Jiro Torninaga
Country Director Indonesia Resident Mission
Asian Development Bank (ADB)
The Plaza Office Tower, 11th Tower
JI. M.H Thamrin Kav.28-30, Jakarta- 10350, Indonesia
Regarding the Request for Mission ConcmTence on Flood Management in Selected River Basins
(FMSRB) Sector Project, ADB Loan No. 3440 - INO, based on your letter dated 30 November
2021, Ref. No. 054/L3440/FMSRB/2021, we would like to suggest the proposed mission schedule
on 13-27 September 2022 with tentative schedule attached within this letter. It shall be noted that
each meeting will be held as hybrid meeting (offline and online via zoom), with exception on field
visit. This mission will discuss with the government on the project progress in the 2021 and 2022
work plans, and review the follow-up on the action plan from the previous mission, safeguards
compliance, gender action plan implementation, and procurement progress.
.
,,_�
Ir. Bob Arth:ur,Lombogia,M.Si
NIP 196609111997031006 1
I
l
C.C - Director General of Water Resources, Ministry of Public Works and Housing (MPWH);
- Director of Water Resources and Irrigation Bappenas
- Director of System and Strategy of Water Resources Management DGWR MPWH
- Director of Synchronization of Regional Government Affairs I, DGRD MOHA;
- Director of Land Expansion and Protection, DGAIF MOA;
- Head of Balai Besar Wilayah Sungai Cidurian-Ciujung-Cidanau, DGWR, MPWH;
- Head of Balai Besar Wilayah Sungai Maluku, DGWR, MPWH.
Attachment 1
Date and Time Activity Institution-in- Propose Agenda Participants Location/ Zoom
Charge Link
13 Sep (Tue)
10.00–12.00 WIB Kick off meeting BAPPENAS, CS04 Review proposed scope and agenda of the mission Bappenas, CPMU, MOA, Bappenas,
Review previous Mission (April 21) mission action plan MOHA, BBWS 3 Cis, BWSM, Meeting room
status CS01, CS02,CS04, CS05, DH-3 (?)
CS06, ADB Mission team
14.00 WIB – end Design, Supervision, and MPWH, CS01, Review progress of subprojects preparation (DED,IEE, CPMU, CS01 (Central and DRC, Batu Tegi
Project management CS02 SSR), and Construction supervision (Physics, EMP/ regional), CS02, CS04, CS05, (?) Meeting room
monitoring CEMP) CS06, ADB Mission team
Reporting requirements (SSMR, ESMR)
Disbursement and financial management
Geospatial project performance monitoring system
14Sep (Wed)
10.00–12.00 WIB MOA Land management and MOA, Banten Review annual work plan, sub projects preparation, budget Bappenas, CPMU, DJPK, DGAIF, meeting
on-granting; governments, allocation, procurement plan. Discuss MOA land MOA, CS05, CS02,CS04, ADB room Building-D
Procurement meeting CS05 management and progress of gender action plans. Project Mission team; DPIUs and Zoom link
Output, O&M plan, and PAM updating,
14.00 WIB -end MOHA Institutional MOHA, Ambon- Review annual work plan, sub projects preparation, budget Bappenas, CPMU, DJPK, DSORGA-I
strengthening, FRMP Maluku, CS06 allocation, procurement plan. Discuss MOHA landslide MOHA, CS06, CS01, meeting room
Procurement meeting management and progress of gender action plans. Project CS02,CS04, CS09 ADB and Zoom link
Output, O&M plan, and PAM updating, Mission team; DPIUs and
PPIUs
15 Sep (Thu)
08.00–10.00 WIB Trip to Serang
10.00-12.00 WIB Procurement meeting, MPWH, BBWSC3, (i) Procurement plan review and updating Action to CPMU, BBWSC3, Bappenas, BBWSC3,
FFEWS; CS01. expedite procurement FFEWS, CS01 (Central and Regional), Serang Meeting
Technical meeting: (ii) Subprojects preparation and timeline, CS02, CS04, CS06, CS09, room
- CW1, CW2, and CW3 (iii) Review work plan, LAR activities and the Budget and ADB Mission team.
implementations; allocation,
- Subprojects preparation (iv) AMDAL and IEE (EMP/CEMP) implementation for
CW1, CW2, and CW3, RKL/RPL to be submitted by
BBWSC3 to DLH;
(v) Problems solving.
Flood Risk Management Plan, MPWH, MOHA, Presentation of the flood risk management plan (FRMP) DRC, Bappenas, BBWSC3, BBWSC3,
14.00-15.00 WIB
TKPSDA, requesting to be transferred to Balai or TKPSDA to TKPSDA, MOHA, MOA, CS01 Serang Meeting
BAPPENAS, CS01, coordinate the preparation of FRMPs among the (Central and Regional), CS02, room
CS06 stakeholders and prepare recommendation for the official CS04, CS05, CS06, CS09,
endorsement by the Governor of Banten; Budget and ADB Mission team
allocation, and, Integration of gender issues
15.00 – 18:00 Field Visit to CW1 and CW3 BBWSC3, CS01, Location of variation order works, constructed bridge at Bappenas, CPMU, MOA, Ciujung Right
WIB Right bank PT. SACNA, and Blokang end, constructed CD/DI, ongoing works MOHA, BBWSC3, CS01, Bank upstream
PT.PP CS02,CS04, CS05, CS06, toll and Ciagel
CS09, ADB Mission team, village (PT
Contractor CW1 and CW3 Paperia)
Date and Time Activity Institution-in- Propose Agenda Participants Location/ Zoom
Charge Link
16 Sep (Fri)
09.00 WIB – Field Visit to CW2 and CW3 BBWSC3, CS01, Location of variation order works, constructed bridge at Bappenas, CPMU, MOA, Ciujung Left
11.30 Left bank PT.Basuki RP, Panosogan end, constructed CD/DI, ongoing works MOHA, BBWSC3, CS01, Bank upstream
PT.PP, and CS02,CS04, CS05, CS06, toll to Kragilan
PT.SACNA CS09, ADB Mission team, (downstream
Contractor CW1, CW2, and ends)
CW3
11.30 - 14.00 WIB Pray and Lunch Time BBWSC3 – CS01
14:00 – 15:30 Technical meeting with Bappeda, MOHA, Review annual work plan, FRMP preparation, budget Bappenas, CPMU, MOA, Bappeda Serang
WIB Serang District government CS06, DPIU allocation, local government plans and integration, MOHA, CS01, CS02,CS04, District office
PWSP, BPBD, community-based activities Integration with regional CS05, CS06, CS09 ADB
Forestry, and plans, progress of gender action plans. Project Output. Mission team, DPIUs, BPKAD.
Agriculture, MOA, O&M plan
and CS05
15:30 – 17:30 Visit to on-granting activities MOA, CS05, DPIU Visit to constructed structures and conservation Bappenas, CPMU, MOA, Serang District
WIB under MOA and MOHA Agriculture; area in Serang District MOHA, CS01, CS02,CS04, Left Bank area.
CS05, CS06, ADB Mission
MOHA, CS06,
team, DPIUs, BPKAD
DPIU PWSP, and
Bappeda
17 Sep (Sat)
18 Sep (Sun)
19 Sep (Mon)
20 Sep (Tue)
15.00 WIT – end Field Visit to CW4A, CW4B, BWSM, CS01, PT. Monitoring on the implementation works. Bappenas, CPMU, MOHA, Petra, Rinjani, and
and proposed CW6A and Jaya Konstruksi BWSM, CS01, CS02, CS04, Wai Ruhu.
CW6B CS06, CS09, ADB Mission
team, Contractor CW4B.
23 Sep (Fri)
09.00 -12:00 WIT Technical Coordination Province Office, (i) Review Annual Work Plan and Disbursement Plan; Bappenas, CPMU, MOHA, Governor
Meeting with PPIUs and and (ii) FRMP preparation; BWSM, CS01, CS02, CS04, meeting room?
DPIUs and BWS Maluku CS06/DSORGA-I, (iii) Establishment of LAR committees and progress of CS06, CS09, ADB Mission DSORGA-I/CS06
BWSM, CS01 activities, team, PPIUs and DPIUs,
(iv) budget allocation and relocation site,
(v) livelihood social program, budget allocation, BPKAD.
(vi) cooperation agreements,
(vii) coordination with the waterfront improvement
program;
(viii) progress of gender action plans
(ix) Project Output and O&M plan
12:00 – 14.00 WIT BREAK
14:00 WIT - end Field visit to on-granting Province Office and Visit to constructed structures and conservation area in Bappenas, CPMU, MOHA, PPIU/DPIU/
activities Ambon City, CS06, Ambon City BWSM, CS01, CS02, CS04, CS06-Facilitators
CS06, CS09, ADB Mission
team, PPIUs and DPIUs..
24 Sep (Sat) Return to Jakarta
25 Sep (Sun)
26 Sep (Mon) ADB MOU preparation meeting ADB ADB mission team ADB office
27 Sep (Tue) Wrap-up meeting BAPPENAS Confirm findings and agreement of the mission