Creating the Project Charter

Final Exam

1. Which of the following is the process of developing a document that


formally authorizes a project or a phase to begin?
A) Develop the business case
B) Develop project charter
C) Develop the statement of work (SOW)
D) Develop the project management plan

2. When is the project authorized?

A) When the project charter is created


B) When the project manager is designated
C) When the project charter is signed off
D) When the project management plan is completed

3. Which of the following is a document that articulates the reasoning for


initiating a project or phase of a project?

A) Project statement of work


B) Business case
C) Project scope
D) Strategic goals and objectives

4. The business case will typically start off with which section?

A) Executive summary
B) Deliverables
C) Scope
D) Business Drivers

5. A __________ is defined as an evaluation and analysis of the potential


or merits of the proposed project based on investigation and research
in order to support the decision-making process.

A) Project statement of work


B) Feasibility study
C) Business case
D) Business proposal
6. What project selection method assigns a weighting for different criteria
and then rates the criteria for each project?

A) Rating model
B) Scoring model
C) Weighting model
D) Discounted cash flow model

7. Which section of the project charter must reiterate the business need
for the project?

A) Project purchase or justification


B) Project objectives
C) High level requirements
D) Assumptions and constraints

8. What is the last section of the project charter?

A) Project risks
B) Assigned roles and responsibilities
C) Signatures
D) Project approval requirements