CHAPTER ONE
Initially the total power of the company was 350 and the work force is relatively 90% young
female with basic knowledge skill is to write and read, to operate and maintain the installed
machine and equipment. The company starts its production process by giving training in one
training room (block 9) and the training length period of time takes maximum 21 days and
minimum 16 days. Since the workers were finished their training program, they will directly
transfer to the production line.
Jay jay textile company
Vision
To be the most trusted baby wear manufacturer in the world.
Mission
To be best top 3 supplier to the buyers
To be best work place for employers
To be the most reliable baby wear manufacturing quality and delivery
To have good learning system by continually eliminate waste.
Goal
Turn over percent below 6%
Achieve 100% delivery on time
Maintain 0% final AQL failure
To maintain budgeted cost per min
Jay jay textile company
Organizational Structure
General
Manager
Deputy
General
Manager
Operational
manager
E Preparing short term and long term plan of HR and submitted to General Manager
(Operational Manager) for approval.
E Studying the need of different departments for human resource
E Selecting workers through identifying their capabilities based on their identity card, Birth
certificate and Exam (for direct workers).
E Providing awareness for workers about The way how to inform their grievance, Safety
procedures, Leave procedures, Termination and resignation procedure.
Jay jay textile company
Types of machines
Over lock
Flat lock
Single needle chain stich
Double needle chain stich
Double needle lock stich
Button
Heat seal
bar tuck
button sower
button hole
single need side cutter m/c
Types of over lock machine
1. Back lack: used for side seam
2. 4 tread over lock: used for sleeve attach, 1st and 2nd side seam.3tread over lock
for neck binding and shoulder attach.
3. Cylinder bed overlock: used for elastic attach
The difference with 4 tread over lock is this one can lock the stich after
finishing and 4 thread overlock is under bed.
Fold type convertible machine:used for binding bottom and neck binding.
Used additional garment
Cylindered flat lock m/c: used for leg hem which doesn’t need tuck.
Jay jay textile company
Heat seal
We use heat seal for two purpose for tagless label attach and fussing the only
difference is temperature, pressure and time. We use fussing when garment
have embroidery, on the inside of the garment there are treads which is
uncomfortable so to remove that we use net then fuse on the garment.
Single needle lock stich: in jay jay we are using for tucking but with this m/c
we can complete one garment.
Double needle chain stich : used for neck rib binding.
Double needle lock stich: used for denim pocket lay out. In this machine we
can lock the needle during sewing.
Single needle side cutter: this machine can stich and cut at the same time.
Button
Ykk scovila
Size of button
GCI: 14L
Carter and H&M: 15L
Bar tuck; used for tucking on the inseam crotch
Button hole: used for insertion of button
Button sower: used for extra attachment like adidas, Nike.
Types of Needle
Jay jay textile company
Size of needle
75, 70,65,60---------European
Needle prossiger
1. First thing we do when needle breaks we stop the machine
2. Collecting the garment before and after stich.
3. Then taking the garment with plastic bag in AQL
4. AQL there is metal detector machine during checking when we find the
needle we can get the replacement of the needle but if there is no needle found
in the garment we must return to the m/c
5. Then we search the needle by using ground magnet for 1-1:30hr still if we
can’t find the needle
6. We must go to the needle center and get the investigation form and
operational manager, quality manager…….. Will sign on it and we can get the
replace needle then call the mechanic then fix the machine.
Needle type
Jay jay textile company
DBx1……………………..single needle
DCx27…………………….over lock
UYx128…………………..flat lock
UYx163……………………Pico
DPxk5…………………….embroidery
DBx5………………………bar tuck
Dpx17……………………button
Operation for TCP (T-shirt)
Heat seal…………… sleeve hem………shoulder attach………neck
rib make…….neck rib attach……….1st side seam……….2nd side
seam……….bottom hem……..tuck….ironing ……cheaking ……
packing.
Types of foot
Jay jay textile company
Single
Narrow foot
-normal: for medium fabric
-heavy: for heavy duty
Zipper foot
-left: for zip outline
-right: for zip attach
Gauge foot(CR&CL): for special outline like shoulder(one side sewing the
garment the other press)
Gauge foot: for special outline
Heming fet:one foot is bigger
Teflon: a foot with plastic
Double needle chain stich foot;have gauge and the needle hole is different
Uptail feet with small hole:for less gsm fabrics
Flat lock
For bottom hem: have gauge
Sleeve hem: have hole
For neck bottom binding: flat without gauge.
Planning
Capacity offering
Jay jay textile company
until mercendizingfulfill all the accessarys @ the same time plannining will do
–what type of m/c is needed
-how many machine is needed
-How many day we needed to finish the order
Job creation
Linking the job
Start production
Follow production
Fig 3 planning flow chart
Types of mercendizing
1. Market: head of mercendizer which have directly connection with
the buyer and doing the costing also.
2. Supply chain: have connection with supplier
Jay jay textile company
Po received
Sample making
Po released to supplier
pp meeting
Production follow
Production process
Order receive
Jay jay textile company
Mockup sample
Allocating operators
Fabric in put
Fabric check
Follow production
Fig4 production flow chart
Fabric inspection
Select the fabric roll based on lot no, rollno, qty &
fabric type & width
Calculate the point for each defect Inform to QA and tpd manger
Pass fail
Pass 20point send the roll to the 20 reject roll and store in
same location rejected area
Accessory store
Receiving package in
receiving area
Racking based on
Item wise
Color wise
Size wise
Release to issue
Dc (delivery channel)
The Single
Sorting and
fabric which is
Cut the spread Numbering the bundling
marker placed
fabric cutted pieces according to
at the top of the
size
spread
Issuing the
pieces to
sewing
department
Jay jay textile company
IE (wok study)
Responsibility of iE
Lay out making
Balancing
Improvement(multi skill) of operators
Increase productivity by reducing man power
Increase salary
Forecast
Prepare operation break down(what kind of operation is needed)
Kayzen system
IE
SMV=45+ (45*10%)
HOURLY TARGET= time (3600sec)
SMV
Individual efficiency =number of pies*SMV
Time
Line efficiency=number of pies*SMV
Number of carder*time
Or we can use this formula eff=SAH
TIME*SMV
n Nam operatio Sm 100 1 2 3 4 5 Averag Allowanc No Efficienc
o e n v %targe e e of y
t 12% pcs
1 Heat seal 0.20 300 1 1 8 1 1 10 11 32 109%
0 1 0 1 7
2 Shoulder 0.30 200 2 2 2 2 2 24.2 27 13 66.5%
attach 2 8 4 3 4 3
3 Neck rib 0.20 300 2 2 2 2 2 23.6 26 13 46%
make 3 2 4 5 4 8
4 Neck 0.45 133 4 3 3 3 3 34.6 39 92 69%
attach 1 1 2 5 4
5 Neck 0.35 171 2 2 2 2 2 22.6 25 14 84%
binding 0 0 2 3 8 4
6 Sleeve 0.55 109 2 2 2 2 2 25.2 28 12 117%
attach 3 4 7 8 4 8
7 1st side 0.30 200 1 2 1 2 2 20.2 23 15 96%
seam 9 1 7 3 1 6
8 2nd side 0.35 171 2 2 2 2 2 24.6 27 13 77%
seam 6 3 4 2 8 3
9 Bottom 0.50 120 2 3 3 2 3 30.2 32 11 93%
hem 6 0 6 6 3 2
10 tuck 0.20 300 2 2 2 2 2 24 27 13 77%
3 2 3 5 7 3
11 ironing 0.45 133 3 3 3 2 3 30.3 34 10 78%
2 0 1 9 1 5
12 packing 0.60 100 1 1 1 1 1 11 12 30 300%
2 0 0 1 2 0
Jay jay textile company
350
250
200
156
150 133 133 133
128
112
105
100
50
0
Category 1 Category
Series 1 2
Series 2 Category
Series 3 3 Category 4
Bottle neck area is 92 so in this time we can balance one girl which
have high capacity and increase the capacity to 120 and improve
there effecinecy.
Type of production system
Bundle system: work by bundle like when sewing 12 bundle then pass 12
bundle to the next operation.
Pcs movement system: sewing one pcs then after pass the pcs to the next
operation.
Section wise: after sewing three pcs then pass.
Jay jay textile company
The main thing iE do is less man power with the same target
No of carder Pcs 8hr efficiency
13 200 1600 85%
12 200 1600 92%
11 200 1600 100%
Operator evaluation
Proceger
1. Every 3 month once, they eligible for evaluation
2. three month absenteeism percentage should be less than 3%this is done by
hr department.
Operator grading
a) 1800 birr
b) 1650 100 birr in every level
c) 1550
d) 1450
e) 1350
Ap3-1350
Ap2-1270 without evaluation
Ap1-1200
When they finish the 3 month evaluation in E grade level after evaluation if
they pass they will move to the next level which is d grade. If they fail after
one month they will evaluate again.
A, B, C [skill operators]
D, E [semi skill operator]
Grade minimum requirement
A……………………..2/4
B……………………..3/5
C…………………….2/4
Jay jay textile company
D……………………..2/3
Efficiency=achieve target
Set target
OB (operation break down): is prepared in sirilanka
Based on buyer the construction vary
Based on construction smv vary
Ob consists of
What kind of m/c is needed
Time
m/c operation
smv
Incentive calculation
to get more production the company gives incentive to the worker
incentive is not your right
incentive gives for motivation in order to increase production
For new style
1st three days factory gives efficiency
After three days incentive gives based on their efficiency
Types of incentive
Individual
Team
Factory
The main advantageous is team incentive because line production
will increase team work will develop.
Lay out
1. Line with center table and operates facing same direction
2. Line with center table and operates facing opposite direction
3. Side by side
In jay jay u-shape lay out is used
Operation class code
1. Ol-over lock
2. Sn-single needle
3. Dn- double needle
4. Fl- flat lock
5. Fs-flat seam
6. Pc- pico
7. Sb-snap button
8. Hs-heat seal
9. Ir-iron
Jay jay textile company
10.Btk-bar tack
11.Sp-spicial machine
Basic operation
1) Sn- tack label
2) Sn-sleeve tack
3) sn-neck tack
4) Sn-button tack
5) Sn-foot tack
6) Sn-tack operation others
7) sn-shoulder tack
8) ol-sleeve rib tack
9) ol-croch attach
10) ol-top foot attach
11) ol-front and back rise
12) ol-ring attach
13) fl-sleeve binding
14) pc-picco stich
15) hs-heat seal operation
16) rc-rib cutting
17) ir-gusset ironing and gusset with planket
18) sb-button attach single side
19) btk-bar tack
intermedet operation
1) SN-arm hole tack
2) SN-tab make
3) SN-attach label
4) SN-shoulder planket close
5) SN-sew dart(on rapil pant)
6) SN-tack bottom end(focling,planket)
7) SN-frill attach
8) SN-elastic attach
9) SN-gazering operation
10) DN-elastic out line
11) FL-sleeve hem
12) FL-front and back neck binding
13) FL-top stich
14) Ol-side seam
Jay jay textile company
Skill operation
1. SN-zipper attach
2. SN-front facing attaching
3. SN-pocket attach
4. DN-pocket attach
5. SN-collar attach
6. SN-tab attach
7. OL-foot attach
8. OL-sleeve attach
9. OL-sleeve attach with arm hole
10.OL-side in inseam
11.OL-cuff ataach
12.OL-rib attach
13.OL-elastic attach
14.FL-sew sleeve hem
15.FL-neck bindig
16.FL-sew binding body around
17.FL-neck binding
18.FL-bottom binding
19.FL-bottom hem
20.FL-wast elastic attach
21.FL-arm hole binding
22.FL-out line opertation
23.FL-waste band band attach
24.FL-elastic attach
25.FL-flat seam operation
26.SB-button attach gusse and shoulder shink planket
Jay jay textile company
Production process
Production process is converting raw material in to final finished goods.
Main department of the company others are supporting department.
6th sigma or 5m
Man power
Machine
Material
Method
Money
By using this 5m we can convert material into final goods
TPD
Accessory
planning store
FABRIC STORE
Production
line MENTENANCE
HR
FGS
MERCENDIZ
ING
Time management
Arranging thing to do some activity
Organizing and bujeting time with purpose of some activity this is a
key to increase our efficiency.
Time management
Task
To do
Priority
Project
plan
Achievement
Jay jay textile company
Recut
Before recut we need some rejection…..un repairable garment
Recut slip fill by quality supervisor and contains
-item number
-line number
-style number
-time
-damage part
-quantity
-size
-fabric
-reason code
Before last hour the slip must fill.
Writing the reject in the packing book need to ask excess
fabric >2% in this process they need a db report.
2%QTY=Order QTY*2%
Assume order quantity is 1000
1000*0.02
20pcs
FABRIC2%=2%QUANTITY*CONSUMPTION FOR 1GMT
=20*0.25
= 9.4M
Calculating missing
For e.g balance =160
In line =10pcs
Reject avaliable Missing pannal Recut
Full 5 10 45 0
Jay jay textile company
Back 40 25 125 80
Front 35 45 105 60
Sleeve 60/2 120 180 90
Reconcelltion
This report is used to know how much balance we have
Order quantity=1000pcs
FGS send=815
Balance =125pcs
Result =full 70
=back 55
Recut%=reject *100%
Order quantity
During reconciliation we consider 6 sleeve as one garment and 2
panel as one garment.
Back panel 30 before heat seal
Back 55/2=27
Recut full garment =70+27=97pcs
Fabric 2%=97*0.45
=44meter
Difference 44m-9.4=35m (excess) more than 2%
For example if the balance is 130 and when we see the rejection it is
125 and the 5 is missing.
Jay jay textile company
reject requirement
full 60 0
back 10 10 front
front 40 40 back
sleeve 15 115 sleeve
125
Accessary reconciliation
Reject In hand required balance
Heat seal 5 14 19 5
label 0 19 19 0
Price ticket 0 19 19 0
Production plan
Process
1. Release 1st po
2. Prepare plan then divide to line per pcs
During line distribution –how much days
-shipment plan
3. Make shipment plan and know when shipment is going
planning department is prepared 6 month then dived in to
month
Monthly: -determine material required (machine)
Jay jay textile company