You are on page 1of 1



 
Name : Rizal Hidayatullah Time : 08.00 AM -05.00 PM  
Position : Inspector Location : PT. Robutech  
Mounth : January Year : 2021  
NO DATE ACTIVITY
 Hardness test at U-bolt hanger of outlet header
Monday final super heater
1
11/01/2021  Hardness test at U-bolt hanger of outlet header
final re heater
 Borescope at inlet header of economizer
Tuesday
2
12/01/2021

 Borescope at Final Super Heater (P25T9, P26T7,


Wednesday P26T9) and Final Re Heater (P9T24, P37T24, P46T24)
3
13/01/2021

 Borescope at Final Super Heater P21T6


Thursday
4
14/01/2021

 Hardness Test at lower waterwall tube


Friday
5
15/01/2021

 Hardness Test at lower waterwall tube


Saturday
6
16/01/2021

 Hardness test at inlet economizer header and outlet


economizer header
Sunday
7  Hardness test at tube to inlet header of economizer
17/01/2021
 Hardness test at tube to outlet header of
economizer