You are on page 1of 3

TECHNICAL AR TICLE

W
hat project manager, con-
tract administrator, or auditor Equipment Compensation in
has not encountered changes
in the nature and scope of
work that required a change in price?
US Government Construction
These price changes, or “equitable price
adjustments,” are common occurrences in Equitable Price Adjustments
all contracting, and particularly in govern-
ment contracting. In order for a contractor Beni Warshawsky
to qualify for an equitable price adjust-
ment, he or she must meet certain criteria.
There are essentially three conditions that
must be fulfilled to qualify for an equitable
price adjustment: under US government regulations. Con- depreciation schedule, they will get more
tractors may use internal equipment rates than if they are at the end of the deprecia-
• there must have been a contractual that burden their jobs, including rates they tion schedule. If the machine is fully
change to the contract by the con- charge their joint-venture partners, rates depreciated, there is no compensation for
tracting officer or owner; they charge owners, and of course, there depreciation because it has been fully
• the change has to be in the contractu- are market rates. The US government, as a expensed. If a piece of equipment is depre-
al scope; and general rule, does not reimburse for any of ciated over the life of a specific job, the
• the change has to increase the con- these charges. It reimburses only “actual contractor will not get any additional com-
tractor’s costs. cost,” unless otherwise stated. The next pensation for depreciation expense if the
section of this article illustrates how the job is extended.
When these three facts have been estab- US federal acquisition regulations deal Another problem area for contractors
lished, a contractor is entitled to an equi- with each type of acquisition and account- is interest expense. Interest expense is
table price adjustment. ing methodology. expressly unallowable under FAR 31.205-
The equitable price adjustment at- 20. The contractor does not receive com-
tempts to make the contractor whole (in pensation for his or her interest expense,
the same relative time and cost position as Contractor-Owned Equipment regardless of how high or low it is. The
before). It compensates the contractor for FAR 31.105(d)(2) states that a con- contractor does, nonetheless, receive com-
the labor, material, equipment, and over- tractor is entitled to allowable ownership pensation for the cost of money, which is
head costs incurred for a change in work and operating costs when equipment is provided to all contractors. It does not mat-
or schedule. The compensation for labor owned outright. Actual costs from the con- ter if the source for the purchase of the
and material is relatively straightforward, tractor’s accounting records are used to equipment is equity or borrowed capital.
and the rates are easily determinable; labor determine the ownership costs and operat- The cost of money is calculated by multi-
rates can be tied to the payroll and materi- ing costs for each piece of equipment. The plying the capitalized cost by the US
als can be tied to their invoices. Com- ownership costs are defined as the depre- Treasury rate, which is established by the
pensation for equipment, however, is a ciation, taxes, insurance, facilities, and the Secretary of the Treasury under public law
more difficult issue since even the defini- cost of money. The operating costs may 92-41, 85 statute 97, and published semi-
tion of equipment is frequently a point of include fuel, filters, oil, and grease; ser- annually in the Federal Register (FAR
contention. Equipment compensation vicing, repairs, and maintenance; and tire 31.205-10 and CAS 417) [5].
hinges on the manner of equipment own- wear and repair. Operating costs are generally not
ership and the method of accounting. The most variable cost listed is depre- problematic except when a piece of equip-
Because there are various ways of acquir- ciation. All normal equipment deprecia- ment is overhauled on the job. In this
ing equipment and accounting for equip- tion is allowable, if it is reasonable. The case, the cost of the overhaul should not
ment cost, there are various levels of com- main test for reasonability is whether the be expensed to the job but should be cap-
pensation that are based upon which cost is reflected in the contractor’s books italized. Any expense that extends the life
method of acquisition was used and which and records and whether it is both used of a piece of equipment should be capital-
accounting system was applied. and acceptable for US federal income tax ized, depreciated, and a cost-of-money fac-
purposes (FAR 31.205-11(c)). This means tor calculated. Only routine maintenance
if a contractor uses the straight-line is a cost of the job.
COST REIMBURSEMENT method, he or she gets a straight-line There are other equipment acquisi-
expense amount. If the contractor uses tion methods that are considered by the
Contractors have many ways of charg- double declining, he or she gets the dou- US federal government to be “contractor-
ing for contractor-owned equipment, ble-declining expense amount. However, owned equipment.” These methods in-
some of which may not be acceptable if contractors are at the beginning of the clude sale-lease-back agreements, capital

Cost Engineering Vol. 38/No. 8 AUGUST 1996 33


leases, and rentals from contractor-owned to be calculated. The only exception to This is the primary way in which the US
subsidiaries, divisions, or family members. this common-control rule is a rental from government compensates contractors for
In the case of sale-lease-back agreements, the contractor’s subsidiary, division, or equipment costs incurred. However, there
the contractor sells his or her equipment family member that is in the business of are exceptions to the rule. The federal
to an outside party and the outside party renting equipment to the general public. acquisition regulations do allow payments
leases it back to the contractor. The con- These rates are acceptable, subject to lim- per rate schedules in two circumstances.
tractor/lessee increases his or her liquidity its of reasonableness (FAR 31.205-36(b)). The first is when the contractor’s records
while the purchaser/lessor receives lease This leads us to the issue of equipment are so poor that costs cannot be deter-
payments plus the depreciation expense as rented from a nonrelated vendor. mined. At that point, the contracting
a tax write-off. When confronted with a Equipment rented from an outside agency may specify the use of a particular
sale-lease-back agreement, the US govern- party is allowable as long as the cost is rea- schedule of predetermined rates. In the
ment acts as if the agreement never took sonable (FAR 31.105(d)(2)(C)(ii)). The second circumstance, the contract speci-
place and limits the rental costs to the US federal acquisition regulations allow fies, in advance, a particular equipment
amount the contractor would have been the rental cost under operating leases to rate schedule by which a contractor will be
allowed if the contractor retained title to the extent that the rates are reasonable at compensated. Rates may or may not be
the equipment (FAR 31.205-36(b)(2)). the time of the lease decision; the regula- reflective of the contractor’s cost. Cost is an
Equipment leased under a capital tions provide five considerations that actual contractor expenditure, while rates
lease is treated as “purchased assets,” as relate to reasonableness (FAR 31.205- are averages. These rates may or may not
required by FAS-13. The lease payments 36(b)(1)). make the contractor whole; since they are
cannot be expensed and the costs must be averages, they could either overcompen-
capitalized. Again, this type of acquisition • What are the rental costs of compara- sate or undercompensate the contractor.
is treated as an item owned outright by the ble equipment? There are various schedules of prede-
contractor (FAR 31.205-11(m)). • What are the market conditions in the termined construction equipment use
Similarly, equipment rented from area? rates. Some of the more common sched-
contractor subsidiaries, divisions, or family • What is the type, life expectancy, con- ules are the US Army Corps of Engineers’
members is treated as contractor-owned dition, and value of the equipment? rate schedule, the Cost Reference Guide
equipment. Rental charges for property • What are the available alternatives? [2], the Blue Book [3], the CalTrans Rate
between any divisions, subsidiaries, or • What are the provisions of the rental Schedule [4], the Contractors’ Equip-
organization under common control are agreement? ment Cost Guide [1], and the Associated
limited to the costs of ownership even if Equipment Distributors’ construction
they are equivalent to market rents. If the equipment cost guides. These rate sched-
contractor’s pension fund, family member, RATE SCHEDULES ules provide average ownership and oper-
or separate division rents equipment to its ating rates for construction equipment.
construction division, the rental cost is dis- Until now, this discussion has focused The allowance for operating costs may
allowed, and the costs of ownership need on cost reimbursement for equipment. include costs for fuel, filters, oil, and

1996 TRAofNSAC
TION S Now Available!
A ACE InNforTETotRN
The Associatio
AT ement
al Cost Manag
IONAL

ENGINEERS
1996 Transactions of
AACE International
A N D C OS T
C OS T M A N AG E R S

ULER S
AND SCHED
PL ANNERS

A N AG E R S
PROJECT M
If you were unable to attend the 1996 Annual Meeting in
VA L U E E N G
INEERS Vancouver, you still have a chance to take advantage of the
many technical papers that made their debut there!
S
E S T I M AT O R

Don’t miss out on this important, up-to-date reference material.


Order your copy of the 1996 Transactions today!

Proceedings of
the 40th Annual
Meeting of AAC
CANADA
E INTERNATIONAL Members Nonmembers
H COLUMBIA,
VANCOUVER, BRITIS
$7995 $9495
Call 800.858.COST or 304.296.8444
to order yours today!
34 Cost Engineering Vol. 38/No. 8 AUGUST 1996
grease; servicing, repairs, and mainte- of the US federal acquisition regulations. 5. Federal Register. Washington, DC:
nance; and tire wear and repair. The rate schedules are highly-standard- US Government Printing Office,
The rates in the schedules mentioned ized methods of compensation and are 1994.
above vary considerably. In 1988, an inter- easily applied. They do not, however,
nal study was conducted at Los Angeles relate to a contractor’s actual cost and may
MetroRail. The study used the US Corps over- or undercompensate the contractor. Beni Warshawsky is
of Engineers’ rates as its benchmark, thus As can be seen by this discussion, there is senior auditor for con-
making it base 100. In relation to the no one perfect method of equipment com- struction claims and
Corps of Engineers’ base 100, the Cost pensation. Each method deserves a full change orders at the
Reference Guide rates were base 134 [2], review and consideration. It is hoped that Los Angeles County
and the Blue Book monthly rates were with an informed decision, future disputes Metropolitan Transpor-
base 154 [3]. In other words, reimburse- will be minimized and work can go on. tation Authority (LAC-
ment under the Cost Reference Guide MTA), which is build-
was 34 percent greater than the Corps’ ing the Los Angeles Metro, the largest pub-
rates [2], while the Blue Book rates were REFERENCES lic works project in the US. He has over 20
54 percent higher [3]. With such varia- years of experience in auditing, cost control,
tions, the choice of rate schedule is a high- 1. Dataquest. Contractors’ Equipment and construction. Before joining LACM-
ly-significant and contentious factor. Cost Guide. San Jose, CA: Data- TA, he worked for New York City,
quest, Machinery Information Washington State, and the US Department
Division, 1992. of Defense. He served as staff consultant to
o conclude, there are essential- 2. Dataquest. Cost Reference Guide. the Washington State Governor’s Task

T ly two ways in which equip-


ment is reimbursed: by cost
reimbursement or by a rate
schedule. Each method has its advantages
and disadvantages. Cost reimbursement
3.
San Jose, CA: Dataquest, Machinery
Information Division, 1992.
Dataquest. Rental Rate Blue Book.
San Jose, CA: Dataquest, Machinery
Information Division, 1992.
Force on Catastrophic Health Care Costs
and as fiscal manager of the New York City
Ambulatory Care Program. He received his
undergraduate and graduate degrees from
the City University of New York. Mr.
gives the truest picture of the contractor’s 4. Department of Transportation, (Cal- Warshawsky is a certified government
cost; however, it is a highly-complex Trans), state of California. Equip- financial manager.◆
undertaking that is subject to the vagaries ment Rental Rates. Sacramento, CA: Back to Table of Contents
of the contractor’s accounting system and CalTrans, 1992.

Project and
AACE International’s Cost Management
Software Directory
This is a 380+ page directory containing product
descriptions and vendor contact information for over
Project and
Cost Management 600 project and cost management related software
Software Directory products. The directory has two listings: one sorted by
product name, and another by vendor name.The direc-
tory also comes with a database containing all of the
A Publication of
information provided in the directory. The database is
in dBase format (which can be read by most common
database programs), and enables you to do searches
by keywords, etc. Periodic updates to this database are
available for AACE members (free of charge) in library
23 (AACEOnly-Tech) of the Project and Cost
Management Forum (TCMFORUM) on CompuServe.
APRIL 1996

Price: US $4500 for AACE members (+S&H)


US $7000 for nonmembers (+S&H)
Cost Engineering Vol. 38/No. 8 AUGUST 1996 35

You might also like