Professional Documents
Culture Documents
Chapter 4: Installing Pistons
Chapter 4: Installing Pistons
Chapter 4
INSTALLING PISTONS
Moris Italia s.r.l.
Via Per Cadrezzate, 21/C
21020 Brebbia (VA) ‐ Italy
Tel. ++39 0332 984211 ‐ Fax ++39 0332 984280
e‐mail moris@moris.it
www.moris.it
MORIS ITALIA S.r.l. reserves the right to make changes without notice to all the documents
Enclosed with this handbook and related production.
DRAWING DESCRIPTION
UTT DATE
Index Chapter 4 09/09
2) PUT THE CYLINDER HEAD SO THAT THE AXIS OF THE RAM IS IN THE
POSITION PREVIEWED IN RELATION TO THE GUIDES.
3) SHIFT THE FFOT OF THE RAM IN A WAY THAT THE GENERATING LINE OF
THE RAM BODY IS // TO THE GUIDES (THE RETRACTED ROD IS ALWAIS // TO
THE BDY OF THE RAM).
4) SCREW THE UPPER FIXING PLATE BY COMPENSATING THE SIDE AND LEVEL
VARIATIONS BY WEDGES.
5) SCREW THE UPPER FIXING PLATE FOLLOWING THE SAME PROCEDURE AND
CONTROL // WITH A LEVEL.
10) REASSEMBLE THE SLIDING GUIDES AND PROCEED, WITH THE HELP OF A
HOIST, IN A COMPLETE MANOUVRE ON THE TOTAL RUN OF THE RAM.
UTT DATA
04/90
ASSEMBLY OF A LATERAL RAM
N.DIS
9316
9320-2-ING
ASSEMBLY INSTRUCTIONS
1) CHECK WHETHER THE INTERRED PIPE IS PLUMB DOWN AND WELL DIMENSIONED
TO HOLD THE CYLINDER.
2) INSERT THE CYLINDER IN THE HOLE, WITH RESPECT TO THE WISHED “B”
DIMENSION, HOLDING IT PROPERLY.
3) CHECK, USING A SPRIT LEVEL, THE RIGHT CENTERING OF THE CYLINDER AXLE
WITH RESPECT TO THE GUIDES.
4) CATCH FROM ROD HEAD THE PROJECTING NYLON WIRE AND FIX IT TO THE
UPPER-STROKE SIDE OF THE EQUIPMENT, SO THAT IT RESULTS EQUIDISTANT
FROM THE GUIDES AND ON THE RAM AXLE.
5) CHECK WHETHER THE NYLON WIRE IS RIGHT CENTRED WITH RESPECT TO THE
HOLE IT’S COMING FROM, SHOULD THAT NOT BE THE CASE, WORK ON THE
CYLINDER TO ADJUST ITS PERPENDICULARITY (SEE DRAWING ON SHEET N.
9320/1)
NOTE:
DUE TO PARTICULAR REASONS, THE CYLINDER CAN BE MOVED FROM THE IDEAL
CENTRE OF 10 cm. IN BOTH DIRECTIONS.
6) AFTER CYLINDER LEVELING, THE BOTTOM OF THE HOLDER MUST BE FIXED WITH
CEMENT OR WITH ADDITIONAL PLATES, SO THAT THE ADJUSTMENT SCREWS
WON’T BEAR THE LOAD, THEN NUT AND COUNTER-NUT MUST BE BLOCKED
(WHEN USING CEMENT WORK ONLY WHEN IT’S SOLIDIFICATED.
- WHETHER THE SEALS HAVE NO OIL LEAKAGES (SEE FOR EVENTUAL CHANGE).
UTT DATA
04/90
DIRECT UNDERGROUND 1:1 RAM
N.DIS
9320/2
DATA
UT PROTEZIONE PISTONI SDOPPIATI DATE 17/01/08
PER TRASPORTO
N°DIS. DWG Nr.
PISTON TWO PIECES PROTECTION
FOR TRASPORTATION PROT/SDOPP
PROT/SDOPP (IT- ING)
9330/1-IN
UTT DATE
09/09
ASSEMBLY INSTRUCTIONS FOR 2-PIECES CYLINDER
DWG Nr
9330/1
PISTONE
PARTE SUPERIORE
RAM UPPER PART
* - Ref. Point: 1
PISTONE
PARTE INFERIORE
RAM LOWER PART
* - Ref. Point: 1
NOTE:
* - Per descrizione vedere Dis. 9330/1
For a detailed description, see Table 9330/1
UT DATA
MONTAGGIO PISTONE IN DUE PEZZI Date 09/09
ASSEMBLY INSTRUCTIONS FOR DIS. N°
2-PIECES CYLINDER Dwg Nr. 9330/MP2-1
* - Ref. Point: 3
* - Ref. Point: 4
PROTEZIONE METALLICA
METALLIC PROTECTION
* - Ref. Point: 3
FONDO FOSSA
NOTE: PIT FLOOR
* - Ref. Point: 2
* - Per descrizione vedere Dis. 9330/1
For a detailed description, see Table 9330/1
UT DATA
MONTAGGIO PISTONE IN DUE PEZZI Date 09/09
ASSEMBLY INSTRUCTIONS FOR DIS. N°
2-PIECES CYLINDER Dwg Nr. 9330/MP2-2
SOLLEVAMENTO
STELO INFERIORE
LIFTING OF LOWER
1° CRAVATTA ROD SECTION
STELO SUPERIORE * - Ref. Point: 6
1st TIE ON UPPER
ROD SECTION
~ 500
~ 500
2° CRAVATTA
STELO INFERIORE
STELO INFERIORE 2nd TIE ON LOWER
LOWER PISTON ROD ROD SECTION
NOTE:
* - Per descrizione vedere Dis. 9330/1
For a detailed description, see Table 9330/1
UT DATA
MONTAGGIO PISTONE IN DUE PEZZI Date 09/09
ASSEMBLY INSTRUCTIONS FOR DIS. N°
2-PIECES CYLINDER Dwg Nr. 9330/MP2-3
UT
PULIZIA PARTI FILETTATE
NOTE:
CLEANING OF THREADED PARTS
* - Ref. Point: 7
2-PIECES CYLINDER
For a detailed description, see Table 9330/1
DATA
DIS. N°
ALLINEATE SUPERIORE
ALLIGNMENT OF SCREW THE UPPER
REFERENCE LINES ROD SECTION
09/09
* - Ref. Points: 7 - 8 * - Ref. Point: 7
NOTE:
CILINDRO SUPERIORE
TIE ON UPPER * - Ref. Point: 10
CYLINDER PART
2-PIECES CYLINDER
For a detailed description, see Table 9330/1
STELO COMPLETO
ASSEMBLED ROD
* - Ref. Point: 9
Date
DATA
DIS. N°
PER AVVITAMENTO
UPPER CYLINDER PART, POSITIONED
FOR SCREWING
09/09
* - Ref. Point: 11
Dwg Nr.9330/MP2-5
VITI BLOCCAGGIO TESTATA
HEAD-FIXING SCREWS
* - Ref. Point: 12
RACCORDO TUBO
RECUPERO OLIO
OIL-RECOVERY FITTING
TESTATA CILINDRO
COMPLETA
VALVOLA COMPLETE CYLINDER HEAD
SPURGO ARIA
BLEEDER VENT
VALVE
NOTE:
* - Per descrizione vedere Dis. 9330/1
For a detailed description, see Table 9330/1
UT DATA
MONTAGGIO PISTONE IN DUE PEZZI Date 09/09
ASSEMBLY INSTRUCTIONS FOR DIS. N°
2-PIECES CYLINDER Dwg Nr. 9330/MP2-6