Organisation Name: Cam Hammond Floors Pty Ltd Contact Name: Tim Hammond
ACN/ABN 609 343 535 / 43 609 343 535 Contact Position: Director
Address: 4/84 Voltri Street, Mentone Contract Phone No: (03) 9584 1833
Project:
Victorian Specialist Centre Head Contractor: Hagta Group
TBA No. of
Expected Start Date: Duration of Work: TBA Max: TBA Min: 1
employees to
be used:
Competencies & Licences: Construction Induction Card, Site Induction, SWMS Toolbox Talk
PPE Required:
Equipment Used: N/A
2. Substitution
This is the next most effective way to manage a
risk. For example – using a less harmful
chemical
3. Isolation / Engineering
Isolation may include limiting how many
people are exposed to a hazard. For example,
using noisy equipment at night time when less
people are present
4. Administrative
Examples of this kind of control include
training and instruction
5. PPE
PPE is the least effective of all the controls and
should be seen as the last line of defense
Potential death, permanent disability or major
H (1)
structural failure/damage. Off-site environmental H (1)
(High level of 1 1 2
discharge/release not contained and significant long- (High)
harm)
term environmental harm.
Potential temporary disability or minor structural
M (2) failure/damage.
M (2)
(Medium level On-site environmental discharge/release contained, 1 2 3
(Medium)
of harm) minor remediation required, short-term
environmental harm.
Incident that has the potential to cause persons to
L (3)
require first aid.
(Low level of L (3)
On-site environmental discharge/release immediately 2 3 3
(Low)
harm) contained minor level clean up with no short-term
environmental harm.
Level Likelihood / Probability
Likely Could happen frequently
Moderate Could happen occasionally
Unlikely May occur only in exceptional circumstances
Minimize contact.
Dust/grout/adhesive
residue left behind causing Ensure all surfaces are swept and cleaned as
other worker/public necessary after works have finished.
Supervisor
exposure 2 & 3
All cleaning equipment and personal protective
equipment used should be discarded in site Installer
bins or thoroughly cleaned after the job.
Waste disposal resulting in Excess chemicals are sealed & removed from Supervisor
contact with chemicals 2 site. Excess building materials (non-chemicals) & 3
causing burns disposed of in site bin. Installer
Site specific hazards
Additional risks encountered during the job that have not been covered in the steps above will be discussed and the steps, hazards, risk ratings, controls and responsibility
documented in the space provided below
Risk Name of Persons Residual
Item Job Step Hazard Controls
Class/Ranking responsible for work Risk Score
Risk Class/ Name of Persons Residual
Item Job Steps Hazard/Risk Controls
Ranking responsible for work Risk Score
This SWMS has been developed through consultation with our employees and has been read, understood and signed by all employees undertaking the works
Review No 01 02 03 04 05 06 07 08 09
Initial: