fair Surface Treatment if
necessary.
- Supply system form such as
RMD, DOKA, PERI system form
or equivalent.
- System Form is used for
Description / Specification for Total Price
No. Item 项目 Description / Specification for Subcontractor Measurement Criteria Unit Qt'y Unit Price
SINOHYDRO (Unit Price x Q'ty)

Machine Trowel Finish 机器抹面 For application of primer and paint.


- Including all material, labor and equipment
M2 4,933 -

Sub-Total -
3.0 Concrete Protection and Waterproofing Work
Bituminous Coating 沥青涂料 For surface protection and waterproofing of underground concrete; Main Materials shall be provided
- Min. 2 times of coating. by SINOHYDRO.
- ASTM D 1079, D 1327 or BS 747 or equivalent.
- SIKA, BASF or equivalent. M2 2,482 -

- Including all material, labor and equipment

Waterproofing(Built-up Liquid) 防水(涂料 For liquid type on the roof slab & parapet; Main Materials shall be provided
) - Min. THK. 3mm. by SINOHYDRO.
- All accessories for the surface preparation work such as chipping,
cutting, grinding, cleaning, etc.
-To guarantee against leaks due to defective materials or poor
workmanship for a period of 7 years from the end of the Defect
Liability Period. M2 2,020 -
- SIKA, BASF or equivalent.
- Including all material, labor and equipment

Waterproofing(Built-up Membrane Sheet) 防水(卷材 For membrane type on the roof slab & parapet; Main Materials shall be provided
) - THK. 4mm Membrane sheet of 2 layer. by SINOHYDRO. Such as: THK
- Sealing & sealant at groove to end waterproofing membrane. 4mm membrane sheet
- All accessories for the surface preparation work such as chipping,
cutting, grinding, clean, etc.
-To guarantee against leaks due to defective materials or poor
workmanship for a period of 7 years from the end of the Defect M2 2,020 -
Liability Period.
- SIKA, BASF or equivalent.

- Including all material, labor and equipment

Thermal Insulation Board 保温板 For the roof slab; Main Materials shall be provided
- Polystyrene board 50mm. by SINOHYDRO. Such
- Sealing & taping at joint. as:Polystrene board 50mm. M2 2,020 -

- Including all material, labor and equipment


Protection Concrete for Roof Waterproofing 屋顶防水保 For the roof slab;
护混凝土 - f'c=17 Mpa (compressive strength at 28 days).
- Wire mesh (#8-150x150).
- THK 100mm.
- Pouring, vibrating, curing and strength test as per technical
specification and local regulation.
- Less than 35℃ at Site after placing.
- All auxiliary items and consumables for concrete work such as
pumpcrete (pump car) and bobcat for pouring (By sub-contractor). M2 2,020 -
- All construction & other joint work (for isolation, construction, etc).
- Sleeve, drain slope if necessary.
- Steel trowel finish, broom finish.

- Including all material, labor and equipment

Vapour Brrier 蒸汽阻凝层 For Under Ground;


- THK 0.2 mm P.E film.
M2 5,299 -
- Including all material, labor and equipment
Description / Specification for Total Price
No. Item 项目 Description / Specification for Subcontractor Measurement Criteria Unit Qt'y Unit Price
SINOHYDRO (Unit Price x Q'ty)

Strip Flashing (Parapet angle) 带状防水( For Parapet waterproofing; Main Materials shall be provided
护角)女儿 - AL. Strip Flashing to cover at the end of waterproofing on the by SINOHYDRO. Such as AL.
墙 parapet. Strip Flashing. M 262 -
- Including all material, labor and equipment
Waterstop (Dumbbell type) 止水带(哑 - W=200-250mm, T=5~7mm (Dumbbell type) Main Materials shall be provided
铃型) by SINOHYDRO. Such as
W=200-250mm, T=5~7mm M 50 -
- Including all material, labor and equipment (Dumbbell type) Water Stop.
Waterstop (Swell bar type) 止水带(膨 - 20×10mm, 20×20mm, 30×30mm (Swell bar-water expansion Main Materials shall be provided
胀杆型) index. material). by SINOHYDRO. Such as
- Including all material, labor and equipment 20×10mm, 20×20mm, M 50 -
30×30mm (Swell bar-water
expansion index. material)
Waterproofing for Basement 地下室防水 For basement waterproofing in Turbine, Lube oil, Condenser Main Materials shall be provided
- 3 coats of asphalt emulsion or 3 layers of coal tar pitch in by SINOHYDRO. Such as
accordance with ASTM specification or local tender specification. asphalt emulsion or coal tar
- 100mm THK. corner chamber. pitch.
- All accessories for the work.
- Scaffolding.
- Using cementitious waterproofing agency, accelerating agency, M2 - -
proper finish work.
- SIKA, BASF or equivalent.

- Including all material, labor and equipment

Protection Board 保护板 For the roof slab; Main Materials shall be provided
- THK 8mm. by SINOHYDRO. Such as:THK
- Sealing & taping at joint. 8mm. M2 - -
- Including all material, labor and equipment

Capillary Waterproofing 毛细防水 - SIKA, BASF or equivalent. Main Materials shall be provided
- Including all material, labor and equipment by SINOHYDRO. M2 - -

Sub-Total -
4.0 Steel Work (Metal Work)
Roof Drain 屋顶排水 - φ150, Cast iron. Main Materials shall be provided
- Conforming to JIS A 5522 or equivalent. by SINOHYDRO. Such as -
- Including horizontal & vertical Steel Pipe to connect between Drain φ150, Cast iron pipe.
and Down Spout Head (Water Collecting Box). EA - -

- Including all material, labor and equipment

Roof Drain 屋顶排水 - φ100, Cast iron. Main Materials shall be provided
- Conforming to JIS A 5522 or equivalent. by SINOHYDRO. Such as
- Including horizontal & vertical Steel Pipe to connect between Drain φ100, Cast iron pipe. EA - -
and Down Spout Head (Water Collecting Box).

- Including all material, labor and equipment


CHKD Plate 检查板 For CHKD plate in reinforced concrete; Main Materials shall be provided
- Galvanized steel Min. THK. 6mm. by SINOHYDRO.Galvanized
- Mild steel plate complying with BS4360 grade 43A or equivalent. steel Min. THK. 6mm. Such as
- Coating based on ASTM A123. Min. THK. 6mm Galvanized
- Touch-Up paint after installation. steel Plate.
- Coating with stripping coat in a dry film thickness of at least
150μm. M2 10 -
- Fixing CHKD plate and all accessories such as embedded
angle, etc by Subcontractor.
- Shop drawing related to all kinds of this supply work.

- Including all material, labor and equipment

Galvanized Steel Grating 镀锌钢格板 For grating cover trench in reinforced concrete; Main Materials shall be provided
- Hot dip galvanized steel Min. THK. 38mm. by SINOHYDRO. Hot dip
- Twisted closed-end type galvanized grating. galvanized steel Min. THK.
- Coating based on ASTM A123. 38mm. Hot dip galvanized steel
- Touch-Up paint after installation. Min. THK. 38mm.
- Fixing grating and accessories such as embedded angle, etc - Twisted closed-end type
by Subcontractor. galvanized grating.
M2 15 -
- Shop drawing related to all kinds of this supply work.
- The maximum span of grating with each thickness shall be
calculated so that the maximum deflection is less than 1/300.

- Including all material, labor and equipment


Description / Specification for Total Price
No. Item 项目 Description / Specification for Subcontractor Measurement Criteria Unit Qt'y Unit Price
SINOHYDRO (Unit Price x Q'ty)

Anchor Bolt (Installation only) 地脚螺栓( For anchor bolt of steel column & equipment; - Anchor Bolt and relative rebar supply by SINOHYDRO.
仅安装) - Including installation of temporary template frame. - Handing-over point for material is at SINOHYDRO laydown area.
- Fixing anchor bolt with necessary accessories such as rebar - Quantity for payment will be calculated by SINOHYDRO supplied
by Subcontractor. material only Anchor Bolt.
- Installation of anchor bolt shall be strictly - Rectification will be carried out by
in accurate position for steel structure & mechanical equipment in Subcontractor if it is out of tolerance
Power House, Central Control Building
- Anchor bolt and misc.metal is embedded in the concrete, and its
location & elevation shall be within 2mm after concrete placing is
completed. TON 4 -
- To fix correctly anchor bolt with misc. steel (Angle, frame, set
anchor, etc) is needed to install supplied by Subcontractor
- Shop drawing for anchor bolt and template which confirmed
by Contractor.

- Including all material, labor and equipment

Template (Installation only) 模板(仅安 For Template of steel column & equipment anchor bolt; - Template and relative rebar supply by SINOHYDRO.
装) - Fixing template with necessary accessories such as rebar - Handing-over point for material is at SINOHYDRO laydown area.
by Subcontractor. - Quantity for payment will be calculated by SINOHYDRO supplied
- To fix correctly template with misc. steel (Angle, material TON - -
frame, set anchor, etc) is needed to install supplied by only Template.
Subcontractor.

Embedded Material (Installation only) 预埋件(仅 - Including


For all material,
embedded plate of labor
Mech,and equipment
Piping, Steel Structure, Electrical, etc. - Embedded material and relative rebar supply by SINOHYDRO.
安装) - Embedded Materials are supplied by Others. - Handing-over point for Embedded Material is at SINOHYDRO
(The definition of ‘Others’ is indicated in Construction Drawings laydown area.
with ‘Others' are Mech, Piping, Steel Structure, Electrical, etc) - The work quantity of NOS shall be calculated based on the
- Fixing embedded plate with necessary accessories such as rebar, supplied Embedded Material.
etc by Subcontractor
TON 5 -
- To fix correctly embedded material with misc. steel
(Angle, frame,
set anchor, etc) is needed to install supplied by Subcontractor.

- Including all material, labor and equipment

Dividing Strip 分隔条 For floor; Main Materials shall be provided


- Stainless steel material (Hairline). by SINOHYDRO. Such as
- Half-hard brass. Stainless steel material M 6 -
- Including all material, labor and equipment (Hairline). Half-hard brass
Sub-Total -
6.0 Miscellaneous Work
Isolation Joint 隔离接头 For around TG Foundation & Pedestal; Main Materials shall be provided - The work quantity shall be the volume in square meter
(STG & Power House, CCB & (STG和动 - THK. 50 mm. by SINOHYDRO.
Power House, Other) 力室,CCB - Premolded joint filler with oil resistant sealant. M2 - -
和动力室, - C/S 0.9T joint cover.
其他)
- Including all material, labor and equipment
Expansion Joint 伸缩缝 For roof & external wall in structural expansion; Main Materials shall be provided
- THK. 25 mm. by SINOHYDRO.
- Premolded joint filler with oil resistant sealant. M - -
- C/S 0.9T joint cover.

- Including all material, labor and equipment


Control Joint 控制关节 For floor, slab; Main Materials shall be provided
- Heavy duty traffic. by SINOHYDRO.
- Max. spacing at 5×5 M.
- THK. 6 mm.
- Saw cutting of concrete or premolded joint filler with oil resistant M 50 -
sealant.

- Including all material, labor and equipment


Control Joint 控制关节 For wall; Main Materials shall be provided
- Max. spacing @ 6M by SINOHYDRO.
- THK. 12 mm
- Saw cutting of concrete or premolded joint filler with oil resistant M 50 -
sealant.

- Including all material, labor and equipment


Separation Joint 分离接头 For around grade slab; Main Materials shall be provided
- THK. 6~12 mm. by SINOHYDRO.
- Premolded joint filler with oil resistant sealant. M 75 -
- C/S 0.9T joint cover.

- Including all material, labor and equipment


Separation Joint 分离接头 For stair, equipment pad Main Materials shall be provided
- THK. 25 mm. by SINOHYDRO.
- Premolded joint filler with oil resistant sealant. M 75 -

- Including all material, labor and equipment


Description / Specification for Total Price
No. Item 项目 Description / Specification for Subcontractor Measurement Criteria Unit Qt'y Unit Price
SINOHYDRO (Unit Price x Q'ty)

Parapet Fillet 护墙角 For parapet, slab; Main Materials shall be provided
- 20×20 mm. Spacing Max. 6M by SINOHYDRO.
- In accordance with or equivalent to ASTM A588 for the backside M 50 -
plate.

- Including all material, labor and equipment


Parapet Ring 护栏环 - The steel rings shall be provided inside the parapets at every 5.0 Main Materials shall be provided
m for maintenance of the building facade, and shall be of 19Ø bar in by SINOHYDRO.
100 mm circles grasped by 12 mm in thickness and 60 mm in width EA 52 -
steel plate conforming to ASTM A36, or equivalent.

- Including all material, labor and equipment


Sub-Total -