PROPOSAL
Client
Consultant
Soil Study & Consultancy for RAPP
TABLE OF CONTENT
1. INTRODUCTION
2. OBJECTIVES
4. SCOPE OF WORK
5. DELIVERY SCHEDULE
6. PROJECT COST
8. PERSONNEL
9. ATTACHMENT
Technical Proposal
Soil Study & Consultancy for RAPP
1. INTRODUCTION
This proposal is prepared in respond to provide engineering Soil Study & Consultancy
for RAPP. This proposal will contain study description, scope of work, quotation and
commercial term.
2. OBJECTIVES
PT Prinsipa issues this document as Technical and Commercial Proposal as Consultant of
mentioned study to execute Study & Consultancy Services on mentioned study above. The
detail list of Scope of Work as below.
CLIENT
4. SCOPE OF WORK
PT Prinsipa scope of work and responsibility shall describe in detail in attachment I , also
include but not limited to the following:
• Engineering Survey
• Topography and Bathymetri
• Soil Analysis Test
• Geolistrik
• Soil and Slope Reinforcement Study
• Konsinyering
5. DELIVERY SCHEDULE
Survey shall be 1 month. Total Time Schedule estimated 1,5 months for 1st Engineering
Issuance, depend on available of Survey Data. Total estimate Completion is 2,5 months.
6. PROJECT COST
Lump Sum Cost
Total cost for this project is: IDR 465.590.000 (Four Hundred Sixy-Five Million Five
Hundred Ninety Thousand Rupiah)
Technical Proposal
Soil Study & Consultancy for RAPP
Terms of Payment
Payment Terms Proposed as bellow:
- 50% on DP
- 20% on Site Survey Finished
- 20% on Submission Docs and Drawings engineering report
- 10% on Approved Docs and Drawings engineering report
Proposal Validity
This proposal and the associate costs are valid for Thirty (30) days from date of issuance.
8. PERSONNEL
This activity shall be support with personnel as bellow:
1. Engineering Leader : Ir. Khairmen Suardi, M.Eng, IPM
2. Deputy Engineering Leader : Aryo Pribadi Wicaksono, S.T
3. Civil Lead Engineer : Agus Suryantoro, S.T, IPM
4. Civil & Structure Engineer : M. Nur Faozi, S.T
5. Drafter : Samsul & Ilham Fakhrurrozi
Technical Proposal
ATTACHMENT FEED DELIVERABLE LIST
Soil Study & Consultancy for RAPP
PROYEK : Soil Study & Consultancy for RAPP
SCOPE : Topography, Bathymetry, Geotechnic,
PEKERJAAN Geolistrik
LOKASI : Riau
PEMBERI TUGAS :
KONSULTAN : PT. Abirama Prinsipa Indonesia
TAHUN : 2020
REKAPITULASI
No. ITEM PEKERJAAN JUMLAH (Rp.)
1 ENGINEERING
D Geolistrik 34.150.000
F Konsinyering 50.000.000
2 CONSTRUCTION MANAGEMENT -
TOTAL 465.590.000
NOTE:
1. Consultant will not develop any of WPS = Welding Procedures Specification , PQR = Procedures Qualification Record, NDE = Non Destructive Examination, or any document produce by WE and any
Project Reporting to End User.
2. Term of Payment:
- 50% on DP
4. Prinsipa will not produce any hardcopy required and submission through email. Final hard copy upon approval are provided.
5. We will generate under crack version for any software required. When license print out will be upon request by Client and will be charge different price.
7. The price are INCLUDED Engineering survey, Engineering Survey for Maximum 3 times, Tickets, aacomodation, Hotel and Land Transport included.
8. The submission are at minimum 3 times (Issued for Comment, Issued For Approval and Approved For Deseign), however, depend on Client requirement. Each revision shall be 7 Days review on
Client Side.
9. Survey shall be 1 month. Total Time Schedule estimated 1,5 months for 1st Issuance Engineering, depend on available of Survey Data, . Total estimate Completion is 2,5 months.
RENCANA ANGGARAN BIAYA
Riau
JUMLAH Rp 39.000.000
RENCANA ANGGARAN BIAYA
PEKERJAAN PENGUKURAN
TOPOGRAFI
Riau
4 PENGUKURAN TOPOGRAFI
Remunerasi personil
Sewa GPS 2 Ha 4.500.00 Rp 9.000.000
0
Sewa UAV
include crossing sungai di area darat
SUB TOTAL Rp 9.000.000
5 PENGUKURAN BATHYMETRI
Remunerasi personil
2 Ha 8.500.00 Rp 17.000.00
Sewa GPS 0 0
Sewa kapal & ecosounder
SUB TOTAL Rp 17.000.000
TOTAL Rp 111.940.000
RENCANA ANGGARAN
BIAYA
PEKERJAAN SOIL
INVESTIGATION
Ria
C. Sondir Test
a. Sondir , maksimal sampai 30 m atau sampai tanah keras (q >
titik 5 Rp. 4.500.000 Rp. 22.500.000
150
kg/cm2)
b. Move area titik 4 Rp. 525.000 Rp. 2.100.000
TOTAL Rp 59.400.000
RENCANA ANGGARAN
BIAYA
PEKERJAAN GEOLISTRIK
Ria
2 PELAKSANAAN LAPANGAN
3 PEKERJAAN STUDIO
TOTAL Rp 34.150.000
ENGINEERING DOCUMENT LIST SOIL AND SLOPE REINFORCEMENT STUDY
SOW: CONSULTANT
DURATION
No DELIVERABLES SOW UNIT PRICE TOTAL PRICE Remark
(HOURS)
E.2 SPECIFICATION
Slope Reinforcement Specification 40 EXT 290.000 Rp11.600.000
Civil and Earth Work Specification 40 EXT 290.000 Rp11.600.000
E.3 CALCULATION
Slope Reinforcement Calculation 50 EXT 290.000 Rp14.500.000
Piling Calculation 50 EXT 290.000 Rp14.500.000
Road Calculation 50 EXT 290.000 Rp14.500.000
E.4 DRAWING
Piling Plan 30 EXT 290.000 Rp8.700.000
Piling Detail Drawing 40 EXT 290.000 Rp11.600.000
Slope Reinforcement Plant 30 EXT 290.000 Rp8.700.000
Slope Reinforcement Detail Drawing 40 EXT 290.000 Rp11.600.000
Cut and Fill Drawing Detail 40 EXT 290.000 Rp11.600.000
Topography Drawing 30 EXT 290.000 Rp8.700.000
Bathymetri Drawing 30 EXT 290.000 Rp8.700.000
TOTAL MH 590
Engineering Leader
Ir. KHAIRMEN SUARDI,
M.ENG, IPM
Project Manager
Resume
SUMMARY
Fiveteen years more of experience, mainly in various oil and gas industry in both
offshore and onshore Projects as a Lead or Sr. Mechanical (Static, Package &
Rotary) Engineer and Mechanical Field Engineer. Current role as Engineering
Manager on Engineering Project for Onshore Gas Plant.
A wide range of experience in Project Bids, Conceptual Design, FEED & Detailed
Engineering Design, Construction and Precommissioning/ Commissioning cover-
ing Green & Brown Field Project, Offshore WHP, Offshore CPP, Offshore Living
Quarter, Onshore Gas Plant, and Small Scale Gas Plant Development.
Familiar with international code and standard such as ASME, API, NFPA, ANSI,
ASTM, ISO, etc.
JOB OBJECTIVE
Seeking Eng. Manager/Lead/ Sr Mechanical / Pipeline Engineer position with a
company in which my skills and training can continue to advance
Ir. KHAIRMEN SUARDI,
M.ENG, IPM
Project Manager
Resume
EDUCATIONAL BACKGOURD
- Master Degree in Mechanical Engineering
- Degree in Engineering
EXPERIENCE
Oct 2015- Engineering Manager (Structural position)
Present
Key Job Responsibilities:
1. To look for any potential project and development of Company business.
2. Manage Company internal and external affair (Employee wages, Company Taxes, Gov regu-
lation, etc)
3. Lead a team for Preparing PQ and Technical and Commercial Proposal on Tender.
4. Manage people: Project Engineer, Lead Engineer, Project Control and Document Control to
run the project.
5. Responsible for Company Quality Product. .
6. Interdisciplinary coordination and interfacing with Client to ensure smooth execution of the
engineering work.
7. Responsible for Employee Skill and Knowledge development.
Latest Project
Resume
Okt 2017 –
Dec 2017 Engineering Manager – PT Consultant Enjinering
□ FEED and DEDC for City Gas in 4 location in Indonesia: Balik Papan; Penajam;
Musirawaas and Sidoarjo, Client: Ministry of Energy and Mineral Resources Republic
of Indonesia, End User: PT Perusahaan Gas Negara, PT Pertamina, PT Pertagas and
PT Chevron Indonesia
FEED and DEDC support to a pipeline and Interconnecting Gas City with Metering and Regu-
lating Station and Regulating Sector of feed gas capacity varies from 1.5 - 5 MMSCFD. Me-
tering and Regulating Station Equipments are: Gas Filter, Pressure Regulating Skid, Meter-
ing, Closed Drain Tank, Gantry Crane, all Instrumentation, piping and Valves.
Key Job Responsibilities:
1. Engineering Manager for Execution of FEED & DEDC works for all multidiscipline engineer-
ing work: Process, safety, piping, mechanical, Instrument and Control, electrical, Civil and
structure and plant design.
2. Responsible for all engineering deliverables such: Engineering Basis of design, Data Sheet,
Specification, Calculation and Sizing, detail Engineering Drawing, MTO and List.
3. PDMS 3D Modeling.
4. Hazid and Haazop activity.
5. Handling study and handling layout.
6. Owner Cost Estimate
7. Interdisciplinary coordination and interfacing to ensure smooth execution of the engineering
work between internal multidiscipline engineering and to external with Client and Vendor
Jun 2017 –
Lead Mechanical / Pipeline Engineer – Petro Vietnam Engineering, South Vietnam
Sept 2017
□ FEED Block B-O MOn Field Project, a Green Field Pipeline and Gas Distribution Sta-
tion/Gas Distribution Center, Client: Petro Vietnam POC Ltd (100 Million Project); End
User: South West Pipiline Operating Company (SWPOC)
SWPOC’s 28-inch subsea gas pipeline departs from offshore platform of Block B Field oper-
ated by Phu Quoc POC in Northeast direction to An Minh Landfall Station. At KP 209, the
pipeline branches to a 18-inch spur pipeline to approach Mui Tram Landfall Station. The 28-
inch main pipeline after approach to An Minh Landfall Station will run in east direction to ar-
rive at Kien Giang Gas Distribution Station (GDS) and feed Kien Giang Power Plant. The
sales gas will be transported to O Mon Gas Distribution Centre (GDC) via 30-inch diameter,
95km onshore pipeline
Key Job Responsibilities:
1. Lead Engineer for Execution of FEED engineering works for Static, Rotating and Package
such as: Launcher, Pressure Vessel with specific internal, Electric Heater, Filters, Over Head
Crane, emergency Diesel Generator, Closed Drain Pump (Air Operate PD Pump), Air Com-
Ir. KHAIRMEN SUARDI,
M.ENG, IPM
Project Manager
Resume
pressor and Dryer Package, Fuel Gas Package, FFG and Flare Tips Package, HVAC Pack-
age for Control Room, and Chemical Injection Package.
2. Responsible for Data Sheet, Design Basis, Specification, Preliminary Vendor Technical Eval-
uation Review.
3. Handling Study and Handling Layout of 5 Station (Anh Minh LFS, Mui Tram LFS, Kien Giang
GDS, O Mon GDC and LBV Station).
4. Interdisciplinary coordination and interfacing to ensure smooth execution of the engineering
work.
Jan 2016 –
Engineering Manager – PT Consultant Enjinering
Dec 2016
□DDfor EPCI Seberida Metering Station, Client: PT Yuan Sejati as Main Contractor,
E
End User: PT Transportasi Gas Indonesia
DED support to main contractor to develop a Metering Station of Feed gas capacity 100
MMSCFD. Metering plant Equipments are: Gas Filter, Pressure Regulating Skid, Metering,
Fuel Gas Conditioning unit, Fire Water Pump Package, Deep Well Pump, Water Treatment,
General Water Pumps, Diesel Engine Generator, Diesel pump, Diesel Tank, Air Compressor
Package, Closed Drain Tank, Gantry Crane, Switch yard, Trafo and Substation, DCS Plant
Control System, all Instrumentation, piping and Valves.
Key Job Responsibilities:
1. Engineering Manager for Execution of DED works for all multidiscipline engineering work:
Process, safety, piping, mechanical, Instrument and Control, electrical, Civil and structure
and plant design.
2. Responsible for all engineering deliverables such: Engineering Basis of design, Data Sheet,
Specification, Calculation and Sizing, detail Engineering Drawing, MTO and List.
3. PDMS 3D Modeling.
4. Hazid and Hazop activity.
5. Handling study and handling layout.
6. Interdisciplinary coordination and interfacing to ensure smooth execution of the engineering
work between internal multidiscipline engineering and to external with Client and Vendor
7. Precommisioning, commsiioning and star up activity for Plant.
Oct. 2015 – Engineering Manager & Lead Pipeline Eng – PT Consultant Enjinering
Des 2015
□ FS, FEED and DED for Pipeline and New Offtake Station, Client: PT Indo Cipta
Gemilang as Main Contractor, End User: PT Cipta Niaga Gemilang
A complete service from FS, FEED and DED study to develop a 2.751 km Pipeline and new
Offtake station consist of Metering Station, Gas Engine Power Plant (IPP), and Compressed
Natural Gas (CNG) Plant The Feed gas is 5 MMSCFD, to devided into 3 MMSCFD for Gas
Engine Power Plat in equal to 12 MW Electrical Power; and 2 MMSCFD for CNG Plant.
Equipments are: Gas Filter, Pressure Regulating Skid, Metering, Fuel Gas Conditioning unit,
Ir. KHAIRMEN SUARDI,
M.ENG, IPM
Project Manager
Resume
Gas Engine, Gas Dryer, Compact Gas Compressor with ACHE, Fire Water Pump Package,
Deep Well Pump, Water Treatment, General Water Pumps, Diesel Engine Generator, Diesel
pump, Diesel Tank, Air Compressor Package, Closed Drain Tank, Gantry Crane, Switch yard,
Trafo and Substation, DCS Plant Control System, all Instrumentation, piping and Valves.
Key Job Responsibilities:
1. Engineering Manager for Execution of FS, FEED and DED works for all multidiscipline engi-
neering work: Process, safety, piping, mechanical, Instrument and Control, electrical, Civil
and structure and plant design.
2. Responsible for all engineering deliverables such: Feasibility Study, Environmental Study,
Waste Management, Engineering Basis of design, Data Sheet, Specification, Calculation and
Sizing, detail Engineering Drawing, MTO and List.
3. PDMS 3D Modeling.
4. Hazid and Haazop activity.
5. Handling study and handling layout.
6. Interdisciplinary coordination and interfacing to ensure smooth execution of the engineering
work between internal multidiscipline engineering and to external with Client and Vendor.
7. Precommisioning, commsiioning and star up activity for Plant.
Resume
2. Responsible for Data Sheet, Design Basis, Specification, Preliminary Vendor Technical Eval-
uation Review.
3. Handling Study and Handling Layout of KNT Wellhead platform.
4. Lead Engineer for Preliminary Study on Solar Turbine Taurus 60 Set for any Interface Engi-
neering.
5. Interdisciplinary coordination and interfacing to ensure smooth execution of the engineering
work.
Oct. 2014 –
April 2015 Lead Mechanical Engineer – PT. Meindo Elang Indah
□ FEED Tank Farm Project Nilam Utara East Java (FEED for a Green Field Chemical Tank
Farm Facilities), Client: PT AKR
A FEED study to develop Chemical Tank Farm at Nilam Utara, east Java. To develop Tank
Farm station to storage CPO, Petrol, Diesel and Molases. Total Plant Capacity of 188,000
Tons, with 4ea Diesel Tank at 20,000 KL, 4ea Petrol Tank at 7,500 KL, 4ea Mollases Tank at
7,500 KL, 6ea CPO Tank at 5,000 KL, and 6ea CPO Tank at 3,000 KL .
Key Job Responsibilities:
1. Lead Mechanical Engineer for Execution of FEED works for Static and Rotating and Package
such as: Erected Tank with self-support roof and Column Support (CPO, Petrol, Diesel and
Molases), Air Compressor Package, Utility and Instrument Air Receiver Vessel, API 610 Cen-
trifugal Pump and Fire Water Pump Package.
Resume
Vendor review.
3. Handling Study and Handling Layout of KLA, KLB and KLC Wellhead platform.
4. Lead Engineer for Solar Turbine Saturn 20 MK III Tandem Compressor Set for any Interface
Engineering.
5. Follow on phase vendor fabrication.
6. Provide assistance on Site Installation work, Commisioning and Star up to the Construction
and Commissioning team.
7. Interdisciplinary coordination and interfacing to ensure smooth execution of the engineering
work.
8. Precommisioning, commsiioning and star up activity for Plant.
Jan. 2014 – □ GG New Development Project (a Green Field GGA NUI Well head Platform and
June 2015 OPF Gas processing Facilities), Client: PT PHE ONWJ (172 Million Project)
Key Job Responsibilities:
1. Lead Engineer for Execution of detailed engineering works for Static and Rotating and
Package such as: Launcher, Receiver, Slug Catcher, other Pressure Vessel with specific in-
ternal, Electric Heater, Filters, Flares Package, Nitrogen Package, Field Erected Tank, In-
dustrial Tank, API 610 centrifugal pump, Deep well pump, ANSI high Pressure pump, Over
Head Crane, Fire Water Pump, Gas Engine Generator, Air Compressor and Dryer Package,
TEG Package, Air Operarated Diaphragm Chemical Injection package, RO package, Jib
Crane (Hydraulic driven).
2. Responsible for Data Sheet, Design Basis, Specification, Technical Evaluation and Detail
Vendor review
3. Handling study and handling layout
4. Follow on phase Vendor fabrication
5. Interdisciplinary coordination and interfacing to ensure smooth execution of the engineering
work.
6. Precommisioning, commsiioning and star up activity for Plant
Ir. KHAIRMEN SUARDI,
M.ENG, IPM
Project Manager
Resume
Resume
1. Lead Engineer for Execution of detailed engineering works for Water Injection Pump
Package with 1.1 MW Electric motor, Valves and piping, Instrumentation, electrical,
Unit Control Panel and skid structural.
2. Lead Engineer for Execution of detailed engineering works for Biocide Injection Pump
Package, Valves and piping, Instrumentation, electrical, Unit Control Panel and skid
structural
3. Responsible for Data Sheet, Specification, Technical Evaluation and Detail Vendor re-
view
4. Handling Study and Handling Layout of EHMR Project.
5. Interdisciplinary coordination and interfacing to ensure smooth execution of the engi-
neering work
6. Follow on phase on Vendor Fabrication
7. Provide assistance on Site Installation work, Precommisioning, Commisioning and
Star up working with to the Construction and Commissioning team
Resume
2. Package Engineer for Execution of detailed engineering works for mechanical Static
equipment covering Launchers, Vessel Drums, Scrubbers, Heaters, ACHE, Filters and
ISO Tanks.
3. Package Engineer for Execution of detailed engineering works for Potable Water
Packages covering RO Water Maker Package, High Pressure Pumps, Potable Water
Tanks Package, Potable Water Pumps and Filters Package, UV Sterilizer Package
and Hot Water Calorifier Package, Valves and piping, Instrumentation, electrical and
skid structural.
4. Package Engineer for Execution of detailed engineering works for Chemical Injection
and Methanol Injection Package covering PD Pumps, Tanks, Valves and piping, In-
strumentation, electrical and skid structural.
5. Package Engineer for Execution of detailed engineering works for Hypochorination
Package covering Electrolitic Cells Generator, Tanks, Centrifugal pumps, Blowers,
Valves and piping, Instrumentation, electrical and skid structural.
6. Interdisciplinary coordination and interfacing to ensure smooth execution of the engi-
neering work.
7. Package Engineer for assistance on Site Installation work, Commisioning and Star up
phase for Launchers, Vessel Drums, Scrubbers, Heaters, Iso Tanks, RO Water Maker
Package, Potable Water Tanks Package, Potable Water Pumps and Filters Package,
UV Sterilizer Package and Hot Water Calorifier Package, Chemical Injection and
Methanol Injection Package.
8. Provide assistance on Site Installation work, Precommisioning, Commisioning and
Star up working with to the Construction and Commissioning team
Dec. 2007 – Sr. Engineer / Temporary Lead Mechanical Eng – PT. Rekayasa Industri
Dec. 2008
Green Field Onshore Propylene Plant (ROPP) Project – Client: PT. Pertamina UP VI –
Balongan, Indramayu – West Java. (248 Million Project)
2. Temporary Lead Engineer for Execution of detailed engineering works works for all
mechanical Static equipment covering Towers (highest tower 100mtrs), Vessel Drums
and Dryers, Filters, Electric Heaters, Spherical Tanks, Shop and Field Tanks (fixed
Cone Roof), Fin Fan Coolers, STHE, Brazed HE, Cold Box, Reactors and boilers.
3. Performing bid evaluation, vendor selection, and vendor print review for all mechani-
cal static equipment.
Resume
>a Green Field Onshore LPG processing Project - Client: PT LPG Lembak at Lembak,
South Sumatra, Indonesia
• Tender proposal for Ulumbu Geothermal Power Plant 2x2.5 MW project (as engineer), responsi-
ble for design engineering for Pressure Vessel, Tanks, Heat Exchanger, HRSG, HVAC and
Ir. KHAIRMEN SUARDI,
M.ENG, IPM
Project Manager
Resume
pumps.
□ Tender proposal for Energi Musi Makmur Gas fired Power Plant 4 x 58 MW project (as coordina-
tor engineer) , responsible for design engineering for Pressure Vessel, Tanks, Heat Exchanger,
HRSG, HVAC and pumps.
□ Tender proposal for Indo Medco Power Gas Fired Power Plant 2x 40 MW project (as engineer),
responsible for design engineering for Pressure Vessel, Tanks, Heat Exchanger, HVAC and
pumps.
□ Tender proposal for Gas Booster Station Project (as engineer); Client: PT. Transportasi Gas In-
donesia, responsible for design engineering for Pressure Vessel, Tanks, Heat Exchanger,
HVAC and pumps.
• Tender proposal for Oil Processing Facilities and LPG Facilities Ujung Pangkah Liquid Devel-
opment Project (as engineer); Client: Amerada Hess (Pangkah – Indonesia) Limited, responsi-
ble for design engineering for Pressure Vessel, Column Treating Vessel, LPG Storage Sphere,
Electrostatic Treater, Field Erected Tanks, Heat Exchanger, HVAC and pumps. Proposal was
the winner for project execution.
• Tender proposal for Floating Roof Oil Storage Tanks Project (as engineer); Client: Amerada
Hess (Pangkah – Indonesia) Limited, responsible for design engineering for Floating Roof Oil
Storage Tanks. Proposal was the winner for projectexecution.
• Tender proposal for Oil Processing Facilities Jambi Merang Liquid Development Project (as en-
gineer); Client: JOB Amerada Hess – Pertamina, responsible for design engineering for Pres-
sure Vessel, Column Treating Vessel, LPG Storage Sphere, Electrostatic Treater, Field Erected
Tanks, Heat Exchanger, HVAC and pumps.
March 2001 – Maintenance Engineer – PT Trimanggada Nusantara Lines-Gear Bulk Ag, Jakarta
July 2002 Indonesia
Resume
1. Monitoring Vessel Maintenance Scheme Plan, responsible for any maintenance on struc-
tural, static and rotating equipments on ship.
2. Monitoring and Coordinating any Ships Repair and Material Order.
3. Monitoring and Prepare any Ships Certificate.
4. Internal Auditor for ISM CODE and ISO 9000.
5. Assisting Superintendent in Vessel Dry Docking.
Registrations/Affiliations
- Persatuan Insinyur Indonesia (PII) , Member no: 0901.09.025010
- Registered as level “Insinyur Professional Madya (IPM), SIP No: 0901.09.025010. The
level in equal to PE or ASEAN Professional Certified Engineer.
- Registered and certified as “Ahli Mekanikal Madya”, from Lembaga Pengembangan Jasa
Konstruksi (LPJK), no registration: 1.2.301.2.142.04.1087020.
Publications/Presentations
1. E. Hamzah, K. Suardi, A. Ourdjini and K.W.Lau. 2002. Effect of heat treatment on microstructure and
properties of γ-base titanium aluminide. Proc. 11th Scient. Conf. E.M.S of Malaysia: 103 – 110.
2. E. Hamzah, K. Suardi, A. Ourdjini and K.W.Lau. 2003. Effect of cooling rate on the microstructures
and hardness of γ-base titanium aluminide. Proc. 3rd Int. Conf. R.A.M 2003: 416 – 424.
3. Khairmen Suardi, E. Hamzah and A. Ourdjini. 2003. Effect of alpha-2 and gamma phases on the sus-
ceptibility to hydrogen attack of gamma-base titanium aluminide. Proc. Conf. Malaysian Science
and Technology Congress: 98.
4. E. Hamzah, Khairmen Suardi, A. Ourdjini. 2003. Corrosion behavior of heat treated gamma-base tita-
nium aluminide after hydrogen attack under immersion in 1.0 m sulfuric acid solution. Proc. 12th Sci-
ent. Conf. E.M.S of Malaysia: 134 – 143.
5. E. Hamzah, Khairmen Suardi, and A. Ourdjini. 2004. Effect of chromium content on titanium alu-
minide due to hydrogen attack under immersion in severe acid solution. Proc. 4th Int. Mat. Tech. Conf.
Exh: 600- 608.
6. Khairmen Suardi , E.Hamzah and A.Ourdjini. 2004. Effect of heat treatment on the diffusion coefficient
of hydrogen absorption in gamma titanium aluminide. Proc. 3rd Int. Conf. Adv. Man. Tech (accepted
for oral presentation on May, 11th – 13th 2004).
7. E.Hamzah, K. Suardi and A.Ourdjini. 2004. Effect of microstructures on the hydrogen attack to gamma
titanium aluminide at low temperature. Proc. First Cappadocia Int. Mech. Eng. Sym. (accepted
for oral presentation on 14- 16 July 2004 at Cappadocia, Turkey).
8. K. Suardi, E. Hamzah and A.Ourdjini, 2004, X-ray diffraction Analysis on Gamma Titanium Aluminide
Subjected to Hydrogen Attack. Proc. ICXRI-2004 Int. Conf. on X-Rays and Related Techniques in Re-
th th
search and Industry (accepted for oral presentation on September, 15 -16 2004 at Penang Malay-
sia).
9. E. Hamzah, K. Suardi and A. Amrin, Applicability of Titanium Aluminides in Oil and Gas Production.
Proc. Int. Conf on Material Selection, Application and Inspection for Upstream Oil and Gas (accepted
th th
as keynote speaker paper on September, 28 -29 at Kuala Lumpur).
Ir. KHAIRMEN SUARDI,
M.ENG, IPM
Project Manager
Resume
10. E. Hamzah, K. Suardi, A. Amrin. High and Low Temperature Corrosion Behavior of Gamma Titanium
Aluminide. Proc. 13th Scient. Conf. E.M.S of Malaysia 2004 (accepted for keynote speaker presenta-
tion on December 2004 at Putra Jaya, Kuala Lumpur).
K. Suardi, E. Hamzah and A. Ourjini. Hydrogen Attack on Chroium Added γ-Ti-48%Al. Proc. 8 Inter-
th
11.
th
national Conference on Quality in Research 2005. (Accepted for oral presentation on 8-9 August
2005, FTUI Depok Indonesia).
E. Hamzah, K. Suardi and A. Ourjini. Hydrogen Attack on Heat Treated γ-Titanium Aluminide. Proc. 2
nd
12.
th
Asian Conference on Material Science and Technology (Accepted for oral presentation on 5-6 August
2005, LIPI Jakarta, Indonesia).
1. E. Hamzah, K. Suardi, A. Ourdjini and K.W.Lau. 2003. Effect of heat treatment on microstructure and
hardness of g- base titanium aluminide (TiAl). Journal Ins. Mat. Mal. 4: 83 – 101.
2. Khairmen Suardi , E.Hamzah, A.Ourdjini and V.C. Venkatesh. 2004. Effect of heat treatment on the
diffusion coefficient of hydrogen absorption in gamma titanium aluminide. Journal Mat. Proc. Tech.
Elsevier. (accepted for publication).
3. E. Hamzah, Khairmen Suardi, and A. Ourdjini. 2004. Effect of chromium content on titanium alu-
minide due to hydrogen attack under immersion in severe acid solution. Journal Ins. Mat. Mal. (accept-
ed for publication).
5. E.Hamzah, K. Suardi and A.Ourdjini. 2004. Effect of microstructures on the hydrogen attack to gam-
ma titanium aluminide at low temperature. Journal Material Science and Engineering Part A. 397/1-
2: pp. 41-49.
• Compress
Resume
• Design and Inspection for Fire Heater, Shell and Tube HE, Boiler, ACHE, PHE, held by PT Rekayasa In-
dustri Engineering and Constructors, May, 4th 2006.
• Design and Inspection for Packaged Unit in Oil and Gas Industry, held by PT Rekayasa Industri Engineer-
ing and Constructors, June, 4th 2006.
•
th
Inspection for Blasting and Painting, held by PT Rekayasa Industri Engineering and Constructors, June, 7 -
th
11 2007.
• Quality Control Manual, held by PT Rekayasa Industri Engineering and Constructors, November, 14th
2006.
• Process Welding Quality, held by PT Rekayasa Industri Engineering and Constructors, November, 13th
2006.
• Tank design and calculation (Tank Coade Application), held by PT Tripatra Engineering and Constructors,
May, 11 - 12 2006.
• Vessel Design and Calculation (PV elite application), held by PT Tripatra Engineering and Constructors,
May, 9 - 10 2006.
• Piping engineering, piping design and piping standard and code, held by PT tripatra Engineering and Con-
structors, December, 1st 2005.
• Valves and its application, held by PT Tripatra Engineering and Constructors, December, 30 2005.
• Pumps and its application, held by PT Tripatra Engineering and Constructors, January, 9 2006.
• Short Course on Risk Base Inspection, held by Faculty of Chemical Engineering Dept. Petroleum Engi-
neering UTM, July 5 – 8, 2004.
• Workshop on advance metallography technique and microstructure analysis for engineering application,
April 9-10 2003, Skudai UTM.
• Superintendent Vessel Maintenance Engineer Course (Role of Superintendent, Ships maintenance, Class
regulation, IMO/IACS regulations, Ships rules and regulations, Project Costing). Held by DNV Indonesia,
th th
Bandung Indonesia, June 8 -13 2002.
• ISM CODE Internal Auditor Course, Held by Biro Klasifikasi Indonesia (BKI), Puncak Indonesia, October,
th th
24 -26 2001.
• Course and Exercise on: Introduction, Documentation technique and Internal Quality Audit of ISO 9000,
April 5 – 8 2000, Bandung Indonesia, held by Lembaga Bantuan Management Indonesia.
• English Language Course on Conversation Class,January – November 2000 at Lembaga Bahasa Asing
LIA ,Jakarta.
• 11th Scientific Conference on Electron Microscopy Science of Malaysia, 12-15 December 2002, Stulang
Laut Johor Bahru Malaysia, as author and presenter of scientific paper.
• Conference of Malaysian Science and Technology Congress, 23-25 October 2003, Kuala Lumpur Malay-
sia, as author and presenter of scientific paper.
• 3rd International Conference on Advance Manufacturing Technology, 11-13 May 2004, Kuala Lumpur Ma-
laysia, as author and presenter of scientific paper.
• ICXRI-2004 International Conference on X-Rays and Related Techniques in Research and Industry, 15-16
September 2004, Penang Malaysia, as author and presenter of scientific paper.
•
nd
2 Asian Conference on Material Science and Technology, 5-6 August 2005, Jakarta Indonesia, as author
and presenter of scientific paper.
•
th
8 International Conference on Quality in Research 2005, 8-9 August 2005, Depok Indonesia, as author
and presenter of scientific paper
Organization
Past
Resume
• Chief of external relation division at Indonesian Student Society Organization-UTM, July 2003- July 2004.
• Member of Institution Materials Malaysia, July 2002 – June 2005.
Present
Page 1 of 4
ARYO PRIBADI WICAKSONO
SENIOR PROCESS ENGINEER / CORROSION ENGINEER
The responsible for this project are checking and approving and Compression System, located in North Java Sea, West
detailed process engineering document such as: Java. The facility consists of Separator, Closed Drain,
♦ Project Design Basis Compressor, and Pump.
♦ Flowline, Trunkline, & Pipeline Philosophy Responsibilities:
♦ PFD and P&ID ♦ PFD and P&ID
♦ Flowline, Trunkline & Pipeline Hydraulic Simulation ♦ Equipment Sizing Report
♦ PSV and BDV Sizing ♦ Line Sizing Report
♦ Line Sizing & Line List ♦ Relief and Blowdown Study
Page 2 of 4
ARYO PRIBADI WICAKSONO
SENIOR PROCESS ENGINEER / CORROSION ENGINEER
Responsibilities: ♦ Prepare line sizing
♦ Prepare PFD and P&ID UL Field Development ♦ Prepare Process Data Sheet
♦ Optimization and De-bottlenecking study report
♦ Relief and Drain calculation June 2007 – February 2009
♦ Shutdown Philosophy PT. LOKA WAHANA USAHA – Subsidiary of PT. PRIME
PETROSERVICES, EPCI and Rental Oil and Gas
March 2009 – Dcember 2011
PT. SINGGAR MULIA – ENGINEERING CONSULTANTS Position held:
Process Engineer
Position held:
Process Engineer Project:
PT KALILA (BENTU) LIMITED – Seng and Segat Field
Project: Development. This project covered engineering of new Gas
Plant located at approximately 90 km South East from Pekan
CHEVRON MAKASSAR LIMITED – Bullhead System Baru, Riau Province, Sumatra Island. The facilities consist of
Upgrade. This project covered installation of Bullhead Separator, Gas Scrubber, Glycol Dehydration Unit, and Liquid
System at TLP-A West Seno Facilities, located in Makassar Tank with capacity 60 MMSCFD.
Strait, East Kalimantan. The Bullhead System consists of Responsibilities:
Bullhead Tank, Bullhead Charge Pump, Diesel Filter, ♦ Prepare PFD and P&ID
Bullhead Pump, and Electric Heater. ♦ Prepare line sizing
Responsibilities: ♦ Equipment sizing (Separator, Gas Scrubber, KO Drum,
♦ Prepare PFD and P&ID Bullhead System Upgrade KO Drum Pump)
♦ Prepare line sizing ♦ HYSYS simulation
♦ Calculation (Utility Consumption, Relief Load) ♦ PIPESIM simulation
♦ Prepare Process Data Sheet ♦ Flare Sizing and Radiation Study
♦ Prepare Process Data Sheet
Project:
CHEVRON MAKASSAR LIMITED – Oil Surge Tank West Project:
Seno. This project covered re-using of Void Tank to Oil Surge PT. INDOGAS KRIYA DWIGUNA – Installation of CNG
Tanks at FPU West Seno Facilities, located in Makassar Compressor. This project covered installation of compressor
Strait, East Kalimantan. for CNG Facility.
Responsibilities: Responsibilities:
♦ Prepare PFD and P&ID ♦ Prepare line sizing
♦ Prepare line sizing ♦ Vent Sizing and Radiation Study
♦ Prepare Process Data Sheet
Project:
Project: PT SEMBERANI PERSADA OIL – Pipeline Semberah
SBM OFFSHORE – FLNG Lease Feasibility Study. This Binangat Project. This project covered engineering of
project covered FLNG feasibility study located at MASELA, pipeline SEMCO UKM4 to VICO
Maluku. The facility consists of Scrub Column, De-Ethanizer, Responsibility:
De-Propanizer, and De-Butanizer. PIPESIM simulation
Responsibilities:
♦ Prepare PFD Project:
♦ Prepare line sizing PT INSANI MITRSANI GELAM – Gelam Gas Production
♦ Equipment sizing (Scrub Column, De-Ethanizer, De- Facility. This project covered engineering of new Gas Plant
Propanizer, and De-Butanizer) located at Jambi Province, Sumatra Island. The facilities
♦ Prepare Process Data Sheet consist of Separator, Glycol Dehydration Unit, and Liquid
Tank with capacity 2.5 MMSCFD.
Project: Responsibilities:
PETROCHINA INTERNATIONAL JABUNG Ltd. – Betara ♦ Prepare line sizing
Complex Development Phase 4. This project covered ♦ Equipment sizing (Fire Water Demand, Fire Water
detailed engineering of Inlet Compression Betara Gas Plant Pump, Instrument Air, KO Drum Pump)
(BGP) located at Jambi Province, Sumatra Island. The ♦ HYSIS simulation
facilities consist of Slug Catcher, Gas Scrubber, Compressor, ♦ Flare Sizing and Radiation Study
and Cooler with capacity 100 MMSCFD.
Responsibilities: Project:
♦ Prepare PFD and P&ID Inlet Compression Betara Gas PT INDELBERG INDONESIA PERKASA – Suci Gas
Plant (BGP) Production Facility. This project covered engineering of new
♦ Remark PFD and P&ID Gas Recovery Facilities (from Gas Plant located at Gresik, East Java Province. The facilities
FEED document) consist of Production Separator, Liquid Tank, CO2 Removal,
♦ Prepare line sizing Desiccant Dehydration Unit, Custody Meter, KO Drum, and
♦ Equipment sizing (Slug Catcher, Gas Scrubber, Ground Flare with capacity 10 MMSCFD.
Compressor, Cooler) Responsibilities:
♦ HYSYS version 7 simulation ♦ Prepare Process Design Basis
♦ Prepare Process Data Sheet ♦ Prepare PFD and P&ID
♦ Prepare line sizing
Project: ♦ Equipment sizing (Production Separator, Liquid Tank,
EXXON MOBIL– Arun Cluster Liquid Consolidation Phase KO Drum Pump)
2. This project covered installation of produced water pump ♦ HYSYS simulation
for Condensate Water Separator Facility. ♦ Flare Sizing and Radiation Study
Responsibilities:
♦ Prepare PFD
Page 3 of 4
ARYO PRIBADI WICAKSONO
SENIOR PROCESS ENGINEER / CORROSION ENGINEER
Project :
KANGEAN ENERGY INDONESIA – Water Treatment
Upgrade. This project covered installation new Production
Separator, Produced Water Pump, Produced Water
Separation Pump, Hydrocyclone, Hydrocyclone Pump and
Water Treatment Unit for Sepanjang Oil Production Facility
located at Sepanjang Island is located 35 km south of
Pagerungan Besar Island, East Java, Indonesia.
Responsibilities:
♦ Prepare PFD and P&ID
♦ Prepare line sizing
♦ Equipment sizing (Production Separator, Produced
Water Pump, Produced Water Separation Pump,
♦ Hydrocyclone Pump, Instrument Air Demand, and Air
Receiver)
♦ HYSYS simulation
♦ Prepare line list
♦ Prepare equipment list
♦ Prepare SAFE CHART
I, the undersigned, certify that to the best of my knowledge and believe, the bio data contained in this CV
correctly describe myself, my qualifications and my expertise. I, hereby agree and commit to be assigned
during the contract period to perform the Work within specified time frame as defined in each Work Order.
Page 4 of 4
ATTACHMENT PERSONEL’S CURRICULUM VITAE
Summary
Experiences in civil design, construction stage and project management for 13 years
extensive experiences throughout international and national project, combine advance
engineering knowledge and site application method.
- My capacity in design and analysis structure i.e general design steel structure & concrete
structure, define loading, define load combination, define specific member of beam &
column, calculated member capacity, calculated steel connection, calculated concrete
reinforcement, detailing concrete reinforce length development,
Determined single pile bearing capacity and soil bearing capacity from CPT & SPT data,
calculate deep pile foundation type, shallow foundation type and calculated heavy
machinery foundation (dynamic) type.
- My capacity in construction work involved in calculated and arrange heavy lifting structure
and equipment (define SWL crane, calculate Pad eye/lifting lug), preparing construction
method and installation procedure. And familiar in project management application such
controlling schedule & budgeting, MTO, pricing and Vendor Evaluating.
Education
Bachelor Degree, Civil Engineering, Engineering Faculty, Gadjah Mada University (2000-2005)
(GPA 3.42/4.00) Academic Paper: Homogenous Soil Embankment Stability Analysis by finite
element method.
Agus Suryantoro, ST, IPM
Mobile Phone: +62 812 197 190 77 (Indonesia)
Works Experiences
Employer: CONSULTANT ENGINEERING
Position : Project Lead Engineer
Period : 01 Jan 2017– Present
Project : FEED - Gas Pipeline Development for domestic
consumption.
Key Skill: Project management, Engineering Design, STAAD Pro,
AutoCAD, Ms. Excel, MTO & BoQ,
Report to: Project Director
Job description / Responsibility:
Coordinate interface discipline, mechanical, pipeline, E&I and civil, developing
topographic survey and consumer location become optimum pipeline alignment.
Provide engineering calculation for structure, foundation shelter Metering, Regulating
and Station. Structure modeled as frame with pin connection at foundation (material
ASTM A36/SS-400), connection bolt as fix connection at frame type, and pin type in
structure modeled as truss member (ASTM A-325M), structure design by STAAD Pro as
per AISC-ASD.
Provide engineering calculation for pipe support (gathering pipeline diameter 12”) and
foundation itself. Pipe support by WF profile and pipe sch.40 and connection type use
fillet welding electrode E60xx (WPS and PQR approved).
Approved, review, design and drawing before submitted to client (ESDM / Energy and
Mine Resources Ministry). Review engineering drawing and fabrication drawing as per
standard drawing.
Prepared overview and calculation presentation to client.
Developing calculation procedure, basic civil philosophy.
Interfacing with others discipline, developing communication system among them.
Monitoring project progress, planning the recovery and speed up strategy to achieved
the target.
Page 2 of 9
Agus Suryantoro, ST, IPM
Mobile Phone: +62 812 197 190 77 (Indonesia)
1) Sludge Catcher modification, modified existing catcher with new finger type catcher
due to pipeline pigging activity. foundation precast concrete, upper structure steel
frame, tapping to existing live pipeline (Hot Tapping), lifting precast on brown field area.
2) BOG cliff Protection, to protect cliff from abrasion by putting geo bag layer in cliff toe,
and next project to be strengthened by pumping dredging mud in front of cliff.
3) CWAA refurbishment, upgrading existing wood structure with new steel structure in
area incinerator, chipper, composter and loading-unloading waste material.
4) NEW Potable Tank dormitory area, Build new potable tank to increase the capacity
water storage due to additional worker on board.
5) BOG Dehumidifier modification, to optimized instrumentation perform of BOG shall be
equipped by dehumidifier (controlling temperature and moist)
6) Road patrol & securities project, upgrading quality road patrol and security facility.
Develop Job safety analysis, level 1 Task Risk Assessment (for routine activities), level 2
Task Risk Assessments, and brought to high level risk assessment based on 8x8
probability-severity diagram, Deliver major safety campaign program to contractor
worker by daily tool box, safety tool box meeting and monthly safety town hall meeting.
Monitoring project under civil blanked contract, performance schedule (SPI), Commercial
Performance (CPI), and Earn Value management. Make a planning of manpower,
equipment and material when it shall be mobilized and demobilization.
Ensure the project execution by prepared activities planning for 2 Weeks ahead, 4 Weeks
ahead, 8 Weeks look ahead before execution, including administration, material,
engineering document, and budget. Submit our planning to maintenance and logistic
department as highlight activities to be considered.
Supervised project execution to guarantee that project will be done as per ITP, schedule
and budget AFE (Authorization for Expenditure) approved by SKK Migas.
Prepared Project Execution Plan / Construction method statement for work pack above,
including lifting arrangement and engineering calculation.
Interface coordination among department, to support the project success, logistic
infrastructure, lifting team, workshop team, maintenance team, operating team and
engineering team.
Page 3 of 9
Agus Suryantoro, ST, IPM
Mobile Phone: +62 812 197 190 77 (Indonesia)
axial and truss connection type), dimension check and quantity of material.
Material erection preparation. Coordinate with warehouse to provide material steel
structure and its part accessories that would be erected.
Construction phase:
Due to actual condition, that is way almost designs need to adjust and redesign.
Majority reasons was existing structure clashing with new structure, the as-built
drawing are not update as per actual condition and interface or interference
between others discipline.
Prepared Field Changed Sheet if our design needs to modified, Site Query if we need
to disturb the owner exiting facility, Site Instruction if we need to inform additional
work / out of scope to our subcontractor (Modern Arab Contractor).
Prepared lifting plan including crane arrangement, lifting accessories detail, valid
certificate (operator and equipment tagging)
Prepared engineering calculation to support site engineering decision, Prepared
structure material prior steel structure erection, develop schedule and method
installation.
Define work sequence; define potential hazard, prepared (TRA) Task Risk Assessment
and conduct tool box meeting prior activity.
Coordinate our subcontractor, monitoring and reporting progress activity to site
manager.
- Define design LOADs, (1) Dead Load, (2) LIVE Load, (3) Equipment Load, (4) Pipe rack
& cable tray Load, (5) Wind Load, (6) Seismic Load, (7) Impact Load, (8) Thermal Load,
(9) Bundle Pulling Load, (10) Blasting Load, (11)
- Define typical Load combination for Allowable stress design or Strength design
(LRFD)
-Check the steel member stress ratio (Beam, column, truss), checking the connection
capacity for Shear connection type, moment connection type, and axial connection
type, checking the structure stability (Deflection L/200, Sway H/200), and checking
the slenderness of steel member.
- for dynamic structure or shelter that coverage the dynamic machine shall check the
resonance between structure natural frequency and machine frequency (30% below
or 130% above the frequency of machine.)
2) Pile foundation design for Brain reactor structure, Caustic soda structure, Chloride
structure, substation building. Determined the pile capacity from CPT and N-SPT soil
investigation (Axial and lateral capacity), determined the requirement/number of pile
in every structure column.
3) Shallow foundation design for pipe rack, shelter, sleeper, lighting pole, small pump,
and small transformer. Check the stability overturning, settlement (1 inc) and sliding,
checking the soil bearing capacity and compare with soil capacity as per soil
investigation.
Structure software design template (STAAD Pro)
3D isometric review design with others discipline by Navis Frame work.
Update standard drawing based on client standard.
Vendor review drawing. (dimension, connection, welding symbol, as per standard
drawing)
Page 6 of 9
Agus Suryantoro, ST, IPM
Mobile Phone: +62 812 197 190 77 (Indonesia)
Organization Experience
2013 – Present Project Management Instituted
2013 – Present PII (Persatuan Insinyur Indonesia), member no. 0905-15-032575
Certificate number.: 2-15-00-000718-00
2007 – Present KMI “Komunitas Migas Indonesia”
2013 – Present IAFMI (Ikatan Ahli Fasilitas Migas Indonesia)
2005 – 2006 Trainer, Plaxis Geotechnical Software course, Computer Laboratory of
Civil Department and lecture assistant.
Page 7 of 9
Agus Suryantoro, ST, IPM
Mobile Phone: +62 812 197 190 77 (Indonesia)
2004 – 2005 Vice Head of Civil Engineering Assistance Corps, Civil Engineering Dept.
2004 Head of Assistant Grant Committee, Civil Engineering Dept.
2003 – 2004 Lecture Assistant for Foundation engineering, Irrigation Engineering and
Concrete Technology
STAAD Pro: advance, AUTOCAD-2D: good, Ms. Project: Good, SAP2000: good, PLAXIS: good,
Navis Frame Work: good, Ms. Office: advance, Math cad: good.
REFERENCE
Page 8 of 9
Agus Suryantoro, ST, IPM
Mobile Phone: +62 812 197 190 77 (Indonesia)
Ir. Edi Zanuar Muhtadi, Civil Section Head Department PT. Pertamina EP Cepu
Ir. AAB. Partha Wijaya, Project & Modification Team Leader British Petroleum Berau,Ltd
Page 9 of 9
ATTACHMENT PERSONEL’S CURRICULUM VITAE
ORGANIZATION
EXPERIENCE
CONTACT INFO • Periode 2017-2018
Mobile Phone : Microsoft office (word, excell, power point), AutoCAD, SketchUp,
085895968401 ETABS, SAP, STAAD.Pro
Marital Status : • Asisten Dosen Ilmu Ukur Tanah, Universitas Bakrie (2018)
Single • Asisten Dosen Gambar Teknik, Universitas Bakrie (2018)
• Asisten Laboratorium Fisika, 2018 (2018)
• Asisten Dosen Ilmu Ukur Tanah, Universitas Bakrie (2019)
• Supervisor at PT. Wiratman Cipta Manggala (2019)
- Thamrin Nine Tower Project
• Structure Engineer 2019-Present)
- 8 km Pipeline Riau Segat and Seng, Pipeline Detail Construction
(2019-2020), on progress
- 7 km NEB#1 Basement Pipeline Construction Detail Design (2019-
2020), completed
- 2 km Sabar#2 Sub-Gathering Line Detail Design (2019),
completed
- GTG and WHRU Instalation at BGP, 1 x 20 MW Power Plant
(2019-2020), on progress
- Boat Crane 150 Ton (2019-2020), on progress
- CPF Bangkudulis (2019-2020), on progress
Scope of work
- Develop calculation sheet for structure and foundation
- Develop drawing for structure and foundation
Declaration:
I declare that all information provided on this CV above (provided by myself) is absolutely true
to the best of my knowledge.
Author
Personal Information
Name : Ilham Fakhrurrozi
Place/Date of Birth : Bekasi/26-09-1996
Gender : Laki-Laki
Religion : Islam
Nationality : Indonesia
Phone Number/E-mail : 0895330705622
aim.fi.642@gmail.com
Alamat : Jl.kelimutu M.5 Komp.Kodau V Rt/Rw 004/02
Kel.Jatimekar Ke.Jatiasih Kota Bekasi
Educations
Informal Education
March2017-May2017 AutoCad Course at AMD Engineering School
Job Experience
Declaration:
I declare that all information provided on this CV above (provided by myself) is absolutely
true to the best of my knowledge.
Author
Ilham Fakhrurrozi
CURRICULUM VITAE
Name : Samsul
Place/Date of birth : Palimanan, August,02nd 1986
Nationality : Indonesian
Religion : Moslem
Status : Menikah
Address : Jalan Raya Bogor Km 33
Gang Sawo Rt 01 Rw 02 Kel. Curug
Kec. Cimanggis Kota Depok 16453
Email : samsul0286@gmail.com
Education Formal :
2002 – 2005 Technical High School SMK Al-Nur – Bogor
1999 – 2002 Junior High School at MTS Al-Islam - Depok
1993 – 1999 Elementary School at MI Al-Islam – Depok
Education In Formal :
January 2012– March 2012
- Course AutoCAD at Depok Engineering Drafting School ( DEDS )
October 2013 – December 2013
- Freelance : Project PT. PHE ONWJ
- Job Description : Redraw Structural Jacket And Deck Platform
Computer Skill :
AutoCAD Release All Version
Microsoft Office
WORKING EXPERIENCE
November 2018 :
GTG & WHRU Installation at BGP
April 2019 :
FEED for Karamba Field Production Facilities ( Pandawa )
Declaration:
I declare that all information provided on this CV above (provided by myself) is absolutely true
to the best of my knowledge.
Author
Samsul