Monthly Progress Report – December’2020
TABLE OF CONTENTS
Chapter Content Page No.
Chapter 1 The Project 03
1.1 Project Details 03
1.1.1 Project Highway Map 03
1.1.2 Salient Features 04
1.1.3 Major Project Facilities 04
Chapter 2 The Concessionaire 05
2.1 Scope of Work 05
2.1.1 Operation Management 05
2.1.2 Maintenance Management 05
2.1.2.1 Highway Maintenance 05
2.1.2.2 Incident Management 05
2.1.2.3 Environment Management 05
2.2 Concessionaire Team and Contacts 06
2.3 Provision for User Services 07
2.3.1 Ambulance 07
2.3.2 Route Patrol Vehicle 07
2.3.3 Crane 07
2.3.4 Highway Emergency Contact Information 08
2.4 Establishment Contact Details 08
Chapter 3 Toll Operation Management 09
3.1 User Fee Details 10
3.2 Monthly User Fee Collection Data 11
3.2.1 Single Journey Traffic 11
3.2.2 Return Journey Traffic 12
3.2.3 Single Journey for commercial vehicles registered within plaza district 12
3.2.4 Monthly pass for 50 Single Journeys in a month 13
3.2.5 Monthly pass for local personal (Non-Commercial) 14
3.2.6 Single, Return & Local RFID Journeys 14
3.3 Traffic Data & PCUs 15
3.4 Forced Exemption Vehicles 17
Chapter 4 Highway Maintenance & Incident Management 18
4.1 Highway Maintenance Activities 18
Chapter 5 Emergency Route Operations 22
Chapter 5 5.1 User Services & Accident Data 22
5.1.1 Ambulance Services 22
5.1.2 Crane Services 23
2|P a g e
Monthly Progress Report – December’2020
Chapter Content Page No.
5.1.3 Route Patrol Services 23
5.1.4 Highway Helpline 24
5.1.5 Incident Management Photos 25
5.1.6 Accident Statistics 28
5.1.7 Cumulative Accident Statement for the current month 30
Road User Complaints 31
Chapter 6 6.1 User Complaints-1033 Helpline 31
6.2 User Complaints registered at plaza 32
Site Visits 33
Chapter 7
Independent Engineer’s Team & Contacts 33
Chapter 8
Chapter 9 Issues 34
Chapter 10 Site Photos 34
Madurai to Kanyakumari highway section is a part of National Highway No. 44 (Old NH 7) in the State of
Tamilnadu. It is one of the Projects comprising of 9 National Highway stretches (Bundle-3) on Toll Operate
Transfer (TOT) Mode.
The Site of the four-lane divided Project Highway starts at Km.52.300 of NH-44 (Old NH 7) and ends at Km.116.500
of NH-44 (Old NH 7) in the State of Tamil Nadu. Having a user fee toll plaza at Km.75+280. The total length of
Project Highway is 64.2 Kms. This project will be for Toll, Operation, Maintenance and Transfer from Km.52.300 to
Km.116+500.
3|P a g e
Monthly Progress Report – December’2020
1.1.1 Project Highway Map
State Tamilnadu
4|P a g e
Monthly Progress Report – December’2020
8 Underpasses 10 nos.
5|P a g e
Monthly Progress Report – December’2020
2.1.2.1 Highway Maintenance
The objective of (project) Highway Maintenance is to maintain the safety, durability and functionality of the
(project) highway throughout the concession period. This contains regular Routine and Preventive Maintenance
for the corridor carriageway and project facilities. Broadly, it will include maintenance of the carriageway, road
furniture, buildings, crust, shoulder, slopes, side drains and cross drainage works.
KUMAR
REDDY
SAFETY
6|P a g e
Monthly Progress Report – December’2020
Name Designation Location Mobile No.
7|P a g e
Monthly Progress Report – December’2020
2.3.1 Ambulance
Date of mobilization of
Vehicle Type and Reg. No. Staff Deployed per Shift
Vehicle
Paramedic
Force Ambulance - TN 30 AH 8989
Ambulance Driver 20th Oct 2020
Ambulance Helper
Date of mobilization of
Vehicle Type and Reg. No. Staff Deployed per Shift
Vehicle
2.3.3 Crane
Date of mobilization of
Vehicle Type and Reg. No. Staff Deployed per Shift
Vehicle
8|P a g e
Monthly Progress Report – December’2020
National Highways Authority of India,
Office of the Project Director,
Plot No.3, Surya Towers, 2nd Floor,
Project nhai_madurai_piu@yahoo.c 0452-
1st East Street,
Director, NHAI o.in 2587750
K.K.Nagar,
Madurai – 625020.
Kanyakumari-Etturvattam Tollway
Authorised Limited
Signatory, Etturvattam Toll plaza, Mettamalai 7892940345
TP2@ketl.co.in
Concess Post, Sattur Taluk, Virudhunagar
ionaire District-626203, Tamilnadu
9|P a g e
Monthly Progress Report – December’2020
Chapter 3: Toll Operation Management
3.1 User Fee Details for Etturvattam Toll Plaza
Light Commercial Vehicle, Light Goods Vehicle or Mini Bus 135 200 4475 65 NA
3.2 Monthly User Fee Collection Data–Dec 2020 (Etturvattam Toll Plaza)
10 | P a g e
Monthly Progress Report – December’2020
The monthly fees collection details (vehicle category wise) along with a comparison of fees collected in the previous month and the same
month in previous year (according to the format provided in Schedule-G of Concession Agreement is tabulated below:
For preceding month For the period 01.11.2020 to For current month For the Period
For corresponding month
30.11.2020 01.12.2020 to 31.12.2020
Vehicle Type of Previous Year
Fees Fees per Fees
No. of Collected Fees Collected Vehicle No. of Collected
Vehicles (Rs.) No. of Vehicles (Rs.) (Rs.) Vehicles (Rs.)
Car, Jeep, Van or Light Motor Vehicle 49647 3971760 91945 7815325 85 77487 6586395
Bus (Two Axle) 4829 1303830 717 200760 280 3720 1041600
Three axle commercial vehicle 3156 931020 3237 987285 305 3449 1051945
HCM/EME/MAV (four to six axles) 3164 1344700 2970 1306800 440 3130 1377200
Oversized Vehicles (seven or more axles) 169 87880 30 16050 535 29 15515
11 | P a g e
Monthly Progress Report – December’2020
For preceding month For the period 01.11.2020 to For current month For the Period
For corresponding month
30.11.2020 01.12.2020 to 31.12.2020
of Previous Year
Fees Fees per Fees
No. of Collected Fees Collected Vehicle No. of Collected
Vehicle Type Vehicles (Rs.) No. of Vehicles (Rs.) (Rs.) Vehicles (Rs.)
12 | P a g e
Monthly Progress Report – December’2020
3.2.3 Single Journey for commercial vehicles registered within the plaza district (Cash)
For preceding month For the period 01.11.2020 to For current month For the Period
For corresponding month
30.11.2020 01.12.2020 to 31.12.2020
of Previous Year
Fees Fees per Fees
No of Collected Fees Collected Vehicle No. of Collected
Vehicle Type Vehicles (Rs.) No of Vehicles (Rs.) (Rs.) Vehicles (Rs.)
13 | P a g e
Monthly Progress Report – December’2020
For preceding month For the period 01.11.2020 to For preceding month For the period
For corresponding month
30.11.2020 01.12.2020 to 31.12.2020
of Previous Year
Fees Fees
No. of Collected Fees Collected Fees per No. of Collected
Vehicle Type Passes (Rs.) No. of Passes (Rs.) Pass (Rs.) Passes (Rs.)
Car, Jeep, Van or Light Motor Vehicle 0 0 1 2770 2770 1 2770
14 | P a g e
Monthly Progress Report – December’2020
For preceding month For the period 01.11.2020 to For preceding month For the period
For corresponding month
30.11.2020 01.12.2020 to 31.12.2020
of Previous Year
Fees Fees
No. of Collected Fees Collected Fees per No. of Collected
Vehicle Type Passes (Rs.) No. of Passes (Rs.) Pass (Rs.) Passes (Rs.)
Car, Jeep, Van or Light Motor Vehicle 358 94870 385 105875 275 406 111650
LCV/LGV/Mini Bus
15 | P a g e
Monthly Progress Report – December’2020
Car, Jeep, Van or Light Motor Vehicle 55256 5135000 125837 9273965 138642 10295835
Three axle commercial vehicle 3174 1067430 5102 1413010 6074 1679920
HCM/EME/MAV (four to six axles) 3939 1911435 13294 5229400 16226 6348320
16 | P a g e
Monthly Progress Report – December’2020
17 | P a g e
Monthly Progress Report – December’2020
Total
Revenue - 41773350
18 | P a g e
Monthly Progress Report – December’2020
19 | P a g e
Monthly Progress Report – December’2020
21-Dec- 70 6 34 1
20 4 8 2 9 4 12 1149
22-Dec- 58 6 32 1 1
20 6 7 7 7 2 1009
23-Dec- 75 7 36 1
20 0 8 7 6 8 12 1231
24-Dec- 78 3 37 1
20 7 4 5 6 6 9 1227
25-Dec- 58 2 33
20 6 9 2 7 - 11 965
26-Dec- 54 4 35 1
20 8 7 4 4 5 13 981
27-Dec- 77 3 42 1 1
20 0 1 2 3 1 4 1251
28-Dec- 73 4 36 1
20 5 0 1 1 3 10 1160
29-Dec- 67 5 30 1 1
20 0 7 3 2 1 12 1065
30-Dec- 67 5 32 2 1
20 6 4 1 2 1 16 1100
31-Dec- 61 5 31 1
20 1 0 1 3 9 12 1006
Total 18509 1513 13755 397 244 280 4 35708
The details of maintenance activities undertaken for smooth and safe operations of the Project Highway during the
month are tabulated below:
20 | P a g e
Monthly Progress Report – December’2020
21 | P a g e
Monthly Progress Report – December’2020
22 | P a g e
Monthly Progress Report – December’2020
16-Dec-2020 1. MCW pavement shoulder crass barrier edge silt cleaning work at Km
52+300 LHS.
2. Median Waste removal at km 52+700, 52+650.
3. SR Median grass Cutting at km 53+250 RHS.
4. Pothole repair at Km 102+200 to 102+600 RHS/SR.
5. Pothole repair at Km 99+490 to 99+500 LHS.
23 | P a g e
Monthly Progress Report – December’2020
24 | P a g e
Monthly Progress Report – December’2020
25 | P a g e
Monthly Progress Report – December’2020
26 | P a g e
Monthly Progress Report – December’2020
27 | P a g e
Monthly Progress Report – December’2020
28 | P a g e
Monthly Progress Report – December’2020
11 35 46
3 No. of Services Provided
29 | P a g e
Monthly Progress Report – December’2020
30 | P a g e
Monthly Progress Report – December’2020
31 | P a g e
Monthly Progress Report – December’2020
32 | P a g e
Monthly Progress Report – December’2020
6.1.7 Accident Statistics
Name of PIU : MADURAI
1) Stretch : Kanyakumari Etturvattam Tollway Limited 50+000 to 100+000 (NH-07)
2) State : TAMILNADU
3) District : Virudhunagar
4) Police Station : Sattur Police Station, R.R.Nagar Police Station, Virudhunagar Bazar Police Station.
Responsible
Vehicle
No. of Affected Persons
`a `b `c `d `e `f `g `h
Legends as per Foot Note Help provided by Ambulance/ RPV/ Crane
Weather Condition
Nature of Accident
Time of Accident
Road Condition
Road Feature
Non Injured
Grievous
Accident Location
Sr.
Causes
Minor
Fatal
Date
No.
PATROL/ AMBULANCE
Car
12.15 65+200 A speedy Motorcyclist proceeding towards Kanyakumari at LHS
1 01.12.2020 3 2 2 4 4 - 1 /Jeep/Van/ 0 1 0 5 0
PM R.R.NAGAR slow track, hit behind the car who also proceeding towards
Taxi
same direction. In this accident Motorcyclist got Injured.
PATROL/AMBULANCE
A three-wheeler rickshaw driver proceeding towards Madurai
at RHS slow track, at the same time a speedy Bus driver
01.27 66+600
2 09.12.2020 4 3 2 4 4 - 1 Bus 0 0 1 2 0 proceeding towards same direction at fast track tried to
PM R.R.NAGAR
overtake the rickshaw, while overtaking hit the rickshaw. In
this accident the passengers from the rickshaw fell down the
road. One minor injury and two non-Injuries.
3 16.12.2020 01.30 68+400 4 3 2 4 4 - 1 Motorised 0 0 3 1 0 Ambulance
PM R.R.NAGAR two A speedy car driver proceeding towards Madurai at RHS slow
33 | P a g e
Monthly Progress Report – December’2020
ACCIDENT DATA FOR THE MONTH OF October 2020
Responsible
Vehicle
No. of Affected Persons
`a `b `c `d `e `f `g `h
Legends as per Foot Note Help provided by Ambulance/ RPV/ Crane
Weather Condition
Nature of Accident
Time of Accident
Road Condition
Road Feature
Non Injured
Grievous
Sr. Accident Location
Causes
Minor
Fatal
Date
No.
34 | P a g e
Monthly Progress Report – December’2020
d. 1. Drunken driving, 2. Over speeding, 3. Vehicle out of control, 4. Fault of driver of motor vehicle/cyclist/pedestrian/passenger, 5. Defect in mechanical /electrical
condition of motor vehicle, 6. Wrong side driving, 7. Tire bust, 8. Rain, 9. Poor visibility(fog/dust) 10. Poor Road condition 11. Others (specify)
e. 1. Single lane, 2. Two lanes, 3. Three lanes or more without central divider (median), 4. Four lanes or more with central divider.
f. 1. Straight road, 2. Slight Curve, 3. Curve, 4. Flat Road, 5. Gentle incline, 6. Steep incline, 7. Hump, 8. Dip
g. 1. T-junction, 2. Y-junction, 3. Four arm junction, 4. Staggered junction, 5. Junction with more than 4 arms, 6. Round about junction, 7. Manned Rail crossing. 9.
Unmanned Rail crossing
h. 1. Fine, 2. Mist/Fog, 3. Cloudy, 4-Light rain, 5. Heavy rain, 6. Hail/sleet, 7. Snow, 8. Strong Wind, 9. Dust Storm, 10. Very Hot, 11. Very Cold, 12. Other extraordinary
weather condition.
1 Fatal 01 01 00 00 01 01
2 Grievous Injury 08 09 03 04 11 13
3 Minor Injury 08 22 02 04 10 26
4 Non Injured 08 50 04 09 12 59
35 | P a g e
Monthly Progress Report – December’2020
Summary of Road User complaints received and attended during the month of November 2020
Complaina
Sr
nt’s
. Complai Complain Complai Resolve
Vehicle No Contact Complaint description Solution explained Remarks
N nt Date t Sr. No nt Time d on
No.
o
(if any)
36 | P a g e
Monthly Progress Report – December’2020
Summary of Road User complaints received and attended during the month of November 2020
Sr
Complainan
. Complaint Complai Complai Resolved
Vehicle No t’s Contact Complaint description Solution explained Remarks
N Date nt Sr. No nt Time on
No. (if any)
o
Sr. No. Date of Visit Name of Officer Designation Purpose of site visit
1 Nil
37 | P a g e
Monthly Progress Report – December’2020
38 | P a g e
Monthly Progress Report – December’2020
39 | P a g e
Monthly Progress Report – December’2020
Chapter 9. Issues
The TOT Concessionaire has taken over the project on 20.10.2020. Due to frequent heavy rains RE Wall facia blocks of ROB-IV at Ch.66+990 has subsided at
RHS service road on 17.11.2020. At this location TOT Concessionaire had done all safety measures.
40 | P a g e
Monthly Progress Report – December’2020
Chapter 10. Site Photos
41 | P a g e
Monthly Progress Report – December’2020
42 | P a g e
Monthly Progress Report – December’2020
43 | P a g e
Monthly Progress Report – December’2020
44 | P a g e
Monthly Progress Report – December’2020
45 | P a g e
Monthly Progress Report – December’2020
Median and Kerb Cleaning at Ch53+900 BHS RE wall Slope cleaning works at Km.67+100 RHS
46 | P a g e
Monthly Progress Report – December’2020
47 | P a g e
Monthly Progress Report – December’2020
48 | P a g e
Monthly Progress Report – December’2020
49 | P a g e
Monthly Progress Report – December’2020
Bridge footpath cleaning work at CH67+150 RHS
50 | P a g e
Monthly Progress Report – December’2020
Service road cleaning work at CH52+400 RHS Toll plaza lane cleaning at CH75+150
51 | P a g e
Monthly Progress Report – December’2020
Clearing of Rainwater logging at CH 101+200 RHS
52 | P a g e