Professional Documents
Culture Documents
Building Systems DBR - 90%
Building Systems DBR - 90%
9 14-Oct-22
Contract No. 815-C14 Building Systems Design Basis Report Revision: A
A 90% Client Review Dec’ 12 NGM ADN ARA HKE JKY ZAT
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
TABLE OF CONTENTS
A-
General Description…………………………………………………………3
B- Introduction……………………………………………………………….…3
D-Design Criteria…………………………………………………………...…..7
E-Scope of Facilities………………………………………………………..…..18
H-Design Analysis………………………………………………………..…….48
Page 2 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
A- GENERAL DESCRIPTION :
The Design Basis Report is a written explanation, and listing of all design codes regulations,
standards, criteria, guidelines, analysis, system’ configuration and description narratives and
graphics, calculations outlines, comprehensive listing of all drawings and specifications to be
developed, operational philosophies, special requirement, design approach, constraints, and
assumptions that will be followed through the development of the design and engineering
work of this task order.
Upon acceptance of the document, it sets an agreed upon path forward, for the Building
Systems Engineering & Design, between the Royal Commission and the A/E to proceed
further with the next stage of design development.
It serves as the ultimate reference, during the Value Engineering (VE) Workshop, to
illustrate and explain to its participants and audience the basis and purpose of each system
specific design.
It is a vital part of the Turn-over Documents to the end-user, as it serves as a reference to
their O&M team of understanding the design basis and concept of the different systems of
their facilities for both O&M needs and/or any future expansion, revisions, and/or renovation
work.
B- INTRODUCTION:
The Royal Commission (RC) for Jubail and Yanbu has awarded Alrabiah & Partners
Co. (ARP), the design of VIP Coach Parking to be built in Transportation Center,
Jubail Industrial City,
The site of the project will be in Transportation Center, south east corner of the site.
This single storey building shall have 6 Bays for 6 VIP buses according to the code
and standard.
Page 3 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
B-3.1 CIVIL
B-3.2 STRUCTURAL
Building Structure.
B-3.3 MECHANICAL
HVAC System
Fire Suppression System
B-3.4 ELECTRICAL
Power & Lighting
Fire Detection & Fire Protection System
B-3.5 TELECOMMUNICATION
Structured Cabling
Voice (Telephone)
Page 4 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
C1- DESIGN:
As per ‘DCN’ procedure Construction of VIP Coach Parking, there will be three
submittal stages which are 10% (Conceptual Design), 90%, and IFC.
Each submission as planned below and A/E will try to their level best to meet these due
dates, unless there were changes in the design required by Engineering Department,
and/or End User (Transportation Department) or reviewing /approval time taken more
time than planned.
C2 - PROCUREMENT:
C2.1 - ARCHITECTURAL:
To use local material and labor, for more efficient life cost cycle of the
project.
C2.2 - CIVIL:
All materials for utilities such as potable water supply system, sanitary waste
water system, and storm drainage system and irrigation water system shall be
locally purchased. Most of the materials used for these utilities are locally
available based on previous tasks provided to Royal Commission.
C2.3 - STRUCTUAL:
C2.4 - MECHANICAL:
Page 5 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
C2.5-ELECTRICAL:
C2.6 - TELECOMMUNICATION:
All equipment and materials should be locally available to speed up the overall
construction. All major materials should have a breakdown schedule so that
the construction contractor can identify and estimate even the small items or
sub items. Schedule of Prices/Quantities shall be in order (aligned) with the
scope of work and specification in order to speed up the identification of each
materials and/or equipment. Coordination with the supplier shall be done in
order to update the latest and available materials and/or equipment.
C-3 CONSTRUCTION:
1. Plan and schedule the work and thus describe the project’s total program.
2. Estimate costs and budgets.
3. Authorize parcels of work and assign responsibilities.
4. Track schedule, cost and quality performance as the project proceeds.
Page 6 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
D- DESIGN CRITERIA:
Task release has triggered the first part of the overall design delivery process, of which
this DBR forms the key component. The period up to the submission of this DBR at
100% (IFA) stage, involve data gathering and coordination process. Information has
been supplied by the RC, relating to previous schools and kindergartens along with
standardized formats.
The design team has absorbed and reviewed this data which has been used to form the
criteria stated in this document.
The Royal Commission (RC) will undertake all work related to the Site Topographical
& Geotechnical Surveys.
D1- ARCHITECTURAL:
o Functionality
Page 7 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
The design of this new service facility VIP Coach Parking is to be accessible to the
VIP buses, and not to interfere with other buses maneuver.
o Aesthetics
The design of the VIP Coach Parking shall be carefully considered to create and
maintain a common site aesthetic with particular emphasis on external finishes,
materials, colors, textures, components and features to match with the surrounding
buildings. The building shall be designed to be energy efficient with an insulated
construction, as appropriate and shall accommodate the local Saudi Arabian
environmental and climatic constraints and conditions.
o Sustainability
VIP Coach Parking shall assertively address long-term concerns for environmental
impact and energy conservation. The following help to address the overall
environmental impact of the building through sustainability.
Minimize impact on the land surrounding the building.
Provide insulation to meet the requirement.
o Maintainability
The evaluation of life cycle costs for building materials, systems and equipment, will
continue to be an issue in preparing construction drawings and specifications for the
foreseeable future. Life Cycle Costing (LCC) is simply selecting the most
appropriate/durable material based upon evaluation against the materials' longevity
and expected maintenance costs. Most LCC systems address mechanical, electrical
and plumbing equipment/systems. Analysis of architectural, civil and structural
materials are more a "judgment" call based upon past performance (life) history and
environmental factors.
o Flexibility
The building was design to be flexible for future expansion if required.
Page 8 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
D2- CIVIL :
In general, the design criteria and parameters to be used in the utilities shall be in
accordance with RC Engineering Manual with the following chapters to be
considered:
For a specific description of the sections mentioned in these chapters, refer to the
Design Basis Report-Site Works, Vol. 1 of 2, Section 1.5, page 13.
Page 9 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
D3 - STRUCTURAL:
This Design Basis Report lists the general design criteria that will be used in the
calculations for the design of structural items involved in this project. This report
complies with all relevant Jubail Royal Commission Codes and Standards, latest
editions of engineering and industry codes and Saudi Arabian Government Codes. The
following shall form part of this report and in calculations and drawings:
o Drawing Arrangement
Order and assemblage of typical structural drawing packages shall put the Structural
drawings after the Architectural drawings and before the Mechanical drawings (Fire
Protection) in accordance with RC Guidelines. The Structural drawings shall be
grouped as follows:
Typical details;
Plans;
Schedules.
Page 10 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
D4.2 - HVAC:
Design criteria used in the HVAC system design is as follows:
Outdoor design conditions as per RC engineering manual 6.17.B.2.
Summer: Dry bulb 46oC
Wet bulb 30oC
Daily Range 13oC
Winter: Dry bulb 5o C
Indoor design criteria will be as per RC engineering manual 6.17.B.3.
Summer: Dry bulb 26o C±1
Relative Humidity 45%
Winter: Dry bulb 21˚C
Ducts would be designed at on 0.65Pa/m maximum pressure.
Page 11 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
Page 12 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
D5 – ELECTRICAL:
D5.4 – LIGHTING:
1. Fluorescent fixtures with T5 energy saving (ES) lamps shall be used
for electrical room.
2. High bay lighting fixtures are used in bays area. These fixtures shall
be provided with high efficiency metal halide light fixture providing
white light, with instant re-strike ballast.
3. Supply voltage for indoor luminaire in general will be 220V, PH/N,
60Hz.
4. Indoor lighting fixtures and its raceways will run thru EMT conduit
with PVC insulated wires and controlled by lighting contactors control
panel.
5. Recommended lighting RC lighting levels shall be attained according
to table 2A of RC Guideline specifications 16150.
6. Emergency lights and illuminated exit signs with battery backups for
3 hours duration shall be provided in conformance with NFPA 101
and shall be internally illuminated type with integral rechargeable
Page 14 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
D5.5 – GROUNDING:
o All feeders and branch circuit raceways shall be provided with separate
insulated, green equipment grounding conductor.
o All equipment enclosures, motor and transformer frames, conduits systems,
cable armored, metallic ladders, exposed structural steel and similar items are
grounded effectively.
o Underground conductor from the MDP to grounding well shall be run in PVC
conduit.
o Grounding loop method shall be used to ensure that the grounding design for
this facility does not exceed five (5) ohms. Additional ground rod/s as
required to achieve or lower this value. Calculations are consistent with IEEE
142, Recommended Practice for Grounding of Industrial and Commercial
Power Systems.
o Soft drawn bare copper conductor shall be used for underground conductors
installed at a minimum depth of 762 mm below finish grade.
o Grounding and bonding of all electrical equipment, systems and devices are
provided in accordance with requirements of NFPA 70 article 250, IEEE
standard 142-1991 and IEEE standard 1100-1992.
Page 15 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
D6 – TELECOMMUNICATION:
Telecommunications spaces vary in size depending on their function and the size
of the usable floor space they serve. Telecommunications space sizing guidelines
for horizontal cabling distribution are based on distributing telecommunications
services to one individual work area per 9.3 m2 (100 ft2) of usable floor space.
Since the V.I.P. Coach Building has no office to serve, therefore a minimum
telecommunication space will be provided. A telecommunication space shall be a
12U wall mounted cabinet that will serve the horizontal cabling and a
500mmX343mmX200mm Pull Box that will serve as an Entrance Facility.
The horizontal cabling system extends from the telecommunications outlet in the
work area to the horizontal cross-connect in the 12U Cabinet. It includes the
telecommunications outlet, an optional consolidation point or transition point
connector, horizontal cable, and the mechanical terminations and patch cords (or
jumpers) that comprise the horizontal cross-connect. This cabling portion shall
not exceed 90 meters.
An allowance of 10m (33 ft.) has been provided for the combined length of patch
cords/cross-connect jumpers and equipment cables/cords in the HC, including the
Work Area (WA) equipment patch cords.
All horizontal cables that will be used for voice/data communication shall be
CAT-6 blue plenum rated.
Pathways for horizontal cabling shall compose of 25mm PVC conduit for the
below the floor slab, 25mm EMT for the above the suspended and a pull box.
Page 16 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
UTP CAT-6 patch panel shall be shared between voice and data communication
and shall be used as the horizontal cabling distribution
For traditional offices with floor-to-ceiling height dry wall partitions, provide a
minimum of one telecommunication outlet box (for telephone and work station
computer) per 10m² of Work Area (WA = 10m²).
Telecommunication connectors for voice and data (telephone and work station
computer) in Work Area offices should be an 8P8C (RJ-45).
Services for the Telephone (Voice) communication shall be connected to the STC
via the existing Secondary Telephone Facility (splice to the nearest Joint-Box JB-
07).
Page 17 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
E- SCOPE OF FACILITIES:
The building will be 3 staggered garages with outside electrical room. In each garage
There will be 2 bays for 2 VIP buses. The building will be fully A/C , to serve the
VIP guest coming to RC.
E1.2 DETAIL:
TYPE OF CONSTRUCTION
Construction Classification - Type IIB
Masonry Walls
150mm CMU inside with 75mm thick extruded polystyrene insulation
(R=15 ) and 200mm fluted blocks external wall.
All masonry works shall conform to RC Guideline Specifications
(Division 4)
Page 18 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
INTERIOR FINISHES
All finish materials shall be selected for their ability to withstand the
harsh environmental conditions prevalent at the site.
Priority shall be given to locally available building materials.
All Architectural finishes shall comply with RC guideline specification
(Division 9).
Wall Finishes
All external walls shall be 425mm from outside to inside (200 mm
fluted blocks with integral color, 75mm extruded polystyrene
insulation and 150mm CMU with paint on plastering.)
Internal wall shall be 150mm CMU with plaster and paint finishes as
applicable.
Semi-gloss non-reflective paint shall be used for interior walls.
Paint color shall be approved by RC prior to purchase
Page 19 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
Floor Finishes
With due consideration given to cost, durability and maintenance
requirements, good quality flooring materials shall be used to comply
with the function of the area. The following materials shall be used:
Bay parking shall be painter with epoxy paint coat, chemical
resistant, non-skid, and solvent free.
Ceilings Finishes
Painted exposed structure for the whole building.
o DOORS
Selection of doors shall conform to RC Guidelines & Specifications (Division 8). The
following Architectural criteria shall be applied:
Doors shall comply with NFPA Code Chapter 7 and IBC 2009 Chapter 10.
The door leaf size shall be selected according to space and code requirements.
Fire rating code requirements shall be strictly adhered to for all doors.
Page 20 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
Door hardware shall comply with the code and selected to meet its specific use.
Weather-proofing devices shall be used for external doors to achieve maximum
efficiency.
Hollow metal doors with vision panel shall be used exit door.
Glass vision panels, ventilation grills, kick plates shall be provided as required.
All fire rated doors shall be in compliance with Underwriter Laboratories.
The door assemblies shall comply with ANSI/UL 10C
Doors shall be provided with door closure in accordance with ANSI/NFPA 80
o METAL WORKS
Page 21 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
All external concrete masonry walls subject to wind load shall be designed to satisfy
ACI 530 requirements.
All external concrete masonry walls subject to wind load shall be designed to satisfy
ACI 530 requirements.
Single skin panel wit 75mm foam concrete is used to cover the roof framing along
with insulation and water proofing.
o Civil
Reference datum for all elevations shall be based on the Royal Commission Datum.
o Concrete Design
All concrete elements shall be designed in accordance with ACI 318 with load
factors and combinations indicated.
Page 22 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
Reinforcing steel for structural concrete in contact with soil or exposed to weather,
salt, salt water, brackish water, seawater, or spray from these sources shall be fusion
bonded epoxy-coated (FBEC) in accordance with ASTM A775M and Royal
Commission Guideline Specification Section 03205.
Minimum Cylinder
Structure Class of Concrete Compressive Strength
at 28 Days
Structural concrete in C35 minimum with Type I
contact with soil or Portland cement and silica
exposed to weather, fume pozzolanic replacement
salt, salt water, brackish as per GS 03310, Table 1C 35 MPa
water, seawater, or
spray from these
sources
All other structural C30a or C30b minimum with
concrete Type I Portland cement and
pozzolanic replacement as per 30 MPa
GS 03310, Table 1C
Page 23 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
Page 24 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
underground manholes)
All sizes of bars 50
Concrete not exposed to weather
and concrete not in contact with
soil or water of any type:
Slabs ,Walls and Joist;
All sizes of bars 20
Beams and Columns;
Longitudinal reinforcing
cover shall be the same as the
bar diameter, but not less than 30
Ties, stirrups and spirals 20
Shells and Folded Plates;
All sizes of bars and WWM 20
High Strength Polymer Grid
All exposure conditions 20
o Slab on Grade
o Steel Design
All steel elements shall be designed in accordance with AISC Steel Construction
Manual, 13th Edition, utilizing either Allowable Stress Design or Load and
Resistance Factor Design, and AISC Seismic Design Manual, 1st Edition. Bolted
connections shall utilize Type N (bearing-type with threads included in the shear
plane) or Type SC (slip-critical) in accordance with RCSC “Specification for
Structural Joints Using ASTM A325 or A490 Bolts”.
The design of base plates shall be in accordance with AISC Design Guide 1: Base
Plate and Anchor Rod Design, latest edition. Holes in base plates shall be in
accordance with Table 2.3 of the Design Guide.
Page 25 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
only where bolting is not possible. The superstructures shall be detailed to not
collect precipitation by toeing flanged sections down and closing the ends of open
sections.
The SE Drawings shall explicitly show and specify requirements for the structural
steel dimensions, sizes, connections, material specifications, surface preparations,
and coatings.
o Anchorage
Anchor rods, nuts, and washers shall be hot dip galvanized to a minimum weight of
915 g/m2 (130 microns) in accordance with ASTM A123 and A153 as applicable for
the parts. Nuts shall be tapped oversize as per ASTM A563M and shall be re-tapped
and lubricated after galvanizing to provide the proper fit. Anchor rods and nuts shall
be purchased from the same supplier and shipped preassembled.
Anchor rods shall be headed-type or threaded/nutted with the opposite end threaded
for the length of the anchor bolt projection. Anchor rods shall be equipped with an
additional nut to serve as a lock to ensure against loosening. Plate washers, sized as
per AISC Design Guide 1: Base Plate and Anchor Rod Design, Table 2.3 to
completely cover the base plate holes, shall be used as ASTM F436 washers are not
large enough to cover the base plate holes. Plate washer hole diameter shall be the
anchor bolt diameter plus 2 mm.
Anchor rods shall be set accurately using templates within the tolerances specified in
the AISC 303 “Code of Standard Practice for Steel Buildings and Bridges”, not the
generous setting tolerances given in ACI 117.
The design of anchor rods and their concrete surrounds shall be in accordance with
the following:
AISC Design Guide 1: Base Plate and Anchor Rod Design, latest edition;
Each column shall have a minimum of four (4) 20 mm diameter anchor rods with 375
mm minimum embedment. Actual anchor bolt number, pattern, diameter, and
embedment required for the applied forces shall be determined. The minimum clear
distance from the anchor bolt centreline to edge of concrete shall be 150 mm and the
anchor rods shall not come in contact with the foundation reinforcing. Actual edge
distance required for the applied forces shall be determined.
Page 26 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
The SE Drawings shall show the anchor bolt patterns, embedment depths, edge
distances, and projections above the top of concrete, which shall account for the
thicknesses of the grout levelling bed, base plate, washer, double nuts, and overrun.
CORROSION PROTECTION
o The atmosphere, soil, and water conditions in Jubail Industrial City are severely
corrosive. The design and construction of foundations and superstructures shall
include competent corrosion mitigation measures to achieve long-term durability.
Contractors are obligated to adopt all Royal Commission-published corrosion related
documents.
o Steel at interior, dry environments where the steel is not embedded in or connected to
concrete:
Steel shall receive one shop coat of a two-component poly-amide cured epoxy
primer containing zinc phosphate corrosion-inhibiting pigment applied as per
the manufacturer’s instruction to produce a dry film thickness of 75 microns
(3 mils) minimum. Omit shop primer at the following conditions:
o Exterior steel, interior steel in wet environments, high-strength bolts, nuts, and washers
for joints, anchor rods, nuts, and plate washers, and steel parts and accessories
attached to or embedded in concrete:
Page 27 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
For HDG steel intended to receive finish paint, the steel shall then be cleaned
in accordance with SSPC-SP7 "Brush Off Blast Cleaning" to produce surface
profiles recommended by the finish paint manufacturer.
o Field Touch-Up: Primer and HDG coatings at all field weld areas, abraded areas, and all
interior and exterior high-strength bolts, nuts, and washers shall be cleaned and
coated as follows:
Steel shall receive one shop coat of a two-component poly-amide cured epoxy
primer containing zinc phosphate corrosion-inhibiting pigment applied as per
the manufacturer’s instruction to produce a dry film thickness of 75 microns
(3 mils) minimum.
o Structural concrete in contact with soil or exposed to weather, salt, salt water,
brackish water, seawater, or spray from these sources:
o Structural concrete formed against soil, including, but not limited to, slabs, footings,
walls, and grade beams, shall be cast on a 50 mm minimum thick blinding slab
complying with Royal Commission Guideline Specification Section 03310 –
Structural Concrete, Table 1C, Type C20 utilizing Type V Portland cement. The top
surface of the blinding slab shall be waterproofed and the waterproofing protected
prior to commencing any work on the structural concrete.
Page 28 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
GEOTECHNICAL CRITERIA
The existing grades, finished grades, geotechnical data, and soil bearing requirement shall be
coordinated with the final site-specific grading plans and geotechnical engineering reports.
A/E shall prepare the following as a requirement for the geotechnical investigation in the
specific site/s:
1. Scope of work and borehole and test pit location plans, including test point
coordinates (northing and easting) and depths of boreholes and pits, to be submitted
for review and approval of RC’s Geotechnical Engineer Specialist.
2. Four (4) hard copies and one (1) soft copy (Autocad and PDF formats) of the
approved location plans to be submitted to RC’s facility engineer.
(a) Soil conditions are favourable and the stratigraphy is consistent for the test
points, then no additional test points will be undertaken and the geotechnical
Page 29 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
engineer specialist will issue a report to the Facility Engineer for A/E for review
and approval;
(b) Soil conditions are unfavourable or the stratigraphy is inconsistent, then the A/E
shall request additional boreholes and/or test pits until sufficient soil conditions
and the stratigraphy data are determined.
The A/E shall produce geotechnical data package for each request for geotechnical
investigation/reporting. As a minimum, the package shall contain:
2. Grading plans showing proposed finished grade levels (topography and spot grades)
and proposed structures superimposed on the existing grade level drawings.
4. General sub- and super-structure descriptions and their estimated foundation service
loads (i.e., un-factored) or the required design bearing pressure.
5. Project’s principal features and locations of any major or special structures (i.e.,
presence of adjacent structures, underground utilities, retaining walls, etc.).
The A/E’s qualified Soil & Foundation Engineer shall review and prepare written comments
on the Reports and submit the comments to the RC’s Authorized Representative within two
(2) week of the receipt of the Reports.
1. A/E shall meet with and discuss the Report’s recommendations with the RC’s
Geotechnical Engineer Specialist and Facility Engineer one (1) week prior to
submitting review comments.
The A/E shall utilize the final Reports’ recommendation (settlements and soil bearing
pressure data, earthwork requirements, dewatering requirements, earth retention data, soil
removal/replacement, soil improvement, etc.) and fully and clearly incorporate into the
Contract Drawings and RFP (BoQ, Attachment “D” SoW, and the Technical Specifications).
Net allowable soil bearing capacity for square and strip footing shall be as
recommended by the Final Geotechnical Reports by the concerned geotechnical firm.
Page 30 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
o Bearing Stratum
o Stability Checks
Page 31 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
E3.2- HVAC:
Three package units are provided for the building, each unit will supply air to 2
parking bays
Temperature will be controlled by return air thermostat.
Exhaust will be taken from all appropriate spaces as per ASHRAE 62.1 - 2007.
Ventilation rates shall be in accordance with ASHRAE (American Society of
Heating Refrigeration Air Conditioning Engineer's) Standards'62.1-2007and
International mechanical code 2009.
The building temperature shall be maintained by wall mounted thermostat.
All spaces shall be kept under slight positive pressure to minimize air and duct
infiltration .
Ductworks design and sizing shall be in accordance with SMACNA
recommendations, ASHRAE fundamentals and RC Engineering Manual.
The air distribution system will be a galvanized metal ductwork system.
The PACU (Packaged Air-conditioning units) are selected for maximum load
conditions.
Page 32 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
Page 33 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
The new fire alarm devices will be connected to the existing loop #1
in the guard house NO. 3.
All circuits are wired Class A supervised using standard 2.5 mm2
stranded copper, twisted shielded pair, PVC insulated rated 300 volts,
105C fires protective, and signaling circuit type cable, pulled inside
conduits.
Page 34 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
F1- ARCHITECTURAL:
IBC International Building Code - 2009
Page 35 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
F2- CIVIL:
IBC – 2009 International Building Code
ACI 318-05 American Concrete Institute: Building Code
Requirements for Structural Concrete and Commentary
F3- STRUCTURAL :
Page 36 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
ACI 318 Building Code Requirements for Structural Concrete and Commentary
(ACI 318RM 2008)
AISC Steel Construction Manual, 3rd edition (LRFD), 9th edition (ASD),
and 13th edition (LRFD and ASD)
AISC 303 Code of Standard Practice for Steel Buildings and Bridges
AWS Structural Welding Codes: D1.1 – Steel, D1.3 – Sheet Steel, D1.4 –
Reinforcing; and D1.7 – Stainless Steel
RCSC Specification for Structural Joints using ASTM A325 or A490 Bolts
Page 37 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
F4- MECHANICAL:
OSHA 3256-07N Fire Service Features of Buildings and Fire Protection System.
F4.2 PLUMBING :
Page 39 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
F4.3 HVAC:
IBC International Building Code 2009
IMC International Mechanical Code 2009
ASHRAE STD. 62.1-2007 Ventilation for Acceptable Indoor Air Quality
ASHRAE 90.1 Energy Standards for Buildings.
Chapter 6 RC Engineering Manual
ASHRAE 2009 Applications Handbook
SMACNA Duct construction standard.
ASHRAE GRP-158 Cooling and heating load calculation manual
Page 40 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
Page 41 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
F6 - TELECOMMUNICATION SYSTEM:
Page 43 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
All designs and project execution activities shall comply with the local safety standards
applicable to this project.
● Orientation seminars for all workers and equipment screening shall be initiated prior to
commencement of work. Daily ‘Tool Box’ meetings regarding work safety shall be held to
update the personnel on the importance of safety issues.
Design Phase:
As per OSHA 3256- 07N, the building will be designed to meet with the general
requirement for safety such as providing the required number of Fire Hydrants as per
NFPA with the required marking, and will be posited in clear location without
obstruction. Design the skylight with the same weight load as the roof...etc.
Construction Phase:
Contractor shall adopt and comply with the latest editions of the Occupational Safety
and Health Administration (OSHA) Standards CFR 29 - Parts 1910, 1915, and 1917.
The requirement of 1926 – Construction such as:
Subpart C – General Safety and Health Provisions
1926.21 – Safety training and Education
1926.23 – First Aid and Medical Attention
Subpart D – Occupational Health and Environmental Controls
1926.50 – Medical Services and First Aid
Subpart E – Personal Protective and Life Saving Equipment
1926.95 – Criteria for Personal Protective Equipment
1926.96 – Occupational Foot Protection
Page 44 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
Page 45 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
Occupant Load
o Estimated Actual Number of Occupants including Visitors:
Parking - 59
Page 46 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
Fire Protection:
The design shall be in accordance with the following considerations:
o Maximum travel distance for fire exit shall not exceed 91.44 m
(Without sprinkler system)
o Portable Fire Extinguisher shall be installed, where the proper
classification and location is based on [NFPA 10] Standard for Portable
Fire Extinguishers.
Page 47 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
H- DESIGN ANALYSIS :
o Site Investigation:
Page 48 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
Proposed location
Future expansion
A site visit was conducted and all the utilities were checked. (Check with the Civil DBR
for more details)
Page 49 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
. option-1
option-2
Option 2 was approved from the client, but they want to have three, joined and
staggered garages, not the six staggered garages. To have each two buses in one
garage which is will be in this 90% layout submission proposal.
The area of the building is 1090 mm, and the height is 7600mm from the top the
street level.
Page 50 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
o Noise Reduction:
N/A
o Environmental Parameters:
N/A
o Water Conservation:
N/A
o Lighting Requirement:
N/A
o Accessibility Provision:
N/A
o Security Provision:
N/A
To use the local material that match with the code and standard requirement
of the project, to control the cost.
The whole buildings were duplicated and adopted (site adaptation) from the Royal
Commission supplied references mentioned in section D above, where building and
structural works to include all sub-structure and any additions not included in the site adapt.
Cursory review was completed by A/E to ensure no additional building works exist beyond
Page 51 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
the site adapted design. All structural calculations from site adapt have received a cursory
inspection and are approved accordingly.
Isolated and/or combined footings will be checked and may re-designed using Spreadsheets
and applicable ACI compliant software (considering dead loads, live loads and lateral loads,
in combination as applicable) based on the maximum support reactions to satisfy ACI 318
Chapter 15 requirements. Net allowable soil bearing pressure shall be as per
recommendation on geotechnical investigation report.
LOADINGS
Design Loads: Minimum design loads shall be in accordance with the Royal
Commission Engineering Manual, Chapter 9; ASCE 7-10 in its entirety; and the
following:
Dead Loads
Page 52 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
Chapter 9, Table 9A
3. Roofing
a. Rigid insulation – 150 mm Royal Commission
thk. (13 mm thick Engineering Manual,
@ 0.04 kN/m3) = 0.48 kN/m2 Design Criteria, Structural,
b. PVC single ply sheet Chapter 9,
(0.06 in. thick) = 0.03 kN/m2 Table 9A
c. Gravel 50 mm thick layer = 0.815 kN/m2
d. Sloped screed (foam concrete) = 1.0 kN/m3
Page 53 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
Composition:
Page 54 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
FLOOR FILL
Cinder concrete, per mm 0.017
Hollow concrete masonry unit wythes:
Wythe thickness (in mm) 102 152 203 254 305
Density of unit (16.49 kN/m3)
No grout 1.05 1.29 1.68 2.01 2.35
1219 mm 1.48 1.92 2.35 2.78
1016 mm 1.58 2.06 2.54 3.02
813 mm grout 1.63 2.15 2.68 3.16
610 mm spacing 1.77 2.35 2.92 3.45
406 mm 2.01 2.68 3.35 4.02
Full grout 2.73 3.69 4.69 5.70
Density of unit (19.64 kN/m3)
No grout 1.25 1.34 1.72 2.11 2.39
1219 mm 1.58 2.11 2.59 2.97
1016 mm 1.63 2.15 2.68 3.11
813 mm grout 1.72 2.25 2.78 3.26
610 mm spacing 1.87 2.44 3.02 3.59
406 mm 2.11 2.78 3.50 4.17
Full grout 2.82 3.88 4.88 5.89
Density of unit (21.21 kN/m3)
No grout 1.39 1.68 2.15 2.59 3.02
1219 mm 1.58 2.39 2.92 3.45
1016 mm 1.72 2.54 3.11 3.69
813 mm grout 1.82 2.63 2.68 3.16
610 mm spacing 1.96 2.82 3.50 4.12
406 mm 2.25 3.16 3.93 4.69
Full grout 3.06 4.17 5.27 6.37
Solid concrete masonry unit
Wythe thickness (in mm) 102 152 203 254 305
Density of unit (16.49 kN/m3) 1.53 2.35 3.21 4.02 4.88
Density of unit (19.64 kN/m3) 1.82 2.82 3.78 4.79 5.79
Density of unit (21.21 kN/m3) 1.96 3.02 4.12 5.17 6.27
Live Loads
Live loads acting on a structure consist of loading not permanently fixed, but
superimposed by use and occupancy. Live loads include those uniformly
distributed and concentrated on floors, handrails, guardrails, vehicle barrier
Page 55 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
systems, ladders, and stairs from use, occupancy, operation, impact, and
vibration.
= 4.79 kN/m2
Each portion of a roof shall be designed to sustain the load of all rainwater
that will accumulate on it if the primary drainage system for that portion is
blocked plus the uniform load caused by water that rises above the inlet of the
secondary drainage system at its design flow.
Wind Loads
All structures and foundations shall be designed and constructed to resist the
wind effects determined in accordance with SEI/ASCE 7-10, Chapter
26,27,28,29 &30.
Page 56 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
5. Velocity Pressure
qz = 0.613(Kz)(Kzt)(Kd)(V2) (N/m2) SEI/ASCE 7-10, Eq 27.3-1
SEI/ASCE 7-10, Sect 26.7.3
Kzt = 1.0 SEI/ASCE 7-10, Sect. 26.8-1
Kd = 0.85 SEI/ASCE 7-10, Table 26.6-1
Earthquake Load
Page 57 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
Short period
SMS = Fa SS SEI/ASCE7-10, Eq. 11.4-1
SM1 = Fv S1 SEI/ASCE7-10, Eq. 11.4-2
Where: SS = 0.15g Royal Commission
Requirement for Jubail
S1 = 0.04g Royal Commission
Requirement for Jubail
Fa = 1.6 SEI/ASCE7-10, Table 11.4-1
Fv = 2.4 SEI/ASCE7-10, Table 11.4-2
where:
= design lateral force applied at story x
= portion of the total dead load of the
structure located or assigned to level x
Page 59 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
Δx = Cd xe/I
Page 60 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
All structures and foundations shall be designed with consideration for the
loads and effects caused by restraining supports, contraction or expansion
resulting from temperature changes, shrinkage, moisture changes, creep in
component materials, differential settlement, and combinations thereof.
Load Combinations
All structures and foundations shall be designed and constructed to resist stresses
produced by load combinations in accordance with ASCE 7-10 and the following.
1. 1.40 D
2. 1.20 D + 1.60 L + 0.5 (Lr or R)
3. 1.20 D + 1.60 (Lr or R) + (L or 0.5W)
4. 1.2 D + 1.0 W + L+0.5 (Lr or R)
5. 1.2 D + 1.0 E +L
6. 0.9D+1.0W
7. 0.9D+1.0E
Page 61 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
1. D
2. D + L
3. D + (Lr or R)
4. D + 0.75L + 0.75(Lr or R)
5. D + (0.6W or 0.7E)
6a. D + 0.75L + 0.75(0.6W)+0.75(Lr or R)
6b. D + 0.75L + 0.75(0.7E)
7. 0.6D+0.6W
8. 0.60D + 0.7E
1. The load factor on L in combinations 3, 4, and 5 is permitted to equal 0.5 for all
occupancies in which Lo in Table 4-1 is less than or equal to 100 psf, with the
exception of garages or areas occupied as places of public assembly.
2. In combinations 2, 4, and 5, the companion load S shall be taken as either the fl at
roof snow load (pf) or the sloped roof snow load (ps).
Where fluid loads F are present, they shall be included with the same load factor as
dead load D in combinations 1 through 5 and 7.
1. Where the effect of H adds to the primary variable load effect, include H with a
load factor of 1.6;
2. Where the effect of H resists the primary variable load effect, include H with a
load factor of 0.9
Where the load is permanent or a load factor of 0 for all other conditions.
Effects of one or more loads not acting shall be investigated. The most unfavorable
effects from both wind and earthquake loads shall be investigated, where appropriate,
but they need not be considered to act simultaneously. Refer to ASCE 7-10 Section
12.4 for specific definition of the earthquake load effect E.
Stability analyses shall demonstrate the ability of the structures to resist overturning,
uplift, sliding, and buoyancy, and that the allowable soil bearing values are not
exceeded. Stability shall be provided solely by dead load plus permanent mechanical
anchorages. In determining the safety factors, allowance shall be made for the
potential removal of resisting dead loads (i.e., excavation, erosion, etc.).
Page 62 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
Retaining wall sliding resistance shall be developed by friction (and passive soil
pressure where necessary) utilizing particularly detailed shear keys to engage the
friction-resistance plane below the plane of the waterproofing and protection.
OM – Overturning Moment
Deflections
The maximum allowable total vertical deflection determined from ASD Load
Combinations shall be L/240; and L/500 for live load only (where L is the beam
length).
Acceptable deflection shall also consider the parameters used in the design of the
partitions and cladding. Coordination between the structure design and partitions
and cladding is critical.
MATERIALS
All materials shall conform to the Specifications and Serial Designations herein. All steel
materials shall be new and un-spliced.
Page 63 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
hot-dip galvanized
Anchor Rods (headed-type or ASTM A36 or F1554 Grade 36; Double nuts –
threaded/nutted with double nuts and ASTM A563, Grade DH; Plate washers –
plate washers) ASTM A36; all hot-dip galvanized
AWS D1.1, D1.4, and D1.6. Low hydrogen
Welding Processes and Electrodes electrodes with a minimum tensile strength of
480 MPa, (e.g., “E7018” for SMAW)
ASTM C150 Type I and V Cements; ASTM
Cementitious Materials C618, C989, and C1240 Pozzolanic
replacements
ASTM C1107 with minimum 7 day
Non-Shrink, Non-Metallic Grout compressive strength at least twice the base
concrete strength
ASTM A615, Grade 60 (414 MPa); ASTM
Reinforcing Steel A775M fusion bonded epoxy-coated reinforcing
(FBECR)
Epoxy adhesives with hot-dip galvanized or
stainless steel high-strength bolt assemblies as
Chemical Anchors
manufacturer by Hilti Corp. or approved
equivalent
o Site Investigation:
N/A
N/A
o Energy Conservation:
N/A
o Noise Reduction:
N/A
o Environmental Parameters:
Page 64 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
o Lighting Requirement:
N/A
o Accessibility Provision:
N/A
o Security Provision:
N/A
All the structural elements shall have a design life of at least 75 years.
o Site Investigation:
Not Applicable
3 Roof top package units will be installed and could be used simultaneously or as
required .
o Energy Conservation:
o Water Conservation:
Not Applicable
o Noise Reduction:
Page 65 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
The Air conditioning system sound control shall be in accordance with the
ASHARE hand book .
o Environmental Parameters:
o Lighting Requirement:
Not Applicable
o Accessibility Provision:
o Security Provision:
Not Applicable
o Site Investigation:
The Electrical power supply to the building listed below shall be taken from the
existing SEC-EOA 13.8kV network and/or the RC low voltage network in co-
ordination with SEC-EOA and/or RC and the scheme shall be developed to provide
power to the facilities in accordance with the SEC-EOA and/or RC standards and
specifications. The power supply to the facilities shall be single metered (SEC-EOA
standard) for load requirements of each single customer. All 13.8kV and low voltage
electrical equipment, transformers, switchgear, enclosures, interface and connections
shall be in accordance with SEC requirements, which include a field survey of the for
utilities and co-ordination with SEC-EOA and/or obtain necessary approvals (100%)
to complete the design.
Page 66 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
During the design stages, the architectural must advice each discipline before any
modifications to reference drawings to avoid inconsistency to the current reference
drawings and other disciplines to do so. Proper coordination is required to have
smooth flow while developing any conceptual and detailed design plans.
o Energy Conservation:
Lighting fixtures and others will comprise of Electronic Ballast and High Power
Factor (EBHPF), which means the higher the power factor the efficient and less
power consumption it will consume. In addition, most of the lightings will be used
are Fluorescent Tube to conserve energy compare and better illumination.
o Environmental Parameters:
Equipment and devices which are subject to exposure from moist, water or even
outdoor location are prone from rust, dust and corrosive environments will also cause
of frequent tripping of circuit breakers and creates potential hazards must be in
NEMA configuration or IP code as required according to its condition in order to
mitigate the effect of equipment’s quick deterioration.
o Lighting Requirement:
Estimated calculated load includes the 20% spares and 20% spaces for the building
as per RC Guideline and Specification 16640 in the event of load growth. The
anticipated load growth has been considered for every panel starting from sub-panel,
to panelboard, main distribution panel and transformer to accommodate the future
electrical load and its system expansion.
o Security Provision:
N/A
Page 67 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
o Site Investigation:
The wall for the installation of 12U Cabinet shall be free from edges and deformation
and shall be continuous.
For electrical requirements, all active equipments shall have at least one (1) dedicated
duplex receptacle 220/20A connected directly to the Power Panel.
o Energy Conservation:
All active equipments shall be carefully selected for its power consumption and heat
dissipation. Less power consumption means less energy needed for the delivery of
Page 68 of 69
027-T11, Task No. 9 DCN#02 14-Oct-22
Contracts 815-C14 Building Systems Design Basis Report Revision: A
90 % for Review
electricity, likewise less heat dissipation means less energy needed by the HVAC
system.
o Noise Reduction:
The 12U Cabinet shall be acoustically design so that the noise generated by the
active equipments inside the Telecommunication room will not pass thru. Noise
generated by the active equipment will cause detrimental effect in the nearby workers
or Guest.
o Environmental Parameters:
Active equipments that consume less power means less carbon emission since all
electricity power generated in this Kingdom uses crude oil to generate electricity.
o Lighting Requirement:
Front panel of the 12U Cabinet needs at least 500lux of light intensity.
o Accessibility Provision:
The 12U Cabinet is easily accessible since no divider is provided inside the building.
o Security Provision:
The 12U Cabinet shall tamper proof and provided with a proper lock.
All equipments and materials should have at least minimum of 20 years life span.
Page 69 of 69