Professional Documents
Culture Documents
AP-R640-20-Design Procedures Lightly Bound Cemented Materials
AP-R640-20-Design Procedures Lightly Bound Cemented Materials
AP-R640-20
Prepared by Publisher
This report has been prepared for Austroads as part of its work to promote improved Australian and New Zealand transport outcomes by
providing expert technical input on road and road transport issues.
Individual road agencies will determine their response to this report following consideration of their legislative or administrative
arrangements, available funding, as well as local circumstances and priorities.
Austroads believes this publication to be correct at the time of printing and does not accept responsibility for any consequences arising from
the use of information herein. Readers should rely on their own skill and judgement to apply information to particular issues.
Development of Design Procedures for Lightly Bound Cemented Materials in Flexible Pavements
Summary
The addition of a small amount of cementitious binder to non-standard granular materials may result in a
fit-for-purpose base or subbase at a significantly lower cost than crushed rock complying with standard
specifications. Such lightly bound cemented (LBC) materials have particular use in pavement rehabilitation
and heavy patching. LBC are unbound granular materials which have been cementitiously stabilised to
produce a low strength material that is less susceptible to block (ladder) cracking and crocodile cracking than
cemented materials. The binder content and strength of LBC materials are significantly lower than heavily
bound cemented (HBC) materials.
The performance of selected Queensland pavements was reviewed. Long lengths of LBC bases showed
little or no signs of block cracking or crocodile cracking, despite the considerable passage of time and
loading since construction. It was concluded that it is possible to design and construct a low-strength material
that develops fine micro-cracking with sufficient base thickness and subbase support to limit the extent that
micro-cracking leads to macro-cracking.
It is proposed that Austroads adopt a 28-day unconfined compressive strength (UCS) range of 1.0–2.0 MPa
for LBC materials based on the advice of the Queensland Department of Transport and Main Roads (TMR)
which has the most experience with these materials. This UCS range is the same as currently used in
Austroads guides. TMR has recommended that additional requirements be included in the definition, namely
that there needs to be a ‘steady’ increase in UCS between 7 and 28 days along with a minimum 7-day UCS
of 1.0 MPa or a degree of saturation requirement if the 7-day UCS < 1.0 MPa. These additional requirements
need consideration in the revision of the Austroads guides. TMR will also consider the use of modified
compaction in the future, possibly with adjusted UCS requirements in the longer term.
A structural design method was developed for pavements containing LBC materials and HBC materials in
the post-fatigue cracking phase of life, including:
• A new elastic characterisation method, applicable to LBC materials and HBC materials in the fatigue
cracked state, including methods to vary the design modulus according to the design modulus of the layer
supporting the cracked material and the thickness and modulus of the overlying bound materials.
• Design charts to select LBC base thicknesses to inhibit the development of block cracking and crocodile
cracking, with the minimum thickness varying with design traffic loading and the support provided by the
layer under the LBC base.
This design method was developed considering the use and performance of LBC for moderate-to-heavily
trafficked roads. Its applicability to the design of lightly trafficked roads needs consideration in the revision of
Austroads guides.
The research highlighted a need for a national test method for the mixing, compacting and curing of UCS
specimens to improve consistency of UCS results across jurisdictions. Given that the use of LBC materials
may increase with the improved design method, there is an increased need for this method lest HBC bases
are used as LBC bases.
Contents
Summary ......................................................................................................................................................... i
1. Introduction ............................................................................................................................................ 1
1.1 Background ...................................................................................................................................... 1
1.2 Purpose ............................................................................................................................................ 2
1.3 Scope ............................................................................................................................................... 2
1.4 Methodology ..................................................................................................................................... 3
2. Research Needs and Project Scope .................................................................................................... 1
2.1 Introduction ....................................................................................................................................... 1
2.2 Road Agency Needs ........................................................................................................................ 1
2.2.1 Queensland Department of Transport and Main Roads ..................................................... 1
2.2.2 Main Roads Western Australia ............................................................................................ 1
2.2.3 Transport for NSW............................................................................................................... 1
2.2.4 Department of Transport Victoria ........................................................................................ 2
2.2.5 Department of Planning, Transport and Infrastructure South Australia .............................. 2
2.2.6 Department of State Growth Tasmania ............................................................................... 2
2.3 Discussion at Austroads PSWG meeting October 2014 .................................................................. 2
2.3.1 Type of Lightly Bound Material ............................................................................................ 2
2.3.2 Project Objectives................................................................................................................ 3
3. Use of Cement Modified and Lightly Bound Cemented Materials .................................................... 5
3.1 Introduction ....................................................................................................................................... 5
3.2 Queensland Department of Transport and Main Roads .................................................................. 5
3.2.1 New Constructions .............................................................................................................. 6
3.2.2 Pavement Rehabilitations .................................................................................................... 8
3.3 Main Roads Western Australia ......................................................................................................... 9
3.3.1 Rural Floodways .................................................................................................................. 9
3.3.2 Hydrated Cement-treated Crushed Rock Base ................................................................. 10
3.4 Department of Transport Victoria ................................................................................................... 11
3.5 Transport for NSW ......................................................................................................................... 13
3.6 Department of Planning, Transport and Infrastructure, South Australia ........................................ 13
3.7 Department of State Growth Tasmania .......................................................................................... 13
3.8 New Zealand Transport Agency ..................................................................................................... 13
4. Literature Review ................................................................................................................................. 14
4.1 Introduction ..................................................................................................................................... 14
4.2 Distress Modes of Cement-treated Materials ................................................................................. 14
4.2.1 Distress Modes .................................................................................................................. 14
4.2.2 Description of Cracking ..................................................................................................... 15
4.3 Shrinkage Cracking ........................................................................................................................ 17
4.3.1 Introduction ........................................................................................................................ 17
4.3.2 Mechanism of Shrinkage ................................................................................................... 18
4.3.3 Measures to Reduce Shrinkage Cracking of Cemented Materials ................................... 18
4.3.4 Inducing Early-life Micro-cracking to Reduce Shrinkage Cracking ................................... 19
4.4 Fatigue Cracking ............................................................................................................................ 20
Tables
Table 3.1: Presumptive values for elastic characterisation of LBC materials ................................................. 7
Table 3.2: Minimum thickness and strength of unbound granular pavement materials required
below the LBC layer ....................................................................................................................... 8
Table 3.3: Target UCS to be used to select the optimum content of cementitious binder ............................11
Table 4.1: Typical crack patterns observed at deep-lift stabilised sites ........................................................16
Table 4.2: Pavement materials subject to accelerated loading .................................................................... 23
Table 5.1: Composition of Sites 2 and 2A ..................................................................................................... 36
Table 5.2: Summary of Coring Investigation at Site 2 ................................................................................... 38
Table 5.3: Summary of Coring Investigation at Site 2A ................................................................................ 38
Table 5.4: Summary of UCS data of cores ................................................................................................... 41
Table 5.5: Composition of Sites 16 ............................................................................................................... 42
Table 5.6: Summary of Coring Investigation at Site 16 ................................................................................. 44
Table 6.1: Design traffic summary ................................................................................................................ 48
Table 6.2: Summary of the construction phases ........................................................................................... 50
Table 6.3: TMR UCS results of laboratory cylinders at Bruce Highway Collinson’s Lagoon ........................52
Table 6.4: Contractor’s UCS results at Bruce Highway Collinson’s Lagoon.................................................52
Table 6.5: Pavement structure and seed moduli with sprayed seal surface.................................................56
Table 6.6: Pavement structure and seed moduli with an asphalt surfacing ..................................................56
Table 6.7: 28-day back-calculated moduli between wheelpaths .................................................................. 57
Table 6.8: 90-day back-calculated moduli between wheelpaths .................................................................. 57
Table 6.9: 1 year back-calculated moduli between wheelpaths.................................................................... 58
Table 6.10: 28-day back-calculated moduli outer wheelpath .......................................................................... 58
Table 6.11 90-day back-calculated moduli outer wheelpath .......................................................................... 59
Table 6.12: 1 year back-calculated moduli outer wheelpath ........................................................................... 59
Table 6.13: Field Trial Site B design traffic summary ..................................................................................... 61
Table 6.14: UCS results obtained by TMR at Bruce Highway – Barratta Creeks ...........................................64
Table 6.15: Summary of UCS test results measured by the contractor at Barratta Creeks ...........................65
Table 6.16: Pavement structure and seed moduli .......................................................................................... 68
Table 6.17: Back-calculated moduli between wheelpaths after 28 days ........................................................68
Table 6.18: Back-calculated moduli between wheelpaths after 90 days ........................................................69
Table 6.19: Back-calculated moduli between wheelpaths after 1 year ...........................................................69
Table 6.20: Back-calculated moduli in outer wheelpath after 28 days ............................................................ 70
Table 6.21: Back-calculated moduli in outer wheelpath after 90 days ............................................................ 71
Table 6.22: Back-calculated moduli in outer wheelpath after 1 year .............................................................. 71
Table 7.1: UCS results .................................................................................................................................. 74
Table 8.1: Parameters determined from the deflection magnitude signals ...................................................91
Table 8.2: Properties of selected materials ................................................................................................... 92
Table 8.3: Slabs tested for fatigue damage characteristics .......................................................................... 93
Table 8.4: Maximum dry densities and optimum moisture contents of the stabilised crushed hornfels .......93
Table 8.5: Maximum dry densities and optimum moisture contents for the stabilised
Barratta Creeks gravel ................................................................................................................. 93
Table 8.6: Density results for test slabs ........................................................................................................ 94
Table 8.7: Vibrating table results ................................................................................................................... 95
Table 8.8: Summary of deflection data from trafficked slabs ........................................................................ 96
Table 8.9: Summary of average deflection data trafficked slabs of comparable cement contents
and curing times ........................................................................................................................... 96
Table 9.1: Summary of road agency the minimum strength requirements of HBC materials .....................103
Table 9.2: Suggested maximum vertical modulus of cracked cemented material bases and subbases ...112
Table E 1: Typical layer compaction sequence ........................................................................................... 164
Figures
1. Introduction
1.1 Background
Austroads member agencies face significant challenges in the provision of a safe, resilient and productive
road network to meet increasing road user demands. The scarcity of quality, cost-effective road-building
materials is an increasing national challenge, particularly in the context of the lack of funding for road
maintenance and rehabilitation. In many instances, the use of alternative approaches, such as treating
granular materials with chemical binders, is becoming commonplace as reserves of high-quality
manufactured granular materials are exhausted or hauling such materials over long distances is
cost-prohibitive.
One output from Austroads project TT1664 Cemented Materials Characterisation was a recommendation to
improve design procedures for granular materials stabilised with cementitious binder contents of 3% or more
(Austroads 2014). To complement that work, road agencies and industry identified a need for improved
guidance for the design of pavements using materials with lower binder contents. The addition of a small
amount of cementitious binder to non-standard granular materials may result in a fit-for-purpose base or
subbase at a significantly lower cost than the use of crushed rock complying with standard specifications.
Cementitious binders may also be added to gravels complying with standard specifications improve shear/rut
resistance in certain traffic and/or high rainfall environments. Such lightly bound cemented (LBC) materials
have particular use in pavement rehabilitation and heavy patching.
This UCS criteria relates to test specimens prepared using 100% standard Proctor compactive effort at
100% standard optimum moisture content, normal curing for a minimum 28 days in moist condition without
soaking in water (Austroads 2019b).
As distinct from LBC materials, the definition of modified granular materials (Austroads 2017a p54) is as
follows:
Modified granular materials are granular materials to which small amounts of stabilising
agents have been added to improve modulus or to correct other deficiencies in properties
without causing a significant increase in tensile capacity (which could lead to crack
propagation). Modification of poor or marginal materials can yield improved material
properties at significantly less cost than the use of premium materials. Modified materials
have a maximum 28-day compressive strength (UCS) of 1.0 MPa, tested after moist curing
but without soaking at 100% standard Proctor maximum dry density and optimum moisture
content.
This UCS criteria also relates to test specimens prepared using 100% standard Proctor compactive effort at
100% standard optimum moisture content, normal curing for a minimum 28 days in moist condition without
soaking in water (Austroads 2017a).
This report is concerned with a particular type of lightly bound material in which only cementitious binders are
used. In this report these are referred to as LCM materials, although, as discussed in this report, it is
proposed to change the 28-day UCS range to 1.0–2.0 MPa consistent with Austroads (2017). In addition,
when significant amounts of binder are used, it is proposed to refer to these as heavily bound cemented
(HBC) materials. Both LBC and HBC are types of cemented materials.
While both LBC and HBC materials may be susceptible to fatigue cracking their condition in the
post-cracking phase of life may differ. As described in Section 8.2.4 (p114) of Austroads (2017):
A post-cracking phase of the design life can only be considered in the mechanistic
thickness design calculations if cracking from the fatigued cemented material does not
reflect through to the surface. To reduce the risk of reflection cracking the pavement should
provide a minimum cover equivalent to 175 mm of asphalt over the cemented material.
The above text relates to HBC materials which have sufficient binder to produce a bound layer with
significant tensile strength. Such cemented materials will commonly have 28-day UCS values above 2 MPa
but it is beyond the scope of this report to develop a minimum UCS value for HBC materials. Research was
required as to whether LBC materials can be designed to have cracking severities markedly less than for
HBC materials. Such LBC bases may have a useful service life in the post-cracking phase of life without the
need for a minimum 175 mm cover: periodic placement of a strain alleviating membrane (SAM) sprayed seal
can be sufficient to provide a serviceable pavement. Austroads (2019a) provides guidance on thin surfacing
treatments which inhibit reflection cracking.
Unlike pavements with HBC bases, pavements with LBC bases would not be designed to inhibit fatigue
because uneconomic thicknesses would be required due to their low strength. Accordingly, LBC bases would
be thinner than HBC bases with an associated lower initial construction cost.
Whilst such LBC materials are currently used throughout Australasia, design procedures are not
well-founded. In some instances this lack of knowledge has led to cracking despite the design intent as
highlighted in a New Zealand Transport Agency report (Gray et al. 2011) and as reported by some Australian
road agencies (Section 3). Road agencies advised (Section 2) that LBC bases would be more widely used if
the cracking could be more reliably limited.
The development of an Austroads mechanistic-empirical (ME) thickness design method would provide a
quantifiable means of comparing low-cost designs incorporating LBC materials to more traditional pavement
configurations. These developments would inform appropriate risk management strategies in the use of LBC
bases in relation to surface cracking.
Accordingly, in 2014 Austroads contracted the Australian Road Research Board (ARRB) to undertake
research project TT1897 Increasing the Use of Low-cost Modified Granular Materials in New and
Rehabilitated Pavements.
1.2 Purpose
The purpose of project TT1897 was to improve understanding of the mechanisms of crack formation
associated with LBC materials and develop Austroads guidance in terms of the pavement design. This report
describes the research undertaken and the proposed thickness design method.
1.3 Scope
There are a number of possible reasons why LBC materials crack in road pavements, including shrinkage
cracking and reflective cracking from underlying expansive subgrades. The principal focus of the research
undertaken in project TT1897 was load-induced fatigue cracking.
1.4 Methodology
The research included:
• identifying the research needs and project scope based on discussions with Australian and New Zealand
road agencies (Section 2)
• summarising what was known about the use and performance of LBC materials by road agencies at the
commencement of the project (Section 3)
• reporting and reviewing previous research findings (Section 4)
• reviewing the performance of selected Queensland LBC bases with thin bituminous surfacings (Section 5)
• monitoring and analysing the findings of field trials addressing the early life in situ moduli of LBC bases
(Section 6)
• undertaking laboratory testing to improve understanding of the fatigue characteristics of LBC materials
(Section 7 and Section 8)
• developing a framework for the design of flexible pavements containing LBC materials (Section 9)
• summarising the research findings and reporting the conclusions (Section 10).
2.1 Introduction
To assist in defining the project scope and tasks, road agency views were sought. These are reported below
together with the outcomes of a meeting of the Austroads Pavement Structures Working Group (APSWG) in
October 2014.
APSWG agreed that there was potential to increase the use of bases stabilised with low quantities of
cementitious binders to improve the performance of nonconforming granular materials used as bases in rural
areas and to provide higher-modulus layers under thin asphalt surfacings in urban roads. However, the field
performance of these LBC bases throughout Australia and New Zealand had been variable. Hence the
importance of this research project.
TMR identified two key research needs for its LBC, both plant-mixed and in situ stabilised:
• improved structural design procedures, if necessary, including an ability to design for fatigue cracking
• improved mix design procedures, particularly the influence of unbound granular material properties on
LBC performance.
TMR considered that there was potential for an increased use of LBC for moderately trafficked urban
pavements in wetter climates where the use of unbound granular bases was risky and premature thin asphalt
fatigue an issue. Thin asphalt-surfaced LBC bases would provide a lower-cost pavement than full-depth
asphalt. The use of LBC bases on rural highways would increase if the overall pavement thickness could be
reduced compared to an unbound granular pavement.
TMR did not consider there was an application for hydrated cement-treated crushed rock base (HCTCRB)
(Section 2.2.2) in Queensland.
The performance of Queensland LBC bases was investigated as part of the project as detailed in Section 5.
Main Roads Western Australia (MRWA) were satisfied with the performance of their process of in situ
modification using 1.5–2% type LH (low heat) binder (65% slag/35% cement) and further research related to
this treatment was a low priority.
MRWA’s principal research need related to improving the design processes for thin asphalt-surfaced
HCTCRB pavements for heavily trafficked urban road applications. Such pavements have considerably lower
whole-of-life costs than full-depth asphalt, deep-strength asphalt or concrete pavement types.
The main concerns of Transport for NSW (TfNSW) with respect to in situ cementitious stabilisation related to
construction practices, including spread rate control and variable depth of mixing.
However, in some parts of NSW, TfNSW asset managers were seeking to develop treatments for marginal
materials that result in improved resistance to shoving without shrinkage cracking. Methods to assess the
minimum or maximum amount of linear shrinkage have yet to be developed.
TfNSW did not consider there was an application for HCTCRB (Section 2.2.2) in New South Wales.
The Department of Transport (DoT) Victoria considered there was potential for an increase in the use of LBC
materials if the design processes were improved. In terms of binder types, over recent years there has been
increased interest in proprietary products including the use of bitumen emulsion. Whilst DoT would like these
binders to be considered further, DoT staff understood that the project funding was not sufficient to
investigate all binder types.
DoT did not consider there was an application for HCTCRB (Section 2.2.2) in Victoria.
The Department of Planning, Transport and Infrastructure’s (DPTI) main interest was in situ stabilisation of
granular pavements in remote rural locations, particularly with marginal materials. If there were more
confidence in design/performance, then it would lead to greater use in other locations.
DPTI considered the main research need was to improve design processes that reduce the risk of shrinkage
and fatigue cracking.
The Department of State Growth (DSG) considered there was potential for an increase in the use of LBC
materials if design processes could be improved to risk the shrinkage, and fatigue cracking reflecting through
thin bituminous surfacings.
DSG did not consider there was an application for HCTCRB (Section 2.2.2) in Tasmania.
APSWG agreed that the most common reason to chemically treat granular pavement materials was to
enhance the shear resistance of unbound granular bases with thin bituminous surfacings. Such treatments
include adding moderate amounts of stabilising binders to unbound granular materials to improve modulus,
and where an increase in tensile capacity may occur.
There are a wide range of binders that have been used, including cementitious binders, lime, bituminous
binders, and a wide range of proprietary products. As the project resources were limited, advice was sought
from road agencies regarding priorities for research needs that would lead to an increase in the use of lightly
stabilised materials. The consensus was that the highest priority was stabilisation with cementitious binders,
which in this report are referred to as LBC materials.
APSWG agreed that concerns about surface cracking were limiting the use of LBC materials. The most likely
causes of cracking are:
• shrinkage of the treated pavement material after construction
• shrinkage of reactive subgrades
• load-induced fatigue cracking.
Shrinkage cracking of cementitiously treated granular materials has also been extensively researched for
HBC materials. As discussed in Section 4.3, Austroads (2017) provides advice regarding measures to
reduce the severity and intensity of shrinkage cracking of HBC materials and also surfacing treatments to
inhibit reflection cracking. It is likely that much of this guidance is also applicable to granular materials lightly
bound with 1–2% cementitious binders. Also, existing surface treatments that have proved adequate for HBC
bases should be equally or more effective for LBC bases.
APSWG agreed that the project scope should not be extended to cover the cracking of LBC bases due to
reactive subgrades. This subject is better addressed in a separate research project across all pavement
types.
Accordingly, APSWG proposed that limited research in relation to shrinkage cracking not be undertaken. It
was agreed that the applicability of this existing guidance for HBC materials be reviewed by:
• collating and reviewing road agency performance data
• if necessary, undertaking short-term field trials to validate guidance on surfacing treatments
(e.g. effectiveness of SAM and geotextile reinforced seals).
Consideration would be given to whether specifications should include drying shrinkage limits.
It was agreed that the major focus of the research in this project should be load-induced cracking of LBC.
Due to their low strengths, it was anticipated that the research would confirm that LBC pavements have very
short fatigue lives. Based on advice of practitioners in Queensland, Western Australia and New Zealand, it
seems that, although the strength/modulus of these LBC materials quickly reduces under traffic loading, the
provision of thin bituminous surfacing treatments is usually sufficient to provide a useful service life after the
modulus has reduced. In this regard, the nature of the fatigue cracking of LBC materials after a reduction in
strength/modulus appears different from the block and ladder cracking typically associated with thick,
cemented materials (Figure 4.4). Consequently, a key research objective was to gain a better understanding
of the condition of LBC post-fatigue cracking. APSWG agreed that a desirable project outcome would be the
development of a design method that reduced the risk of fatigue of LBC base and the resulting unacceptable
surface cracking.
Similar to the findings of New Zealand research (Section 4.4.3), a key objective of the Austroads project was
also to gain a better understanding of the continuum from cement-modified materials to LBC materials to
HBC materials. In particular, an improved understanding was required of the variation in the extent and
severity of surface cracking with binder content. As shown in Figure 2.1, thin bituminous-surfaced HBC
bases at their end of fatigue life may have large blocks of cracked cemented materials. Such cracking has
not been reported by practitioners for LBC bases (see Section 5) which are thinner, have lower flexural
strengths, and shorter fatigue lives.
3.1 Introduction
In scoping the project in 2014–15, advice was sought from Australian and New Zealand road agencies on
their use of cement modified granular materials and LBC materials. Of particular interest was whether they
could identify a list of LBC projects that could be investigated during the project. Rural highway projects with
the following characteristics were requested:
• in situ stabilised granular bases under thin bituminous surfacings
• stabilisation using 1–2% of lime or medium-to-slow-setting cementitious binders
• with three or more years of moderate-to-heavy trafficking.
Road agency uses of cementitiously modified and LBC materials are summarised below.
In relation to LBC materials the following key applications and drivers were identified:
1. New constructions
Pavements in both wet environments and dry environments (with lower-level drainage) have experienced
problems in terms of the specification of unbound pavement base materials. In conjunction with good
cross-section design (drainage, full-width homogenous materials, etc.) a LBC is often utilised to
eliminate/minimise the moisture sensitivity of unbound gravels. Low amounts of cement have been used
to minimise cracking effects. For design purposes, the LBC is treated as a good-quality unbound
pavement layer.
Some experienced practitioners and designers also made the unproven (or un-tested) comment that
pavements designed in accordance with the current material specifications do not appear to be
withstanding the loading from the current legal heavy vehicles. It is suspected that pavements are
suffering from both overloading and a high number of quick axle repetitions from B-doubles, road trains,
and other approved configurations. With the failure mode often being a rut/shove type failure there is a
suspicion that shear failure from heavy loads could be a major contributor. It is often difficult to determine
whether elevated pavement moisture levels have pre-existed (migrated into the pavement somehow
before failure) or have subsequently entered via rainfall post a loading shear failure.
New construction projects typically use a controlled mixing process in a plant (pugmill) with the mixed
material placed and compacted as part of a designed pavement structure. Base quality gravel is typically
mixed with 1.5–2.0% of type general blend (GB) cement and used as a base layer (on top of a
substructure designed in accordance with Austroads (2017) and TMR (2018). Generally, construction is
conducted according to MRTS10 Plant-mixed Lightly Bound Pavements (TMR 2019). Some district
variations exist, in particular the slurry requirements between cementitious layers, where applicable.
The underlying pavement (subbase) layer materials vary, with unbound granular (gravel),
cement-stabilised subbase (Category 2) and cement-modified all in use.
In certain clay subgrade areas, lime-stabilised subgrades have also been noted and rock treatments over
swampy ground sometimes apply. In areas where the grade line is elevated with embankment works
required, select fill subgrade materials (300 mm total layer) with a minimum soaked CBR of 10–15% often
apply. Otherwise, natural materials are compacted to 97% standard maximum dry density.
2. Rehabilitation projects
Where sufficient funds allow, projects are designed for a 20-year design traffic loading. This often
includes widening existing pavements to meet current geometric standards or widening to cater for
additional gravel overlay material.
Typical applications, after widening works to match the existing pavement, include:
• the existing pavement remains ‘as-is’ and is overlaid with new plant-mixed LBC
• the existing pavement is in situ modified with cementitious additive and overlaid with a new unbound
base (gravel) or plant-mixed LBC (that is, the existing pavement becomes a lightly bound subbase)
• the existing pavement is overlaid with gravel to a defined depth and then mixed with the in situ
pavement material to provide a total LBC depth of between 150 mm and 250 mm.
The driver for the use of LBC is either as per (1) above and/or to maximise the utilisation of existing in situ
materials to provide adequate and cost-effective pavement structures for the largest possible length.
TMR’s pavement design supplement (TMR 2018) uses terminology and definition that is broadly in alignment
with Austroads (2017) as follows:
Lightly bound granular materials are typically specified to have a UCS between 1.0 and
2.0 MPa at 28 days when used as LBC bases, and 1.0–2.0 MPa at seven days when used
as improved layers/subbase.
While this approach may result in a material that is more prone to fatigue and/or shrinkage
cracking than cement-modified materials (with maximum 28-day UCS of 1.0 MPa, as
defined in Austroads (2017)), it has a number of benefits, including:
• reduced moisture sensitivity
• higher strength and stiffness
• reduced permeability
• reduced erodibility
• reduced sensitivity to variations in grading and plasticity
• higher binder content is more readily and consistently achieved.
To alleviate some of the concerns relating to cracking when used in basecourses, TMR
typically adopts additional controls such as:
• SAM/SAMI seals over the LBC bases
• minimum 200 mm total thickness of LBC base
• minimum support conditions, as detailed in Section 8.2.8 of Austroads (2017).
The TMR specification MRTST10 (TMR 2019) for lightly bound base and subbase requires a 28-day UCS
minimum of 1.0 MPa and a maximum of 2.0 MPa, tested after moist curing but without soaking at
100% standard Proctor maximum dry density (MDD) and optimum moisture content (OMC). The
cementitious binder most commonly used is 75% cement/25% fly ash (complying with type GB cement).
Over the last 15 years TMR has placed over 100 lane-km of plant-mixed lightly bound base (PM-LB) and
carried out a significant amount of in situ stabilisation. Binder contents were generally in the range of
1.5–3.0%. Figure 3.1 is an example of a PM-LBC trial in Brisbane placed in 2011 using 1.5% type GB
(general blend) cement. The lightly bound base was 300 mm thick, placed in two 150 mm layers. Several
other projects are described in Section 5.
Figure 3.1: LBC trial on Frank Mallan Drive Lytton about 2.5 years after construction
In terms of the TMR structural design method, the lightly bound layer is modelled as unbound granular
material as follows (TMR 2018):
• sub-layered into five sublayers using Austroads (2017) sub-layering
• cross-anisotropic (with a degree of anisotropy of 2)
• Poisson’s ratio of 0.35
• modulus of top granular sublayer in accordance with Table 3.1.
1 Transport and Main Roads Specification MRST10 Plant-mixed lightly bound pavements (TMR 2019).
2 Lightly bound base layers are typically covered with either a thin asphalt or sprayed bituminous treatment, with the
lightly bound pavement material forming the main structural pavement layer. These pavements would typically be
specified in moderately trafficked pavement applications or where moisture control is required during construction or
throughout the service life of the pavement.
Due to the sensitivity of the performance of lightly bound bases to underlying support conditions, TMR (2018)
provides the following minimum requirements:
For lightly bound base pavements, the base is typically supported on a subbase with a
thickness of at least 150 mm and which achieves a vertical design modulus of at least
150 MPa at the top of the subbase (determined using the procedures detailed in
Sections 8.2.2 and 8.2.3 of AGPT02). This may be achieved by increasing the thickness of
the subbase, and/or including additional select fill or unbound granular material beneath
the subbase.
TMR (2018) provides the following advice concerning the risk of cracking:
When using lightly bound granular materials, the risks of both shrinkage and fatigue
cracking should be recognised and accepted, and associated maintenance interventions
over the life of the pavement should be anticipated.
TMR has used cement stabilisation of pavement materials as a rehabilitation treatment on an intermittent
basis for many years, including for the treatment of flood-affected roads. In Section 5, the performance of
LBC bases in Queensland is described in detail, particularly the performance of in situ stabilisation of rural
roads.
In the design of pavement rehabilitation treatments (TMR 2020), the definition of LBC and the thickness
design methods differ from those used in the design of new pavements. For rehabilitation projects, LBC
materials have a target 7-day UCS of 1.5 MPa within an allowable 7-day range of 1–2 MPa. The 28-day UCS
values could be 30–50% higher for a type GB cement. These criteria relate to specimens compacted to
100% standard Proctor maximum dry density (MDD) at standard optimum moisture content (OMC), then
moist cured without soaking.
Where LBC are used, the following TMR requirements apply to in situ stabilisation:
• The minimum thickness and strength of unbound granular pavement material specified in Table 3.2 shall
be provided under the modified layer.
• The thickness of the modified layer shall be between 200–300 mm.
• Must complete direct measurement of the characteristic modulus as per AGPT02.
Table 3.2: Minimum thickness and strength of unbound granular pavement materials required below the LBC
layer
1 Where there the subgrade CBR is less than 3%, a capping layer is required as per TMR pavement design
supplement.
2 CBR is California Bearing Ratio.
Modified materials are considered to behave as unbound granular materials with improved stiffness. For the
purpose of mechanistic design, they are modelled with the following properties:
• cross-anisotropic (degree of anisotropy of 2)
• a Poisson’s ratio of 0.35
• sub-layered
• have a maximum potential modulus less than the characteristic modulus determined by direct
measurement as per AGPT02 and 600 MPa.
For many years Main Roads Western Australia (MRWA) has used in situ modified granular bases for rural
floodways – MRWA policy is to stabilise all floodway pavements (where bridges are not provided) and repair
of sprayed seal surfaced rural granular pavements. The binder used is 1.5% to 2% type LH binder
(35% cement/65% slag). The UCS requirement for this use is a 7-day value of 0.6–1.0 MPa on laboratory
samples stabilised with type GP cement, compacted to 100% modified Proctor MDD and OMC, and tested
after four hours soaking in water. Layer thicknesses are designed using the Austroads (2017) empirical
design chart for unbound granular materials. The modified granular base is normally surfaced with a cutback
prime and a Class 170 bitumen double/double sprayed seal. MRWA reports these pavements are generally
performing well.
When the granular base is crushed gravel or crushed rock achieving a 7-day UCS below 1.0 MPa is not
always possible at the minimum practical cement contents of 0.75%. In those circumstances, the stabilised
base is surfaced with a geotextile reinforced seal (GRS) to inhibit surface cracking.
In response to the project request for performance data, MRWA identified three floodways on the Great
Eastern Highway between chainages 239.3–240.7 km. All three floodways include a 200 mm thick
cement-modified laterite (PI = 6%) base overlying 300–400 mm thick granular subbase. These pavements
were constructed in 2006.
The three floodways (Figure 3.2) were inspected in December 2014 as part of this research project. After
eight years of trafficking, all the pavements had minimal rutting and good ride quality. At two of three sites
there was no cracking in the traffic lanes. At the other floodway, about 5–10% of the eastbound lane was
cracked with pumping of fines (Figure 3.3). The spacing between cracks was about 500 mm. There was no
cracking in the westbound lane. The difference in cracking between the east and westbound lanes could not
be explained.
Site 3 242.39–242.50 km
The other significant MRWA application of cement-treated bases is hydrated cement-treated crushed rock
base (HCTCRB). HCTCRB is crushed rock base plant-mixed with 2% cement then stockpiled and reworked
at the quarry before placement in roadbed. Thin asphalt-surfaced HCTCRB was extensively used for Perth
freeways between 2000 and 2009. In recent years, use has been limited due to HCTCRB cracking reflecting
through the thin asphalt surfacing.
HCTCRB currently has a specified maximum 28-day UCS of 1.3 MPa when tested at 100% modified Proctor
MDD and soaked for four hours before testing. HCTCRB test results indicate the 28-day UCS values at
100% standard Proctor MDD without soaking are less than 1 MPa. Despite this UCS value being within in
the Austroads (2017) range for modified materials, MRWA considers HCTCRB susceptible to fatigue
cracking and now requires consideration of this in thickness design.
Due to this risk of HCTCRB cracking, MRWA now requires the following surfacing for HCTCRB in freeway
applications:
• 30 mm open-graded asphalt
• 30 mm size 10 mm dense graded asphalt
• geotextile reinforced seal.
At the October 2014 meeting of APSWG (Section 2.3), it was agreed not to consider the field performance of
HCTCRB in this research project as this material is only used in Western Australia.
DoT’s in situ stabilisation specification (VicRoads 2008) allows a wide range of binders to be used in
cementitious modification, from fast-setting type GP cement to slow-setting blends such as slag/lime.
Rehabilitation practices vary between regions; for example, at the commencement of the research project:
• Western Region – a variety of pavement rehabilitation treatments are used including in situ stabilisation
for lower-trafficked rural roads. Slow-setting slag/lime or sometimes triple blends are used at a binder
content of about 2%.
• Northern Region – there is limited use of in situ cement stabilisation; when it is used, slow-setting
slag/lime binders are preferred. They have also treated granular bases with dry powdered polymer.
• Eastern Region – favours stabilising existing granular materials bases for use as a subbase followed by a
200 mm thick granular resheet. Commonly, type General Purpose (GP) cement is used; however, type
GB cement has also been used.
For cement stabilisation, binder contents range from 1.5–3.5% to meet the 7-day UCS requirements in
Table 3.3. Note that for type GB cement, the 7-day UCS of 1.5 MPa equates to a 28-day UCS value of about
2.0 MPa. This value relates to specimens compacted to 100% modified Proctor MDD rather than
100% standard Proctor MDD as used in the Austroads definition of modified materials. Assuming that
standard MDD is 5% lower than modified MDD and assuming a 9% reduction in UCS for a 1% decrease in
density (White 2006), the VicRoads 28-day UCS for type GB cement is about 1.4 MPa.
Table 3.3: Target UCS to be used to select the optimum content of cementitious binder
Cementitious binder
Target 7-day UCS at modified
content
compactive effort (MPa)
(% by mass)
Type of work
Slow(1) Medium(2) Rapid(3)
Min Max
Setting Setting Setting
Material modification 1.5(4) 3.5 1.0 1.5 2.0
Fully bound not
4.0 5.5 2.5 3.5
(deep-lift stabilisation) applicable
Bound subbase for deep strength asphalt
not
pavements where assigned design 3.0 2.5 3.5 5.0
applicable
modulus is not more than 500 MPa
1 Slow-setting: Slag/lime blends, alkali-activated slag and other supplementary cementitious blends.
2 Medium-setting: type GB cements, cement/slag blend (50% to 60% cement content),cement/fly ash blend (70% to
80% cement content), cement/slag/fly ash blend (55% to 65% cement content), slag/lime blends, alkali-activated slag
and other supplementary cementitious blends.
3 Fast-setting: type GP cement.
4 The Superintendent may agree to a cementitious binder content of less than 1.5% but at least 1% by mass if the UCS
requirement at a binder content of 1.5% is more than 50% above the target UCS. If less than 1.5% by mass of
cementitious binder is permitted, a minimum of two mixing runs shall be undertaken after spreading of cementitious
binder and the minimum density ratio specified in Clause 307.13 shall be increased by one percentage point.
Since the specification values shown in Table 3.3 were selected, VicRoads tested the UCS of three
high-quality crushed rocks treated with 1% type GP cement (Figure 3.4). The testing arose from the need to
investigate the practice of adding 1% binder to plant-mixed crushed rock during the construction of unbound
granular pavement material as an aid to achieving dry back. The results indicated that the 28-day UCS
values of specimens compacted to 100% standard Proctor MDD and without soaking ranged from
2.6–3.2 MPa, with an average value of 2.9 MPa.
Figure 3.4: Unconfined compressive strength (UCS) of unsoaked samples after 28 days curing
In addition, all three stabilised crushed rock subbase materials had UCS values exceeding the DoT target
(Table 3.3). For these high-quality granular materials it seems unlikely that type GP cement can be used to
manufacture a material meeting the proposed Austroads definition of LBC (Section 9.3).
DoT consider that in situ stabilised material should be of a reasonable quality; otherwise, it becomes overly
dependent on the performance of the binder or it may require a higher than desirable binder content, thus
increasing the incidence of cracking. Also, with higher binder contents there is a greater risk that the
specified density may not be achieved. A satisfactory grading and plasticity index also improve resistance to
deformation (rutting).
When using in situ stabilising granular bases, DoT anticipates that special surfacing treatments such as a
SAM seal are required to inhibit surface cracking.
In terms of structural thickness design for in situ stabilisation, DoT uses its unbound granular design chart
(based on Austroads (2017)) to select stabilisation depth and desirable material properties. No reduction is
made in the thickness of cover over subgrade for the increased modulus of the cement-treated base.
Due to the limited use of this type of rehabilitation treatment in recent years, DoT did not identify any projects
for a performance review in this project other than one possible project on Maroondah Highway, Merton. It
appears the Merton project was stabilised with a slow-setting binder, being a mixture of cement, slag and
lime, but it was not inspected as the exact location of the project could not be established.
The modified material may be plant-mixed or in situ stabilised. LBC bases are not commonly used.
Deep-lift in situ stabilisation has been used over the last 20 years as a strengthening treatment for rural
highways. The high binder content associated with deep-lift stabilisation, typically 4–5%, makes the layer a
HBC base susceptible to cracking. Slow-setting binders such as lime, slag/lime and to a less extent
slag/lime/fly ash and slag/cement are used. These binders have the benefit of minimising shrinkage cracking.
Due to the limited use of LBC materials in NSW, TfNSW was unable to provide performance data for the
project.
Due to the limited use of LBC materials, DPTI was unable to provide performance data for the project.
Due to the limited use of LBC, the Department was unable to provide performance data for the project.
4. Literature Review
4.1 Introduction
To assist in fulfilling the project objectives previous research on granular materials cementitiously treated
with 1–2% cementitious binders was summarised.
Section 4.2 describes the distress modes of materials treated with cementitious binders. As shrinkage
cracking is common, Section 4.3 describes relevant research findings and current guidance on reducing its
effect on pavement performance. Section 4.4 summarises research that has been undertaken on how LCM
materials respond to loading.
Chakrabarti, Kodikara and Pardo (2001) reported a survey of Australian local government agencies on the
distress modes of chemical treatments of lightly trafficked pavements (see Figure 4.1). At that time type GP
cement and lime were the most commonly used binders.
Cracking was the predominant distress type of chemically treated pavements (Figure 4.2). Shrinkage of the
treated material was the most reported reason for the cracking, followed by cracking due to expansive
subgrades and load-induced fatigue cracking (Figure 4.3).
Over the 15 years since this survey was taken there has been an increase in the use of medium-to-slow
setting binders, improvements in stabilisation equipment and surfacing treatments. This may well have
altered the predominant distress modes; nevertheless, the review of Queensland cracking data
(Section 5.3.2) concluded longitudinal and transverse cracking were the dominant cracking types of LBC
bases with a very minor amount of traffic-induced crocodile cracking.
It should be noted that the binder contents in use were not reported by Chakrabarti, Kodikara and
Pardo (2001), but were most likely in the range 2–4%. By comparison, the objective of the Austroads project
is to investigate granular bases lightly bound with lower contents, commonly around 2% cementitious binder.
As mentioned in Section 2.3.2, the scope of this Austroads research project does not cover cracking of LBC
materials due to expansive subgrades. This subject is better addressed in a separate research project
across all pavement types.
Vorobieff, Walter and Anwar (2010) provide a detailed description of the nature of cracking of HBC bases
stabilised using slow-setting cementitious binders (5% binder) in New South Wales. The description was
based on periodic inspections of deep-lift in situ stabilised pavements over 15 years. The observed cracking
patterns of HBC bases provide a useful benchmark to compare and contrast with that for LBC materials
investigated in this research project.
Table 4.1 lists the typical crack patterns observed in pavements with HBC bases. The primary cracking is
transverse shrinkage cracking. Vorobieff, Walter and Anwar (2010) attribute the secondary longitudinal
cracking to shrinkage cracking. George (2002) provides an alternative explanation:
In fact, the performance of a cement-bound base is often hardly affected by primary
cracking, which is the occurrence of transverse cracking due to shrinkage and occasionally
thermal effects. Traffic causes further deterioration of primary cracks through shear
movement of the crack edges, in some cases resulting in longitudinal wheel-path cracks.
Transverse cracks widen, with possible reduction in interlocking characteristics of the crack
faces. Little et al. (1995) with calculations, showed that transverse cracks induced by
shrinkage and exacerbated by thermal contraction can increase the intensity of
load-induced flexural stresses by a factor of as much as 2.0, which explains how the
longitudinal cracks evolve with time. This phenomenon, termed secondary cracking, is the
chief cause of a significant reduction in the performance of a cement-bound base and
hence, eventually, to pavement distress. The primary transverse cracks, if reflected
through the wearing surface, may permit ingress of surface water and consequent
degradation of the lower layers by pumping and/or debonding.
Vorobieff, Walter and Anwar (2010) reported that with the development of a weaker subgrade through
moisture ingress, the formation of short sections of wheelpath block (ladder) cracking can result in the larger
block crack pattern (Figure 4.4). Over the 15 year observation period three of the four crack patterns shown
in Figure 4.4 were observed: crocodile fatigue cracking was not observed at any of the sites.
The key difference between the cracking characteristics of HBC base and that observed for Queensland LBC
bases (Section 5) was the absence of block cracking for LBC bases.
4.3.1 Introduction
Road agency practitioners advised that the shrinkage cracking of LBC bases is of concern as it can lead to
increase surfacing and routine maintenance costs and possibly affect service and structural lives albeit to a
lesser extent than for HBC bases.
Austroads (2017) does not provide any specific guidance on the shrinkage characteristics of LBC. As
described in Section 4.3.3, Austroads (2017) provides advice on measures to reduce shrinkage cracking of
HBC materials, which to some extent applies to LBC materials.
For HBC bases with cement contents of 3% or more shrinkage cracking due to drying and/or thermal
movement with time can reduce the pavement service life considerably by erosion and degradation of
material in the vicinity of these cracks. Shrinkage cracking also increases load-induced stresses and
therefore influences fatigue life.
Shrinkage of cement-treated material mainly consists of drying shrinkage and autogenous shrinkage. Drying
shrinkage is a result of water from the mixture evaporates to the atmosphere (Figure 4.5). Autogenous
shrinkage is not related to moisture loss to the environment, but it is caused by water consumption through
hydration reaction which is called self-desiccation (Dunlop, Moss & Dodd 1975; Zhang, Hou & Han 2012).
Shrinkage cracking occurs when the shrinking cement-treated layer is restrained in movement by the
underlying layer and/or are self-restrained (e.g. by strain gradient).
Shrinkage cracks are generally fine/narrow during initiation, but subsequently become wider. This is
attributed to continued drying shrinkage and thermal cycling.
The cause of shrinkage cracking has been studied extensively for cemented materials. It has been found to
be related to the shrinkage of the fine aggregate fraction, the amount of water used during placement, and a
lack of adequate curing.
In relation to HBC (commonly ≥ 3% binder), Austroads (2017) states the following measures may be
considered to reduce shrinkage cracking:
• Minimise the total cementitious binder content – the lower the binder content, the lower the moisture
required, and the less the shrinkage. However, this renders the material susceptible to erosion when
subjected to moisture ingress under loading.
• Use slow-setting binders, which promote slightly less shrinkage than type GP cement. These binders are
also likely to require less moisture for compaction which also reduces shrinkage.
• Minimise the clay content of the material to be cemented by controlling the amount and plasticity of fines
in the aggregate. This can be achieved by limiting the fines content to less than 20% passing the 75 µm
sieve and the plasticity index to values not greater than 20.
• Treat the existing pavement materials which have an excess of plastic fines by:
– pre-treating with lime or lime and cement, followed by stabilisation with fly ash blend cement
– mixing in gravel or crushed rock with little or no fines, the amount of material varying with the plasticity
and fines content of the existing pavement compared to the desired levels and the proposed depth of
stabilisation
– applying both of the above treatments
– using the existing material as a subbase only or, alternatively, programming for an early overlay.
• Place a bituminous curing coat as soon as possible after construction to inhibit rapid drying out of the
cemented layer and delay surfacing as long as possible so that cracking occurs before surface
placement.
• In addition, whilst the following two measures do not serve to minimise shrinkage cracking they do
ameliorate the influence of shrinkage cracking on overlying layers:
– in situations where the final seal is to be placed immediately following curing, apply a SAM (or a SAMI)
or geotextile seal to inhibit potential shrinkage cracking of the surfacing
– use an appropriate polymer modified binder asphalt surfacing in preference to conventional asphalt
(refer to Austroads 2009).
The benefits of these treatments are not reflected by the Austroads thickness design process because the
design model is not capable of predicting the onset and development of reflective cracking. Therefore, similar
pavement compositions and structures result regardless of the presence of these treatments. The benefits,
however, can be shown in terms of improved reliability of the design by providing a surfacing less prone to
the onset and development of reflective cracking. The use of SBS or crumb rubber modifiers has been
shown to provide a more elastic response and hence, provide a surface with a greater capacity to resist
reflection cracking. Further discussion on the selection of appropriate PMBs for this type of application can
be found in the Part 4F: Bituminous Binders of the Guide (Austroads 2017b).
Freeman and Little (1998) concluded that laboratory research showed that the following practical factors
affect the amount of base shrinkage:
• initial shrinkage is caused by loss of water due to drying of the base
• the soil type is an important variable: low clay content granular materials shrink less
than fine-grained soils
• a mixture compacted above optimum moisture will shrink more than the same mixture
compacted at optimum moisture content
• changes in stabiliser content, density and temperature have only a minor effect on the
amount of shrinkage compared to the effect of initial compaction moisture content
• the spacing and width of the cracks depend on the tensile strength of the stabilised
material, shrinkage properties (soil type), and the friction between the base and
subgrade/subbase.
Smith and Caltabiano (1987) reported the results of field trials of low-shrinkage cement-treated base (CTB
category 1 with a minimum 7-day UCS of 3 MPa). Based on early-life performance it was concluded that
low-shrinkage cement-treated base reduced but not eliminated shrinkage cracking. Interestingly, it was
observed that the shrinkage cracking of low-shrinkage cement-treated bases was finer for pavements on
high strength subgrades and those opening to traffic soon after construction. The authors concluded that
there is ‘no known process which will eliminate shrinkage cracking in cement-treated bases so the only
course is to limit this inherent weakness as much as possible’. Section 9.5describes minimum support to
LBC bases to inhibit the development of macro-cracking.
Over the last 10 to 15 years, there has been considerable research in the USA on the effect of inducing
micro-cracking in cement-treated bases on the extent and severity of shrinkage cracking (Sebesta 2005; Wu
& Gaspard 2013).
Micro-cracking is commonly induced by passing a vibratory roller over a newly constructed cement-treated
base (Figure 4.6) to relieve the internal shrinkage stresses that develop during the initial cement hydration.
The desired result of this micro-cracking process is a network of fine, closely spaced cracks that are
uniformly distributed throughout the cement-treated base.
Sebesta (2005) reported the findings of field trials in Texas from which it was concluded that roller-induced
micro-cracking of a 4% cement-treated granular material reduced the extent of shrinkage cracking by 50%.
No information has been reported on the influence of roller-induced micro-cracking on the fatigue cracking
characteristics of cemented materials.
4.4.1 Introduction
While Austroads (2017) provides a method to predict the fatigue life of HBC layers, there is currently no
method to design for the fatigue cracking of LBC layers.
Concerning the need to develop a method to predict the fatigue life of LBC, summarised below are the
findings of previous research related to:
• laboratory fatigue testing
• fatigue in the roadbed, including accelerated loading and in-service performance.
There is a very limited amount of research that has been undertaken on the fatigue of granular materials
treated with around 2% cementitious binder.
Arnold, Morkel and van der Westhuizen (2012) reported the findings of flexural beam fatigue testing of a size
40 alluvial gravel with type GP cement at contents of 1%, 2% and 4%. This testing was undertaken to
complement the results of New Zealand accelerated loading described in Section 4.4.3. Test beams were
subjected to accelerated-curing prior to fatigue testing as follows:
• compacted beams were wet cured in the compaction mould for about 20 hours
• the beams were then removed from the mould, placed in sealed plastic bags and then cured in an oven at
a temperature of 40 °C for 72 hours
• lastly, the beams were removed from the bags and dried for 24 hours in the laboratory, presumably at a
temperature of about 21 °C.
This is a different curing process from the ≥ 90 days moist curing at a temperature of 21 °C used in
Austroads research (Austroads 2014). The use of accelerated curing at 40 °C may have led to more
micro-cracking of the test beams than the Austroads long-term moist curing process. This micro-cracking
may be the reason the test beam moduli were a factor of 10 lower than the Austroads (2014) measured
values. The tolerable strains for a given fatigue life were also significantly higher. In support of their
accelerated-curing process, Arnold, Morkel and van der Westhuizen (2012) state:
a case can therefore be presented for the carefully controlled temperature-induced
cracking in laboratory samples to reflect (field) performance better.
The results of the beam fatigue testing are given in Figure 4.7.
Using the laboratory test results, Arnold, Morkel and van der Westhuizen (2012) calculated the tensile strains
in accelerated loading of pavements which included alluvial greywacke gravel stabilised using cement
contents of 1%, 2% and 4%. Figure 4.8 illustrates the pavement structure used in the cemented material
strain predictions.
Figure 4.9 shows the predicted fatigue lives using a design modulus of 2000 MPa for all three cemented
materials rather than using the measured modulus. Note the very low predicted fatigue lives of the 1% and
2% mixes, consistent with the findings of this research project (Section 9.2).
Note: that the thickness of cemented-stabilised material should read 200 mm rather than 300 mm.
In addition the pavement included a 40 mm dense-graded asphalt surfacing.
Figure 4.9: Pavement fatigue lives predicted for the CAPTIF pavements using 2000 MPa modulus
Materials in this research may have not been fully bound and future research should
investigate higher cement contents. The 1% and 2% cement-stabilised aggregates did
result in solid and ‘bound’ looking beams. However, when tested they were low in tensile
strength and the numbers generated for the design tensile fatigue criteria resulted in short
fatigue lives for typical pavement designs. Therefore, 1% and 2% cement-stabilised
aggregates in this study would always be considered as unbound as their phase 1 bound
behaviour is very short. Thus a boundary in terms of tensile strength or cement content is
not needed to define when a material is unbound, modified and bound because the tensile
strength measured in the laboratory, combined with use in design, will quickly determine if
any phase 1 fatigue life is possible.
Alabaster et al. (2013) describe an extensive New Zealand research project which included the following
objectives:
• Objective1: Determine the benefits of using cement and/or lime-modified aggregates in terms of
increased performance (rut resistance) and incorporate this in a design methodology, filling a gap
identified by Austroads.
• Objective 3: Understand the continuum from unbound (no binder), modified (small amounts of binder) to
bound (high amounts of binder) behaviour.
The methodology to complete the objectives involved a combination of accelerated pavement tests at the
Canterbury Accelerate Pavement Testing Indoor Facility (CAPTIF) in 2007–08 and 2008–09, and a limited
review of the field performance of bound stabilised pavements.
Accelerated loading was undertaken on six material types listed in Table 4.2. All stabilised layers were
200 mm thick with a nominal 40 mm thickness of dense graded asphalt surfacing. Unfortunately, the testing
of the 2% cement mix was affected by accidental flooding when a water pipe burst.
About 1.5 million cycles of 60 kN dual-tyre loading were applied which equates to about 7.6 x 106 ESA of
loading. One interesting finding was that at the end of loading no surface cracking, either fatigue or
shrinkage, was observed. This absence of fatigue cracking in the thin asphalt surfacing is consistent with the
very limited surface cracking observed in an Australian accelerated loading trial of crushed rocks stabilised
with 3% and 4% cement (Austroads 2008). However, in this Australian research cracking was observed
when the pavement was excavated. The absence of surface cracking in both these accelerated loading trials
may be due to bituminous surfacings being newly placed and hence more ductile than for in-service
pavements.
As mentioned in Section 4.4.2, laboratory beam testing indicated that the 1, 2 and 4% mixes were all
susceptible to fatigue cracking. However, surface cracking was not observed under accelerated loading.
Nevertheless, the measured vertical subgrade strains (Figure 4.10) and the moduli back-calculated
(Figure 4.11) from Falling Weight Deflectometer (FWD) surface deflections both indicated the cemented
materials decreased in modulus under accelerated loading. (Note the performance of the 2% mixes was
affected by accidental flooding.) Of interest to this research project were the relative moduli of the 1% mix
and 4% mix at the end of loading. The 1% mix was about only 20% lower in modulus than the 4% mix. The
moduli of both these mixes after trafficking were more than twice that for the unbound granular base. This
information was used in developing the proposed Austroads design method (Section 9).
Note that the FWD testing before accelerated loading was taken a month after construction. Consequently,
the cemented materials may not have cured to a long-term modulus value at the commencement of loading.
This may have been a factor in the 4% mix mean back-calculated modulus (4 550 MPa) being low. Also, the
test pavement was compacted to a relatively low field density.
Figure 4.10: Change in measured vertical subgrade strains with loading cycles
Whilst Site 16 was in good condition after four years of trafficking, Site 12 cracked and rutted after 1 year of
trafficking (Figure 4.12).
The investigation included periodic deflection testing at two sites stabilised with 3% cement. From these
deflections, the isotropic moduli of the cement-treated base were back-calculated (Figure 4.13). The solid
blue line is the 50 percentile modulus value which, after the first two years, gradually reduced to an isotropic
modulus of about 1000 MPa, presumably due to fatigue damage. The dashed blue line is the 10 percentile
modulus values corresponding to the weaker areas of pavement that most likely cracked and rutted first. The
isotropic modulus of these weakly cemented materials was about 500 MPa. According to Austroads (2019a),
an isotropic modulus of 500 MPa is roughly equivalent to the following cross-anisotropic characterisation: a
vertical modulus of 550 MPa and a horizontal modulus of 275 MPa. This information was considered in the
development of the proposed elastic characterisation (Section 9.4).
4.6 Summary
Road agencies have identified the potential to increase the use of granular bases treated with
1–2% cementitious binders to improve their rut resistance when used in thin bituminous surfaced pavements
and to provide higher modulus layers under thin asphalt surfacings.
This review of Australian and New Zealand research has concluded that:
• LBC materials have the potential to crack due to shrinkage, albeit to a lesser extent than HBC materials.
Much of the extensive research that has been undertaken on measures to minimise the effects of
shrinkage of HBC materials with binder contents of 3% or more is considered applicable to LBC
materials.
• LBC materials have very low fatigue lives.
• HBC bases are susceptible to load-induced block-cracking that forms following transverse shrinkage
cracking. Based on the extensive use of LBC bases in Queensland (Section 5), it is unlikely that
appropriately designed and constructed LBC bases develop block (ladder) cracking and crocodile
cracking. This is the key difference in cracking characteristics that has led to the use of LBC with thin
bituminous surfacings.
5.1 Introduction
An important element of developing a mechanistic-empirical structural design method was an understanding
of in-service performance of pavements which include LBC. The propensity of LBC bases to crack was of
particular interest.
As described in Section 3.2, TMR has developed design procedures and specifications for the use of LBC in
new flexible pavements (TMR 2018) and also for use in pavement rehabilitation (TMR 2020). TMR have
constructed more LBC bases than the other Australian state road agencies combined. Accordingly, it was
decided to review the performance of Queensland pavements as follows:
• As described in Section 5.2, 16 sites were identified on the Queensland road network where granular
base materials had been treated with around 2% cementitious binder by both in situ stabilisation and
plant-mixed materials. Key findings resulted from site inspections, data collation and analysis.
• Queensland network condition data was analysed to assess the extent and type of cracking of LBC
pavements and to identify factors related to cracking.(Section 5.3).
• In addition, coring of the LBC layer at two of the 16 sites described in Section 5.2 provided insight as to
whether the LBC is a bound material with the potential for macro-cracking or if it is in a micro-cracked
state with reduced potential for surface cracking (Section 5.4).
5.2.1 Methodology
Investigation of data records of over 8500 km of the Queensland network identified 16 projects that met the
criteria aimed at selecting structures where any evident surface cracking could reasonably be expected to be
attributed to load. The criteria included:
• cement-stabilised granular
• base thicknesses in the range 150–250 mm
• bituminous surfacing thickness 50 mm or less
• pavements without bound subbases or stabilised subgrades
• unlikely to have been constructed on highly expansive subgrades
• more than 200 heavy vehicles per day
• bases constructed at least three years ago.
Using these criteria, 16 projects were chosen, representing 90 km, a little over 1%, of the current lightly
cemented road network. The locations of the sites are shown in Figure 5.1.
(Site 3: Far North Queensland District Bruce Highway (Ingham – Innisfail): Job 216/10N/66Z. This site is not
reported as the treatment was found on inspection to be foamed bitumen stabilisation.)
Source: http://ontheworldmap.com/australia/state/queensland/.
Before field visitation, asset management data, construction drawings and UCS records (if available) were
collated for each project prior to site visits.
A visual inspection focussing on load-induced cracking defects but also the recording of other major defects
and patch repairs were undertaken along with local TMR district staff.
Appendix A contains notes and photographs taken during the inspections which were conducted between
June and September 2016.
From the field inspections conducted it can be concluded that the plant mixed lightly cemented bases have
performed well. As such materials are placed as part of new construction, it is reasonable to assume that the
underlying support to the lightly-cemented base to be expected in new pavement design is a significant
factor in the good performance of these projects. However, in some cases the thin LBC bases were
constructed on cemented subbases and transverse cracking was observed on the surface; this was most
likely due to shrinkage of the cemented subbases.
The in situ stabilised bases showed a much wider range of performance, but generally the extent of block
cracking and crocodile cracking was minimal. All LBC bases that were well supported demonstrated good
performance, as did some pavements where the underlying support could be considered as inadequate from
a structural design point of view.
However, some in situ stabilised pavements exhibited very poor performance with the formation of major
block cracking evident. Additionally, some sections were found to have been extensively patched, indicating
that significant distress had been evident and the pavement had needed treatment to restore serviceability.
Despite extensive attempts to source additional information and records, including the recollections of
regional staff, it is difficult to prove a definitive cause for some of the major distress.
It has been postulated that the application of excessive binder has resulted in a continuous length of one
project exhibiting extreme block cracking in all wheelpaths. Adjacent lengths of road, which were part of the
same rehabilitation project did not demonstrate this cracking and are performing well. Documentation could
not be found to demonstrate that an increase in binder application rate, or the use of binder from a different
source, had been the cause of the poor performance; however, it was the most likely cause of the
block-cracking.
Nevertheless, long lengths of LBC showed little or no signs of block cracking, despite the considerable
passage of time and loading since construction. It is apparent that, with improved design and construction
processes, LBC bases can more consistently perform well.
5.3.1 Introduction
Following the field inspections, the network pavement condition data was analysed to clarify the extent and
type of cracking at the sites inspected and the factors associated with this cracking.
From Figure 5.2 it can be seen that the predominant cracking type was longitudinal followed by transverse.
The transverse cracking is likely to be due to shrinkage of the LBC bases, whilst the cause of longitudinal
cracking could be:
• shrinkage cracking (Section 4.2.2)
• expansive subgrade soils
• the beginnings of load-induced fatigue cracking
• construction joints (e.g. pavement widenings).
Based on the inspections (Appendix A), the most likely cause of longitudinal cracking at the sites inspected
was the presence of expansive subgrade soils.
The extent of crocodile cracking was minimal, suggesting the pavements have generally been designed and
constructed as intended.
The percentage of the site length cracked is compared with the maximum deflection (D0) and the curvature
(D0-D200) measured using the traffic speed deflectometer (TSD) in Figure 5.3 and Figure 5.4. It was
concluded that the extent of longitudinal cracking was significantly related to surface deflection. This may be
because pavements on highly expansive clay subgrades generally have higher deflections than
higher-strength low-expansive subgrades.
The extent of transverse cracking also tended to increase with deflection, despite the cause of this cracking
type being most likely shrinkage rather than load-induced. A possible reason is that the higher the deflection,
the greater the load-induced movement at a transverse crack with associated gradual loss of load transfer
across the crack and hence the development of wider, more detectable cracking.
The extent of crocodile cracking was so low that no conclusions could be drawn about its dependence on
deflection.
A critical issue to investigate was whether the extent of cracking was related to the LBC base thickness.
Accordingly:
• Figure 5.5 shows the variation in the percentage of total length with any cracking with the LBC base
thickness at each site sorted according to subbase thickness.
• Figure 5.6 shows the variation in the percentage of length with longitudinal cracking with the LBC base
thickness at each site sorted according to subbase thickness.
• Figure 5.7 shows the variation in the percentage of length with transverse cracking with the LBC base
thickness at each site sorted according to subbase thickness.
• Figure 5.8 shows the variation in the percentage of length with crocodile cracking with the LBC base
thickness at each site sorted according to subbase thickness.
In each plot the larger the data point plotted the greater the cumulative traffic loading at the time the
pavement was inspected.
Again the extent of crocodile cracking was low which hindered conclusions being drawn relating the
pavement structure to this type of load-induced damage.
LBC thickness does not seem to influence cracking extents. This may be because the procedures used by
TMR to vary the LBC base thickness with traffic loading, based on engineering judgment, are reasonable.
In terms of transverse and longitudinal cracking, high percentages of cracking were observed for pavements
with lower subbase thicknesses (Site 2 and Site14). The subbase seems to be the predominant factor
influencing cracking extent. This can be seen at Site 14, which had the least amount of traffic loading but
much higher cracking extent. Where the subbase depth was above 225 mm, all sites showed a total average
cracking extent of less than 3% (Site 2A, 14A, 16, 17 and 17A).
Since the sites inspected were constructed, the TMR (2018) design procedures have been improved to
provide sufficient granular subbase thickness such that the top sublayer of granular has a minimum design
modulus of 150 MPa.
5.4.1 Introduction
As described in Section 5.3, there was only a minor load-induced crocodile and block cracking of the LBC
bases on the Queensland road network. This is likely to differ from the performance of cemented material
bases which have higher strengths than LBC; the cracking of these bases was not addressed in this report.
To investigate this difference in behaviour of the LBC bases, coring was conducted at two of the 16 sites
inspected (Section 5.2.1) to provide insight about the cracking characteristics of LBC bases.
Pavement Composition
This 1.6 km length of the Cunningham Highway was in situ stabilised in 2007 to a depth of 250 mm using
2% type GB cement. The host material was river gravel.
Note that between chainages 85.4–86.6 km (Site 2) the granular subbase under the stabilised layer was only
50 mm thick, whereas between 86.6–87.0 km (Site 2A) the thickness of granular was 325 mm (Table 5.1).
The subgrade CBR was similar in both sections.
The surfacing was a size 10 mm primerseal followed by a size 14 mm polymer modified binder seal.
UCS testing after 7 days curing was undertaken by TMR before construction to determine the binder content
(Figure 5.9). From this testing it was decided to adopt 2% cement as this value produced UCS values within
the specified 7-day UCS range of 1.0 to 1.5 MPa.
Figure 5.9: 7-day UCS testing used to select the binder content
3.0
2.5
2.0
UCS
1.5
(MPa)
1.0
0.5
0.0
1.5 2.0 2.5 3.0 3.5 4.0 4.5
Content of type GB cement (%)
Visual Inspection
This section of Cunningham Highway was a visual inspection in 2016, which was about nine years after
construction and opening to traffic.
Overall 4–5% of the total 1.6 km project was distressed exhibiting either crocodile cracking (Figure 5.10),
transverse cracking, or patching. The distress was more apparent in Site 2 which had only a 50 mm
thickness of granular subbase, whereas Site 2A was generally in good condition.
There was some longitudinal cracking on the shoulder edges, indicating the likelihood of expansive
subgrades.
Coring
The LBC base was cored (Figure 5.11, Figure 5.12) from 12 locations along the site (see Table 5.2 and
Table 5.3) and the rut depth measured.
Dry coring rather than wet coring so that the UCS results were not influenced by water used during coring. A
total of 12 cores were attempted, however only four cores were successfully extracted (Figure 5.13,
Figure 5.14). At the other sites, cores could not be retrieved (Figure 5.15, Figure 5.16) due to their low
strength (see notes in Table 5.2, Table 5.3). It could not be established whether or not the LBC base was
broken down due to trafficking or as a result of coring. All the core holes appeared solid and intact, which
seems to indicate an absence of macro-cracking.
Note: OWP = outer wheelpath, IWP = inner wheelpath, RHS= right hand side, LHS= left hand side.
Note: OWP = outer wheelpath, IWP = inner wheelpath, RHS= right hand side, LHS= left hand side.
Figure 5.15: Example of disintegrated of the LBC base observed after coring
Figure 5.16: Example of LBC base layer not able to be extracted in tact
Coring was carried out at a total of 12 locations in Sites 2 and 2A, however there were only three sound
cores were suitable for UCS testing (Table 5.4). The UCS of these sound field cores was around 2 MPa. It is
important to note here that Site 2 was constructed in 2007 and so was 10 years old when the investigation
was carried out. It would be expected that the in situ UCS would have increased in situ since constructed
due to curing offset possibly by traffic-induced fatigue damage.
An important finding was that the sites at which cores were able to be extracted were located in areas with
greater cracking distress, whereas for two locations in Site 2A in good condition LBC core could not be
retrieved. For the sites in good condition, the LBC base may have micro-cracked to such an extent that cores
cannot be retrieved. Perhaps due to the fineness of the micro-cracking it was not detectable when the walls
of the core holes were inspected (Figure 5.14).
Pavement Composition
This 5.3 km length of the Dawson Highway (chainages 50.8 km and 56.1 km) was in situ stabilised in 2007 to
a depth of 150 mm using 2.8% type GB cement. Prior to stabilisation 100 mm thick type 2.5 granular bases
was placed on the existing pavement. After stabilisation, the underlying granular subbase was about 280 mm
thick (Table 5.5).
Site 16
No details of UCS testing before construction could be obtained. However, the ‘as constructed’ drawings
recorded the average cement content used was 2.8% and the UCS values measured during construction
were between 0.9 MPa and 2.3 MPa. The mean UCS was 1.5 MPa, with four of 12 results between
2.2–2.3 MPa. Although not stated in the drawings, it is likely these results relate to the UCS values after
7 days curing.
Visual Inspection
When inspected in 2016, the pavement had been in-service for about nine years old at which time the
accumulated traffic loading was about 106 ESA.
Three forms of distress were observed in isolated areas (Figure 5.17), as follows:
• 97 lineal metres (113 m2) of crocodile cracking
• 42 m2 of rut/shove failure
• 381 m2 of patches.
In total, 1.3% of the total wheelpath length displayed one of these three forms of distress.
Coring
Cores were taken at eight locations (Table 5.6). None of the core could be extracted intact, in all cases the
materials disintegrated due to traffic loading or due to the coring process.
Figure 5.18 shows the coring hole walls and so some very large aggregate sizes. In most cases the cored
LBC broke down into a granular material (Figure 5.19 and Figure 5.20). There was one instance documented
where some layers of intact material could be extracted (Figure 5.21).
Consistent with the Cunningham Highway findings (Section 5.4), when the pavement was cored at the sites
in sound condition, intact cores of LBC could not be retrieved. However, for the Dawson Highway site the
large aggregate sizes in the LBC may also have led to the poor coring success rate.
In addition, like Cunningham Highway micro-cracking was not apparent on the wall of the core holes, but
again this maybe because the cracking is too fine to be observed.
The LBC base may have micro-cracked consistent with the desired characteristics of LBC. Alternatively, the
intact cores could not be retrieved.
Figure 5.18: Core hole showing large aggregate size Figure 5.19: Broken down material extracted
from core hole
Figure 5.20: Material extracted from core hole Figure 5.21: Partial core extracted with layers
of intact material
5.5 Conclusions
The performance of LBC bases in Queensland was investigated and the following conclusions were drawn:
• LBC bases have been used in Queensland for over 10 years generally produced using in situ stabilisation
but also including plant-mixed LBC for use as base.
• From the field inspections conducted it can be concluded that, plant mixed LBC bases have performed
well. As such materials are placed as part of new construction, it is reasonable to assume that the
underlying support to the LBC base in a new pavement design was a significant factor in the good
performance of these projects. However, in some cases the thin LBC bases were constructed on
cemented materials subbases and for these project transverse cracking was observed on the surface
most likely be due to shrinkage of the cemented material subbases.
• The in situ stabilised LBC bases showed a much wider range of performance. All bases that were well
supported demonstrated good performance, as did some pavements where the underlying support could
be considered as inadequate from a structural design point of view.
• However, some in situ stabilised LBC bases exhibited very poor performance with the formation of major
block cracking evident. Additionally, some sections found to have been extensively patched, indicating
that significant distress had been evident and the pavement had needed treatment to restore
serviceability. It has been postulated that the application of excessive binder has resulted in a continuous
length of one project exhibiting extreme block cracking in all wheelpaths, but evidence in support of this
could not be found. Inadequate subbase support to the LBC base was suggested as a cause of the poor
performance. Current TMR (2018) design procedures reflect this experience as now the LBC bases
needs to be supported by a granular subbase with a minimum design modulus of 150 MPa.
• Several sites were cored to improve understanding of the required properties of good and poorly
performing LBC bases. For sites with good performance with no crocodile cracking, it has not been
possible to extract intact cores and they disintegrated either due to traffic loading or during coring. Two
sites where cores could be extracted from poor performing areas with visible crocodile cracking. These
findings are consistent with TMR design concepts for LBC bases, namely to design and construct a low
strength material that develops fine macro-cracking with sufficient base thickness and subbase support to
limit the extent that micro-cracking leads to macro-cracking.
• Long lengths of LBC bases showed little or no signs of block cracking or crocodile cracking, despite the
considerable passage of time and loading since construction. Further improvement to design and
construction practices should reduce the risk of premature distress.
6.1 Introduction
The mechanistic-empirical thickness design method for flexible pavements (Austroads 2017a) includes two
critical components:
• a linear elastic response-to-load model in which critical strains are calculated
• performance relationships that estimate the allowable traffic loadings to pavement distress.
The response-to-load of a pavement structure requires the elastic characterisation of pavement layers and
the subgrade. Consequently, to extend the current design procedures to pavements containing LBC
materials, methods needed to be developed to determine the design modulus of LBC.
To assist the development, two field trials were constructed and monitored over the first year of life to enable
the change in moduli with curing and early-life trafficking to be investigated.
6.2.1 Location
In March 2017, the first trial section was constructed and opened to traffic and the performance monitored over
12 months. The trial site was a 100 m long section of the Bruce Highway between Ayr and Townsville in
Queensland that was opened to traffic. The trial section was as part of in situ cementitious stabilisation works
from chainage 13 300 to 14 400 m at Collinson’s Lagoon (Figure 6.1). This site had suitable clearance from the
abutment of the bridge at chainage 13 955 m and also from the Lochinvar Intersection at chainage 13 650 m.
Townsville
Trial location
Bruce Hwy –
Ayr Lochinvar Rd
junction
The original pavement design was conducted in 1992. It was based on a design traffic of 4.1 x 106 ESA’s
and a subgrade design CBR of 3%. According to the pavement design manual in use at that time
(Queensland Department of Transport and Main Roads 1990), the required thickness of cover over the in
situ subgrade is 625 mm, which is exactly that recorded in the TMR plans (Figure 6.2a). The original
pavement structure comprised 300 mm of base gravel on 325 mm of select fill. Based on the design chart in
the TMR manual, the quality of the selected embankment material should have been a minimum CBR of
20%.
In 2016, the design consultant’s pavement design report recommended in situ cement stabilisation to a
depth of 250 mm to upgrade the existing road pavement. For the design of this rehabilitation treatment, TMR
provided NPC (Northern Pavement Consultants) with 2012 traffic data for the 10L link. Traffic data from site
91699 located at the Greenacres weigh-in-motion site (Ch. 20 640 m), was adopted.
The 10 and 20-year design traffic loadings for the project were calculated based on this data assuming year
1 to be 2015. The adopted 10 and 20-year design traffic loadings were 4.9 x 106 ESA and 1.1 x 107 ESA,
respectively (see Table 6.1).
Project Two way Per cent Heavy Number of Design traffic (ESA)
AADT heavy vehicle heavy vehicle
vehicles growth axle groups 10 years 20 years
(HV) rate (%) per heavy
vehicle
Bruce Highway 10L 2614 16.83 2.5 2.80 4.9 x 106 1.1 x 107
Pavement Composition
TMR ARMIS (A Road Management Information System) data provides details of the pavement structure
from 1992. The pavement structure in the trial section length consisted of 300 mm of granular material on top
of a minimum of 325 mm of selected embankment material (Figure 6.2a).
In 1993, a 7 mm sprayed bituminous seal surfacing was placed, followed by a 16 mm sprayed seal. A 10 mm
sprayed seal was used to seal the pavement. In 1999 an additional polymer modified binder (PMB) sprayed
seal was placed.
In 2014, Northern Pavement Consultants undertook a pavement investigation in preparation for the
pavement upgrade work (250 mm in situ cement stabilisation). The pavement at the test pit closest location
to the trial section consisted of a 40 mm thick sprayed bituminous seal surfacing over 330 mm of sandy
gravel base and 240 mm of sandy gravel subbase (Figure 6.2b). The subgrade was identified as a silty clay
with sand.
FWD surface deflection measurements were carried out on this section of road in 2014 before cement
stabilisation. At this time, the recorded maximum deflections (D0) ranged from 0.6 to 1.0 mm and curvatures
(D0 – D200) from 0.23 to 0.43 mm (see Figure 6.3).
Figure 6.3: Maximum deflections and curvatures under 40 kN FWD load in 2014
Construction phasing
In December 2016, the contractor milled off the existing bituminous surfacing, followed by pulverisation of the
gravel base on the southbound lane between chainage 13 730 and 13 949 m. The target depth for the
pulverisation was 200 mm. This was followed by light compaction and grading to profile, before spreading
top up gravel base, which was about 40 mm thick. Profiling and grading were then undertaken to bring the
levels close to that of the design, in preparation for the in situ stabilisation.
In situ stabilisation was specified as 2.5% type GB cement. This binder content appears to have been
selected based on UCS test results of field cores rather than laboratory-manufactured specimens (see
discussion below). The stabilisation of the southbound lane between chainage 13 730 and 13 949 m was
carried out on 20 December 2016.
Undesirably on the day of stabilisation, the contractor elected to split the stabilising work within the lot into
two stages. A construction joint was created in the works at chainage 13 839 m, close to the middle of the
selected trial section (chainage 13 800 to 13 900 m). Subsequent sampling and testing in this research
project was then undertaken away from this joint. However, it should be kept in mind, especially when
interpreting the deflection results (Section 6.2.6) at chainage 13 840 m.
The stabilised pavement was surfaced with a sprayed bituminous surfacing, details of which are not
available.
In March 2017, due to excessive roughness, a 50 mm thick size 14 mm dense-graded asphalt (AC14M)
surfacing layer was placed.
The asphalt surfacing was placed after the 28-day deflection measurement, but before the retesting
105 days after in situ stabilisation. Note that it was intended to measure deflections at 90 days but this was
delayed due to Cyclone Debbie and its aftermath. Table 6.2 summaries the construction phases.
The pavement composition after sealing and the subsequent asphalt surfacing of the trial pavement section
are shown in Figure 6.4.
Subgrade (Silty Clay with Sand) Subgrade (Silty Clay with Sand)
During construction, a bulk sample of the gravel base was sampled from the pavement approximately 1.0 m
from the centreline at chainage 13 860 m. This material was excavated following light compaction and grader
profiling after top-up gravel was placed. Approximately two tonnes of material was obtained using a small
tracked excavator. This material was delivered to TMR’s Townsville Materials Laboratory and subsequently
sent to ARRB in early May 2017.
The cement used for the stabilisation was also sampled during construction for laboratory testing. Due to the
difficulties in safely sampling raw cement from the on-site spreader, arrangements were made directly with
the supplier (Wagners Townsville) to sample the cement during the loading of the spreader truck.
Approximately 200 kg of cement was taken and placed in sealed containers. This was delivered to TMR’s
Townsville Materials Laboratory and subsequently sent to ARRB’s laboratory in Melbourne in early
May 2017.
During the construction, quality control information was collected and compiled by the contractor for the test
lot that encompasses the test section (Lot SPRHS001).
Base gravel for the ‘top-up’ was sourced from BQC Quarries, which provided material quality test results.
The contractor’s surveyor supplied data on probe measurements of the depth of the stabilisation achieved.
The stabilisation depths from a range of offsets ranged from 235 to 289 mm with an average of 259 mm.
A number of density measurements were taken on the materials at various locations along with the
construction. The achieved dry density ratios were between 101.2% and 104.1% of standard Proctor MDD,
with an average density ratio of 102.7%.
Other data about the project included the cement spread rate, which was calculated as 13.1 kg/m2 and the
reported achieved rate was 13.0 kg/m2. However, the 30 minutes maximum time limit between cement
spreading and mixing was exceeded. This was conditionally approved by TMR subject to road roughness
measurements. The final surface levels exceeded the specified tolerance being up to 16 mm above and
14 mm below design levels. TMR delayed the decision on acceptance until the road roughness was
evaluated.
The measured road roughness figures exceeded the permissible 60 NAASRA roughness counts. As a result,
a 50 mm thick dense grade asphalt surfacing was placed in early March 2017. This asphalt surfacing
covered both the southbound and northbound lanes from the project commencement at chainage 13 300 m
to the first bridge (chainage 13 950 m) which covers the research test section.
UCS testing
Table 6.3 summarises the UCS testing undertaken by TMR of field-mixed material sampled behind the
stabiliser and later compacted in the laboratory. Note that the test specimens were compacted below
100% standard Proctor MDD, perhaps due to the time delay between field mixing and compaction in the
laboratory or lower field moisture compared to standard Proctor OMC.
Table 6.3: TMR UCS results of laboratory cylinders at Bruce Highway Collinson’s Lagoon
Chainage Offset Achieved dry density Relative compaction(1) 28 day UCS (MPa)
(t/m3) (%)
Individual Reported
13 860 1.0 m RHS of 2.06 94.5 1.3 1.4
centreline behind
2.06 94.3 1.4
stabiliser
2.04 93.6 0.8(2)
13 890 1.0 m RHS of 2.05 94.3 2.0 2.0
centreline
2.05 94.4 1.7
behind stabiliser
2.06 94.8 2.3
At chainage 13 860 m, the average 28-day UCS was 1.4 MPa at a relative compaction of about 94% of
standard Proctor MDD. At chainage 13 890 m it was slightly higher at 2.0 MPa.
The contractor also measured the UCS testing at 7 days of field mixed and laboratory compacted cylinders
(Table 6.4). In this case the material was compacted close to 100% standard Proctor MDD. Allowing for the
increase in UCS with time, the estimated value at 28 days would be close to 2 MPa.
The contractor also tested cylinders 28 days after construction. This data is reported in Table 6.4, again the
results are close to the TMR upper limit of 2 MPa.
During the project, FWD deflection testing was undertaken over the 100 m trial section at 28 days, 90 days
and 1 year. The FWD testing was carried out at 10 m intervals both between the wheelpaths (BWP) and in
the outer wheelpath (OWP). All deflection data below and in Appendix B have been normalised to values
under a 40 kN FWD load.
An important element of the monitoring program was to investigate how the modulus of the cement-stabilised
layer changed with time and traffic loading. Accordingly, in this section the deflections measured at various
times (28 days, 105 days and 1 year) are compared.
The analysis of the change in FWD deflection was complicated by the placement of the 50 mm thick asphalt
surfacing which was not present when the 28 days testing was conducted but present when the 105 days
and 1 year measurements were conducted.
In addition to this discussion of deflection trends, Section 6.2.6 describes the trend in the modulus
back-calculated from the deflection bowls.
Maximum deflections
Figure 6.5 shows the variation in maximum deflections with time. The highest D0 values were measured at
chainage 30 and 40 m (13 830 and 13 840 m), which corresponds to a construction joint. The deflections in
the OWP followed a similar trend, although they were slightly lower than the values between the wheelpaths.
As expected the 28-day deflections are higher than the 105 day and 1 year. The 28-day measurements were
taken before placement of the 50 mm asphalt surfacing. Had the asphalt surfacing existed it would be
expected the maximum deflections would have been about 15% lower, as shown in the adjusted 28-day
values plotted.
It was concluded that the deflections in the untrafficked areas decreases up to 105 days and thereafter
remained similar. This is consistent with the expected curing of the cementitious binder with time.
Figure 6.6 shows the trends in outer wheelpath deflections, including the 28-day deflections adjusted to the
estimated values with a 50 mm asphalt surfacing.
Unlike the untrafficked area, there was no clear trend in the deflections with time and loading given the
scatter of results. It maybe that the effect of curing in the initial lowing of the deflections has been offset by
traffic-induced damage to the stabilised layer.
Curvature
Figure 6.7 shows the variation in curvature (D0-D200) with time. As expected, the 28-day curvatures were
higher than the 105-day and 1-year values. The 28-day measurements were taken before the placement of
the 50 mm asphalt surfacing. Had the asphalt surfacing existed it would be expected the curvatures would
have been about 25% lower, as shown in the adjusted 28-day values plotted.
Consistent with the untrafficked maximum deflection results, it was concluded that the curvatures in the
untrafficked areas decreased up to 105 days and thereafter remained similar. This is consistent with the
expected curing of the cementitious binder with time.
Figure 6.8 shows the trends in OWP curvatures, including the 28-day curvatures adjusted to the estimated
values with a 50 mm asphalt surfacing.
Unlike the untrafficked area, there is no clear trend in the deflections with time and loading. It may be that the
effect of curing in the initially lowing of the deflections has been offset by traffic-induced damage to the
stabilised layer.
Introduction
An important element of the monitoring program was to investigate how the modulus of the cement-stabilised
layer changed with time and traffic loading. Accordingly, in this section the layer moduli back-calculated from
the deflections measured at various times (28 days, 105 days and 1 year) were compared.
To enable the modulus of the various pavement layers to be estimated, the ARRB modulus back-calculation
software. This back-calculation process requires several inputs. Firstly, the pavement structure is required.
The information about the previously existing structure and the cement stabilisation process was used to
determine the expected structure. As noted above a 50 mm thick asphalt surfacing course was applied
between the 28-day and 90-day deflection testing. This has resulted in a structure immediately after
construction and a second structure, which was used in the analysis of the 90-day and 1-year deflection
data. These structures are shown in Figure 6.4a. It can be seen that the initial sprayed seal surface
pavement had 250 mm of cement-stabilised base, over 80 mm of a sandy-gravel base, 240 mm of a sandy
gravel subbase and a silty clay subgrade. After the addition of the asphalt surfacing on 2 March 2017, the
structure remained the same, but with an additional 50 mm thick surface of dense-graded asphalt
(Type AC14M) as shown in Figure 6.4b.
It is general practice during modulus back-calculation to split the subgrade into three separate layers, an
upper layer of 300 mm thick, a middle layer of 500 mm thick and a lower semi-infinite layer
(Austroads 2019a).
Table 6.5 and Table 6.6 summarise the pavement compositions used in the modulus back-calculation and
the seed moduli used to commence the layer moduli iteration. Note that, due to the very low deflections and
curvatures, a high seed modulus of 10 000 MPa was used for cement-stabilised layer.
Table 6.5: Pavement structure and seed moduli with sprayed seal surface
Table 6.6: Pavement structure and seed moduli with an asphalt surfacing
The back-calculation generated moduli values for between the wheelpaths are reported in Table 6.7,
Table 6.8, and Table 6.9. It is noted that the cement-stabilised layer has a very high modulus. These values
are significantly higher than would normally be expected for a LBC material. It was concluded that the
Collison’s Creek cemented material has a modulus more closely aligned with a HBC material rather than
LBC.
Modulus
Modulus
Modulus
Similar results were found for the back-calculation of moduli in the outer wheelpath (see Table 6.10,
Table 6.11, and Table 6.12). Again, it is noted that the cement-stabilised layer has a very high modulus.
These values are significantly higher than would normally be expected for a LBC base. It is concluded that
the Collison’s Creek cemented material has a modulus more closely aligned with a HBC material rather than
LBC.
Modulus
Subgrade Subgrade
Chainage (m) Upper Lower Subgrade
Base (upper (middle
granular granular (lower)
(MPa) 300 mm) 500 mm)
(MPa) (MPa) (MPa)
(MPa) (MPa)
0 7 179 500 293 206 257 351
10 7 286 500 300 181 266 425
20 6 526 500 300 323 300 257
30 3 693 249 239 259 250 231
40 5 578 262 300 270 255 226
50 5 557 500 300 209 221 243
60 20 000 496 280 123 168 254
70 8 501 500 214 314 301 276
80 7 398 500 300 241 245 254
90 6 457 333 300 316 296 259
100 5 931 500 170 320 280 205
Mean 7 646 440 272 251 258 271
Modulus
Subgrade Subgrade
Chainage (m) Upper Lower Subgrade
Base (upper (middle
granular granular (lower)
(MPa) 300 mm) 500 mm)
(MPa) (MPa) (MPa)
(MPa) (MPa)
0 29 945 200 61 30 203 600
10 10 415 359 191 100 162 279
20 11 640 311 178 141 188 276
30 16 88 347 115 178 192 219
40 3 011 200 157 157 176 211
50 8 175 216 166 123 164 240
60 5 110 200 257 133 156 198
70 9 580 282 206 114 165 259
80 15 042 548 257 93 145 242
90 18 296 281 207 97 161 281
100 10 000 350 180 110 180 260
Mean 11 173 299 180 116 172 279
Modulus
Subgrade Subgrade
Chainage (m) Upper Lower Subgrade
Base (upper (middle
granular granular (lower)
(MPa) 300 mm) 500 mm)
(MPa) (MPa) (MPa)
(MPa) (MPa)
0 19 167 369 184 58 174 392
10 14 953 462 227 99 178 326
20 15 013 276 180 181 219 291
30 10 000 350 180 120 180 260
40 10 000 350 180 120 180 260
50 6 044 208 215 235 230 222
60 20 891 500 112 178 202 246
70 9 957 500 96 222 238 269
80 20 070 500 300 133 184 281
90 20 152 325 300 131 184 284
100 22 076 200 185 84 148 267
Mean 15 302 367 196 142 192 282
The Collinson’s Lagoon trial site consists of a 100 m section between chainages 13 800 and 13 900 m along
the southbound carriageway of the Bruce Highway between Ayr and Townsville. This section included a
250 mm deep in situ cement stabilisation with 2.5% type GB cement content. This binder content was
selected without mix design testing of laboratory-mixed and compacted cylinders.
The construction work was carried out in December 2016. Field-mixed material was sampled from behind the
stabiliser and compacted for UCS testing after 28 days of curing. Due either to the time delay between field
sampling and laboratory compaction or the lower field moisture compared to standard Proctor OMC, the
UCS test specimens were not compacted to 100% standard MDD. Consequently, there is uncertainty about
the 28-day UCS of laboratory-manufactured cylinders.
FWD monitoring was carried out after 28 and planned for 90 days (noted that the second monitoring was
actually carried out at 105 days due to adverse weather conditions) and after 1 year. This was carried out
between the wheelpaths and in the OWP.
It was concluded that cement-stabilised layer had very high in situ modulus well over that expected for a
LBC. It was doubtful the moduli at this site was representative of LBC base and hence the results were not
used in developing the proposed design method (Section 9).
6.3.1 Location
The second trial section was on the Bruce Highway between Ayr and Townsville near Barratta Creeks. The
project was on a section between chainage 19 400 and 23 200 m. Initially, the chosen 100 m long test
section was from chainage 23 000 to 23 100 m in the northbound lane. However, the contractor chose to
split construction within this section at 23 020 m and so the test section was adjusted to chainage 23 020 m
to chainage 23 120 m, which still gave suitable clearance from the abutment of the West Barratta Bridge at
chainage 23 185 m. An aerial view of the trial section is shown in Figure 6.9.
Trial location
Source: J765 Pavement Rehabilitation Design Report – Historical Data and Design Traffic.
The 1997 plans provided by TMR indicate that the original pavement design was based on a design traffic
loading of 4.0 x 106 ESA and a subgrade design CBR of 3%. The pavement design manual then in use in
1997 (Queensland Department of Transport and Main Roads 1990), indicates that the total cover thickness
over the subgrade of 620 mm would have been required.
Traffic census data from 2011 provided by TMR was used to calculate design traffic values for 10 and
20-year periods. Data was collected from the WIM station at Greenacres (i.e. Ch. 20 640 m). A summary of
the data, assumptions and adopted design loadings are included in Table 6.13. The 10-year and 20-year
design traffic loadings for this section of the project were calculated based on this data assuming year 1 to
be 2015. The adopted design traffic loadings for 10 and 20-year periods were 4.7 x 106 ESA and
1.2 x 107 ESA respectively.
Two-way Heavy Annual HV Number axle ESA per heavy Design traffic (ESA)
AADT vehicles growth rate groups per vehicle axle
(%) (%) heavy vehicle group 10 20
years years
Pavement composition
Figure 6.10a shows the pavement structure before in situ stabilisation based on TMR ARMIS data defining
the pavement structure and TMR plans. Based on this information, the original pavement consisted of a
sprayed seal surfacing over 250 mm of type 2.1 base gravel, and 370 mm of type 2.5 subbase gravel. There
were variable thicknesses of select fill under the subbase.
In 2014, Northern Pavement Consultants (NPC) investigated the existing pavement. This involved digging
test pits at various locations along the road, including chainage 23 057 m, which is within the test section. At
this chainage the pavement comprised a 70 mm thickness of bituminous seals over 200 to 220 mm thickness
of sandy gravel base and 350 mm of sandy gravel subbase(Figure 6.10b). The subgrade was a sandy clay.
The ARMIS database does not reveal any records of asphalt being placed at this location. This database
reveals a surfacing depth of 41 mm, comprising of a 10 mm and 16 mm spayed bituminous seal in 1996 and
a 15 mm thick slurry seal in 2010.
In 2013 before treatment the surface deflections were measured using the FWD and reported by NPC. The
40 kN maximum deflections and curvatures are shown in Figure 6.11.
From the 2013 measured deflections and the pavement structure, NPC back-calculated the layer moduli
before rehabilitation. NPC concluded that the sandy gravel base had a vertical modulus of 300 to 400 MPa,
whereas the modulus of the sandy gravel subbase was only 50 to 100 MPa. The subgrade modulus was
estimated to be 100 to 130 MPa, but this may have been over-estimated as the subgrade was not
sub-layered.
Figure 6.11: Measured maximum deflections and curvatures at Bruce Highway – Barratta Creeks prior to
stabilisation
A series of UCS tests were carried out on gravel base recovered from a test pit at chainage 23 820 m, which
is close to the test section. For this testing the existing in situ gravel base was mixed with an appropriate
proportion of the expected ‘top-up’ gravel (type 2.1) from ‘Pats Pit’, just west of Townsville. The proportions
of this mix were 1 part in situ gravel to 0.36 parts imported gravel.
Based on this preliminary testing it was agreed cement stabilisation was appropriate, with a binder content in
the range 2–3%. Later a binder content of 2% was selected.
The test material had a plasticity index of about 7 with about 5–10% passing the 75 µm sieve.
The 100 m long trial section fell within the contractor’s lot SC-6A-1, which covered chainage 22 860 to
23 185 m in the northbound lane. Within this lot, there were no asphalt patches requiring removal and
replacement with top-up gravel.
On 6 March, the existing bituminous surfacing was removed and the gravel base pulverised to a target depth
of 200 mm. This was followed by light compaction and grading to profile, before selected spreading of top-up
gravel only between chainage 23 100 and 23 120 m at an average thickness of 25 mm, which was a lower
proportion of top gravel than used in the mix design.
Profiling and grading proceeded to bring the levels close to design, in preparation for the subsequent in situ
stabilisation process.
In situ cement stabilisation was originally specified as 2.5% type GB cement (by weight) based on the mix
design results. It was agreed to monitor the UCS results during construction to consider whether any
modification was required to this binder contents as it was considered close to that required to produce a
HBC material rather than the intended LBC material.
Based on the progressive UCS testing from the field-mixed material on earlier sections of the project, a
decision was taken before construction of the trial section to reduce the binder content to 2% type GB
cement.
The trial section was stabilised on 7 March 2017 to a target depth of 250 mm.
After construction and before the 28-day deflection measurements, a primerseal was placed. A double seal
was then applied after the 28-day deflections measurements and before the 90-day measurements.
Figure 6.12 details the pavement structure after construction.
During the construction, a bulk gravel sample was extracted from the inside run of the stabiliser at chainage
23 070 m. Approximately 2 tonnes of material was obtained and loaded into three bulk bags. This material
was excavated from chainage 23 065 to 23 072 m over 2.2 m wide to a depth of 250 mm. No top-up gravel
was placed in this area instead the area was grader profiled and lightly compacted.
These samples were transported to TMR’s Townsville materials laboratory and subsequently sent to ARRB’s
laboratory in Melbourne in May 2017 for testing (Section 7, Section 8).
The type GB cement was supplied by Wagners in Townsville. Due to the difficulty of safely sampling raw
cement from the on-site spreader, the cement was sampled at the plant during the loading of the spreader
truck.
A cement sample of approximately 200 kg was taken and placed in sealed containers. This was delivered to
TMR’s Townsville materials laboratory and subsequently sent to ARRB’s laboratory in Melbourne in
May 2017.
Relevant construction quality control information was collected and compiled by the contractor for the lot that
encompasses the project test section (Lot SC-6A-1).
The base gravel material which was sourced for the ‘top-up’ material came from the Pats Pit west of
Townsville and quality test results were provided. These results were historic test records from 2015 but
were issued to TMR for acceptance of the top-up gravel. The top-up gravel test results show compliance with
the Type 2.1 granular material specification requirements.
In situ density tests within the project test section were carried out at chainage 23 040 m and another two
tests at chainage 23 018 and 23 123 m, which are just outside the ends of the project test section. Dry
density ratios (based on standard compaction) of 103.2%, 101.8% and 101.0% respectively were recorded.
These were accepted as the specified minimum dry density ratio (standard Proctor compaction) was 100%.
The measured spread rate for cement was 10.4 kg/m2 which slightly exceeded the target rate of 10.3 kg/m2
associated with 2% cement content. The measured depth of stabilisation was recorded as 252 mm, 255 mm
and 256 mm, which corresponded well with the specified depth of 250 mm.
TMR sampled field mixed material behind the stabiliser at chainage 23 040 and then compacted test
cylinders in the laboratory for UCS testing after 7 and 28 days laboratory curing. The results are summarised
in Table 6.14. The cylinders were compacted to a density considerably less than the target 100% standard
MDD, perhaps due to the time delay between field mixing and compaction in the laboratory or lower field
moisture compared to standard Proctor OMC.
Table 6.14: UCS results obtained by TMR at Bruce Highway – Barratta Creeks
The mean 7-day was 1.3 MPa at about 96% standard MDD. The mean 28-day UCS value was slightly lower
at only 1.2 MPa in part due to the lower density of the test cylinders.
Also, the contractor sampled field-mixed material behind the stabiliser at chainage 23 040 and then
compacted test cylinders in the laboratory for UCS testing. The results are summarised in Table 6.15. The
7-day UCS values were lower than TMR values but that the mean 28-day UCS values was 1.5 MPa at about
95–96% standard Proctor MDD.
Note that the test specimens were not compacted to 100% standard Proctor MDD as provided in the current
Austroads definition of modified materials. Assuming, a 9% increase in UCS for each 1% increase in density
(White 2006), the contractor’s 28-day UCS would be about 2 MPa which is significantly different from the mix
design results.
Table 6.15: Summary of UCS test results measured by the contractor at Barratta Creeks
An important element of the monitoring program was to investigate how the modulus of the cement-stabilised
layer changed with time and traffic loading. Accordingly, FWD deflections were measured 28 days, 90 days
and 1 year after construction. All maximum deflections and curvatures reported below and Appendix C has
been normalised to the values under a 40 kN FWD load.
It should be noted that during the 28-day testing, the pavement surfacing was a primerseal. A double seal
was placed before the 90-day testing.
Maximum deflections
Figure 6.13 shows the variation with time of between wheelpath maximum deflections. Although the results
are scattered the data tends to show a decrease in deflections between 28 days and 90 days, as expected
for untrafficked areas subject to curing. However, between 90 days and 1 year the deflections increased. A
possible explanation is that the increases in modulus due to curing had largely been completed at 90 days
and thereafter the traffic-induced damage in the wheelpaths was affecting the deflections between the
wheelpaths.
Figure 6.13: Maximum deflections between wheelpaths on Bruce Highway – Barratta Creeks section
Figure 6.14 shows the variation of the maximum deflections measured in the outer wheelpath. There was no
significant change in deflections between 28 days and 90 days, possibly due to the increase in modulus due
to curing being offset by the traffic-induced damage. Similar to the between wheelpaths results, the
maximum deflections increased considerably between 90 days and 1 year. Again, a possible explanation is
that the increases in modulus due to curing had largely been completed at 90 days and thereafter the
traffic-induced damage results in an increase in deflections.
Figure 6.14: Maximum deflections in outer wheelpath: Bruce Highway – Barratta Creeks section
Curvatures
Figure 6.15 and Figure 6.16 shows the curvature variations with time and loading. The trends are similar to
those discussed above for maximum deflections, albeit that the curvature results are more variable than the
maximum deflection values.
Figure 6.15: Curvature between wheelpaths: Bruce Highway – Barratta Creeks section
Figure 6.16: Curvatures in the outer wheelpath: Bruce Highway – Barratta Creeks section
Introduction
The pavement layer and subgrade moduli were back-calculated from the measured deflection bowls as
described in Austroads (2019a).
This modulus back-calculation process requires several inputs. Figure 6.12 shows the pavement structure
assumed at the time the deflections were measured. Consistent with Austroads (2019a), for the
back-calculation the subgrade was split into three separate layers:
• a top layer, 300 mm thick
• a middle layer, 500 mm thick
• a lower semi-infinite layer.
Initial moduli are required to commence the modulus iteration. These so-called seed moduli are shown in
Table 6.16.
The back-calculation moduli between wheelpaths are listed Table 6.17, Table 6.18and Table 6.19, whilst the
LBC base moduli are plotted in Figure 6.17.
The mean moduli of the lightly cemented base were 786 MPa, 875 MPa and 880 MPa after 28 days, 90 days
and 1-year curing respectively. Due to the scatter of results, there was no significant trend in modulus with
time that could be deduced.
1500
1400
BWP 28 days
1300 BWP 90 days
1100
LCM 1000
modulus
(MPa) 900
800
700
600
500
400
10 20 30 40 50 60 70 80 90 100
Chainage (m)
The back-calculation moduli in the outer wheelpath are listed in Table 6.20, Table 6.21 and Table 6.22, and
LBC base moduli are plotted in Figure 6.18.
The mean moduli of the LBC base in the outer wheelpaths were 987 MPa, 818 MPa and 695 MPa after
28 days, 90 days and 1 year in-service. The results indicate a progressive reduction in modulus with traffic
loading notwithstanding the effect of curing.
1800
1700
OWP 28 days
1600
OWP 90 days
1500
OWP 1 year
1400
1300
1200
LCM
modulus 1100
(MPa)
1000
900
800
700
600
500
400
10 20 30 40 50 60 70 80 90 100
Chainage (m)
The Barratta Creeks trial site was a 100 m section of the northbound carriageway of the Bruce Highway
between Ayr and Townsville, between chainages 23 020 and 23 120 m. This pavement consisted 250 mm of
in situ cement stabilisation with 2% type GB cement content. The pavement was constructed in March 2017
and surface deflections were monitored over the first year of opening to traffic.
Laboratory UCS testing showed that the stabilised material had a 28-day UCS in the range of a LBC,
i.e. 1–2 MPa.
FWD monitoring was carried out both between the wheelpaths and in the OWP after 28 days, 90 days and
1 year. From this data, the moduli of this LBC base were estimated.
The mean vertical moduli of the LBC base in the outer wheelpath were 1170 MPa, 1150 MPa and 770 MPa
after 28 days, 90 days and 1 year in-service respectively. In contrast, the moduli in the untrafficked area
between the wheelpaths were relatively constant: 930 MPa, 980 MPa and 900 MPa. The reduction in LBC
moduli in the OWP between 90 days and 1 year is consistent with the LBC being fatigue damaged due to
loading. This information was used to develop the proposed modulus characterisation used in the proposed
structural design of LBC bases (Section 9).
In the untrafficked area between the wheelpaths, there was no significant change in modulus with curing
time, which was unexpected. This may have been related to load-induced damage to the LBC base in the
wheelpaths influencing the measured deflections between the wheelpaths.
7.1 Introduction
As described in Section 6.1, the mechanistic-empirical thicknesses design method for flexible pavements
(Austroads 2017a) includes two critical components:
• a linear elastic response-to-load model in which critical strains are calculated
• performance relationships that estimate the allowable traffic loadings to pavement distress.
To supplement the early-life LBC in situ modulus investigation (Section 6), the following laboratory testing
was undertaken of laboratory-manufactured and compacted mixtures:
• UCS (Section 7.2)
• indirect tensile modulus (Section 7.3)
• indirect tensile strength (Section 7.4)
• flexural beam modulus (Section 7.5)
• flexural beam strength (Section 7.6).
In the testing program, the characteristics of the LBC (1%-2% cement content) were compared with the HBC
material containing 3–4% cement content.
After mixing the cement and water into the host material the sample was conditioned for two hours. The
mixture was then poured into a split cylindrical mould and the compacted using modified Proctor compactive
effect. (Note that some road agencies use standard Proctor compactive effect, which results in lower
densities and lower UCS values.)
The UCS samples were capped with a fly ash and sulphur compound to provide uniform load to the sample.
The samples were soaked in water for 4 hours, and then left standing for 15 minutes before being tested.
The load rate was 60 kN/minute as specified in AS 5101.4-2008.
The testing included hornfels mixed with 1.5% and 3% cement contents with both type GB and type GP
cement, and Barratta Creeks gravel mixed with 2% and 4% type GB cement contents. These samples were
cured for either 1, 7, 14, 28 or 90 days before testing. Three samples were tested at each condition. The
UCS data are plotted as a function of curing time, in days, in Figure 7.1 and Figure 7.2.
Note that the method used to compact and test UCS specimens differed from that used by TMR. This
hindered an assessment of whether hornfels with 1.5% type GB cement and the Barratta Creeks gravel with
2% type GB cement complied with the proposed definition of a 28-day UCS in the range 1.0–2.0 MPa
(Section 9.3).
As seen from Table 7.1 and Figure 7.2, the 28-day UCS of the 1.5% type GB cement hornfels mixture was
3.3 MPa at 96.7% modified Proctor MDD. Assuming the UCS reduces by 9% for each 1% decrease in
density (White 2006) and that the standard Proctor MDD is about 5% lower than the modified Proctor MDD,
then the 28-day UCS at 100% standard MDD would reduce to about 2.8 MPa, which is above the proposed
maximum UCS limit for LBC (Section 9.3).
From Table 7.1 and Figure 7.2, the 28-day UCS of the 2% Barratta Creeks mixture was 3.7 MPa at
93% modified Proctor MDD. Assuming the UCS reduces by 9% for each 1% decrease in density
(White 2006) and that the standard MDD is about 5% lower than the modified MDD, then the 28-day UCS
would be about 4.3 MPa. By comparison with the field trial B testing (Section 6.3), the TMR and contractor’s
28-day UCS values of field-mixed laboratory compacted material at 100% standard MDD were about 2 MPa.
There is a need to improved national consistency in the preparation and testing of UCS cylinders.
7.0
6.0
5.0
UCS (MPa)
4.0
3.0 GB_2%
GB_4%
2.0
1.0
0.0
0 20 40 60 80 100
Age (Days)
As part of the UCS testing of the stabilised crushed hornfels, the variation of displacement with load was
measured from which the stress-strain plots shown in Figure 7.3 and Figure 7.4 were derived. The drop in
stress was more pronounced in the higher cement content materials, indicative of a higher strength, more
brittle material.
The sample size of the test specimens was nominally 150 mm in diameter and 85 mm thick. Samples were
prepared in the laboratory and compacted to 100% modified Proctor MDD using gyratory compaction. The
ITT samples were cured for up to 90 days before testing. The ITT test method used was based on
AS 2891.13.1-2013, modified for cemented materials. To avoid damaging the specimens a target strain of
10 µm was used.
Figure 7.5 shows the results of the ITT modulus testing. The key findings were:
• The 90-day mean moduli of the 1.5% type GB cement mixture was about 9 800 MPa, whereas the mean
90-day modulus of the 3% type GB cement mixture was 19 200 MPa. For the type GB cement, the
modulus of the 1.5% mixture was roughly half the 3% mixture value.
• The 90-day mean modulus of the 1.5% type GP mixture was about 14 600 MPa whereas the mean
90-day modulus of the 3% type GP cement mixture was 20 800 MPa. The modulus of 1.5% cement
content mixture was about 70% of the 3% mixture value.
• The rate of strength gain in the type GP mixture was faster than the type GB mixture.
25000
20000
Modulus (MPa)
15000
GB 1.5%
GP 1.5%
GB 3%
10000
GP 3%
5000
0
0 10 20 30 40 50 60 70 80 90 100
Curing time (days)
0.7
0.6
0.5
Strength (MPa)
0.4
GB 1.5%
GP 1.5%
0.3
GB 3.0%
GP 3.0%
0.2
0.1
0
0 10 20 30 40 50 60 70 80 90 100
Curing time (days)
The flexural modulus of each test beam was measured in line with Austroads Test Method AGPT-T600-18.
The crushed hornfels mixtures with 1.5% and 3% type GB cement were cured for 14 days before testing. As
seen from Figure 7.7, the results for the 1.5% mixture were very scattered with a mean modulus of about
5 800 MPa. The mean modulus of the 3% cement mixture was higher, about 14 300 MPa. The modulus of
the 1.5% mixture was about 40% of the 3% mixture modulus reasonably consistent with the indirect tensile
modulus findings (Section 7.3).
Note: The ‘field beams’ and ‘laboratory beams’ points are those from Austroads (2008).
The crushed hornfels from the same quarry with 3% type GP cement was previously tested
(Austroads 2008). The modulus results of laboratory manufactured beams were similar, however, the flexural
moduli of field beams (Austroads 2008) were lower, consistent with the different curing that occurs in the
roadbed.
Similarly, beams of the Barratta Creeks material stabilised with 2% or 4% type GB cement and cured for 1, 7,
28 or 90 days were prepared. As seen Figure 7.8, the flexural moduli were very high, even for the
2% cement material, with the 28-day flexural modulus being about 15 000 MPa. The influence of cement
content on modulus was less significant than that observed for the crushed hornfels (Section 7.3).
15000
Flexural modulus (MPa)
10000
5000
0
0 10 20 30 40 50 60 70 80 90 100
Age (days)
2.0% GB Barratta Creeks 4.0% GB Barratta Creeks
The crushed hornfels stabilised with 1.5% and 3% type GB cement were prepared and cured for 14 days. As
seen from Figure 7.10, the flexural strength the 1.5% mixture was very low (about 0.2 MPa) which was about
one-third of the mean strength of the 3% mixture. This was reasonably consistent with the indirect tensile
strength findings (Section 7.4).
Also plotted in Figure 7.10 are results for the same hornfels stabilised with 3% type GP reported previously in
Austroads (2008). This shows that the 14-day strength of 3% type GB material was similar to the 7-day
strength to the 3% type GP material reported previously.
Similarly, beams of the Barratta Creeks gravel stabilised were with 2% or 4% type GB cement and cured for
1, 7, 28 or 90 days. As seen Figure 7.11, the flexural strength of the 2% cement mixture was unexpectedly
high but consistent with the flexural modulus results. The influence of cement content on modulus was less
significant than that observed for the crushed hornfels and also the indirect tensile modulus testing
(Section 7.3).
1.6
Flexural strength (MPa)
1.2
0.8
0.4
0
0 10 20 30 40 50 60 70 80 90 100
Age (days)
2.0% GB Barratta Creeks 4.0% GB Barratta Creeks
7.7 Summary
In summary:
• The estimated 28-day UCS of the Barratta Creeks gravel stabilised with 2% type GB cement was greater
than 2.5 MPa, which may not have complied with the proposed Austroads upper limit of 2.0 MPa for LBC.
However, this UCS result was higher than that measured by TMR and the contractor before and during
construction (Section 6.3.4). This difference in UCS cannot be explained by the difference in the densities
of the test specimens. A national test method for the preparation of UCS test specimens is required to
improve the consistency of UCS testing.
• The estimated 28-day UCS of the crushed hornfels stabilised with 1.5% type GB cement was 2.5 MPa
when compacted to 100% standard Proctor compaction. This value was above the proposed upper limit
of 2 MPa for LBC. However, given the above findings for the Barratta Creeks material, had this material
been tested by TMR the UCS may have been lower.
• Concerning the relative moduli of a 1.5% type GB mixture compared to a 3% mixture, for the crushed
hornfels both the indirect tensile and flexural modulus testing indicated the modulus of the 1.5% mixture
was roughly half of the 3% mixture value. However, the flexural moduli of the Barratta Creeks gravel
2% mixture were unexpectedly high (about 14 000 MPa), which was similar to the 4% mixture value.
• Concerning the relative strength of a 1.5% type GB mixture compared to the 3% mixture, both the indirect
tensile and flexural strength testing of the crushed hornfels indicated that the modulus of the 1.5% mixture
was approximately one-third the 3% mixture. However, the flexural strength of the Barratta Creeks gravel
2% mixture was unexpectedly high (about 1 MPa at 90 days) which was only slightly lower than the
4% mixture value.
8.1 Introduction
The aim of the mix design of LBC materials is to inhibit shrinkage cracking and crocodile and ladder cracking
which can lead to durability issues of the sprayed sealing or thin asphalt surfacing. It is important to
understand the relationship between the material binder content and the type of cracking mechanism to
manage the cost-effectiveness of the technology.
At the commencement of the project, laboratory test methods to investigate the cracking mechanisms of
stabilised materials, and to differentiate between materials susceptible to block cracking as observed for
HBC bases (Section 4) as opposed to the absence of block cracking for LBC bases (Section 5), did not exist.
As described below, an extra-large wheel-tracking (XL-WT) test was developed to investigate cracking
mechanisms of cemented materials in the laboratory. A key advantage of the wheel-tracking test is that it
applies a rolling wheel load and provides support and confinement to the specimen which more closely
mimics field conditions than traditional tests.
This section describes the development of the testing equipment, the test method and the results of testing
stabilised materials with different binder contents.
8.2.1 Introduction
As part of the research project a test method for evaluating the fatigue characteristics of LBC was developed.
This draft methods are provided in Appendix D, Appendix E and Appendix F, the development of which is
described below.
8.2.2 Equipment
The extra-large wheel tracking (XL-WT) device (Figure 8.1) was designed and manufactured to test unbound
granular materials as part of a previous Austroads project (Austroads 2013a). This work provided the starting
point for the development of a wheel-tracking test using the same XL-WT device to apply heavy
wheel-loading to LBC to induce cracking.
To assess the cracking characteristics, the test was modified as described below to enable flexure of the
stabilised material by the provision of flexible support instead of the steel base plate used in rut-resistance
testing.
The dimensions of the stabilised material test slabs (Figure 8.2) are as follows:
• slab length of 700 mm (direction of compaction and wheel-tracking)
• slab width of 500 mm mould width (transverse to the direction of traffic)
• slab thickness typically 100 mm; the thickness can be adjusted considering the desired amount of slab
flexure and the maximum aggregate size.
Note: Where LDPE sheets are labelled, this support setup, for some specimens, was replaced with neoprene sheets.
To allow flexure of the test slab specimens under the rolling wheel load, two variations for supporting the
slabs were used.
• Setup 1: slabs were supported by layers of 9 mm thick, low-density polyethylene (LDPE) sheets (nominal
flexural modulus of 200 to 400 MPa (Design Flow 2019) depending on the grade).The total thickness of
LDPE is 200 mm when testing a 100 mm thick LBC slab. While slab support is slightly stiffer than LBC
bases in service, the LDPE still allows flexure of the test slabs deflections under rolling wheel loading.
• Setup 2: slabs were supported by an alternate sandwich support structure of 9 mm thick LDPE sheets
and 10 mm thick neoprene rubber sheets with a flexural modulus of 1.65–2.1 MPa (Course Hero 2020).
The mould assembly used for testing is shown in Figure 8.2. The steel base plate is designed to attach
displacement gauges as in Section 8.2.3. Around two-thirds of the mould is filled with LDPE (or neoprene)
sheets providing support for specimen compaction and testing.
In the XL-WT device, a rolling wheel load (Figure 8.3) is applied using a solid rubber tyre which is capable of
carrying loads up to 20 kN This load was applied along a length of 500 mm centred around the middle of the
700 mm slab length.
Figure 8.3: Rolling wheel loading Figure 8.4: Planetary concrete mixer used to mix stabilised
materials
In a previous Austroads project (Austroads 2013a and b), a test method was developed to mix and compact
unbound granular materials for rut-resistance testing. This method provided the starting point for the
development of a method to mix and compact stabilised materials for fatigue testing.
Following a method previously used for cemented materials (Austroads 2014), the untreated material is firstly
mixed dry using a planetary mixer (Figure 8.4). The desired amount of water was then added, and mixing
was continued for two minutes. The material was then placed in large plastic containers and stored overnight
to allow homogenisation of the moisture content. The following day the required cementitious binder was
added followed by mixing using a planetary mixer for 10 seconds. Additional water was added to bring the
mixture up to optimum moisture content along with additional mixing for a further two minutes. The required
mass of material was then placed into the steel mould for compaction within 30 minutes of mixing being
completed.
The compaction of the test slabs was undertaken within the XL-WT device. The loose mixture was firstly
spread and tampered in the steel mould on top of either the LDPE or neoprene sheets Figure 8.2. A steel
compaction foot then folds down around the moulded rubber tyre and this was used to compact the material
into the mould (Figure 8.5). The speed of the compaction foot is slower than when testing the slab for fatigue
characteristics using the rubber tyre. The compaction was carried out in position control mode, where the
machine controls by height as opposed to load applied. This was found to help maintain a level surface
during the process. The target wet density was commonly determined as a percentage of standard or
modified Proctor maximum dry density to reflect in-service densities.
Figure 8.5: Austrack Extra Large Wheel-tracking device a) with compaction foot down, b) in wheel-tracking
mode
The compacted specimens were cured in humidity-controlled conditions using a fog room (100% humidity)
for their relevant curing times before testing.
For fatigue testing, a load of 20 kN was applied to a solid rubber tyre. This loading regime differs from
Austroads Test Method AGPT-T054-15 used for the rut-resistance of granular materials (Austroads 2013a
and b). For the latter, an 8 kN load is applied to a pneumatic tyre, however this load was considered
insufficient to induce fatigue damage in stabilised materials. As such, it was decided to use a 20 kN tyre load
which is closer to the damaging tyre loads applied to in-service pavements. To apply this load level, it was
necessary to use a solid rubber tyre.
The wheel-tracking load is bi-directional, with a full wheel cycle taking 2.5 s for a travel frequency of 0.4 Hz.
The load is applied over a 500 mm length rather than the entire slab length of 700 mm.
• The second phase of the testing involves spreading water over the surface of the specimen. The test was
stopped regularly, and water was applied. The objective of this phase was to accelerate the damage
which has initiated during the first phase and facilitate the identification of the major cracks in the material.
The number and length of the cracks observed at the surface of the specimen increased significantly in
this phase.
The addition of water in the second phase did not influence the rate at which the damage accumulated. The
water was added after the slabs were defined to have reached their fatigue lives and hence the performance
in second phase was not used in the analysis.
Under the repeated application of rolling wheel loads, stabilised materials may be damaged due to fatigue. In
the field, fatigue damage to cemented materials has been assessed using variation in the measured surface
deflections with time and/or cumulated loading (Jameson, Sharp & Yeo 1992; Austroads 2008). The same
principle was applied in the laboratory wheel tracking test where a means of measurement slab deflection
was developed.
A set of displacement sensors was installed underneath the test slab to monitor the dynamic deflection of the
bottom of the slab under the rolling wheel load. The sensors were attached to the steel base plate as
illustrated in Figure 8.6.
Figure 8.6: Schematic view and photographs of the deflection monitoring system developed for wheel tracking
slab
After wheel tracking testing, the fatigue damage was evaluated using several methods as follows:
Visual inspection
After trafficking the slabs were investigated to determine the cracking characteristics. Initially the slab surface
was visually inspected and the surface cracking pattern recorded, together with the condition of the bottom of
the slab. Figure 8.7 shows examples of surface cracking of an LBC slab and a HBC slab and also
differences in loose material at the bottom of the test slabs.
After visual inspection the amount of loose material generated by the wheel loading was weighed as a
measure of fatigue distress. A vibrating table was used to shake the loose material from the test slab,
including a steel cradle to safely hold the slabs during this process (Figure 8.8). The material generating after
vibrating the slab for 2, 4, 6, 8, 10 and 15 minutes was collected in trays housed in the cradle and weighed.
Under the repeated effect of the rolling wheel load the test slabs were gradually damaged. As the damage
was not visible until cracks propagate to the surface, as described in Section 8.2.5 slab deflections were
measured to quantify the changes of the test material modulus. The modulus changes provide an indication
of the fatigue damage in addition to the visual observations.
During the wheel trafficking, the sensors under the slab measured the deflections as a function of
time/loading. The deflections of centre sensor were recorded by an external data logger. Figure 8.9 is an
example of the measured elastic and permanent displacement of the bottom of the slab under repeated
loading passes. The peak deflections occurred when the tyre load was directly above the displacement
sensor and the troughs when the tyre was furthest away from the sensor (close to the edge of the mould).
The deflection of the bottom of the slab in each cycle was determined from the difference in displacement
between the peak and trough.
The deflection per loading cycle were then plotted as a function of the number of cycles. Figure 8.10 shows
an example where the deflection in each cycle of loading initially increased significantly and then reached a
point after which the deflections tended to plateau.
Figure 8.10: Example of variation in deflections per loading cycles with number of loading cycles
It was postulated that the higher the deflection per cycle, the lower the slab modulus and that modulus
reduction is indicative of the fatigue damage under cyclic loading. Furthermore, it was hypothesised that
when a deflection plateau is reached the material has degraded to a fully micro-cracked state.
To compare the fatigue characteristics of different materials, further analysis of the deflection data was
performed to determine parameters that may be relevant to fatigue damage. The measured deflections were
divided into several segments (Figure 8.11) that may be related to the damage state.
Figure 8.11: Analysing peak to peak deflections from the centre sensor under the wheelpath
These parameters are represented schematically in Figure 8.11 and are described in Table 8.1.
8.3.1 Introduction
In this project, a total of 22 test slabs (varying from lightly bound to heavily bound materials) were prepared
and tested. Although the number of specimens for each cement content, type, and curing time is limited,
these test results allowed an appreciation of the usefulness of the test.
Table 8.2 shows the liquid limit, plastic limit, plasticity index (PI), maximum dry density (MDD) and optimum
moisture content (OMC) as determined using modified Proctor compaction test, for both the aforementioned
materials.
When LBC materials are constructed in the field, it is common to use a slower-setting cementitious binder
such as type GB cement. However, it was determined from laboratory testing that the crushed hornfels
material stabilised with type GP cement after 14 days curing had a similar UCS to type GB cement after
28 days curing (Section 7.2). Based on this finding it was decided to use type GP cement to initially prepare
the stabilised crushed hornfels slabs as it expedited testing. Later type GB cement was used. The stabilised
Barratta Creek gravel was prepared using type GB cement, consistent with field trial B (Section 6.3).
Slabs have been prepared at various cement content between 1% and 3% and tested after a range of moist
curing times (Table 8.3).
*These specimens had a slurry layer applied to their surface before trafficking in the XL-WT device.
The target compaction levels were 95% of the modified Proctor maximum dry densities (MDD). The MDD
values and optimum moisture contents (OMC) of the materials tested are reported in Table 8.4 and
Table 8.5.
Table 8.4: Maximum dry densities and optimum moisture contents of the stabilised crushed hornfels
* 1% GB cement slabs were compacted to the same MDD and OMC values.
Table 8.5: Maximum dry densities and optimum moisture contents for the stabilised Barratta Creeks gravel
2% GB cement 4% GB cement
MDD (t/m3) 2.10 2.13
OMC (%) 8.3 8.0
Using the MDD, the slab target dry densities were calculated (Table 8.6) for use in compacting the test slabs.
The slab dry densities were measured post-trafficking by oven-drying a portion of each slab, coating it with
silicone and wax, and then tested as per a combination of the two methods: TMR Q306C 2016 and
AS/NZS 2891.9.1-2014. These measured dry density results are listed in Table 8.6. Generally, the measured
dry densities were within 2% of the target value.
*These specimens had a slurry layer applied to their surface before trafficking in the XL-WT device.
8.3.4 Curing
The specimens were cured in ideal humidity-controlled conditions using a fog room (100% humidity) for their
relevant curing times before testing.
For type GP cement-treated specimens, 14 days curing was considered ideal for laboratory testing to enable
more specimen conditions to be tested during the laboratory program. This was the main reason for the
selection of type GP cement as it cures faster than GB cement that would be used in the field. Laboratory
investigation showed that the UCS of a type GP cement specimen after 14 days curing was the equivalent of
28 days curing of a specimen containing type GB cement.
As such, the average curing time for specimens treated with type GB cement were longer (often 28 or
90 days instead of 14 days) to allow sufficient strength gain to take place before fatigue testing.
8.3.5 Results
Surface cracking
It was expected that a significant difference would be observed in the pattern of surface cracking with the
amount of cementitious binder. Figure 8.7 is an example of observed surface cracking variation with binder
content. It was concluded that due to the similarity of surface cracking observed in the XL-WT test
(e.g. Figure 8.7) irrespective of the binder content, surface cracking in the XL-WT was not indicative of the
different cracking characteristics of these materials in-service.
However, the visual inspection of slabs did tend to indicate a difference in the slab break down due to
loading. The bottom of the slabs with lower binder contents tended to break down more than those with
higher values, the latter tending to break into larger block cracks after trafficking.
Load-induced breakdown
For each of the test specimens, the mass of loose material collected in each tray (that is; left of the
wheelpath, right of the wheelpath, and underneath the wheelpath) was recorded after 2, 4, 6, 8, 10 and
15 minutes of slab vibration. The total mass collected from each slab after 15 minutes is given in Table 8.7,
with the mass recorded at each time interval provided in Appendix H.
For the Barratta Creeks gravel the results were too scattered to reach conclusions about the variation in the
mass of loosened with the strength of the stabilised material at the commencement of testing. In terms of the
stabilised hornfels, the 28-day result was unexpectedly high. In terms of the 14-day crushed hornfels results,
the mass for the loosened material tended to be greater for the slabs with lower cement content, i.e. the
degree of breakdown varied with the strength of the cemented material at the time of traffic loading.
* These specimens had a slurry layer applied to their surface before trafficking in the XL-WT device.
Note: Slabs 4833, 4866, 4932, 5029, 5383, 5492, 4811, 4876 and 5469 are not included here as they were unable to be
assessed on the vibrating table.
* These specimens had a slurry layer applied to their surface before trafficking in the XL-WT device
Table 8.9: Summary of average deflection data trafficked slabs of comparable cement contents and curing times
Figure 8.15: Overview of XL-WT testing for stabilised Barratta Creeks gravel
The initial deflection (D0) reflects the initial modulus of the slab. For the stabilised crushed hornfels, the
measured initial deflections generally decreased with cement content consistent with the expected increase
in modulus. As expected, slabs stabilised with 1.0% and 1.5% of cement had lower initial deflections than the
3% cement slabs. No similar trends were observed for the stabilised Barratta Creeks gravel.
The final deflection (D1) reflects at the inflection point. To some extent it may reflect the slab modulus in the
cracked state. For the stabilised crushed hornfels, three of the four 3% cement slabs had significantly lower
D1 values than the 1.0% and 1.5% cement slabs. This data suggests that the higher the pre-cracking
modulus, the higher the post-cracking modulus. No similar trends were observed for the stabilised Barratta
Creeks gravel.
The most interesting finding related to the relative fatigue lives. Concerning the stabilised hornfels,
Figure 8.16 shows the variation in the number of cycles to the inflection point with initial slab deflections. As
the higher the deflection the higher the tensile strain at the bottom of the stabilised layer, it is not surprising
that the number of cycles increases with reducing deflection.
60000
3 % cement
40000
Number of
load cycles to 30000
inflection point
20000
10000
0
0.1 0.12 0.14 0.16 0.18 0.2 0.22 0.24 0.26 0.28 0.3 0.32 0.34 0.36
For the hornfels stabilised with 1.5% cement, the number of load cycles to the inflection point was
approximately half that for the 3% cement mixture, suggesting the fatigue life of 1.5% cement mixture was
half the 3% mixture. Such a difference in fatigue life for a 100 mm thick slab is in agreement with the
predictions of the Austroads (2017) cemented materials fatigue relationship assuming the material stabilised
with 1.5% cement has half the design modulus and half the design flexural strength of a material stabilised
with 3% cement. This provided assurance that the fatigue life of LBC could be approximated by extrapolation
of the Austroads method of predicting the fatigue life of cemented materials as used in Section 9.2.
The Barratta Creeks gravel results were limited and due to the variability of results the significance of binder
content could not be determined.
• The final deflection (D1) is the deflection at the inflection point. To some extent it may reflect the slab
modulus in the cracked state. For the stabilised crushed hornfels, three of the four 3% cement slabs had
significantly lower D1 values than the 1.0% and 1.5% cement slabs. This data suggests that the higher
the pre-cracking modulus, the higher the post-cracking modulus. A similar trend was not observed for the
stabilised Barratta Creeks gravel.
• The most interesting finding related to the relative fatigue lives of the LBC and HBC materials. For the
hornfels stabilised with 1.5% cement, the number of load cycles to the deflection inflection point was
approximately half that for the 3% cement mixture. This finding was used in the development of the
design method (Section 9). However, the Barratta Creeks gravel results were limited; due to the variability
of the results the significance of binder content on fatigue could not be determined.
9.1 Introduction
In this section, a framework is proposed for the structural design of new flexible pavements containing LBC for
incorporation into updates of the Austroads Guide to Pavement Technology Part 2: Pavement Structural Design
(Austroads 2017a) and to the design of rehabilitation treatments provided in the Austroads Guide to Pavement
Technology Part 5: Pavement Evaluation and Treatment Design (Austroads 2019a). This design framework has
been developed based on the use and performance of LBC for moderate-to-heavily trafficked roads. Its
applicability to the design of lightly trafficked roads needs consideration in the revision of Austroads guides.
As discussed below, the development of design procedures for LBC materials required a reconsideration of the
design procedures for HBC materials post-fatigue cracking. Hence, this section proposed changes to cemented
materials in the post-cracking phase of life irrespective of the type of cemented material pre-cracking.
Based on the project research, the following are the guiding principles used in developing this method:
• Like other cemented materials, LBC materials are susceptible to fatigue cracking, but the severity of
fatigue cracking is different from cement materials with binder contents of 3% or more.
• Pavements containing LBC bases are designed and constructed with limited strength such that the
allowable traffic loading before fatigue cracking is insignificant compared to the allowable traffic loading
post-cracking. As such, there is no need to consider the fatigue life of LBC in structural design. The
structural design only needs to consider pavement performance in the post-cracking phase of LBC life.
• In the design of new pavements containing HBC materials (Austroads 2017a), a post-cracking phase of
the design life can only be considered in the mechanistic-empirical thickness design calculations if
cracking from the fatigued HBC material does not reflect through to the surface. To reduce the risk of
reflective cracking the pavement should provide a minimum cover equivalent to 175 mm of asphalt over
the HBC material. To enable relaxation of this minimum cover requirement when LBC materials are used
as bases, it is essential that bases are designed and constructed such that in the post-cracking phase, to
limit the develop of block cracking and crocodile cracking from a state of fatigue-induced micro-cracking.
• The field performance of Queensland pavement containing LBC bases has indicated that when LBC
bases are constructed on low modulus supporting layers there is an increased risk that the fatigue of the
LBC may result in macro-cracking. Accordingly, when LBC layers are designed to inhibit macro-cracking,
minimum support conditions need to be provided.
• LBC materials are susceptible to fine shrinkage cracking and load-induced micro-cracking. To reduce the
likelihood that macro-cracking will develop, the loss load transfer across such fine cracking with traffic
loading needs to be minimised. This is similar to the need to maintain load transfer across undowelled
contraction joints in plain concrete pavements. In the micro-cracked state the extent of load transfer
depends on the properties of the granular host material, the support of the underlying materials and
importantly the thickness of the LBC layer thickness. As a consequence, the proposed design method
provides a minimum LBC layer thickness when LBC layers are designed to inhibit macro-cracking.
• Like cracked HBC materials, LBC materials are more rut-resistant than unbound granular materials
however no change to the design procedures is proposed to allow for this enhanced performance.
• South African experience suggests that weakly cemented materials are susceptible to crushing. This was
confirmed in Australian during accelerated pavement testing of cement-stabilised fly ash (Jameson et
al. 1995). To avoid this type of distress and to maintain load transfer across micro-cracks, limits are
placed on the quality granular materials used in LBC materials. Austroads (2019a) provides guidance on
materials suitable for cementitious stabilisation.
• LBC materials may be used as subbase, in which case it is usually not be necessary to inhibit
macro-cracking. In such cases, the above-mentioned minimum thicknesses and support conditions are
not necessary.
The fatigue results in the laboratory wheel tracking testing (Section 8.3) tended to support this method of
predicting the fatigue life of LBC. In the wheel tracking test the fatigue life of LBC was about half the value for
cemented materials with 3% cement (Figure 8.16). The slab subjected to wheel tracking was 100 mm thick.
When the Austroads (2017) design method is applied to a 100 mm thick cemented material layer supported
by a modulus of 150 MPa, the predicted fatigue life of the 1.5% cement mixture is half the value for a mixture
with 3% cement using the following design inputs:
• 1.5% cement mixture: a pre-cracking design modulus of 2000 MPa and a design flexural strength of
0.6 MPa
• 3% cement mixture: a pre-cracking design modulus of 4000 MPa and a design flexural strength of
1.2 MPa.
As this predicted reduction in fatigue life with reduction in cement content agrees with the measured values
(Section 8.3.5), it was concluded that the in-service fatigue life of LBC could be approximated by using the
Austroads (2017) method currently used for HBC but with a design modulus of 2000 MPa and a design
strength of 0.6 MPa.
Using the Austroads (2017) method, including the Appendix F traffic load distribution, the required LBC base
thicknesses for a range of traffic loadings were calculated using:
• a subgrade vertical design modulus of 50 MPa
• a range of granular subbase thicknesses resulting in top granular sublayer moduli of 150 MPa and
250 MPa supporting the LBC base.
As shown in Figure 9.2, for a design traffic loading of 106 ESA and 200 mm subbase thickness
(Etop = 150 MPa), a 400 mm thick LBC base would be required. This required thickness of the LBC base to
inhibit fatigue cracking is about 170 mm more than that required when only the post-cracking phase is
considered (Figure 9.10).
It is apparent that, in order to inhibit fatigue cracking of low strength LBC bases, very thick base layers would
be required and, as such, they would generally not be cost-effective. Accordingly, it is proposed that the
Austroads thickness design method considers only the post-cracking phase of LBC material life.
Figure 9.2: Example of LBC base thickness requirement to inhibit fatigue cracking
400
380
360
340
Etop = 150 MPa
320
Etop = 250 MPa
300
LBC
base
280
thickness
(mm) 260
240
220
200
180
160
10 100 1,000 10,000 100,000 1,000,000
Design traffic in ESA (DESA)
In providing a structural design method for LBC material, this material type needs to be defined.
Austroads (2017) defines lightly bound materials as follows, which provides a useful starting point for the
definition of LBC materials:
Lightly bound are granular materials to which moderate amounts of stabilising agent have
been added to improve modulus, and where an increase in tensile capacity may occur.
Lightly bound granular materials may exhibit behaviour between modified granular
materials (Section 6.3) and more heavily bound cemented materials. While the properties
of lightly bound materials and their response to loading is the subject of further research, it
is currently common practice to categorise materials with a 28-day UCS of 1.0 to 2.0 MPa
as lightly bound. At this stage this Part does not provide specific guidance for these lightly
bound materials.
Given that LBC materials are a particular type of cemented material, in defining LBC material consideration
was given to the current definition of cemented materials (Austroads 2017a):
Cemented materials are described as a combination of a cementitious binder, water and
granular material that are mixed and compacted in the early stages of the hydration
process to form a pavement layer that is subsequently cured. The cementitious binder may
consist of Portland cement, blended cement, lime, or other chemical binder and may
include one or more supplementary cementitious materials such as fly ash or ground
granulated blast furnace slag. The binder should be added in sufficient quantity to produce
a bound layer with significant tensile strength.
An important characteristic that is not defined by Austroads for cemented materials is the minimum 28-day
UCS. Australian road agency specifications for cemented materials were reviewed (Austroads 2013c) and
the results are shown in Table 9.1 with several updates. It is beyond the scope of this research project to
investigate appropriate minimum UCS values for HBC materials.
Table 9.1: Summary of road agency the minimum strength requirements of HBC materials
1 For plant mixed cement treated material used as subbase under thick asphalt use soaked values. For in situ
stabilisation unsoaked values are used for cementitious binder contents 3% or greater.
2 Updated in accordance with TMR (2018).
Similarly, it was also useful to consider the current Austroads definition of modified granular materials
(Austroads 2017a):
Modified granular materials are granular materials to which small amounts of stabilising
agents have been added to improve modulus or to correct other deficiencies in properties
(e.g. by reducing plasticity) without causing a significant increase in tensile capacity
(i.e. producing a bound material). Modified materials have a maximum 28-day unconfined
compressive strength (UCS) of 1.0 MPa, tested after moist curing but without soaking at
100% standard maximum dry density and optimum moisture content.
In the design of new pavements TMR (2018) defines lightly bound materials as follows:
Lightly bound granular materials are typically specified to have a UCS between 1.0 and
2.0 MPa at 28 days when used in lightly bound base layers, and 1.0 to 2.0 MPa at seven
days when used in lightly bound improved layers.
Note that when lightly bound materials are used as improved layer/subbase in new pavements the required
range of strength effectively increases (TMR 2018), being approximately equivalent to a 28-day strength
between 1.5 and 2.5 MPa.
In the design rehabilitation treatments (TMR 2020), UCS limits used by TMR differ, namely a 7-day UCS
range of 1–2 MPa with a target 7-day UCS of 1.5 MPa. However, for slow setting binders a 28-day UCS
range of 1–2 MPa is stated.
The proposed design produces are primarily based on the use of LBC materials by TMR. Consistent with
TMR (2018) and Austroads (2017), it is proposed that Austroads continue to use a 28-day UCS range of
1.0–2.0 MPa for LBC materials.
TMR has recommended that additional requirements be included in the definition, namely that there needs to
be a ‘steady’ increase in UCS between 7 and 28 days along with a minimum 7-day UCS of 1.0 MPa or a
degree of saturation requirement if the 7-day UCS < 1.0 MPa. These additional requirements need
consideration in the revision of the Austroads guides. TMR will also consider the use of modified compaction
in the future, possibly with adjusted UCS requirements in the longer term.
A major issue that needs to be addressed with the inclusion of more detailed LBC design methods in
Austroads (2017 and 2019a) is consistency in the methods of preparing and curing UCS test specimens. The
differences in methods between laboratories include:
• The target compacted densities being related to both standard and modified Proctor maximum dry
densities.
• The target moisture contents during compaction being related to both standard and modified Proctor
optimum moisture content.
• The use of laboratory-mixed and field-mixed materials and consequently variable time delays between
mixing and test specimen compaction. Also, the field-mixed material can be at a lower moisture content
during laboratory compaction than the laboratory-mixed material.
• Soaking or not soaking before testing.
It is recommended that Austroads develop a test method related to the mixing, compacting and curing of
UCS test cylinders.
9.4.1 Introduction
The elastic characterisation of the two methods differs. However, in both cases the elastic characterisation is
a variation on the Austroads (2017) elastic characterisation of unbound granular and modified materials.
For unbound granular materials, there is strong evidence that the modulus in the vertical direction is different
from that in the horizontal direction (i.e. they are anisotropic). In the mechanistic-empirical design procedure
the vertical modulus of unbound granular materials is taken as being equal to twice the horizontal modulus.
Conversely, Austroads (2017) assumes cemented materials are isotropic. In terms of cracked cemented
materials, no such evidence exists as to whether they are isotropic or anisotropic. It is proposed that all
cracked cemented materials be assumed to anisotropic consistent with the characterisation of unbound
granular and modified materials.
Similarly, there is an absence of data related to Poisson’s ratio of cracked cemented materials. Again, it is
proposed that all cracked cemented materials be assumed to have a value of 0.35 consistent with the
characterisation of unbound granular and modified materials.
The following provides guidance for the determination of the vertical design modulus of cracked cemented
materials, that is LBC and HBC materials.
To develop a method to determine the design modulus of cracked cemented materials, the principal factors
affecting modulus needed to be considered. It is not unreasonable to assume the modulus of cemented
materials in post-cracking phases may depend on:
• the pre-cracking design modulus of the cemented material, reflecting the quality of the host materials,
cementitious type, and content and in situ density
• applied stress level as affected by the thicknesses and moduli of overlying bound (e.g. asphalt) layers
• the underlying support to cement material layer and the cemented material thickness.
In the pre-cracking phase of life, the design modulus is influenced by host materials, cementitious type and
content, and in situ density. In the absence of a laboratory method to prepare cement material test
specimens in an appropriate cracked state hinders consideration of whether the moduli in the cracked state
should vary or not with these same factors.
From the laboratory wheel-tracking of slabs with varying cement contents (Section 8), the vertical slab
deflections (D1) at the point of inflection may provide insight as to whether or not the cracked moduli are
related to the pre-cracking design modulus. The slab deflections of the stabilised crushed hornfels in the
cracked state were generally lower the higher the pre-cracked modulus. Assuming the measured slab
deflection is inversely related to the slab modulus, this suggests the post-cracking moduli are related to the
pre-cracking moduli.
However, the back-calculated moduli of 1% and 4% cement-stabilised materials at the end of accelerated
loading reported by Alabaster et al. (2013) (Figure 4.11), indicated the opposite; namely the cracked
cemented material modulus was not related to the pre-cracking modulus. Although the initial back-calculated
modulus of 1% cement mixture was about half the 4% mixture value, the moduli were similar at the end of
loading.
Given this limited and conflicting information, it is proposed to adopt the simpler approach that the
post-cracking modulus does not vary with the pre-cracking modulus. That is, the same values apply for
cracked LBC materials and cracked HBC materials.
Modulus stress-dependency
For unbound granular and modified granular materials, the maximum vertical modulus that a material can
develop depends on the applied stress. The applied stress reduces with the thickness and modulus of
overlying bound materials (Austroads 2017a). Consequently, granular design moduli reduce as the thickness
and modulus of overlying materials increase.
Conversely, for bound materials (e.g. asphalt, cemented materials), in Austroads (2017) no allowance is
made for the variation in design modulus with the level of applied stress.
Concerning the stress dependency of cracked cemented materials, Austroads (2008) reported the findings of
accelerated pavement loading of a 3% cement-treated crushed rock subbase supported by a sand subbase.
Figure 9.3 shows the variation in back-calculated moduli with the number of cycles of loading.
Figure 9.3: Modulus reduction of 3% cement-treated crushed rock subbase on a sand subbase
Using the data from experiment 3310, Figure 9.4 shows how the back-calculated modulus of the
3% cement-treated crushed rock at the end of loading varied with the applied FWD plate contact stress. This
material would be categorised as HBC material. At the end of trafficking when the HBC material was
micro-cracked (Austroads 2008) the back-calculated modulus tended to increase with load (Figure 9.4), yet
before accelerated loading there was no statistically significant variation in back-calculated modulus with
stress.
Figure 9.4: Experiment 3310 back-calculated HBC materials at the end of the loading
2000
1800
1600
1200
Cemented
materials
modulus 1000
(MPa)
800
600
400
500 550 600 650 700 750 800 850 900 950 1000
This data indicates that cracked HBC material modulus increases in modulus by about 50% when the
applied stress is doubled. This modulus increase with stress is about half the increase of unbound granular
base moduli (Figure 6.3 of Austroads 2017a). In the absence of other data, it is proposed that the cracked
HBC material bases be reduced for the effect of overlaying bound material thickness and modulus at half the
rate at which granular moduli reduce (Figure 9.5). Although, there is no supporting data concerning LBC
material, it is proposed this reduction also applies to this material as it is consistent with the assumption that
the characterisation in the cracked state is similar irrespective difference in pre-cracking characterisation.
For unbound granular materials and modified granular materials, the Austroads (2017) sub-layering process
in part addresses the effect of stress reductions with depth below the surface. However, as this sub-layering
process also addresses the effect of the underlying support, the significance of the modulus
stress-dependency in the sub-layering rules is uncertain. It would also be possible to allow for the
stress-dependency within cracked cemented material layers. However, a simple set of design rules suitable
for any layer depth below the surface would be complex. Hence it is not proposed to sublayer cemented
materials in mechanistic-empirical design calculations.
Figure 9.5: Proposed cracked cemented material modulus reduction factors with overlaying thickness of bound
materials
For unbound granular and modified granular materials, the maximum vertical modulus that a material can
develop is dependent on the modulus of the underlying supporting layer (Austroads 2017a). Conversely, for
bound materials (e.g. asphalt, cemented materials), no allowance is made for the variation in modulus with
the underlying support.
Concerning cracked cemented materials, Figure 9.6 shows the variation of back-calculated moduli of a
150 mm thick 3% cement-treated crushed rock subbase under accelerated loading (Jameson, Sharp &
Yeo 1992). This HBC material was placed directly on a clay subgrade with an estimated in situ CBR of about
6%. The back-calculated HBC vertical modulus reduced to about 250 MPa when cracking was observed on
surface.
Figure 9.6: Modulus reduction of 3% cement-treated crushed rock subbase on clay subgrade
However, in a later research project (Austroads 2008) when the 3% cement-treated crushed rock was
supported by a sand subbase (Figure 9.4) the back-calculated HBC vertical modulus reduced to about
800 MPa or more at the end of trafficking. In this case, surface cracking was not observed but cracking was
detected when the pavement was excavated at the completion of loading.
Based on this Australian accelerated loading trial data, the modulus of cracked cemented materials needs to
vary with the support provided by the underlying layers: the lower the modulus of the supporting layers, the
lower the cracked cemented material modulus.
However, the results of New Zealand accelerated pavement testing (Section 4.4.3) on a subgrade with an in
situ CBR of about 4% were not consistent with this conclusion. As seen from Figure 4.11, under a 60 kN dual
wheel load the back-calculated moduli of 1% and 4% cement-treated crushed rock reduced to 1400 MPa
despite the low support to the cemented material layers. Note that the strength of the subgrade was similar
to the Australian data used to derived Figure 9.6, however the cracked cemented materials at the end of
trafficking differed markedly. Again, in this research surface cracking was not observed.
It was not possible to resolve the findings from these three accelerated loading trials other than to note that
surfacing cracking was observed at the completion of the initial Australian research (Figure 9.6) but not at the
end of the New Zealand testing (Figure 4.11) or later Australian research (Figure 9.4).
It is proposed to base the Austroads procedures on the initial Australian modulus reductions (Figure 9.6) as
this resulted in a more conservative design moduli of cemented materials in the cracked state.
Note that the effect of the supporting layers on limiting modulus is different from that currently used for
unbound granular materials and modified granular materials. For instance, the 250 MPa back-calculated
modulus for the cracked cemented material (Figure 9.6) is about four times the modulus of the supporting
subgrade. Using Austroads (2017), the top modulus of granular material on this subgrade would be about
140 MPa. The Austroads (2017) sub-layering method for unbound granular materials would be overly
conservative for cracked cemented materials.
The most conservative design rule from these three accelerated loading trials is that the modulus to which
cemented materials reduce is limited to four times the modulus of the supporting layer.
Figure 9.7 shows the variation of vertical design modulus for cracked cemented materials with the modulus
of the supporting layer. This method is based on the assumption that the modulus of cracked cemented
material is limited to a maximum of four times the modulus of the supporting layer.
As there was no available data about high modulus (> 150 MPa) supporting layers, no increase in modulus
above a supporting value of 150 MPa is proposed. This chart includes a maximum vertical design modulus of
600 MPa as discussed below.
600
550
500
450
Cracked cemented
material design
400
modulus
(MPa)
350
300
250
200
150
30 50 70 90 110 130 150 170
Supporting layer vertical design modulus (MPa)
The maximum modulus a cracked cemented material base can develop occurs when the base modulus is:
• not limited by the modulus of the supporting layer and
• the applied traffic-induced stresses are not limited by the thickness and modulus of overlying bound
materials (e.g. asphalt).
This is consistent with the characterisation of unbound granular materials and modified granular materials.
Concerning LBC bases, modulus data in the cracked state was limited to the back-calculated modulus of the
250 mm thick LBC base in field trial B (Section 6.3). After one year of trafficking the mean back-calculated
modulus reduced to about 770 MPa (Table 6.22), with the moduli at three of the ten sites being below
600 MPa. At that time the mean back-calculated modulus of the underlying granular subbase was low,
80 MPa. Given the very low fatigue lives LBC bases it is not expected that the back-calculated modulus
would decrease significantly with additional loading.
As mentioned above, in Austroads (2008) research when the 3% cement-treated crushed rock was
supported by a sand subbase (Figure 9.4) the back-calculated vertical moduli of the cracked cement material
at the end of trafficking exceeded 800 MPa.
As discussed in Section 4.5, as part of a review of the in-service performance of New Zealand stabilised
pavements, back-calculated moduli of two pavements stabilised with 3% cement were estimated
(Figure 4.13). The weaker areas of the test pavements had an isotropic modulus of 500 MPa which did not
change over 10 years. Converting this isotropic modulus to the Austroads cross-anisotropic characterisation,
this equates to a vertical modulus of about 550 MPa.
As seen from the above, information about the modulus of cracked cemented materials was limited to
back-calculated moduli rather than laboratory testing as a method of preparing cracked test specimens has
yet to be developed. It should be noted that back-calculated moduli are currently not used in the design of
new pavements (Austroads 2017a) so care is needed in determining design moduli from back-calculated
values.
The New Zealand research (Figure 4.11) indicated that cemented materials after accelerated loading had
about twice the back-calculated modulus of an unbound granular base. Consequently, it seems reasonable
to assume that the maximum design modulus that a cracked cemented material base can develop should
exceed the presumptive vertical design moduli for unbound granular bases produced from the same source.
Considering the above information and TMR design method (Section 3.2.2) it is proposed that the maximum
presumptive vertical design modulus of 600 MPa be used for cracked LBC and HBC materials.
For unbound granular materials and modified granular materials, a vertical design modulus greater than
600 MPa may be derived from repeated load triaxial testing (Section 6.2.3 of Austroads 2017a). The use of
higher design moduli for these materials than cracked cemented materials is counter-intuitive.
Consequently, it is proposed that the maximum modulus of cracked cemented materials be the greater of
600 MPa and design modulus obtained by direct measurement of a cement-modified granular material
produced from the same host material, limited to a maximum of 1000 MPa.
Note that the direct measurement of resilient modulus of modified granular materials is recommended for
review to ensure the condition at the time of testing reflects in-service values including load-induced damage.
As described above, research data existed (Jameson, Sharp & Yeo 1992; Austroads 2008) about the
modulus of cement treated crushed rock subbases manufactured for Victorian host materials which most
likely had a laboratory soaked CBR of 30% or more. The characteristics of such high-quality subbases was
considered in the proposed maximum modulus of 600 MPa. However, there is lack of information about the
moduli of LBC materials manufactured from lower quality subbase materials. Until such information is
obtained, it is proposed that the design modulus of LBC materials manufactured from subbase materials with
a laboratory soaked CBR less 30% be limited to a maximum modulus of 210 MPa. This value is the
maximum modulus for subbase layers currently used by TMR (Section 3.2.1).
Procedures have yet to be developed to prepare laboratory test specimens in a cracked state that reflects
the state in situ. Consequently, a presumptive elastic characterisation is proposed as described above. As
discussed in Section 9.4.2, it is proposed that this elastic characterisation be used for cracked LBC and
cracked HBC materials.
For mechanistic-empirical design, the following elastic characterisation is proposed for LBC and HBC
material in the post-fatigue cracking phase of life:
• For subbases manufactured from granular materials with a laboratory soaked CBR less than 30%, the
vertical design modulus is the minimum of 210 MPa (Section 9.4.2) and the value obtained from
Figure 9.7 reflecting the effect of the supporting layer.
• For bases and subbases manufactured from granular materials with a laboratory soaked CBR of 30% or
more, the vertical design modulus is the minimum of:
– the value obtained from Figure 9.7 reflecting the effect of the supporting layer,
– the greater of 600 MPa and the design modulus obtained by direct measurement (Austroads 2017a) of
an unbound granular material or cement-modified granular material produced from the same host
material, limited to a maximum of 1000 MPa, and
– For LBC layers covered by bound materials, the Table 9.2 maximum vertical design moduli which
reflects the modulus stress-dependency of these materials.
• For LBC and HBC layers in the post-fatigue cracking phase of life, the above design modulus are applied
to the entire layer thickness: the layers are not sublayered.
• Cracked cemented materials are cross-anisotropic (with a degree of anisotropy of 2) and have a
Poisson’s ratio of 0.35.
Table 9.2: Suggested maximum vertical modulus of cracked cemented material bases and subbases
Note: These maxima apply to LBC bases and subbases, manufactured using unbound granular material with a
laboratory soaked CBR greater than 30%. For LBC materials manufactured using unbound granular material with a
laboratory soaked CBR less than 30%, a maximum modulus of 210 MPa applies regardless of the thickness and
modulus of the overlaying bound materials.
9.5.1 Introduction
The guidance below is limited to inhibiting macro-cracking when LBC materials are used as base as it is
unlikely LBC subbases will need to be designed to inhibit macro-cracking given likely overlaying surfacing
and base thicknesses.
As discussed in Section 9.2, due to the use of low cement contents LBC materials have low strength and
modulus and as a consequence, very thick LBC layers are required to inhibit fatigue cracking. Hence, an
Austroads design method to inhibit fatigue cracking of LBC materials is not proposed.
The design method is based on the premise that LBC layers are susceptible to fine shrinkage cracking and
load-induced micro-cracking. The thickness design method needs to inhibit the micro-cracking of LBC bases
with thin bituminous surfacings leading to surface macro-cracking, resulting in additional road maintenance
and rehabilitation.
There is empirical evidence (Section 5) that two key characteristics are important to inhibiting block cracking
and crocodile cracking:
• the support provided to the LBC base by the underlying layers
• the LBC base thickness.
Both these characteristics are considered in the TMR design process which requires a minimum LBC base
thickness of 200 mm and a minimum design modulus of 150 MPa for the layer supporting the LBC.
As discussed in Section 5.3.3, the analysis of selected Queensland pavements tended to suggest the extent
of surface longitudinal and transverse cracking reduced with increasing granular subbase thickness.
The current TMR (2018) design method recognises the importance of the support provided to the LBC base
as follows:
For lightly bound base pavements, the base is typically supported on a subbase with
thickness of at least 150 mm and which achieves a vertical design modulus of at least
150 MPa at the top of the subbase (determined using the procedures detailed in
Sections 8.2.2 and 8.2.3 of AGPT02).
This may be achieved by increasing the thickness of the subbase, and/or including
additional select fill or unbound granular material beneath the subbase.
It is proposed the Austroads method for LBC bases include the TMR minimum support requirements.
In addition to the minimum support provided to LBC bases, consideration was given as to whether additional
guidance is required to inhibit macro-cracking. In particular whether the required LBC base thickness needs
to increase with design traffic loading. The need for minimum thickness can be appreciated considering the
very limited fatigue life of LBC bases less than 200 mm thick as illustrated in the example designs in
Figure 9.2. There is a risk that low base thicknesses will result in block and crocodile cracking due to one
overloaded truck and this may result in undesirable cracking characteristics.
In the post-cracking phase of LBC life, it was considered the formation of LBC macro-cracking from
micro-cracking is influenced by the maintenance of load transfer across micro-cracking. The provision of
minimum support under the LBC base is important in this respect as it influences the load-induced
movement of cracks. It is postulated that by reducing crack movement the attrition of fines at cracks will be
reduced and hence inhibit micro-cracks widening into macro-cracks.
Of particular importance to the design method is whether the extent of crack movement needs to reduce as
the number of load repetitions increase. It was considered the Austroads thickness design procedures for
concrete pavements provided insight in this respect.
In the design of concrete pavement, erosion refers to the load-induced pumping of the subgrade/subbase
underlying the concrete base arising from repeated deflections at joints and planned cracks. The resulting
voids lead to faulting at transverse contraction joints under the slab. The Austroads thickness design
procedure for erosion was developed from finite element modelling and the performance of AASHO Road
Test concrete pavements (Vorobieff & Hodgkinson 2001). The amount of erosion was correlated with the
predicted deflection of the corner of the slab, the pressure on the subbase/subgrade, shape of the surface
deflection bowl and the load transfer across the joint (Figure 9.8).
Using the Austroads erosion damage method for a jointed plain concrete pavement, Figure 9.9 shows the
influence of concrete base thickness in erosion life for an effective subgrade CBR of 10%. Increasing the
base thickness:
• reduces the stress on the top of the subbase/subgrade
• reduces deflections at the slab corners
• lengthens the surface deflection bowl, thereby reducing the rate of which energy is applied to the
subbase/subgrade
• increases the contact area at the contraction joint, thereby increasing load transfer across the joint.
Figure 9.9: Example variation in allowable traffic loading in terms of erosion with concrete base thickness
260
250
240 SAST 60 kN
SADT 80 kN
230
TADT 170 kN
Concrete
210
base
thickness 200
(mm)
190
180
170
160
150
1.0E+05 1.0E+06 1.0E+07 1.0E+08
Allowable axle group repetitions
In order to maintain load transfer across joints, the extent of joint movement clearly needs to reduce as the
number of load repetitions increases. This concept was considered to apply to LBC bases designed to inhibit
the development of macro-cracking from micro-cracking: namely, the load-induced movement of
micro-cracks needs to reduce as the number of load repetitions increase.
The proposed LBC base design method addresses this issue by providing a minimum base thickness that
varies with the design traffic and the modulus of the underlying supporting layers. Figure 9.10 shows the
proposed design chart for minimum base thicknesses with thin bituminous surfacings. For pavements where
the LBC base is covered with asphalt less than 175 mm thick, the minimum LBC base thickness obtained
from Figure 9.10 may be reduced by the thickness of structural asphalt subject to a minimum LBC thickness
of 200 mm. These Figure 9.10 minimum layer thicknesses do not apply to LBC bases covered by 175 mm or
more thickness of structural asphalt as such asphalt thickness inhibit reflection cracking.
Figure 9.10: Minimum LBC base thicknesses for pavements with thin bituminous surfacings
300
260
Minimum
250
LBC
thickness
240
(mm)
230
220
210
200
190
1.0E+05 1.0E+06 1.0E+07 1.0E+08
Design traffic in ESA (DESA)
To develop this method, a pavement structure needed to be identified with the required ability to inhibit
development of macro-cracking from micro-cracking. The Queensland pavements reviewed in Section 5
were used to guide this reference case together with the TMR (2018) design method. A 20-year design traffic
loading of 5 x 106 ESA is a mid-range value for the Queensland application of LBC bases. With the provision
of a vertical design modulus of 150 MPa at the top of the subbase, a LBC base thickness of 250 mm was
selected which is within the 200–300 mm range commonly used by TMR. This was the assumed reference
case with the desired structural characteristics to inhibit macro-cracking.
The next issue to address was how to vary the LBC base thickness with the number of load repetitions, such
that the daily damage to micro-cracking was the same as the reference case. It was postulated that if the
early-life daily fatigue damage was the same as the reference case, the damage to the micro-cracking would
be the same. This seemed reasonable given that fatigue damage causes micro-cracking. As seen from
Figure 9.2 when the LBC base thickness increases from 250 mm to 285 mm, the fatigue life increases by a
factor of 10. Using this thickness variation, it was assumed that to limit the daily damage to the
micro-cracking the LBC base, the base thickness needs to increase by 35 mm for each 10-fold increase in
design traffic loading. Figure 9.11 shows the resulting variation in LBC base thickness when supported by a
granular subbase with design modulus of 150 MPa at the top of the subbase consistent with the reference
case.
Figure 9.11: Minimum LBC base thickness for granular subbase with E = 150 MPa
300
290
280
270
260
Minimum 250
LBC
thickness 240
(mm)
230
220
210
200
190
1.0E+05 1.0E+06 1.0E+07 1.0E+08
Design traffic in ESA (DESA)
Also, it is reasonable to assume the higher the support provided by the granular subbase the lower the
movement of the micro-crack which enables a reduction in LBC base thickness. From Figure 9.2, it can be
seen that for a given fatigue life increasing the top modulus from 150 MPa to 250 MPa reduces the required
LBC base thickness by 25 mm. Using this base thickness adjustment, Figure 9.10 shows the proposed
design chart for minimum LBC thickness. Note the thicknesses were all derived based on the assumption
that if the daily fatigue damage to the LBC base was the same as the reference case, the extent of
macro-cracking would be the same as the reference case.
In relation to the moduli of granular materials under the LBC, typically these granular materials would be of
subbase quality but may extend to a normal standard base material. The modulus of the top granular
sublayer under the LBC base is limited in a similar manner to described in Section 6.2.3 of Austroads (2017).
Assuming the LBC base has a vertical design modulus of 600 MPa, Figure 9.12 shows the maximum vertical
modulus of normal standard base material with LBC base thickness increases. In relation to selecting the
maximum moduli of subbase materials: for high-quality crushed rock subbases, which have a laboratory
soaked CBR greater than 30%, an assigned maximum modulus of the lesser of the value from Figure 9.12
and 210 MPa may be used, otherwise a maximum value of 150 MPa may be assigned.
Figure 9.12: Suggested maximum vertical modulus of top sublayer of normal standard base material
260
250
240
230
220
180
170
160
150
140
200 210 220 230 240 250 260 270 280 290 300
LCM base thickness (mm)
The proposed methods of elastic characterisation of LBC and HBC materials in the post-cracking phase of
life are described above. In addition, guidance is provided on the proposed minimum LBC layer thicknesses
to inhibit macro-cracking and determined on design moduli of underlying granular materials.
Thereafter, the pavement thickness design steps are the same as currently provided in Austroads (2019a)
for the design of cement materials in the post-cracking phase of life. This includes the use of the
mechanistic-empirical design method to determine the pavement composition required to inhibit permanent
deformation and asphalt fatigue cracking.
Given the use of LBC materials to date has been largely limited to Queensland, an option for consideration
by Austroads to allow the national use of the guidance provided in this report for an agreed period of time
prior to incorporation in these Austroads guides.
Queensland Department of Transport and Main Roads (TMR) has adopted cement stabilisation of pavement
materials on an intermittent basis for many years. In recent years, the use of LBC bases has been more
frequent in some regions, particularly North Queensland. These LBC bases are generally used to rehabilitate
existing pavements using in situ stabilisation; however, plant-mixed and paver-laid LBC bases have been
used for new pavements. The LBC bases are generally surfaced with a sprayed seal or thin asphalt
surfacing. These bases have been designed and constructed to inhibit the development of block cracking
and crocodile fatigue cracking that can develop with heavily bound cemented (HBC) bases. In the design of
rehabilitation treatments, the binder content is selected such that the UCS after 7 days curing is 1–2 MPa.
The objectives of this research project were to investigate the in-service performance of LBC pavements, to
improve understanding of the characteristics of LBC bases that inhibit the development of block cracking,
and to develop pavement structural design methods.
Consistent with Austroads (2017), the proposed definition of LBC materials is:
Lightly bound cemented materials are described as a combination of a cementitious binder,
water and granular material that are mixed and compacted in the early stages of the
hydration process to form a pavement layer. The cementitious binder may consist of
Portland cement, blended cement, and lime and may include one or more supplementary
cementitious materials such as fly ash or ground granulated blast furnace slag. The binder
should be added in sufficient quantity to produce a weakly-bound layer with low tensile
strength. Where lightly bound cemented bases are designed to inhibit block cracking and
crocodile cracking, a maximum 28-day unconfined compressive strength (UCS) of 2.0 MPa
applies, and a minimum above 1.0 MPa determined after moist curing but without soaking
at 100% standard maximum dry density and optimum moisture content applies.
TMR has recommended that additional requirements be included in the definition, namely that there needs to
be a ‘steady’ increase in UCS between 7 and 28 days along with a minimum 7-day UCS of 1.0 MPa or a
degree of saturation requirement if the 7-day UCS < 1.0 MPa. These additional requirements need
consideration in the revision of the Austroads guides. TMR will also consider the use of modified compaction
in the future, possibly with adjusted UCS requirements in the longer term.
The performance of LBC bases in Queensland was investigated and the following conclusions were drawn:
• From the field inspections conducted it can be concluded that plant mixed lightly cemented bases have
performed well. As such materials are placed as part of new construction, it is reasonable to assume that
the underlying support to the LBC base to be expected in new pavement design is a significant factor in
the good performance of these projects. However, in some cases the thin LBC bases were constructed
on cemented subbases and transverse cracking was observed on the surface, most likely related to
shrinkage of the cemented material subbases.
• The in situ stabilised bases showed a much wider range of performance. All LBC bases that were well
supported demonstrated good performance, as did some pavements where the underlying support could
be considered as inadequate from a structural design point of view.
• However, some in situ stabilised pavements exhibited very poor performance with the formation of major
block cracking evident. Additionally, some sections were found to have been extensively patched,
indicating that significant distress had been evident and the pavement had needed treatment to restore
serviceability. It has been postulated that the application of excessive binder has resulted in a continuous
length of one project exhibiting extreme block cracking in all wheelpaths, but evidence in support of this
could not be found. Inadequate subbase support to the LBC was suggested as the most likely cause of
poor performance. Current TMR (2018) design procedures reflect this experience as now the LBC bases
needs to be supported by a granular subbase with a minimum design modulus of 150 MPa.
• Several sites were cored to improve understanding of the required properties of good- and
poor-performing LBC bases. For sites with good performance with no block cracking, it was not possible
to extract intact cores because they disintegrated, either due to traffic loading or during coring. Two sites
where cores could be extracted were in poor-performing areas with visible block cracking. These findings
are consistent with TMR design concepts for LBC bases, namely to design and construct a low-strength
material that develops fine micro-cracking with sufficient base thickness and subbase support to limit the
extent that micro-cracking leads to macro-cracking.
• Long lengths of LBC bases showed little or no signs of block cracking or crocodile cracking after up to
10 years of trafficking.
To develop a design method for pavements containing LBC, a method first needed to be developed to
determine the design modulus of LBC. To assist the development, two field trials were constructed and
monitored for 12 months to enable the change in moduli with curing and early-life trafficking to be
investigated. Field trial A was located on the Bruce Highway at Collinson’s Lagoon. The 250 mm thick LBC
base was constructed by in situ stabilisation using 2.5% type GB cement. This binder content was selected
without the guidance of UCS testing of laboratory-manufactured cylinders. From deflection testing it was
concluded that the cement-stabilised layer had very high in situ modulus (> 5000 MPa) well above that
expected for a LBC base. It was doubtful that the moduli at this site were representative of a LBC base and
so the results were not used in developing the proposed design method.
Field trial B was located on the Bruce Highway near Barratta Creeks. The 250 mm LBC base was
constructed by in situ stabilisation of sandy gravel using 2% type GB cement; the UCS after 28 days was
determined as being approximately 2 MPa. From measured deflections the mean back-calculated modulus in
the outer wheelpath decreased from 1150 MPa after 90 days of trafficking to 770 MPa after one year. This
information was used to select the design modulus of LBC bases for use in the Austroads design method.
An important component in the development of a design method was gaining an understanding of the fatigue
characteristics of LBC compared to HBC materials. In terms of HBC materials, which commonly have binder
contents of 3% or more, flexural strength and flexural modulus can be used to predict fatigue life.
Accordingly, the strength and modulus of LBC materials and HBC materials were measured and the relative
fatigue lives determined. The key findings were as follows:
• One of the two LBC materials was Barratta Creeks gravel stabilised with 2% type GB cement. The
measured 28-day UCS of this material was 2.5 MPa and hence did not comply with the proposed
Austroads upper limit for LBC material. This UCS result was contrary to the testing carried out by TMR
and the contractor prior to and during construction (Section 6.3.4). This difference in UCS could not be
explained by the difference in the densities of the test specimens.
• The other LBC material was crushed hornfels stabilised with 1.5% type GB cement. It had a 28-day UCS
of 2.5 MPa and hence did not complied with the proposed Austroads upper limit for LBC material.
• In terms of the relative moduli of the hornfels stabilised with 1.5% type GB cement compared to the
3% mixture, both the indirect tensile and flexural modulus testing indicated that the modulus of
1.5% mixture was approximately half of the 3% mixture value. However, for the Barratta Creeks gravel
the flexural modulus of the 2% mixture was unexpectedly high (about 14 000 MPa), a value similar to the
4% mixture.
• In terms of the relative strength of the hornfels stabilised with 1.5% type GB cement compared to a
3% mixture, both the indirect tensile and flexural strength testing indicated that the modulus of the
1.5% mixture was approximately one-third of the 3% mixture value. However, for the Barratta Creeks
gravel the flexural strength of the 2% mixture was unexpectedly high (about 1 MPa after 90 days), a value
only slightly lower than the 4% mixture.
An extra-large wheel-tracking (XL-WT) laboratory test was developed to investigate the cracking
mechanisms of LBC materials compared to HBC materials. A total of 22 test slabs were prepared and tested
under repeated rolling wheel loading. The main findings were as follows:
• In terms of surface cracking that developed with loading cycles, there was not a significant difference in
the nature of the cracking with binder content. The block cracking that may occur in pavements with HBC
bases in-service could not be replicated in the wheel-tracking test. This most likely relates to the limited
length, width and depth of the test slabs compared to the dimensions in the roadbed.
• The mass of material loosened from the bottom of the test slab under loading tended to be greater for the
slabs with lower cement contents and shorter curing times. That is, the degree of breakdown varied with
cemented material strength at the time of traffic loading. This supports the view that early opening of
cemented materials to traffic may reduce the risk of macro-cracking.
• For the stabilised crushed hornfels, three of the four 3% cement slabs had significantly lower slab
deflections at the end of testing than the 1.0% and 1.5% cement slabs. This suggests that the higher the
pre-cracking modulus, the higher the post-cracking modulus. A similar trend was not observed for the
stabilised Barratta Creeks gravel.
• The most interesting finding related to the relative fatigue lives of the LBC and HBC materials. For the
hornfels stabilised with 1.5% cement the number of load cycles to the deflection inflection point was
approximately half that for the 3% cement mixture. This finding was used in the development of the
design method. However, the Barratta Creeks gravel results were limited and, due to the variability of
results, the significance of binder content in relation to fatigue could not be determined.
From this laboratory testing, a procedure was developed to predict the fatigue of LBC materials, this being an
extrapolation of the current method for HBC materials. It was concluded that LBC fatigue lives are so low that
excessive LBC thicknesses would be required to design pavements to inhibit fatigue cracking. Hence, and
consistent with the TMR design method, it is proposed that the Austroads design method only consider the
post-cracking phase of LBC life.
The research highlighted the need for a national test method for mixing, compaction and curing of UCS
specimens to improve consistency of UCS results across jurisdictions. Given that the use of LBC materials
may increase with the improved design method, there is an increased need for this method lest HBC bases
are used as LBC bases.
A structural design method was developed for pavements containing LBC materials and HBC materials in
the post-fatigue cracking phase of life, including:
• A new method for the elastic characterisation applicable to LBC materials and HBC materials in the
fatigue cracked state, including methods to vary the design modulus with the design modulus of the layer
supporting the cracked material and with the thickness and modulus of overlying bound materials.
• Design charts to select LBC base thicknesses to inhibit the development of block cracking and crocodile
cracking, with the minimum thickness varying with design traffic loading, the support provided by the layer
under the LBC base and thickness of asphalt surfacing (if any).
This framework is applicable to materials suitable for cement stabilisation as defined in Austroads (2019b).
This design framework was developed based considering the use and performance of LBC for
moderate-to-heavily trafficked roads. Its applicability to the design of lightly trafficked roads needs
consideration in the revision of Austroads guides.
Austroads (2019a) provides guidance about surfacing treatments to inhibiting reflection cracking due to
cracking of cemented materials. TMR (2018) requires the use of SAM/SAMI over LBC bases. This
information can be utilised in the revision of the Austroads guides.
Given the use of LBC materials to date has been largely limited to Queensland, an option for consideration
by Austroads to allow the national use of the guidance provided in this report for an agreed period of time
prior to incorporation in Austroads guides.
References
Alabaster, D, Patrick, J, Arampamoorthy, H & Gonzalez, A 2013, The design of stabilised pavements in New
Zealand, research report 498, NZ Transport Agency, Wellington, New Zealand.
Arnold, G, Morkel, C & van der Westhuizen, G 2012, Development of tensile fatigue criteria for bound
materials, research report 463, NZ Transport Agency, Wellington, New Zealand.
Austroads 2008, Fatigue performance of cemented materials under accelerated loading: influence of vertical
loading on the performance of unbound and cemented materials, AP-T102-08, Austroads, Sydney, NSW.
Austroads 2009, Guide to pavement technology part 3: pavement surfacings, AGPT03-09, Austroads,
Sydney, NSW.
Austroads 2012, Preliminary investigation of the influence of micro-cracking on fatigue life of cemented
materials, AP-T198-12, Austroads, Sydney, NSW.
Austroads 2013a, Improved rut resistance characterisation of granular bases: manufacture and
commissioning of a wheel-tracking device, AP-T239-13, Austroads, Sydney, NSW.
Austroads 2013b, Development of a wheel tracking test for rut resistance characterisation on unbound
granular materials, AP-T240-13, Austroads, Sydney, NSW.
Austroads 2013c, Review of definition of modified granular materials and bound materials, AP-R434-13,
Austroads, Sydney, NSW.
Austroads 2014, Cemented materials characterisation: final report, AP-R462-14, Austroads, Sydney, NSW.
Austroads 2017a, Guide to pavement technology part 2: pavement structural design, AGPT02-17,
Austroads, Sydney, NSW.
Austroads 2017b, Guide to pavement technology part 4F: bituminous binders, AGPT04F-17, Austroads,
Sydney, NSW.
Austroads 2019a, Guide to pavement technology part 5: pavement evaluation and treatment design,
AGPT05-19, Austroads, Sydney, NSW.
Austroads 2019b Guide to pavement technology part 4d: stabilised materials , AGPT05-19, Austroads,
Sydney, NSW.
Chakrabarti, S, Kodikara, J & Pardo, L 2001, ‘An overview of stabilisation methods and performance of local
government roads in Australia’, International symposium on subgrade stabilisation and in situ pavement
recycling using cement, 1st, 2001, Salamanca, Spain, Conference Organising Committee, Salamanca,
Spain, 16 pp.
Design Flow 2019, Polyethylene sheets, web page, Design Flow, Carrum Downs, Vic, viewed 24 June 2020,
<https://www.matrixpanels.com.au/polyethylene_sheets.html>.
Dunlop, RJ, Moss, PJ & Dodd, TAH 1975, ‘Prediction of cracking in soil-cement’, Australia-New Zealand
conference on geomechanics, 2nd, 1975, Brisbane, Qld, Institution of Engineers, Barton, ACT, pp. 120–4.
Freeman, TJ & Little, DN 1998, Develop maintenance strategy selection procedures for pavements
incorporating semi-rigid or chemically stabilized layers, FHWA/TX-99/17222-2, Texas Transportation
Institute, Austin, TX, USA.
George, KP 2002, Minimising cracking in cement-treated materials for improved performance, research and
development bulletin RD123, Portland Cement Association, Skokie, IL, USA.
Gray, W, Frobel, T, Browne, A, Salt, G & Stevens, D 2011, Characterisation and use of stabilised
basecourse materials in transportation projects in New Zealand, research report 461, NZ Transport
Agency, Wellington, New Zealand.
Jameson, GW, Sharp, KG & Yeo, R 1992, Cement treated crushed rock pavement fatigue under accelerated
loading: the Mulgrave (Victoria) ALF trial, 1989/1991, ARR 229, Australian Road Research Board,
Vermont South, Vic.
Jameson, GW, Dash, DM, Tharan, Y & Vertessy, NJ 1995, Performance of deep-lift in situ pavement
recycling under accelerated loading: the Cooma ALF trial, 1994. APRG report 11, Australian Road
Research Board, Vermont South, Vic.
Course Hero 2020, Katholieke Universiteit Leuven n.d., CR (chloroprene rubber _ neoprene), webpage,
Katholieke Universiteit Leuven, Leuven, Belgium, viewed 24 June 2020,
<https://www.coursehero.com/file/18781343/CR-Chloroprene-Rubber-Neoprene/>.
Lam, T & Bryant, P 2014, ‘CMB pavement trial: Frank Mallan Drive Lytton (constructed August 2014)’,
Queensland Department of Transport and Main Roads, Brisbane, Qld.
Queensland Department of Transport and Main Roads 1990, Pavement design manual, 2nd edn, TMR,
Brisbane, Qld.
Queensland Department of Transport and Main Roads 2018, Pavement design supplement: Supplement to
Part 2 Pavement Structural Design of the Austroads Guide to Pavement Technology, TMR, Brisbane,
Qld.
Queensland Department of Transport and Main Roads 2019, Transport and Main Roads specifications
MRTS10: plant-mixed lightly bound pavements, TMR, Brisbane, Qld.
Queensland Department of Transport and Main Roads 2020, Pavement rehabilitation manual, TMR,
Brisbane, Qld.
Roads and Maritime Services 2018, Construction of unbound and modified pavement course, QA-R71, RMS,
Sydney, NSW.
Scullion, T 2002, ‘Pre-cracking of soil-cement bases to reduce reflection cracking: field investigation’,
Transportation Research Record, no. 1787, pp. 22-30.
Smith, G & Caltabiano, M 1987, ‘The use of low shrinkage CTB in district 14 (metropolitan south)’, Main
Roads Department of Metropolitan Divisional technical symposium, Brisbane, Qld, Queensland
Department of Transport and Main Roads, Brisbane, Qld.
VicRoads 2008, In situ stabilisation of pavements with cementitious binders, section 307, VicRoads, Kew,
Vic.
VicRoads 2011, ‘Potential effects of a low percentage of GP cement in subbase crushed rock’, TR 211,
VicRoads, Kew, Vic.
VicRoads 2017, Registration of crushed rock mixes, RC 500.02, VicRoads, Kew, Vic.
Vorobieff, G & Hodgkinson, J 2001, ‘Technical basis of the 1992 guide procedures for design of rigid
pavements’, in G Jameson (ed) 2003, Technical basis of Austroads Guide to Pavement Technology Part
2: Pavement Structural Design, ARR 384, ARRB Transport Research, Vermont South, Vic.
Vorobieff, G, Walter, P & Anwar, S 2010, ‘Long-term performance of recycled granular materials in southern
NSW’, ARRB conference, 24th, 2010, Melbourne, Victoria, ARRB Group, Vermont South, Vic, 20 pp.
White, G 2006, ‘Laboratory characterisation of cementitiously stabilised pavement materials’, MEng thesis,
University of New South Wales, Canberra, ACT.
Wu, Z & Gaspard, K 2013, Minimizing shrinkage cracking in cement-stabilized bases through the use of
micro-cracking, research project capsule 12-3P, Louisiana Transportation Research Center, Baton
Rouge, LA, USA.
Yeo, YS 2011, Characterisation of cement-treated crushed rock basecourse for Western Australian roads,
PhD thesis, Curtin University, Perth, WA.
Zhang, J, Hou, D & Han, Y 2012, ‘Micromechanical modelling on autogenous and drying shrinkages of
concrete’, Construction and Building Materials, vol. 29, no. 3, pp. 230–40.
AS 5101.4-2008, Methods for preparation and testing of stabilized materials: unconfined compressive
strength of compacted materials.
AS 2891.13.1-2013, Methods of sampling and testing asphalt: determination of the resilient modulus of
asphalt: indirect tensile method.
AS/NZS 2891.9.1-2014, Methods of sampling and testing asphalt: determination of bulk density of
compacted asphalt: waxing procedure.
T147 2012, Working time for road construction materials (blended in the laboratory with slow setting
binders).
A.1 Introduction
As described in Section 5.2, selected sites in Queensland were inspected as part of the project. This
Appendix contained notes and photographs related to the roads inspected. The text is based on an
unpublished project Working Paper dated October 2016 prepared by Phil Hunt of Road Engineering Services
and Dr Michael Moffatt of ARRB as part of Austroads project TT1897.
Source: http://ontheworldmap.com/australia/state/queensland/.
Prior to field visitation, asset management data, construction drawings, UCS records (if available), were
collated for each project.
The site inspections were undertaken between June and September 2016.
A.2.1 Overview
The site inspected was Cunningham Highway (National Highway), between Ipswich and Warwick. 2.9 km
between chainages 85.8 and 88.7 km, in Darling Downs District. The road is located in undulating terrain
with good pavement drainage.
The pavement was widening and rehabilitated in 2008 with the following pavement structure:
• 250 mm LBC
• 300 mm of granular pavement
• subgrade design CBR of 15% due to use of selected fill on embankments and sound cuttings.
The existing lanes were overlaid with 250 mm thickness of Type 2 base and then in situ stabilised.
The LBC was produced using 1.5% cementitious binder, the binder being a 60% type GP/40% fly ash blend.
The 2.9 km study section was eight year old when inspected in 2016 and had experienced a cumulative
traffic loading 4.4 x 106 ESA.
Fifty per cent of the total through-lane wheelpaths (4 x 2.9 km) either have been patched or currently show a
rut/shove or fatigue cracking (Figure A 2).
During construction UCS testing was taken at two locations, both locations subsequently needed to be
patched due premature distress. The UCS results of field-mixed and laboratory compacted specimens were:
• Chainage 86.79: 7-day UCS of 1.3 & 1.6 MPa
• Chainage 88.315: 7-day UCS of 0.6 MPa.
In general, the patch repairs have consisted of 150–200 mm deep, 2% type GB re-modification (adding
additional cement using a stabiliser/reclaimer). The repairs are performing very well, with the exception of
one section that is showing signs of crocodile cracking. As shown in photograph on the immediate right of
Figure A 2.
Due to the extensive distress very early in life, this pavement was clearly a poor performer.
A.3.1 Overview
The two sites inspected were on the Cunningham Highway (Inglewood – Goondiwindi) between chainages
85.4 and 87.0 km (Figure A 3) in Darling Downs District. The terrain is very flat grades. The presence of
longitudinal cracking possible indicates expansive clay subgrades in parts of the project.
In 2007 the pavement was rehabilitated with the resulting pavement compositions:
• Site 2 85.4–86.6 km: 250 mm LBC on remaining 50 mm of unbound granular material. Total pavement
depth 300 mm.
• Site 2A 86.6–87.0 km: 250 mm LBC on 325 mm of unbound granular material. Total pavement depth
575 mm.
The surfacing comprised a size 10 mm primerseal followed by size 14 mm final size using PMB Olexobit
S0.3 binder.
The subgrade materials included clays to sandy clays with estimated low to medium CBRs in the ranged of
3–5% in weakest areas to CBR of 7–9% elsewhere.
The existing pavement materials were in situ stabilised to a depth of 250 mm using 2% type GB cement. The
7-day UCS at 2% binder was 1.3 MPa which was within the 7-day target range of 1.0 to 1.5 MPa.
The 1.6 km study section was 9 years old when inspected in 2016 and had cumulative traffic loading of
4.4 x 106 ESA.
Site 2 with 300 mm total pavement depth has performed to a fair standard (Figure A 4), whilst Site 2A with
575 mm total pavement depth has performed to a good standard.
Overall 4.5% of the wheelpaths exhibits either crocodile cracking, transverse cracking or patching.
There is some longitudinal cracking on the shoulder edges, indicating the likelihood of expansive subgrades.
A.4.1 Overview
Sites 5 and 5A were located on the Malanda-Atherton Road between chainages 13.5–14.4 km and
15.5–16.3 km, in far North Queensland District. The terrain is flat to very flat with good table drains
(Figure A 5).
The pavement was rehabilitated in 2009 using LBC, with the resulting pavement compositions:
• Site 5 13.5–14.4 km: 200 mm thick overlay of plant-mixed LBC on 240 mm unbound granular on a red
clay subgrade with a design CBR of 6% (soaked). Total pavement depth 440 mm; however, this could be
greater where the old pavement existed.
• Site 5A 15.5–16.3 km: 200 mm thick overlay of plant-mixed LBC on 160 mm unbound granular pavement
on a red clay subgrade with a design CBR of 6% (soaked). Total pavement depth 360 mm.
The LBC was produced in a pugmill using 1.5% type GB cement and placed with a paver. Design or
construction UCS results were not obtained in the investigation.
At the time the pavements were inspected after 7 years of trafficking, the cumulative traffic loading was
8.4 x 105 ESA and 5.2 x 105 ESA for Sites 5 and 5A respectively.
After seven years of trafficking both sites are in sound condition with no signs of any pavement distress. It is
possible that a reseal was placed before the inspection was masking cracking and other repairs, however the
pavement maintenance costs were low and there was no surface deformation.
A.5.1 Overview
Site 6 was located on the Flinders Highway (Hughenden- Richmond) between chainages 70.5 km and
74.5 km in North West District. The terrain was flat to slightly undulating terrain with good table drains. The
road formation is 0.5–1.0 m above natural subgrade, which is an expansive black soil (Figure A 6).
The pavement was rehabilitated in 2005 and the resulting pavement composition was:
• 250 mm thickness LBC achieved by in situ stabilised of existing pavement after it was topped up with
50–100 mm Type 3 granular base.
• 100–250 mm thickness of sandy loam subbase
• black clay subgrade.
The LBC was produced using 5% of a 50% lime/50% fly ash blend.
Before construction UCS testing was undertaken using both type GB cement and 50% lime/50% fly ash
blend. The target 7-day UCS for the type GB cement was 1.0 to 1.5 MPa, whereas for 50% lime/50% fly ash
the target was a 28-day UCS of 1.0 to 1.5 MPa. From the results (Figure A 7) it was decided to 5% of
50% lime/50% fly ash.
This pavement was about 11 years old when inspected 2016 and had experienced a cumulative traffic
loading was 9.3 x 105 ESA.
The pavement was in good condition (Figure A 8). However, a reseal six months before the inspection may
have masked some defects and/or old maintenance repairs. There is also evidence that a 1 m wide
shoulder/OWP geotextile reinforced seal placed a year after construction (2006) was used to control
environmental longitudinal cracking on a reactive clay subgrade (Figure A 9).
A.6.1 Overview
Site 7 was located on the Flinders Highway (Hughenden-Richmond) between chainages 91.6 km and
102.3 km in North West District. The terrain is flat to slightly undulating, with the pavement on an elevated
formation with good table drains. The subgrade was an expansive black soil, which had a design CBR of 3%
or less.
In 2012 after a major rain event damaged the existing granular pavement, the pavement was rehabilitated by
in situ stabilisation to a depth of 250 mm. The resulting pavement composition was:
• 250 mm thickness of LBC
• 75 mm thickness of granular subbase
• black clay subgrade with a design CBR of 3%.
The LBC was produced using 2% type GB cement. UCS test results were not available for this site.
This pavement was four years old when inspected in 2016 and had experienced a cumulative traffic loading
was 4.8 x 105 ESA.
The performance of the four-year-old LBC pavement was considered generally good. However, the 2015
network road condition data indicated average rutting between 7 to 10 mm, with maximum rutting up to
15 mm occurring. This high amount of rutting would be considered poor performance for a 4-year-old
pavement. This depth of rutting was not readily observed onsite.
There was one very poor performing area between 101.6 km to 102.9 km (16% of job length) exhibiting block
cracking in all wheelpaths (Figure A 11). It was suspected that a major cement overdose or double cement
application after some type of initial construction failure was experienced.
A.7.1 Overview
Site 8 was located on the Bruce Highway (Bowen – Ayr) between chainages 43.7 km and 45.6 km in
Mackay/Whitsunday District. The terrain is flat to very flat (Figure A 12) with a bridge crossing of the Elliot
River at chainage 44.6–44.75 km.
The existing pavement was reconstructed in 1999, with the following composition:
• 200 mm thickness of LBC
• 125 mm thickness of Type 2.3 granular subbase
• 175 mm thickness of Type 2.5 granular subbase
• clay subgrade with a design CBR of 4%.
No details could be found concerning whether the LBC was plant-mixed or produced by in situ stabilisation,
but given the year of construction was 1999 it seemed more likely to be in situ stabilisation. The LBC was
manufactured using 1.5% type GB cement. UCS results were not available for this site.
The 1.9 km study section was 17 years old when inspected and was in very good condition (Figure A 13)
with generally no deflects after 5.2 x106 ESA of traffic loading. In 2010, the pavement was resealed using a
polymer modified binder. It is not known whether there was surface cracking before the reseal.
A.8.1 Overview
Site 9 was located on the Bruce Highway (Bowen – Ayr) between chainages 75.2 km and 78.9 km in
Mackay/Whitsunday District. The terrain was flat with good surface drainage (Figure A 14). This site was not
identified before commencing the field inspections but was noticed when travelling to Site 8 because of the
substantial extent of block cracking.
The pavement was rehabilitated in 2008. Limited information was available about the pavement composition
other than it includes a 200 mm thickness of LBC on an unbound granular subbase (depth unconfirmed) on a
clay subgrade with an estimated subgrade CBR in the range of 3–4%.
No details could be found about the cement content and type used to produce the LBC.
At the time of inspection in 2016, the pavement was eight years old and had experienced a cumulative traffic
loading of about 1.8 x106 ESA. This pavement was severely cracked with block cracking on a total 23% of
the length (Figure A 15).
As details of the cement content and type are not known it is uncertain whether this is an LBC. Due to this
doubt its performance was not considered in the final analysis.
A.9.1 Overview
Site 10 was the Townsville North Road (Woolcock St: Townsville Port Road) between chainages 0.8 km and
4.7 km in Northern Queensland District. This road was originally part of the old Bruce Highway through
Townsville. It is now known as the North Townsville Road or colloquially as Woolcock St: Townsville Port Rd.
This asphalt surfaced urban road is a divided road with two lanes in each direction (Figure A 16).
The terrain is flat to slightly undulating, with the pavement on elevated select fill (CBR = 10) and good
drainage. The underlying subgrade is low strength clay (possibly originally swamps) with a design CBR of
1%.
The LBC was plant-mixed using 1.5% type GB cement and placed with a paver. TMR testing indicated the
resulting 7-day UCS was 0.50–0.75 MPa, a low strength compared to other in situ stabilised projects.
In 2008 the pavement was overlaid with 45 mm of DGA providing a total of 90 mm of DGA.
The 3.9 km long site was 18 years old when inspected and had experienced a cumulative traffic loading of
5.2 x 106 ESA. The pavement had no visual deflects in 2016 and had performed very well (Figure A 17).
A.10.1 Overview
Site 11 was the Douglass – Garbutt Road (Duckworth St) between chainages 4.1 km and 5.4 km in Northern
Queensland District. This road is an asphalt surfaced urban arterial in Townsville (Figure A 18). The road
was originally part of the old Bruce Highway.
The LBC base was plant-mixed using 1.5% type GB cement and placed with a paver. UCS test results were
not available for this project.
In 2011 after 13 years in-service the original 45 mm DGA surfacing layer was removed and replaced with the
same material 45 mm DGA.
The 1.3 km study section was 18 years old when inspected in 2016 at which time it had a cumulative traffic
loading experience of 7.6 x 106 ESA, exceeding the design traffic loading of 6 x 106 ESA.
No pavement defects were observed, the pavement was in sound condition (Figure A 19).
A.11.1 Overview
Site 12 was the Bruce Highway (Townsville to Ingram) between chainages 42.8 km and 50.6 km in Northern
Queensland District. The site had a flat terrain with good table drains (Figure A 20).
The pavement was constructed in 2000 with the following pavement composition:
• 200 mm thickness of LBC base
• 250 mm thickness of cement-treated subbase (TMR category 1)
• subgrade with a design CBR of 4%.
The LBC was plant-mixed using 1.5% type GB cement and placed with a paver. UCS test results were not
available for this project.
Details of the original surfacing are not available. In 2011 the pavement was resurfaced using
microsurfacing.
The 7.8 km study section was 16 years old when inspected in 2016 and had experienced a cumulative traffic
loading 6.6 x 106 ESA which exceeded the design traffic loading of 5.9 x 106 ESA. The pavement was
generally in sound condition considering its age.
A microsurfacing was placed in 2011 and had performing well when inspected. Whilst the reason for the
microsurfacing is unknown, it is usually selected for its rut filling and surface texture correction abilities. The
more recent microsurfacing treatments utilise a polymer modified bitumen binder and a fibre to resist
cracking. Whilst there was a lot of fine transverse cracking in the shoulder that was beginning to show
through, the microsurfacing did not appear to resist the larger crack widths in the shoulder area. Interestingly,
the transverse cracks were very rarely observed in the traffic lanes.
A.12.1 Overview
Site 12 was the Bruce Highway (Townsville to Ingram) between chainages 87.6 km and 92.3 km in Northern
Queensland District. The terrain was flat between 87.6–90 km and slightly undulating 90.0–92.3 km
(Figure A 22).
The pavement was constructed in 2001 with the following pavement composition:
• 180 mm thickness of LBC base
• 205 mm thickness of cement-treated subbase (TMR category 1)
• subgrade with a design CBR of 7%.
The LBC was plant-mixed using 1.5% type GB cement and placed with a paver. UCS test results were not
available for this project.
Details of the original surfacing are not available. In 2009 the pavement was resurfaced using
microsurfacing.
The 4.7 km study section was 15 years old when inspected in 2016 and had experienced a cumulative traffic
loading of 5.2 x 106 ESA which was close to the design traffic loading of 5.7 x 106 ESA.
Similar to Site 12, the pavement had performed well except for (Figure A 23):
• fine to large width transverse cracks (cementitious origin) occur intermittently in the shoulder region
• two locations (240 m2) of crocodile cracking in the OWP, equating to 1.1% of the total project wheelpath
area.
A microsurfacing was placed in 2009 was performing well. Whilst the reason for the microsurfacing is
unknown, it is usually selected for its rut filling and surface texture correction abilities. The more recent
microsurfacing treatments utilise a polymer modified bitumen binder and a fibre to resist cracking. It is
suspected that microsurfacing works in 2009 may not have included the fibres. It was not able to resist the
crocodile cracking occurring at chainages 89.8 km and 90.5 km.
A.13.1 Overview
Sites 14 and 14A were located on the Bundaberg – Miriam Vale Road between chainages 59.9 km and
61.6 km in Fitzroy District. The terrain is slightly undulating, dipping down to baffle creek on both sides.
Whilst some table drains are close to the pavement, they drain well (Figure A 24).
The pavement was rehabilitated in 2010 to form the following pavement structure:
Pavement structure:
• Site 14 59.9–61.0 km: 200 mm thickness of LBC directly on subgrade with design CBR of 10–20% as
indicated on the TMR project drawings.
• Site 14A 61.2–61.6 km: 200 mm thickness of LBC on 350 mm of unbound granular subbase on subgrade
with a design CBR of 10–20%.
The CBM was produced by in situ stabilisation. To provide sufficient material to stabilise, a 50 mm thickness
of imported granular base was placed on the surface before in situ stabilisation. The LBC was produced
using 2% type GB cement. UCS test results were not available for this project.
This 1.7 km long section was about 6 years old when inspected in 2016 and had experienced a cumulative
traffic loading of 4.5 x105 ESA which is 15% of the design loading 3 x 106 ESA.
Two distinct pavement compositions either side of Baffle Creek, labelled site 14 and site 14A as described
above. The inspection found (Figure A 25):
• Site 14A which includes 350 mm thick granular subbase) has no defects.
• Site 14 where the LBC is not supported by a granular subbase had defects (cracking, patches, and
rut/shoves) over about 13% (558 m) of its length after only 6 years.
It was concluded that Site 14A had performed reasonably well (Figure A 25), but that Ste 14 was not
performing well given its condition after only 6 years in-service.
A.14.1 Overview
Site 15 was Western Yeppoon – Emu Park Road between chainages 14.4 km and 16.3 km in Fitzroy District.
The terrain was flat with the majority of this section across swampy wet terrain (Figure A 26).
The pavement was rehabilitated in 2010 by in situ stabilisation to a depth of 150 mm. The 150 mm thick LBC
pavement is on an embankment for the majority of the length, well elevated over swampy ground. The
pavement layers under the LBC are not recorded in the TMR asset management database. It is suspected
the LBC was supported by at least 200 mm thickness of the unbound granular pavement, 500 mm
earthworks (select fill, CBR ≥ 10) and geotextile wrapped rockfill at natural surface level exists. The natural
subgrade had an estimated design CBR of 1%.
The CBM was produced by in situ stabilisation to a depth of 150 mm using 2% type GB cement.
With 2% type GB cement, the 7-day UCS was measured to be 0.5–0.8 MPa, which was below the 7-day
target range of 1.0–1.5 MPa.
The 1.9 km study section was six years old when inspected in 2016 at which time it had a cumulative traffic
loading of 4.2 x 105 ESA.
No cracking was evident, and the pavement was performing reasonably well after six years, except for
flushing/embedment of the sprayed seal surfacing (Figure A 27).
A.15.1 Overview
Site 16 was the Dawson Highway (Gladstone – Biloela) between chainages 50.8 km and 56.1 km in Fitzroy
District (Figure A 28). The terrain was undulating with table drainage mostly good, but some sections only
fair.
In 2007 Dawson Highway was rehabilitated using in situ cementitious stabilisation to a depth of 150 mm. The
material stabilised comprised 100 mm thickness of imported gravel plus 50 mm of existing pavement
material. Whilst there are some anomalies in the TMR asset management database, it was considered that
there was 280 mm of granular material under the LBC. The underlying sandy/gritty clay had an estimated
CBR of 5–7%.
The LBC base was produced by in situ stabilisation to a depth of 150 mm using 2.5% type GB cement.
The ‘as constructed’ drawings reported cement contents and UCS test results measured during construction.
The average cement content cement content was 2.8% resulting an average 7-day UCS of 1.5 MPa at the
top end of the 7-day target range of 1.0–1.5 MPa. Individual UCS results were in the range 0.9 MPa and
2.3 MPa, with 4 out 12 results between 2.2–2.3 MPa.
The 5.3 km study section was about nine years old when inspected in 2016 and had experienced a
cumulative traffic loading of 1.0 x 106 ESA.
Defects recorded in this section included crocodile cracking, patches and rut/shoving (Figure A 29). The
defects totalled 1.7% (362 m) of the total wheelpath length.
Considering the minor amount of distress after nine years, the pavement was concluded to be performing
satisfactorily.
A.16.1 Overview
Sites 17 and 17A were located on the Dawson Highway (Biloela – Banana) between chainages 9.7 km and
45.0 km in Fitzroy District. The terrain was flat between 9.7–12 km, slightly undulating to hilly 12–42 km the
flat again between 42–45 km. The surface drainage varied from poor to fair to good (Figure A 30).
In 2007 the pavement was rehabilitated by in situ stabilisation using 2% type GB cement. No records of UCS
testing were obtained. The thickness of LBC varied along the project (Figure A 31, Figure A 32) but was
generally 150 mm and 180 mm thick.
According to local TMR staff, the TMR asset management database did not represent accurately the
granular materials under the LBC for this project. It seems likely that there is 250–400 mm thickness of
existing unbound granular pavement.
The review of the performance was complicated by severe rain depressions in 2011–13 which caused
approximately 9.9 km (full-width equivalent) or 28% of total wheelpath length to be reconstructed in 2013.
The reconstruction work consisted of re-in situ modification via stabiliser/reclaimer with some sections also
obtaining a 125 mm plant-mixed (1% type GB) cement-modified gravel overlay. The majority (80%) of the
reconstruction occurred between chainages 30–45 km.
Source: TMR.
Source: TMR.
This large 35.3 km section was about nine years old when inspected in 2016 at which time the pavements
had experienced the following cumulative traffic loadings over nine years:
• Site 17 9.7–26.8 km: 1.17 x 106 ESA, which was 98% of the design traffic loading 1.2 x 106 ESA
• Site 17A 26.8–45 km: 9.4 x 105 ESA, which was 62% of the design traffic loading 1.2 x 106 ESA.
Concerning the performance of Site 17 (Figure A 33), which included only minor areas of re-stabilisation,
pavement distress was observed in isolated areas:
• two areas totalling 40 lineal metres (48 m2) of crocodile cracking
• 50 lineal metres of longitudinal cracking in the OWP
• 354 m2 of rut/shove failure
• 2730 m2 of patches.
For Site 17 a total of 2% of the wheelpath length displayed one of these three forms of distress. Given the
pavement had already carried its design traffic by 2016, the LBC performed well at Site 17.
Site 17A has fewer deflects in 2016 but this was likely to be due to substantial lengths that needed to be
reconstructed in 2013. Because substantial areas needed to be reconstructed in 2013, the performance of
the LBC was considered to be poor in this section of the project.
D.1 Introduction
This Appendix describes the method to split and mix samples for wheel tracking fatigue testing (Section 8).
D.2 Splitting
The bulk untreated material was split into representative samples using a motorised rotary splitter shown in
Figure D 1. The splitter has a large funnel into which the bulk material can be loaded. A conveyor belt then
delivers this material at a constant speed to 12 removable canisters which rotate underneath the belt, also at
a constant speed. The process involved splitting two or more batches of 12 numbered (10 L) buckets each.
Corresponding numbers from each of the batches would then be combined for a second (final) round of
splitting to improve uniformity between samples.
Batches of aggregate material were weighed and preconditioned (addition of moisture) 24 hours prior to
mixing. The preconditioned mix was then combined with the remaining water and cement in a motor-driven
planetary concrete mixer with a tank size of 800 mm diameter and 350 mm high (Figure D 2).
Following mixing, the material was placed in containers and covered with a plastic sheet and let stand for
some time before compaction. The intention was to make allowance for the commencement of the cement
binder reaction and also to replicate the field placement of cemented materials which can involve quarry
mixing and then the delivery time before placement. The standing time was at most 30 minutes as beyond
this time samples were too difficult to compact due to the initial ‘set’ of the cement binder.
Note: After completion of the compaction, the thickness of the slab at all points of the measuring zone must
not within 2 mm of the 100 mm target slab thickness.
Load
Compaction phases Compaction passes number
(kN)
Pre-compaction Compaction load gradually increased from 1 to 9 kN in increments of 2 kN every two
passes (i.e. one cycle)
Compaction 10 6
14 6
18 6
20 6
25 6
30 20
Mass Mass
Shaking Mass under Total
under under
Slab ID time wheelpath mass Graph of results
left side right side
(minutes) (kg) (kg)
(kg) (kg)
5555 2 0.668 0.554 0.57 1.792
4 0.216 0.382 0.206 0.804 Slab 5555 (14 dyas, 1% GP, Hornfells)
6 0.168 0.382 0.112 0.662 6000
8 0.412 0.618 0.056 1.086
10 0.410 0.118 0.034 0.562
5000
15 0.380 0.314 0.024 0.718
Total 2.254 2.368 1.002 5.624
1000
0
0 5 10 15 20
Shaking Time (Minutes)
Mass Mass
Shaking Mass under Total
under under
Slab ID time wheelpath mass Graph of results
left side right side
(minutes) (kg) (kg)
(kg) (kg)
5568 2 0.422 1.06 0.526 2.008
4 0.18 0.418 0.226 0.824 Slab 5568 (14 days, 1% GP, Hornfells)
6 0.086 0.41 0.1 0.596 5000
8 0.052 0.248 0.032 0.332
4500
10 0.058 0.276 0.036 0.37
15 0.094 0.426 0.078 0.598
4000
Total 0.892 2.838 0.998 4.728
3500
1000
500
0
0 5 10 15 20
Shaking Time (Minutes)
Mass Mass
Shaking Mass under Total
under under
Slab ID time wheelpath mass Graph of results
left side right side
(minutes) (kg) (kg)
(kg) (kg)
5688 2 2.844 3.840 6.100 12.784
4 1.946 0.988 3.442 6.376 Slab 5688 (28 days, 1% GB, Hornfells)
30000
6 1.590 0.926 1.402 3.918
8 0.718 0.436 0.332 1.486
10 1.078 0.638 0.136 1.852
15 1.218 0.23 0.282 1.730 25000
20000
5000
0
0 5 10 15 20
Shaking Time (Minutes)
Mass Mass
Shaking Mass under Total
under under
Slab ID time wheelpath mass Graph of results
left side right side
(minutes) (kg) (kg)
(kg) (kg)
5694* 2 0.338 0.728 0.240 1.306
4 0.030 0.078 0.030 0.138 Slab 5694 (14 days, 1.5% GP, Hornfells)
6 0.026 0.120 0.016 0.162 2000
8 0.034 0.080 0.016 0.130
10 0.020 0.024 0.004 0.048 1800
1400
400
200
0
0 5 10 15 20
Shaking Time (Minutes)
Mass Mass
Shaking Mass under Total
under under
Slab ID time wheelpath mass Graph of results
left side right side
(minutes) (kg) (kg)
(kg) (kg)
5922 2 0.022 0.020 0.032 0.074
4 0.004 0.002 0.004 0.010 Slab 5922 (1 day, 2% GB, Barratta)
6 0.002 0.002 0.002 0.006 140
8 0.002 0.002 0.006 0.010
10 0.002 0.002 0.008 0.012
15 0.002 0.002 0.006 0.010 120
Total 0.034 0.03 0.058 0.122
100
Centre (Under
Wheel Path)
60 Right of Wheel
Path
Sum of All Sections
40
20
0
0 5 10 15 20
Shaking Time (Minutes)
Mass Mass
Shaking Mass under Total
under under
Slab ID time wheelpath mass Graph of results
left side right side
(minutes) (kg) (kg)
(kg) (kg)
6012 2 0.034 0.026 0.040 0.100
4 0.004 0.002 0.002 0.008 Slab 6012 (1 day, 2% GB, Barratta)
6 0.030 0 0.002 0.032 180
8 0.002 0 0.002 0.004
10 0 0 0 0 160
15 0.004 0.002 0.004 0.01
Total 0.074 0.03 0.05 0.154
140
120
40
20
0
0 5 10 15 20
Shaking Time (Minutes)
Mass Mass
Shaking Mass under Total
under under
Slab ID time wheelpath mass Graph of results
left side right side
(minutes) (kg) (kg)
(kg) (kg)
5998 2 0.010 0.016 0.022 0.048
4 0.002 0.004 0.010 0.016 Slab 5998 (28 days, 2% GB, Barratta)
6 0.002 0.004 0.002 0.008 80
8 0 0 0 0
10 0 0 0 0
70
15 0 0 0 0
Total 0.014 0.024 0.034 0.072
60
20
10
0
0 5 10 15 20
Shaking Time (Minutes)
Mass Mass
Shaking Mass under Total
under under
Slab ID time wheelpath mass Graph of results
left side right side
(minutes) (kg) (kg)
(kg) (kg)
6028 2 0.098 3.618 0.072 3.788
4 0.062 0.540 0.010 0.612 Slab 6028 (28 days, 2% GB, Barratta)
6 0.064 0.404 0.026 0.494 7000
8 0.062 0.266 0.032 0.36
10 0.012 0.158 0.064 0.234
15 0.054 0.306 0.068 0.428 6000
Total 0.352 5.292 0.272 5.916
5000
1000
0
0 5 10 15 20
Shaking Time (Minutes)
Mass Mass
Shaking Mass under Total
under under
Slab ID time wheelpath mass Graph of results
left side right side
(minutes) (kg) (kg)
(kg) (kg)
5945 2 0.048 0.036 0.016 0.100
4 0.014 0.004 0.004 0.022 Slab 5945 (90 days, 2% GB, Barratta)
6 0.004 0.004 0.002 0.01 200
8 0.010 0.002 0.006 0.018
10 0.002 0.002 0.004 0.008 180
15 0.008 0.002 0.004 0.014
Total 0.086 0.05 0.036 0.172 160
140
40
20
0
0 5 10 15 20
Shaking Time (Minutes)
Mass Mass
Shaking Mass under Total
under under
Slab ID time wheelpath mass Graph of results
left side right side
(minutes) (kg) (kg)
(kg) (kg)
5951 2 0.218 1.218 0.262 1.698
4 0.014 0.092 0.032 0.138 Slab 5951 (90 days, 2% GB, Barratta)
6 0.002 0.030 0.028 0.060 3000
8 0.008 0.296 0.012 0.316
10 0.002 0.104 0.008 0.114
15 0.004 0.305 0.015 0.324 2500
Total 0.248 2.045 0.357 2.65
2000
1000
Sum of All Sections
500
0
0 5 10 15 20
Shaking Time (Minutes)
Mass Mass
Shaking Mass under Total
under under
Slab ID time wheelpath mass Graph of results
left side right side
(minutes) (kg) (kg)
(kg) (kg)
5541* 2 0.008 0.002 0.018 0.028
4 0.018 0 0.006 0.024 Slab 5541 (14 days, 3% GP, Hornfells)
6 0.010 0.002 0.008 0.020 140
8 0.010 0 0 0.010
10 0.008 0 0.002 0.010
15 0.028 0.002 0.008 0.038 120
Total 0.082 0.006 0.042 0.130
100
20
0
0 5 10 15 20
Shaking Time (Minutes)
Mass Mass
Shaking Mass under Total
under under
Slab ID time wheelpath mass Graph of results
left side right side
(minutes) (kg) (kg)
(kg) (kg)
5928 2 0.018 0.016 0.018 0.052
4 0 0 0.002 0.002 Slab 5928 (1 day, 4% GB, Barratta)
6 0.002 0.002 0.002 0.006 70
8 0 0 0 0
10 0 0 0 0
15 0 0 0.002 0.002 60
50
10
0
0 5 10 15 20
Shaking Time (Minutes)
Mass Mass
Shaking Mass under Total
under under
Slab ID time wheelpath mass Graph of results
left side right side
(minutes) (kg) (kg)
(kg) (kg)
6095 2 0.024 0.114 0.046 0.184
4 0.010 0.01 0.004 0.024 Slab 6095 (28 days, 4% GB, Barratta)
6 0.006 0.004 0.004 0.014 300
8 0.004 0.004 0.008 0.016
10 0.002 0.002 0.002 0.006
15 0.004 0.022 0.002 0.028 250
Total 0.050 0.156 0.066 0.272
200
100
Sum of All Sections
50
0
0 5 10 15 20
Shaking Time (Minutes)
*These specimens had a slurry layer applied to their surface before trafficking in the XL-WT device.