Professional Documents
Culture Documents
Yoshio Masuda
RYOKUSEISHA CORPORATION
(MEMBER CRUST STUDY COMMIlTEE, JAPAN RESOURCES ASSOCIATION
ASAHI BDG., 5-29-19,TOKYO, JAPAN)
Michael J. Cruickshank
UNIVERSITY OF HAWAII
MARINE MINERALS TECHNOLOGY CENTER
HONOLULU, HI 96813
James A. Abernathy
CONSULTANT
REPUBLIC OF MARSHALL ISLANDS
Ronald Winston
DEVELOPER ON BEHALF OF
REPUBLIC OF MARSHALL ISLANDS
NEW YDRK, NY
Abstract
Adaption of an existing cargo vessel of around 15,000 tons. MnO + H,S04 -,MnSO, + H,O
(b) Mining rate The net leaching reaction is,
When bucket volume is 1.785 cubic meter as shown in Figure MnO, + H,O, + H,SO, --. MnSO, + HzO + 0,
4, bucket interval 50 m, rope speed 0.8 m/s with time on the bottom
of 30 seconds for each bucket, production rate should be 400 tlday. and without the need of heating, CO,Ni and Mn are dissolved about
96%.
(c) Rope tension and traction power
Most CLB sea trials have used the re-attachable system, but
recent developments indicate that a non detachable system using a ball
roller parallel drive machine instead of a multi-wheeled traction
device may be safer and less costly.
Mining Cost
Using a 15,O00 ton mining ship with a 400 t/d mining rate,
each production cycle will consist of 26 days of mining operation, 4
days in harbor, totalling 30 days. Figure 5: Ball roller parallel drive traction machine
1476
(b) Iron removal 1.000.000
m i l l i o n Yer
Fe is eliminated from leach solution in 1 hour by adding milk
of lime
1477
ExDense Der vear
Mining cost ________________ 1,380 million yen
Processing cost ------------- 4,480 million yen
DeveloDment Plan
The small scale CLB mining test and processing tests will
each cost about 500 million yen for a total of 100 million yen.
This is about one tenth of the cost of a commercial system to mine
and process 400 t/d. Such a pilot test at 1/10 scale will save
considerably on development costs and allow for commercial
operations to be planned and started with much reduced risk.
Reference8
1478