Professional Documents
Culture Documents
SABP Q 015 Investigation Scope
SABP Q 015 Investigation Scope
Contents
1 Introduction ................................................................ 2
2 References ................................................................. 3
3 General Requirements of Geotechnical
Scope of Work ............................................................ 5
4 Geotechnical Investigations
at Various Project Phases .......................................... 7
5 Site Selection Geotechnical
Reconnaissance Investigations ................................. 9
6 Preliminary Geotechnical Investigations................... 11
7 Detailed Geotechnical Investigations ....................... 15
8 In-Situ Field Tests and Laboratory Tests
within All Investigation Phases ................................. 15
9 Monitoring or Verification Investigations ................... 19
Appendix 1 - Guideline for Borehole Density
and Depth…………………………………….. 20
1 Introduction
1.1 Purpose
1.2 Scope
The requirements in this Best Practice are applicable for Saudi Aramco
onshore/near shore process industry facilities and for Saudi Aramco-managed
non-industrial and government projects, including geotechnical investigations
conducted directly for design and/or construction Contractors.
1.3 Disclaimer
The material in this Best Practice document provides the most correct and
accurate guidelines available to Saudi Aramco which complies with
international industry practices related to the Scope of Work for the procurement
and execution of geotechnical investigations. This material is being provided
for the general guidance and benefit of Saudi Aramco engineers and engineers
working on Saudi Aramco projects. Use of the Best Practices in preparing
geotechnical investigation Scopes of Work for Saudi Aramco, however, does not
relieve the Contractor from his responsibility to verify the accuracy of any
information presented or from his contractual liability to provide safe and sound
designs that conform to Mandatory Saudi Aramco Engineering Requirements.
The use of the information or material contained herein is no guarantee that the
resulting product will satisfy the applicable requirements of any project. Saudi
Aramco assumes no responsibility or liability whatsoever for any reliance on the
information presented herein or for designs prepared by Designers in accordance
with the Best Practices. Use of the Best Practices by Designers is intended
solely for, and shall be strictly limited to, Saudi Aramco projects.
In the event of a conflict between this Best Practice and other Mandatory Saudi
Aramco Engineering Requirements, the Mandatory Saudi Aramco Engineering
Requirement shall govern.
2 References
This Best Practice is based on the latest edition of the references below, unless
otherwise noted. Short titles will be used herein when appropriate.
British Standards
BS5930:2010 Code of Practice for Site Investigations
B1377-9:1990 Test of Soils for Civil Engineering Purpose
Eurocode 7
BS EN 1997-2:2007 Eurocode 7, Geotechnical Design – Part 2: Ground
Investigation and Testing
Geotechnical investigations are mandatory except when all of the conditions indicated
in SAES-A-113, Paragraph 5.2 have been satisfied.
Geotechnical investigations are essential for all new onshore/near shore structures
(including, but not limited to, buildings, tanks, roads, tunnels, pipelines, process
facilities, pump stations, airports, marinas etc.) and significant earthworks. Structures
undergoing significant upgrades or load changes may also require a geotechnical
investigation.
Commentary Note:
The information described below shall form the basis for any geotechnical
Scope of Work document to be prepared. However, modifications may be
included for each specific project depending not only on the nature of structures
to be constructed, but also on the site and geologic conditions and the stage of
the project (Site Selection, DBSP, or Project Proposal).
Commentary Note
Satellite-based GPS units are based on UTM WG84 datum and must
be translated to (and from) International 1924 Ellipsoid, Ain (Ayn) Al
Abd 1970 datum. See SAES-A-100 Paragraph 8.2 and 8.3.
8. Proponent information.
Commentary Notes:
Some of the above information may not be available at the very early
stage of the project. However, providing detailed information to the
geotechnical contractor will result in more specific geotechnical
analysis and recommendations, possibly saving the project both
construction time and money. Previous geotechnical investigations
(Item #2 above) may be obtained from On-shore Engineering Group,
CSD.
The goals of all staged geotechnical investigations are, generally, summarized as;
2. Determine soil and rock parameters required for design. These parameters are to
be determined based on established procedures given in literature as well as on
relevant engineering judgement.
Commentary Note
A typical project lifecycle includes the site selection, planning, design and
construction phases, and geotechnical investigations may be required for any
and all of these stages. Geotechnical investigations are thus broadly classified
as follows and described in more detail in the following sections of this Best
Practice:
Deadline for
Project
Type of Investigation Project Phase Geotechnical Report
Type
Completion*
Reconnaissance investigation A, B FEL 1 - Business Case G1 of FEL1
Detailed Investigation Report A, B, C, C1 FEL3 - Project Proposal (PPA) 30% PPA of FEL3
* It shall be noted that the Report completion deadline is for final report completion and acceptance after review
cycles and not for initial report submission.
Source – Saudi Aramco Front End Loading (FEL) Manual (1 June 2014)
- Topographical maps;
- Geological maps and sections, including descriptions;
- Geological history of the area;
- Hydrological data;
- Historical information available;
- Aerial photos within different dates;
- Previous geotechnical investigations at the site and on adjacent/surrounding
locations.
A site reconnaissance walkover survey is essential during the early site selection
phase for identifying hazards, risks and situations where, for example, poor
soil/rock conditions, water bodies on surface, elevations changes, and/or
filling/cutting operations may be encountered. This information allows for
specific field investigations to be carried out in a cost effective way.
The number of above mentioned field tests is to be decided based upon the
results of the desk study, the size of the site to be considered, and structures to
be constructed.
They differ from the detailed structure-specific investigation mainly by the density of
the field exploration and thus costs are relatively small compared to the overall project
cost.
The findings of both the desk study surveys and the site reconnaissances/visits
should be taken into account when choosing the investigation methods to be
used as well as detecting the various field test points to be carried out within the
preliminary staged phase. Widely spaced exploratory holes including boreholes,
cone penetration tests, trial pits etc. as well as corresponding laboratory testing
are generally included within the preliminary geotechnical investigations.
The layout of the exploration points may be in a grid pattern with selected points
of exploration targeted at places representing possible variations in ground
conditions related to soil, rock and groundwater if the layout of the facility is not
known.
Commentary Note
Commentary Note
Generally 30m deep boreholes are required to determine the ASCE-7 Site
Class. However, 30m deep boreholes are not required when the mapped
maximum considered earthquake spectral response acceleration at a
short period, Ss, is less than or equal to 0.15 and the mapped maximum
considered earthquake spectral response acceleration at a period of 1
sec, S1, is less than or equal to 0.04.
- Recommendations of any additional studies to be performed for both
enumerating and mitigating the risks associated to the
geological/geotechnical hazards identified above (if any), and in turn,
evaluations of any possibility of high level modifications (e.g. location) to be
performed;
Appendix 1 provises guidelines on borehole test density and depths for site
investigation. It is to be noted that each site investigation is unique as it relates
to specific project needs, thus density/depth of preliminary investigation points
provided in Appendix 1 may differ due to project specific details and thus are
not standards or rules.
The findings of both the planning level and preliminary geotechnical investigations
should be considered when identifying the investigation methods and the various field
test points to be carried out within the detailed design phase. Modifications on
locations, sizes, and loads of the corresponding structures to be constructed representing
the actual /final design phase compared to the preliminary phase investigations shall
clearly identified.
Appendix 1 provises guidelines on borehole test density and depths for site
investigation. It is to be noted that each detailed geotechnical investigation is
site and structure-specific as it relates to specific project needs, thus
density/depth of investigation points provided in Appendix 1 may differ due to
project specific details and thus are not standards or rules.
8 In-Situ Field Tests and Laboratory Tests within all Investigation Phases
8.1 In-Situ Field Tests
In addition to the above in situ field tests, laboratory testing (e.g. classification,
compaction, strength, consolidation) on selected samples retrieved from the
boreholes - and any trial pits done - as necessary to determine relevant
engineering properties in relation to the proposed structures, shall be carried out
as part of the various investigation phases.
Saudi Aramco: Company General Use
Page 18 of 24
Document Responsibility: Geotechnical Standards Committee SABP-Q-015
Issue Date: 27 May 2018
Next Planned Update: TBD Scope of Work Guide for Geotechnical Investigations
The scopes of work for these investigations are unique to the specific project need and
as such are not further addressed in this Best Practice.
Revision Summary
27 May 2018 New Saudi Aramco Best Practice.
Appendix 1 -
Type of
Investigation Density Investigation Depth Investigation Density Investigation Depth
Structure/Activity
Page 21 of 24
Document Responsibility: Geotechnical Standards Committee SABP-Q-015
Issue Date: 30 May 2018
Next Planned Update: TBD Scope of Work Guide for Geotechnical Investigations
Large One Story Minimum depth of 15m or 4 times Minimum depth of 15m or 4
the expected isolated footing width times the expected isolated
Structures
or 2 times the expected mat width footing width or 2 times the
(Warehouses, Minimum1 boring per Minimum 1 boring per
whichever is more; in case of expected mat width whichever is
Commercial Centers, 1000sqm or less in size 300sqm
expected pile usage depth to be more; in case of expected pile
Manufacturing taken 10 times the pile diameter usage depth to be taken 10 times
Facilities) below pile tip the pile diameter below pile tip
Minimum depth of 20m or 4 times Minimum depth of 20m or 4
the expected isolated footing width times the expected isolated
or 2 times the expected mat width footing width or 2 times the
Stadiums/Sports Minimum 1 boring per Minimum 1 boring per
whichever is more; in case of expected mat width whichever is
Centers 1000sqm or less in size 300sqm of structure footprint
expected pile usage depth to be more; in case of expected pile
taken 10 times the pile diameter usage depth to be taken 10 times
below pile tip the pile diameter below pile tip
Minimum depth of 15m or 4 times Minimum depth of 15m or 4
the expected isolated footing width times the expected isolated
Transmission Towers, or 2 times the expected mat width footing width or 2 times the
Minimum 1 boring per Minimum 1 boring per
Electrical Substations, whichever is more; in case of expected mat width whichever is
structure structure
Transformer Pads expected pile usage depth to be more; in case of expected pile
taken 5 times the pile diameter usage depth to be taken 5 times
below pile tip the pile diameter below pile tip
Minimum depth of 20m or 4
times the expected isolated
footing width or 2 times the
Overhead Transmission Minimum of 1 boring every 1 Minimum 1 boring per each
Minimum depth of 20m expected mat width whichever is
Line km (linear route) transmission tower
more; in case of expected pile
usage depth to be taken 10 times
the pile diameter below pile tip
Minimum depth of 1.5 times the Minimum 1 boring at center
Circular Tanks (steel or Minimum 1 boring at center 1.5 times the tank diameter or 7m
tank diameter or 7m in rock with and borings at circumference
concrete) of each tank in rock with RQD>40%
RQD>40% at spacing of 30m
Saudi Aramco: Company General Use
Page 22 of 24
Document Responsibility: Geotechnical Standards Committee SABP-Q-015
Issue Date: 30 May 2018
Next Planned Update: TBD Scope of Work Guide for Geotechnical Investigations
Page 23 of 24
Document Responsibility: Geotechnical Standards Committee SABP-Q-015
Issue Date: 30 May 2018
Next Planned Update: TBD Scope of Work Guide for Geotechnical Investigations
Near Shore investigation (rubble mound or composite breakwater, sloping seawall, vertical gravity type seawall and gravity type quay wall, piled
near shore structure, dry docks, dredging - lowering sea bed, dredging - slope stability, reclamation - fill material) shall follow SAES-Q-014
Page 24 of 24