Professional Documents
Culture Documents
General Dupont HAZOP are structured in a way that generally does not
2008, question the basic design assumptions and therefore is not
44, 17.3 the preferred hazard analysis method for new installations.
PHAs have not included consequence analyses and even Not attended
qualitative risk assessments are not typically used in a well-
structured way. Charters for PHA teams were not
prepared.
Dupont There is no documented Quality Assurance process for
2008, initial hardware and spare parts. It is clear that
45, 17.4 considerable attention is paid to QA aspects for facilities
Not attended
and hardware. It is not possible to audit the program, as
there is neither documentation nor an explicit
accountability.
Dupont There is no practice or procedure for a Pre-Startup Safety
2008, Review to provide a final verification that ALL aspects of
45, process safety have been properly addressed PRIOR to
17.5 commissioning. What we saw most frequently in field
observations were the absence of locking mechanisms on
block valves placed under PSVs, hand valves located where Completed
they were very difficult to operate, inadequate space or
facilities for maintenance activity (such as pulling tube
bundles from horizontal heat exchangers), inadequate
barricades to control truck traffic around loading /
unloading facilities.
110 All management and technical staff positions have a Job Manage
Description. This includes a statement of the Job ment of
Qualifications in terms of education, experience and skills / Personne
competencies. Despite the lack of a documented system, l Change
the turnover of personnel is being accomplished
successfully.
There is no way to ensure this will continue without a Not attended
documented system to follow.
So that practices will not deteriorate with the passage of
time and the turnover of key managing personnel, analyze
how personnel change is being managed for safety-critical
positions (staff and operating) and document the
requirements in a procedure.
111 Stores management (all sites) felt no particular PSI
responsibility to have an accurate MSDS on-hand for ALL of
the chemicals they stored. One of the Stores Managers
said, “That’s Purchasing’s responsibility” (which is decidedly Not attended
is NOT).
There should be a procedure by which Stores does not
accept ANY chemical without a proper MSDS on-hand.
113 International process safety standards require that the Not attended PSI
mechanical design basis be updated. A list of “safety
critical equipment” is also mandated and this definition
must be well-understood. The point is that all “safety
critical equipment” be placed on an inspection and
maintenance program.
113 Develop and implement procedures satisfying the PSI
requirements of the PSI standard. The requirements for an
adequate PSI package are much too numerous to include in
this report, but there are many reference texts and internet
sites where this information resides. Each operating unit
will have to develop and implement process safety Completed
procedures to meet these requirements and designate an
individual to be responsible for developing and maintaining
their PSI package. Project procedures will also have to be
upgraded to ensure that all required information is put into
the proper PSI package when the project is executed.
113 Work should begin immediately to extend the definition of PSI
critical equipment to include everything that contains
hazardous materials or whose failure could conceivably
lead to release of a hazardous substance. This definition is
Not attended
crucial to adequate coverage and it is one of the
foundations of process safety compliance. Then, the
mechanical integrity system must be reviewed and
expanded to include all of this equipment.
113 Whenever a Process Risk Analysis is done, the PSI should be PSI
reviewed and completed sufficiently for the purpose of the Not attended
PRA.
117 Full responsibility for all aspects of PRAs in each operating PRA
unit must rest with the operating management. This
responsibility must include at least:
Providing formal charters to PRA teams,
Selecting team members meeting all the team composition
guidelines,
Arranging for the team members to have the necessary
time available for quality PRAs, rather than trying to
compress them into one or two days Not attended
Monitoring progress of PRAs in progress,
Carefully reviewing PRA reports,
Responding in writing to the recommendations,
Recognizing and rewarding good performance by teams,
and
Following-up on accepted recommendation until
completed and documented as an attachment to the file
copy of the PRA report.
117 The Process Safety Sub-committee should sponsor work on PRA
a critical PRA while the Sub-committee on Procedures and
Not attended
Standards comes up with a comprehensive set of
procedures for process safety implementation.
SFGCS 117 Concerning the Cold Vent on the Relief Header at SFGCS: Engineering PRA
Verify “as built” situation, in particular the exit Study has
diameter of the vent pipe and the number / been
location of residences and the mosque relative to completed.
the vent. However, the
Conduct a formal Consequence Analysis based on
total blowdown through existing vent
w/detonation and (separately) w/fire. Estimate the
ground-level H2S concentration and consider toxic
effects from H2S and (separately) the product of remaining job
H2S combustion, SO2 (which is also toxic). is in progress.
Develop an appropriate location for a flare stack
(NOT a “cold vent) and place this on fast track 40 %
project schedule (As on 12
o Inside the fence and away from Mar’12)
encroachment
o Possibly use area south and west of SGFCS
Tell Provincial and National authorities. (We can
assist with this, if asked.)
118 Develop a standard for block valves under pressure-relief PRA
devices that complies with the ASME Code. This code was
developed from long years of experience and should be
respected as a minimum standard. Existing standards and Not attended
practices should be upgraded to comply with it. A locking
device is definitely required for valves that the code
requires to be secured from inadvertent opening.
120 The Process Safety Sub-committee should sponsor work on Manage
a currently active project involving MOC-Technology while ment of
the Sub-committee on Procedures and Standards comes up Technolo
with a comprehensive set of procedures for process safety gy
implementation. Change
120 Add a review for adequacy of engineering and conformance “
to standards by peers or technical management for projects
above the basic level or complexity of major scope.
120 Consider adding a test authorization section to the “
management of change procedure to control conditions,
duration, etc. of tests and to ensure that results are
Completed
properly documented in the PSI package and that
recommendations emanating from tests are followed to
completion.
Sui Prod Appendix The two old Acid Tanks are a safety hazard. They should be
Completed
II, Page 02 flushed and removed.
Sui Appendix This note in the DHP Logbook describes a Change in
Dehydra II, Page 05 Technology for one of the control valves. There is no
tion formal Management of Change Procedure, so this change
Plant was verbally authorized. There was no HAZOP or other
hazard analysis and no consequence analysis. There was no In progress
Pre-start Up Safety Review. There was no Test
Authorization. And the drawings have not been updated.
All this is deficient versus commonly accepted process
safety standards.
SFGCS Appendix We could find no maintenance records for these Pressure
II, Page 16 Safety Relief Valves. There is nothing to indicate they have
Not included
ever been inspected, cleaned and re-calibrated since they
in Action Plan
were installed about 15 years ago. This is contrary to multi-
national standards and good process safety management.
Sui PP Appendix Lots of damaged insulation. This creates safety problems
II, Page 10 and wastes energy. The problem is mostly due to poor Not included
maintenance practices and a lack of Supervision. in Action Plan
Sui Appendix The underground fuel storage tanks at Sui Field (and Adhi)
Stores II, Page 16 are almost certainly leaking. In any case, they should be
inspected for internal corrosion and for external corrosion
(at the fittings, especially). It would be MUCH safer for
many reasons to replace these tanks with overhead tanks.
Not included
At Sui Field, there are some perfectly good fuel storage
in action plan
tanks that could be used (if only the Army gave permission).
At some point, PPL executive management will need to
decide who runs the Operation and who will get blamed if
there is a major safety incident because of these obsolete
tanks.
DUPONT STUDY 2016
Action plan Develop QHSE capabilities to carry out HAZID, LOPA, HIRA,
Sui Field
point 34 FMEA, hazardous consequence analysis and QRA
Conduct SIL for electrical and instrumented equipment
whose primary function is to contain harm (e.g. interlocks,
Action plan ESDs) –
Sui Field
point 60 Conduct RCM for equipment whose primary function is
production, however by improving the reliability of the
equipment the Plant will be inherently safer
Codify into written procedures and methodologies all
Action plan interlock testing during overhauls - it is not clear if WI exist,
Sui Field
point 62 example we could not tell what RAGAGEP was used (e.g.
IEC61511);
Record Test failures (of interlocks) when fixed and these
Action plan need to be recorded and tracked as leading indicators -
Sui Field
point 63 Launch specific RCA to find patterns of failure based on the
records
Codify Materials & Contracts Manual – it should clearly lay
Action plan
Sui Field out purchase, handling and storage of store PSM Critical
point 64
Equipment
Identify tools for facility siting (Consequence modelling
Action plan
Sui Field studies e.g. QRA) needs to be considered in different
point 123
emergency scenarios for personal and plant safety