Take a look at pictures of a vessel used to lift heavy weight (ranging from ships to
offshore installations), if you have never been on a ship or seen one in real. Observe
those huge cranes on the ships which carry out a series of careful manoeuvres during
heavy lift operations, which are very common these days.

It is hard to imagine heavy lifting such as offshore installation, cargo operations (or for
that reason, any commercial vessel having some payload) etc. without such cranes.

Credits: Hall, Bill /wikipedia.org

With such huge power wielded by these cranes or lifting equipment, certain stability and
safety issues needs to be considered in their design and operation. There are
contractual issues to be looked into too as well, but we will concentrate on something
more central to the topic, i.e. the stability of the ship during such an operation.

Several lifting operations simultaneously take place on a single ship and therefore it is
not possible to work with the cargo handling without proper assessment of the risks
involved. They are the so called Project cargoes (which require disassembly for
transport and are again reassembled before delivery). Heavy lift ships and major
commercial operations have to customarily adhere to the accepted regulations for the
Safety of Life at Sea.

Let us see how heavy lift operations affect a ships stability.


Figure 1: Schematic showing the shift in CG with location of load away from ship centreline.

When the crane or the derrick of your ship carries a load on either side of the centreline of the
vessel at a certain height from the deck, there is a tendency of the ship to heel in that direction
(as a rule of the thumb). Something similar thing happens as in the case of a simple pendulum
where its weight is free to swing. The weight shifts the centre of gravity, and the CG of the ship
being at a different position has to be previously accounted for so that it does not violate the
original intact stability of the ship!

Figure 2: The Swing Analogy in Hydrostatics gives a mathematical model to the phenomenon
This term swing as we will use henceforth, has an interesting feature. It happens so that when
this cargo hangs at a certain height, such that the length of the ‘pendulum’ is minimised by
loading it close to the crane head thereby killing the swing (reducing the swinging motion of the
weight is necessary to prevent damage to the nearby structures) and improving the stability.
This is because the weight always acts, as a rule, at the point of suspension or the pivot, and
thus, the stability of the vessel is not affected any further.

Image Credits: U.S. Navy photo by Mass Communication Specialist 2nd Class Meranda L. Keller

Let us say, at a port, our ship is loading a very heavy weight, almost comparable to a
fraction of the ship’s own weight. The derrick/crane lifting the weight from the port is
initially upright. In other words, the centre of gravity is on the plane of the centreline of
the ship. When the loading is in progress, (that is the crane’s boom is now outboard),
the ship lists in that direction. This list must be kept as small as possible so as to keep it
under control.

If you look closely, the derrick has to first raise the head and swing it in order to move
the cargo across into the position in the hold. This means at first, transverse shift (port
to starboard) in the centre of gravity is less while the vertical rise is prominent. This
becomes critical especially when the lift is quite inboard almost next to the centreline
(because if the lifting is inboard, then it can be visualised as the ship’s centre of gravity
to be rising), here the vessel tends to become upright very quickly,  so that by virtue of
its pendulum like motion, it will swing to the other side!
Figure 3: Illustration of the effect of the violent up righting motion which might cause a swing to the other side.

Such motion can have implications of its own as the vessel will lose control and heel to
the opposite side. Also, it is not always the CG which is the main culprit here, when your
vessel sinks partly, the metacentre of the vessel won’t remain the same either.

Finally what would matter would be the metacentric height GM.

A negative metacentric height causes a situation of unstable equilibrium, which is


responsible for generating a capsizing movement (Not Good!). Although this doesn’t
persist for the entire range of heel, as the submerged portion on the heeling side
generates enough buoyant force to counter the moment and eventually the GM
becomes zero again. Beyond this, the vessel recovers positive stability. If a vessel has
an inherent negative stability, the ship will find stability at a certain angle of loll.

Figure 4: The angle of Loll for a typical vessel plotting GZ for various values of inclination. Taken simply, the GZ gives
the indication of vessel stability and should necessarily be postive like the GM
It is important be able to differentiate between a list and a loss in stability, as a vessel
cannot be simply ‘levelled’ by ballasting the higher side. Why?

Imagine your ship has a list towards the port. So your starboard side is higher. A normal
person would assume, that ballasting on the starboard side would reduce the list. But
that is wrong. Why? Because, since the starboard side is already higher than the port,
adding weight on the higher side would raise the centre of gravity, therefore reducing
the metacentric height GM. As a result, you are losing more stability. Ballasting should
be done on the lower side (in this case, the port side). Initially the ship heels slightly
towards the port, but when the GM increases, the ship is more stable. When sufficient
righting moment is achieved, then the weight can be balanced on both the sides to bring
the ship back to upright position.

Speaking of heavy lifts, let’s think of a fishing vessel with some catch in it. Now, if this
vessel recovers a sizeable catch comparable to its own weight (unfortunately, which is
not known beforehand) and is about to swing the catch inboard, a highly overweight
cargo would cause enough instability to swing beyond to the other side causing an
immediate opposite list. This roll might continue dangerously with reduced stability and
vessel will be prone to flooding from an open hatch. (Warning: your wet fish cargo is
good at sliding across the deck during rolling motions; enough care must be taken to
prevent cargo shift).

Figure 5: Simplified schematic of a ship with shifting cargo. (G Moves in the direction of derrick head)

Now, for the bigger picture, finally. What we told you above is a special case with a smaller
vessel. Now, remember somewhere in the beginning where we told you about offshore heavy
lifting vessels? We are talking in terms of lifting weights of the scale of 10,000 tonnes! Many of
these vessels have specialised water ballast systems for the purpose as it is not as simple as
retrieving the fish catch in smaller amounts. These sort of operations (especially with oil rig
installations) require high degrees of accuracy as per stability criteria. This is expressed in terms
of the tolerances which would usually be in the range of a few metres. A vessel this capable is
normally equipped with ‘Dynamic Positioning’ (DP) Systems. The entire ship operates based on
the working of an on board mainframe computer system in conjunction with thrusters,
propulsion units and control surfaces (by having a numerical model of the ship interacting with
the external live forces taken into account).

Figure 6: Example of a moonpool arrangement for heavy lifting operations

Another facility that only some vessels can have are the moonpool arrangements where the
lifting operation is done through an opening running parallel along the depth of the vessel. Here,
the crane operation is done while keeping the ship’s centre of gravity close to the centre line
and so the heel motions are limited.

Some things which require repeated checks before the operation are:

 For a lift from a position A to B (say), the GM positions for both the positions
need to be estimated for acceptable values by keeping in accordance with a
stability booklet. The list should be kept with as this doesn’t adversely affect the
stability
 Since the ship’s stability is reduced when it comes to having a reduced
metacentric height, it doesn’t help in anyway to have slack tanks with free
surfaces which also reduce GM. Therefore it would be sensible to ‘press up’ these
tanks for lessening the effect
 Also, you should take care that your vessel does not ground at the jetty at the
expected angles of list. The cranes should not be raised more than what is
needed