Electrical Work: Work Description Duration Required Tech. Required Helper Required

You might also like

You are on page 1of 2

Electrical Work

Work Description Duration Required Tech. Required Helper Required


Installation including alignment,
fixing, levelling, cabling 6 days / 1 switchboard 2 2
termination and assembly of
switchboards

Installation including alignment,


fixing, levelling, cabling 6 days / 1 transformer 4 3
termination and assembly of
transformers

Installation including alignment,


fixing, levelling, cabling 4 days / 1 distribution panel 2 2
termination and assembly of
distribution paneles

Installation including alignment,


fixing, levelling, cabling
termination and assembly of 5 days / 1 panel 2 2
Electrical power and control
panels for the packaged
equipment

Cable termination of electrical


EQUIPMENT including, but not
limited to, all the above 3 days / 1 item 2 2
items,electrical bulk materials
and the electrical EQUIPMENT

Installation of earthing system 1 day / 20 meter 2 3


Installation of electrical cable
ladders, trays, accessories and 1 day / 10 meter 1 2
relevant supports.
Installation of electrical conduits,
1 day / 11 meter 1 2
fitting and accessories
Pulling of underground electrical
1 day / 4 meter 1 6
cables
Laying and fixing above ground
1 day / 5 meter 1 6
electrical cables
Bonding, installation of earthing
and lighting protection materials
1 day / 20 protection materials 2 2
and related connections to
structures and EQUIPMENT

Installation of internal & external


lighting systems materials
including, but not be limited to
2 day / 1 lighting system 2 3
fixtures, junction boxes, local
commands. Roadway lighting is
deemed to be included
Installation of all cable
trays/racks/ladders, including
ancillaries, painted structural 1 day / 10 meter 2 3
supports and
the like