LAPORAN HARIAN GEOLOGI

Tanggal : Dec, 2nd 2020 Distribusi : Imam Arif, Basuki DP


Pelaporan : Dec, 3rd 2020 # lembar : 3 Lembar
Proyek : Sindue Gold Mine Kode Proyek : -
Blok : - Dibuat oleh : Rully Aditya Syauzie

DETAIL AKTIVITAS LAPANGAN RENCANA HARI BERIKUTNYA


NO. KEGIATAN MULAI SELESAI TOTAL DESKRIPSI DESKRIPSI
1 Diskusi rencana kerja 10:00 16:00 06:00 Diskusi metode sampling BLEG dinding sungai Kavaya Pengecekan dinding-dinding singkapan di Sungai Kavaya

2 Analisa Geologi 09:00 19:00 10:00 Pembuatan analisa komplek endapan sedimen sungai Kavaya pemetaan detail Sungai Kavaya

3 Database dan Laporan 09:00 17:00 08:00 Pembuatan laporan harian tanggal 2 Desember 2020, pembuatan peta analisa geologi, Pembuatan laporan harian, melanjutkan pembuatan peta analisa
Pembuatan rencana area produksi placer sungai (lebar bukaan 50m), Pembuatan peta geologi
rencana geomagnetik Blok Kavaya

MASALAH LAINNYA (JIKA ADA) :


- Hujan Lebat 08:00 - 11:00
-
-

SNAPSHOT KEGIATAN LAPANGAN


SNAPSHOT PROYEK
Waktu Kegiatan : 10:00 Hours Total Sampel : 0
Mobilisasi : 0 Hours SS : 0
BLEG : 0
Rock Chip : 0
Float : 0
Petrografi : 0
Rock Grab : 0
Rock Channel : 0 Dibuat oleh Diketahui oleh
Mineralografi :
XRF :

Rully Imam Arif Basuki D.P.


Sr. Geologist Principal Geologist General Manager
GEOLOGICAL DAILY REPORT
Date : Dec, 2nd 2020 Distribution : Imam Arif, Basuki DP
Report as of : Dec, 3rd 2020 Pages : 3 Pages
Project : Sindue Gold Mine Project Code : -
Block : - Prepared By : Rully Aditya Syauzie

DETAILS FIELD ACTIVITIES PLANNING FOR NEXT DAY


NO. TASK START END HOURS DESCRIPTION DESCRIPTION
1 Work Plan Discussion 10:00 16:00 06:00 BLEG sampling discussion in Kavaya river wall Outcrop checking at Kavaya River

2 Geological Analysis 09:00 19:00 10:00 Sample sediment channel workplan at Kavaya Block Detail geological mapping at Kavaya River

3 Report and Database 09:00 17:00 08:00 Daily report December 01 2020, creating geological analysis map and sediment channel Daily report, continue create geological analysis map
sampling plan map

OTHER PROBLEMS (IF ANY) :


- Heavy rain (08:00 - 11:00)
-
-

FIELD ACTIVITY SNAPSHOT


PROJECT SNAPSHOT
Activities Time : 10:00 Hours Total Sample : 0
Mobilization : 0 Hours SS : 0
BLEG : 0
Rock Chip : 0
Float : 0
Petrografi : 0
Rock Grab : 0
Rock Channel : 0 Prepared by Acknowledged by
Mineralografi :
XRF :

Rully Imam Arif Basuki D.P.


Sr. Geologist Principal Geologist General Manager