Professional Documents
Culture Documents
Sand Control Screen Plugging & Control
Sand Control Screen Plugging & Control
Screen Selection. The following three screens were selected During a retention test, inlet and outlet samples are collected
to evaluate four various cleanup methods. in a given time increment for size distribution analyses and
removal efficiency determination.
1. 20/40 PMF, porous fiber materials. This screen is The retention test for this project was conducted with a
characterized to have a slot opening of a 20/40 mesh formulated drill-in-fluid containing drill solids, which was
pore throat sand. pumped at a selected rate to produce a constant 60 psi pressure
2. A 20/40 Stratapack. This screen is characterized to drop across the 5 ft screen. The 60 psi pressure drop was
have a slot opening of a 20/40 mesh sand with a based on a 12 ppg mud density and 90 ft screen joint. The
thicker filtration layer than that of 20/40 PMF. pressure drop was maintained at 60 psi throughout the 2 hr
3. An 0.008 in. gauge wire wrap prepacked with 40/60- retention test by continuously adjusting flow rate. In the case
mesh resin coated sand. where the screen was fully plugged and fluid could not enter
the screen, fluid was allowed to pass around the screen and
Two tests were conducted with 20/40 PMF screens and one on exit through the annulus between the Plexiglas and the screen
each of the 20/40 Stratapck and 0.008 in. gauge screen. while the 60 psi pressure drop was maintained. Rate variation
Testing conditions for each of these screens were similar. as a result of increase in pressure drop helped to understand
the effect of flux change on screen plugging, which is claimed
Drill-in-Fluid. Sand control screen is based on a simple to be a major factor.7
relationship between screen openings and particle size Inlet and outlet samples were collected every 30 minutes
distribution, which was presented by Coberly in 1937.5 for size distribution analysis of solids as well as total solid
According to Coberly, screens should retain all solids with a measurements. A computer program was then used to
diameter of 2.5 times or more than screen openings. He evaluate removal efficiency of each screen.
suggests that screen slots should be selected such that
openings are twice as the 10-percentile diameter of the solids. Plugging and Cleanup. Plugging of a screen may occur as a
This is based on the larger particle being more responsible for result of formation fines migration into a wellbore. These fine
screen plugging. However, if pore throat size is large enough, solids flow through the throat of the gravel pack surrounding
finer materials can potentially plug the pore throat and the screen and into the screen openings causing partial
eventually impair production. This emphasizes the plugging. As production continues, these fine solids will
importance of fine solids in screen plugging.6 Therefore, to bridge against the screen and eventually plug the screen. Once
understand the effect of small size particles on screen a screen is fully plugged, a cleanup method is used to clean the
plugging, selected solids for these tests include both fine and plugged screen. The productivity of wellbore after screen
coarse materials. Fig. 2 shows particle size distribution of cleanup depends upon variety of factors including the
solids used in this study. Also, Fig. 3 shows sieve analysis of efficiency of the cleanup method.
these solids. Today, a number of different cleanup methods are
implemented upon plugged screen to increase productivity.
Procedure The mores common technique is to use brine based fluid
A retention test was performed on each screen to evaluate solution with breaker and acid to break the gel and to dissolve
removal efficiency. Also, a cleanup technique was used upon carbonate. The brine solution is usually used to reduce mud
each plugged screen to study the performance of each cleanup solids loading and consequently to increase mud weights.8,9,10
technique. Screen’s area open to flow after cleanup treatment In this study, four cleanup methods were selected and
was then calculated based on the retained permeability. implemented upon plugged screens as follow,
Retention. A retention test is usually conducted to evaluate 1. Acid spotting using 10% HCl at 150oF for 6 hrs
the ability of a screen to remove solids. It is also referred to as 2. Enzyme breaker spotting at 150oF for 12 hrs followed
screen removal efficiency. To conduct such a test, a polymer by acid spotting using 10% HCl at 150oF for 6 hrs
solution with known solid size and concentration, which 3. Acid-activated breaker followed by acid spotting
should be formulated for a particular formation and screen, is using 10% HCl at 150oF for 6 hrs and backflowed
pumped around a screen where fluid can then flow into the with water in the production direction
screen through the screen’s openings and out of the screen’s 4. Acid-activated breaker followed by acid spotting
base pipe. The test can be based on the basis of either a using 10% HCl at 150oF for 6 hrs
constant pressure drop across the screen with varying flow
rates, or constant flow rate with pressure drop variation. By Previous works have shown that 15% HCl spotting is the most
knowing the mud density and using the following equation, effective remedial treatment for removing the CaCo3 based
one can calculate a constant pressure drop across a screen, filtercake.11 However, in the previous works conducted by the
authors it was concluded that acid spotting can be as effective
P at 10% HCl for a period 6 hrs at temperatures of 120oF or
ρ= (1) higher.12,13 In addition, it is also suggested that sodium
0.52 L hyphochloric may be more effective in cleanups of organics
SPE 64413 SAND CONTROL SCREEN PLUGGING AND CLEANUP 3
Bran-Leubbe
intensifier pump
Gel Water
dP
6' long
Flowmeter Direct
6" ID Effluent
Sample
Data
Acquistion
System Sampling
Valve Flow Screen Samples for
Diverter Malvern Sieve
Analysis
Not to Scale
Graded
5 Carbonate
Wt. Percent
2
Solid
0
0.01 0.1 1 10 100 1000
Size Microns
100.00
90.00
80.00
Graded
Carbonate
70.00
Cumulative Percent
60.00
50.00
40.00
30.00
Solid
20.00
10.00
0.00
0 50 100 150 200 250 300
Size Microns
Fig. 3- Sieve Analysis Curve Constructed from the Cumulative Percentage and Retained
0.16
Original Acidized
0.14
0.12
Pressure Drop, psi
0.1
0.08
0.06
0.04
0.02
0
0 0.5 1 1.5 2 2.5
Flow Rate, gpm
Fig. 4- Pressure Drop Measurements Corresponding to Pre-plugging and after Treatment, Test 1
8 MAHMOUD ASADI AND GLENN S. PENNY SPE 64413
1.00
0.90
0.80
0.70
Removal Efficiency (%)
0.60
0.50
0.40
0.30
0.20
0.10
0.00
0 20 40 60 80 100 120 140 160 180 200
Size Microns
100
90
80
70
Pressure Drop, psi
60
50
40
30
20
10
0
0 20 40 60 80 100 120 140
Time, min
Fig. 6- Pressure Drop Across the Screen during the Plugging Stage, Test 1
SPE 64413 SAND CONTROL SCREEN PLUGGING AND CLEANUP 9
10
7
Permeability, D
0
Original Acidized
0.5
Screen Before Use Enzyme-S Acidized
0.45
0.4
0.35
Pressure Drop, psi
0.3
0.25
0.2
0.15
0.1
0.05
0
0 0.5 1 1.5 2 2.5
Flow Rate, gpm
Fig. 8- Pressure Drop Measurements Corresponding to Pre-plugging and after Treatment, Test 2
10 MAHMOUD ASADI AND GLENN S. PENNY SPE 64413
10
7
Permeability, D
0
Original Enzyme-Breaker Acidized
1.2
0.8
Pressure Drop, psi
0.6
0.4
0.2
0
0 0.5 1 1.5 2 2.5
Flow Rate, gpm
Fig. 10- Pressure Drop Measurements Corresponding to Pre-plugging and after Treatment, Test 3
SPE 64413 SAND CONTROL SCREEN PLUGGING AND CLEANUP 11
25
20
Permeability, D
15
10
20% 22%
0
Original Breaker/Acid Flowback
140
120
100
Pressure Drop, psi
80
60
40
20
0
0 20 40 60 80 100 120 140
Time, min
Fig. 12- Pressure Drop Across the Screen during the Plugging Stage, Test 3
12 MAHMOUD ASADI AND GLENN S. PENNY SPE 64413
1.00
0.90
0.80
0.70
Removal Efficiency (%)
0.60
0.50
0.40
0.30
0.20
0.10
0.00
0 20 40 60 80 100 120 140 160 180 200
Size Microns
Fig. 13- Removal Efficiency of an 0.008 in. Gauge Screen Prepacked with
40/60 Mesh Resin Coated Sand
0.14
0.12
0.1
Pressure Drop, psi
0.08
0.06
0.04
0.02
0
0 0.5 1 1.5 2 2.5
Rate, gpm
Fig. 14- Pressure Drop Measurements Corresponding to Pre-plugging and after Treatment, Test 4
SPE 64413 SAND CONTROL SCREEN PLUGGING AND CLEANUP 13
14
12
10
Permeability, D
8 75%
0
Original Acid-Activated Breaker
90
80
70
60
Pressure Drop, psi
50
40
30
20
10
0
0 20 40 60 80 100 120 140
Time, min
Fig. 16- Pressure Drop Across the Screen during Plugging Stage, Test 4
14 MAHMOUD ASADI AND GLENN S. PENNY SPE 64413
1.00
0.90
0.80
0.70
Removal Efficiency (%)
0.60
0.50
0.40
0.30
0.20
0.10
0.00
0 20 40 60 80 100 120 140 160 180 200
Size Microns